for
APRIL 2018
Prepared for:
TABLE OF CONTENTS
CONTENT PAGE
CERTIFICATION 4
PROJECT SUMMARY 5
LDP2M2 SUBMISSION CHECKLIST 6
CHAPTER 1: INTRODUCTION 12
1.1 Introduction 12
Page 1
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
4.14 Discharge 30
4.17 Maintenance 31
CHAPTER 5: CONCLUSION 32
REFERENCES 33
Page 2
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
APPENDIX B Tanjung Langsat Clinical Waste Plant Project Site Development Layout
APPENDIX C LDP2M2 Best Management Practices (BMP’s) Proposed Installation for Tanjung
Langsat Project Site
APPENDIX D LDP2M2 Best Management Practices (BMP’s) Specification for Tanjung Langsat
Project Site
Page 3
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
CERTIFICATION
NAME OF REPORT: LAND DISTURBANCE - POLLUTION PREVENTION AND MITIGATION MEASURES FOR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM.
I, the undersigned, acknowledge by signature that these documents meet or exceed the design
standards of the Department of Environment, Malaysia and that they were prepared under my
supervision. I, the undersigned, further acknowledge that to the best of my knowledge and belief, the
products resulting from these documents will function as intended.
VERIFIED BY:
_______________________ (CPESC)
(Signature)
Name : MOHD JOHARI BIN ABDUL MALIK
NRIC No. : 810929-04-5203
CPESC No. : 7218
Date : 21 APRIL 2018
___________________________
(Signature)
Name :
NRIC No. :
Date :
Page 4
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
PROJECT SUMMARY
Project Name:
Scope:
Team Member:
Page 5
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
LDP2M2 SUBMISSION CHECKLIST (ENVIRONMENTAL IMPACT ASSESSMENT GUIDELINES FOR MALAYSIA, 2016)
ITEMS PAGE MARK REMARKS
√ - Yes
× - No
NA - Not Applicable
1.1 PROJECT ACTIVITIY AND IMPLEMENTATION
(d) Construction scheduled for each major land disturbance complete with timeline or chart for the √ Appendix A
installations of P2M2s
(e) Typical method statement for site site clearing, cut and fill, excavation of foundation, drilling of 26 - 31 √ Chapter 4
borehole, instream works and construction of temporary / permanent stream / river crossing and
diversion that incorporate the significance elements of pollution prevention and mitigation measures
(f) Estimated start date, completion date and stabilization scheduled for each major land-disturbing √ Appendix A
activities or construction activities phases, stages and sequences
Page 6
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
(b) Site runoff velocity and flow rate, both pre and during development 18 √ Chapter 3
Appendix E
(c) Description of site soil characteristics: 21 √ Chapter 3
i. Soil types
ii. Soil test erodibility
iii. Soil hydrologic group
iv. Dispersible fine clay: Percentage of dispersible material
v. Anticipated excavation depth for the proposed land disturbing activity
(d) Description of adjacent areas, such as streams, lakes, residential areas, and roads that might be √ Refer EIA Report
affected by the land disturbance.
(e) List of streams and rivers identified on-site. (Use coding for unnamed streams and rivers). √ Refer EIA Report
(f) List of receiving streams and rivers. (Use coding for unnamed streams and rivers). √ Refer EIA Report
(g) List of existing drainage identified on-site. √ Road drainage of industrial area
(h) List of P2M2s proposed also make reference to P2M2s description can be accessed. 26 - 31 √ Chapter 4
Appendix D
(i) Identify access roads and other outsourced components (such as mobile batching or premix plant) √ Refer EIA Report
that are located outside the proximity of the project boundary.
Page 7
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
(n) Spill Prevention and Control from fuel and chemical use or storage. √ Refer EIA Report
(p) Soil loss prediction using the Universal Soil Loss Equation (USLE), sediment yield calculation using 19 - 25 √ Chapter 3
Modified Universal Soil Loss Equation (MUSLE) and runoff estimation for pre, during and post Appendix H
development accounted for both with and without the implementation of LDP2M2s. All of the data and Appendix I
parameters used in the calculations shall be measured or rationally determined, and identified. If
secondary sources are used, they shall be clearly identified.
(q) Calculation of proposed sediment trap/basin based on drainage area disturbed and projected runoff √ Appendix D
flow direction from each disturbed land segment that will drain into the proposed sediment trap/basin.
1.3. MAP OF SITE PLAN WITH THE EXISTING SITE CONDITIONS (PREDEVELOPMENT)
Page 8
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
Page 9
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
(i) Identify and mark on-site temporary access or construction or haul road √ Appendix B
Appendix C
(j) Identify and mark site office area. √ Appendix B
Appendix C
(k) Identify and mark stockpile areas. √ Appendix B
Appendix C
(l) Identify and mark temporary preservation of existing vegetation. X
(n) Identify and mark material staging area or equipment storage area. √ Appendix B
Appendix C
(o) Identify and mark workshop / maintenance or engineering work √ Appendix B
area. Appendix C
(p) Identify and mark generators set and/or motorized equipment area. X
(q) Identify and mark Vehicle and Equipment Washing Facility. √ Appendix B
Appendix C
(r) Identify and mark petroleum based material/refueling, chemicals and skid tank area. X
(x) Identify and mark spoil (unsuitable material) area or disposal area. √ Appendix B
Appendix C
Page 10
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
(z) Identify and mark the location(s) of all proposed P2M2s application. √ Appendix C
(aa) Identify and mark all of the designated point(s) of water discharge and also any other potential √ Appendix C
point(s) of water discharge to off-site drainage ways.
(bb) Provide the GPS location of the construction ingress/egress and all designated point(s) of water 14 √ Chapter 2, Item 2.1
discharge for the site.
Size: A3 or A1.
Page 11
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
CHAPTER 1
INTRODUCTION
1.1 Introduction
The objectives of the Land Disturbance Pollution Prevention and Mitigation Measures report (LDP2M2)
for the Project Site entitled “THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT
PLANT AT PTD 4865, KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG TIRAM, JOHOR DARUL
TAKZIM” are:
a) To provide a guide and effective control measures for the developer in managing erosion and
sediment impacts during the development activities.
b) To assess the hydrological condition for pre, during and post development.
c) To provide adequate drainage network to suit with development and environmental friendly
demand.
d) To determine the sediment storage required and provide suitable construction program to prevent
excessive and uncontrol sedimentation.
e) To indicate the level of erositivity for the whole development area.
f) To propose prevention measures and control of offsite damage.
The site key plan and site location plan for the proposed Project Site are shown in Figure 1.1 and 1.2
respectively.
Page 12
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
Page 13
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
CHAPTER 2
SITE DESCRIPTION
The topography of the Project Site is perimetered by an industrial complex with a flat terrain in general.
The Project Site location is approximately at 2.5 km away from the nearest residential area of Kampung
Tanjung Langsat. The GPS coordinates of the Project Site is 1.460183 N, 103.979963 E.
Details of stages of the Project Site development is tabulated in Table 2.1 and Figure 2.1.
In regard to Table 2.1 and Figure 2.1, construction development shall cover 0.2959 acre (refer Appendix
B) and the detail of work program is as attached in the Appendix A.
Page 14
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
Page 15
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
CHAPTER 3
Erosion risk and engineering analysis is required to be performed for Project Site as listed-
a) Hydrological Assessment
b) Soil Loss Estimation
c) Sediment Yield Estimation
d) Evaluation of Impact
The Hydrological Assessment were assess for the Project Site as to determine the peak flow
discharge (Qp) based on the following requirement:-
a) Existing which is before construction (Qpre) for for minor (2, 5 and 10 years ARI) and
major (50 and 100 years ARI) conditions.
b) During construction (Qduring) for minor (2, 5 and 10 years ARI) and major (50 and 100
years ARI) conditions.
c) Post construction (Qpost) for minor (2, 5 and 10 years ARI) and major (50 and 100
years ARI) conditions.
The Project Site catchment considered for the hydrological assessment are shown in Figure 3.1.
The summary results of the peak flow discharge assessment as described in item 3.2 (a), 3.2 (b)
and item 3.2 (c) is shown as in Table 3.1 for Existing Condition, During Construction and Post
Construction.
Page 16
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
The calculation method and application used in Hydrological Assessment were based on the
Quantity Design Fundamentals of the Urban Stormwater Management Manual for Malaysia 2nd
Edition 2011 (MSMA, updated on May 2015). The applied calculation method is described as
below:-
b) Empirical IDF Curves as to determine the average Rainfall Intensity (i). The selected
station for fitting constants dependant on the rain gauge location are:
DID Station Name: Johor Silica
Station ID: 15441139
Fitting Constant Determined: (λ=59.060), (ƙ=0.202), (Ɵ=0.128), (ŋ=0.660)
The time of concentration (t-con, minute) for pre-construction and post-construction found to
have improve which mean the provided slope gradient and surface cover is suitable for this
development. This is also proven from the flowrate calculation (refer Table 3.1) where the peak
flow discharge for post construction are lower compared to pre construction, hence the
flowrate for post construction are improved and controllable. Detail calculation of hydrology
assessment is attached in Appendix E.
Page 17
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
Table 3.1: Summary Results of Peak Flow Discharge for Project Site
2 Years ARI 5 Years ARI 10 Years ARI 50 Years ARI 100 Years ARI
Page 18
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
The Universal Soil Loss Equation (USLE) is used to assess the Erosion Risk at the Project Site
under these required conditions:-
R factor for the Project Site at Pengerang (Johor) falls in the range of 15,000 to 17,500
MJ.mm/ha.yr with reference to Appendix F. For evaluation purposes, the higher limit is used,
therefore,
Page 19
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
PROJECT SITE
Page 20
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
The types of soil series representing the soil background at the Project Site which is based on
the Reconnaissance Soil Map (Appendix G) are:-
The selection of the appropriate value in design consideration is based on factor of safety and
reliability. Thus, we decided to select the higher value of soil erodibility as given in Table 3.2.
Table 3.2: The Selection of Erodibility Factor for Soil Loss Estimation
Table 3.3: The Determination of LS Factor for Soil Loss Estimation for Project Site
PROJECT: SWMCJ Condition Slope Length, λ (m) Slope Steepness, s (%) LS Factor
Before (Existing) 0.30 0.15
SWMCJ 600.00
During Construction 0.05 0.13
*Refer to the Calculation Sheet Appendix H
Page 21
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
For the determination of cover management, the appropriate value was selected as shown in
Table 3.4.
PROJECT:
Condition C Factor Description
TANJUNG LANGSAT
Before Construction
0.35 Bushes / Shrub - 50% Cover
(Existing)
TANJUNG LANGSAT
1.00 Bare Soil
During Construction
0.05 Proposed to apply compacted gravel layer
For the determination of management support value, the proposed and appropriate practices
are described in Table 3.5.
PROJECT:
Condition P Factor Description
TANJUNG LANGSAT
Before Construction
1.00 No support practice
(Existing)
During Construction
1.00 No support practice
(No BMP’s)
To apply sediment containment systems
(Silt Trap)
* Remarks
Additional practices shall be proposed in a
TANJUNG LANGSAT
way to adhere and ensure the reduction of
soil loss estimation which is:-
During Construction
0.5 a) Check dam
(With BMP’s)
b) Silt fence
c) Temporary Diversion Drainage
Page 22
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
3.4.6 Conclusion
As summarized in Table 3.6, the application of the Best Management Practices (BMP’s) which is
to have a sediment trap systems and a combination of check dam, silt fence and diversion ditch
at the Project Site can minimize and reduce the erosion risk (soil loss) up to an average range of
97.50% compare to no application of BMP’s.
Table 3.6: Summary of Soil Loss Estimation based on the Various Conditions at the Project Site
PROJECT:
CONDITION DETAILS OF APPLICATIONS SOIL LOSS ESTIMATION (ton/ha/year)
TANJUNG LANGSAT
Before Construction Existing 48.281
TANJUNG
No BMP’s 116.242
LANGSAT During Construction
With BMP’s 2.906
*Refer to the Calculation Sheet Appendix H
Page 23
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
The Modified Universal Soil Loss Equation (MUSLE) is used for sediment yield estimation for the
Project Site as a result of a specific storm event. The sediment yield estimation for the Project
Site shall be based on these required conditions:-
The summary results of the sediment yield estimation as described in item 3.5 (a), 3.5 (b) and
3.5 (c) is shown as in Table 3.7.
The design criteria for the sediment yield estimation for the existing and during construction
conditions are described as below:-
d) Design ARI is 100 years as to fulfill the requirement of runoff quantity and quality
design criteria of BMP’s facilities in MSMA 2nd Edition. The total estimated
construction period is about 24 months.
e) Storm Duration (D) is assume to be similar with Time of Concentration (tc) which is
(D = tc) for each conditions (existing and during construction).
f) The application of No BMP’s and With BMP’s conditions is applied for sediment yield
estimation for during construction condition.
3.5.2 Conclusion
As summarized in Table 3.7, the estimated total sediment yield from the Project Site is 0.028
tonne per storm event with the application of BMP’s together with designated design storm of
100 ARI. The recommendation for BMP’s pollution prevention and mitigation measures of
Project Site shall be covered in the next chapter.
Page 24
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
Table 3.7: Summary of Sediment Yield Estimation based on the Various Conditions at the Project Site
Page 25
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
CHAPTER 4
a) Schedule site meeting (kickoff meeting) shall be carried out before commencement of
works which to be attended by project proponent, environmental officer, consultant and
contractor.
b) During the works progress, site meeting required to be performed as well to facilitate the
works progress by parties involved.
c) Proper minute meeting need to be recorded in order to trace progressive works.
a) As for the construction monitoring, construction markers shall be provided with pole to
indicate barrier of construction area.
b) Discharge Point from the Project Site need to be marked.
Page 26
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
a) Access road shall be stabilized with hardcore layer and sufficient drainage networks.
b) All vehicles going out of the Project Site must pass through a washing bay / wash trough to
wash away the dirt. The water in the washing bay must be channeled to nearby drainage
network and channeled to detention pond.
c) If earth is transported into the Project Site by lorries, they must be covered with adequate
tarpolin to reduce spillage on the roads and to avoid dust pollution.
d) Dust emitted during earthworks can be reduced by regularly spraying the dusty surfaces
and the water channeled into a nearby drainage network and channeled to detention pond.
e) Any pothole or road crack shall be repaired to avoid water seeping through and worsen the
condition.
a) A minimum 20m vegetated buffer zone are required to be provided near discharge point as
indicated in the guidelines (Environmental Impact Assessment Guidelines in Malaysia).
b) The buffer shall be maintained as it will assist to reduce any direct inflows into the river and
affect the river quality.
Page 27
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
a) Sediment trap are required and to be maintained until the site area is permanently
protected against erosion or water quality control structure constructed.
b) The sediment trap to be designed as specified in the standard specification.
c) All waters from disturbed area should be channeled first to a sediment trap prior to
discharge.
d) The outlet of the sediment trap should have a layer of geotextile materials to reduce silt
being discharged.
e) For sediment inspection and maintenance checklist are attached in Appendix J.
a) All waters from disturbed area should be channelled first to a sediment trap prior to
discharge.
b) The outlet of the sediment trap should have a layer of geotextile materials to reduce silt
being discharged.
c) Check dam is also recommended to be constructed across a temporary earth drain as to
reduce the velocity of stormwater, erosion and sedimentation. Hence, check dams will be
installed at 10 m intervals.
a) For water course crossing installation (circular culvert), adequate collar joint required to
provided to avoid water leakage.
b) Exposed soil near the outfall structure need to be turfed.
Page 28
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
a) Stockpile required to be localized minimum 20m away from any watercourse nearby.
b) Surrounding stockpile, sufficient drainage networks (toe drain) must be provided and
channel to sediment trap for sediment control.
a) Disposal area required to be localized minimum 20m away from any watercourse nearby.
b) Disposed soil are required to be laid with not steeper than 2H:1V (H=horizontal, V=vertical)
and well compacted.
c) Sufficient drainage system required to be provided to control surface runoff within the
Project Site.
a) Accumulated runoff water from disturbed are shall be channelled to sediment trap.
b) De-silting works required to be carried out to remove all clogged material.
Page 29
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
4.14 Discharge
a) Water from ongoing construction area required to be channel to sediment trap prior to
final discharge point.
b) Untreated process water, washing water shall be channeled to Effluent Treatment Plant
before final discharge point.
a) For the situation where structures or facilities installed incorrectly, rectification works are
required to be carried out within 7 days upon encountering the issue.
b) Any status of rectification works shall be recorded and informed to DOE via online
communication system.
a) Prior to commence any works, site inspection shall be carried out by Project Proponent,
Environment Officer or equivalent competency of Certified Competent Person Stormwater
Inspector (CESSWI) or Competent Inspector Sediment Erosion Control (CISEC) and
contractor to evaluate the site condition.
b) Usually in the normal practice, contractor will submit Request for inspection (RFI) at least
two (2) days early to notify EO or consultant on the particular items to be inspected.
c) In the case of incorrect installation, EO or consultant shall assess the quality or wrongly
installed and seek the rectification works. Second inspection shall be performed upon
completion of rectification works.
d) Minimum one (1) unit of rain gauge are recommended to be installed at project site in
order to determine the quantity of rainfall particularly.
e) Reading of rain gauge need to be taken daily and the data shall be recorded properly.
f) Inspection need to be carried out at least once in seven (7) days or 24 hours after storm
event more than 12.5mm on the constructed elements.
Page 30
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
4.17 Maintenance
a) Sediment trap must be de-silted when it reaches half of the sediment trap capacity to
ensure it function effectively.
b) Clogged check dam shall be de-silted when the clogged reach half of the maximum height.
c) Regular maintenance shall be performed as well on the drainage networks to avoid flood
event.
Page 31
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
CHAPTER 5
CONCLUSION
5.1 Conclusion
Based on the assessment performed, land disturbance and pollution control can be adopted to
Project Site with the following:-
a) One (1) unit of sediment trap following to the standard specification installation specified
in the Appendix D.
b) Effective mitigation measure with the following provided:-
i. Check dam
ii. Silt fencing.
iii. Significant earth drain network.
d) Frequent maintenance (i.e. de-silting of the sediment inside sediment trap, check dam)
need to be carried out at site.
e) Since development will be carried by phases, earthwork and sediment can effectively be
controlled.
f) Regular site inspection by PP, EO, consultant and contractors.
g) Inspector of BMP’s is required for Certified Competent Person Stormwater Inspector
(CESSWI) or Competent Inspector Sediment Erosioin Control (CISEC).
As shown in this modeling exercise, the estimation of soil erosion at the construction stage
without BMP’s will generate a very high soil erosion rate. The estimated soil erosion value was
however drastically reduced with the adoption of BMP’s. As such, the usage of BMP’s is
considered to be critical when the site is developed. Some of the key measures utilized shall be
the usage of sediment trap, silt fencing as well as the opening of the site in phases. This means
that the entire area should not be left exposed but rather developed in sequence where each
phase is stabilized prior to the opening of the next phase.
The BMP’s proposed installation for Project Site can be refer to Appendix C with a reference to
BMP’s standard specification installation as in Appendix D.
Page 32
LAND DISTURBANCE – POLLUTION PREVENTION AND MITIGATION MEASURES (LDP2M2) FOR
APR
THE PROPOSED DEVELOPMENT OF CLINICAL WASTE THERMAL TREATMENT PLANT AT PTD 4865,
KAWASAN PERINDUSTRIAN TANJUNG LANGSAT, MUKIM SG. TIRAM, JOHOR DARUL TAKZIM. 2018
REFERENCES
3. Erosion and Sediment Control Plan (ESCP) Volume 1 Report For PETRONAS Refinery and
Petrochemical Integrated Development (RAPID) In Pengerang, Johor (September 2012),
Integrated Environtech Sdn. Bhd.
4. Erosion and Sediment Control Plan (ESCP) for the “Projek Infrastruktur dan Kemudahan
Awam Bagi Pembangunan Kompleks Petroleum Bersepadu Pengerang, Daerah Kota
Tinggi, Johor: Membina Jalanraya 4 Lorong 2 Hala dari Jalan FT92 Persimpangan Bukit
Gelugor ke Persimpangan Punggai J91 (P4)” Jabatan Kerja Raya Malaysia (April 2017).
5. Land Disturbance Pollution Prevention and Mitigation Measures (LD-P2M2) for the
Proposed Development of Satelitte Waste Management Centre Johor (SWMCJ) at PTD
2288 In Mukim Pantai Timur, District of Kota Tinggi, Johor for CENVIRO Johor Sdn Bhd.
(September 2017), AMR Environmental Sdn. Bhd.
Page 33
NOTES:
RIZA
RIZA B TNB
B KT
M
KOMPLEK PERINDUSTRIAN TG LANGSAT
RIZAB
KTM
JALAN NIBONG
1000
2000
2500
6000
TAJUK :
3500
TAJUK LUKISAN
Lukisan ini adalah hakcipta dan hakmilik ICSB dan tidak boleh disimpan, ataupun disalin ataupun
digunakan tanpa kebenaran daripada ICSB.
Pihak Kontraktor mestilah menyemak segala ukuran di tapak pembinaan, hanya ukuran yang
dinyatakan akan digunakan.
Sebarang perselisihan dalam ukuran haruslah dilaporkan kepada Jurutera dengan serta-merta
sebelum meneruskan kerja.
DEVELOPER
BOUNDARY LINE
TNB
9000 10425
1200
450
1200
WASH AREA
6.096m MIN. BUILDING SETBACK
OFFICE AREA
6000
WWTP AREA (TBA)
LOADING AREA
BY SPECIALIST No. 18-02, Jalan Perjiranan 2,
Bandar Dato' Onn,
3150 81100 Johor Bahru, Johor Darul Takzim.
Tel : +607 - 351 7313
Fax : +607 - 364 0313
e-mail : projects@irfaconsult.com
3715
GUARD POST
6000
2400
TANK TANK RUMAH SAMPAH .....................................................
SEPTIC TANK
5 PE Ir. MOHD AFANDI BIN KONTING
B. Eng. (Hons) Civil, UTHM, M.I.E.M, P. Eng.
IC. No. : 810106-01-6575
BOUNDARY LINE I hereby certify that these structural details / calculations are in accordance
with the uniform building by-laws (Chapter 5, Structural requirements)
NO LUKISAN
ICSB/1802/ARCH/01
U
0
270
90
KOMPLEK PERINDUSTRIAN TG LANGSAT
180
CROSS SECTION CROSS SECTION
TRANSACTION BETWEEN TRANSACTION BETWEEN
SECTION B & C SECTION B & C
ELEVATION
SCALE : N.T.S
SECTION B
SCALE : N.T.S
CHANNEL GRADE
D50= 300mm Ø RIPRAP
SEE SHEET D-30 FOR GRADIENT
SECTION C
SCALE : N.T.S
NOTE : ALL UNITS MILIMETER (mm)
W
FLO
EXISTING GRADE
RIPRAPLINED - DETAIL D
SCALE : N.T.S.
COMPACTED
EMBANKMENT UNLINED - DETAIL A
MATERIAL SCALE : N.T.S.
ANCHOR TRENCH AT PERIMETER OF BLANKET AND AT THE ANCHOR TRENCH AT PERIMETER OF BLANKET AND AT
OVERLAPPING JOINTS WITH ANY ADJACENT ROLLS OF BLANKET. SEE THE OVERLAPPING JOINTS WITH ANY ADJACENT ROLLS
DETAIL 9 OF BLANKET. SEE DETAIL 9
EROSION CONTROL BLANKET
(ECB) SEE DETAIL 9
1. SEE PLAN VIEW FOR: 1. THE ESCP MANAGER SHALL INSPECT DIVERSION DITCHES WEEKLY, DURING AND
AFTER ANY STORM EVENT AND MAKE REPAIRS OF CLEAN OUT THE NECESSARY.
- LOCATION OF DIVERSION DITCH.
-TYPE OF DITCH (UNLINED,ECB LINED,PLASTIC LINED, OR RIPRAP LINED. 2. DIVERSION DITCHES ARE TO REMAIN IN PLACE UNTIL THE END OF
-LENGTH OF EACH TYPES OF DITCH. CONSTRUCTION.
-DEPTH 'D' AND WIDTH 'W' DIMENSIONS.
-FOR ECB LINED DITCH, EROSION CONTROL BLANKET TYPE ( SEE DETAIL 9) 3. IF DIVERSION DITCHES ARE REMOVED, THE DISTURBED AREA SHALL BE DRILL
-FOR RIPRAP LINED DITCH, SIZE OF RIPRAP IS 'D50'. SEEDED AND CRIMP MULCHED OR OTHERWISE STABILIZED IN A MANNER
APPROVED BY THE AUTHORITY.
2. SEE DRAINAGE PLANS FOR DETAILS OF ANY PERMANENT CONVEYANCE FACILITIES
OR DIVERSION DITCHES EXCEEDING A 2-YEARS FLOW RATE.
3. DIVERSION DITCHES INDICATED ON INITIAL ESCP PLAN SHALL BE INSTALLED NOTE: ALL UNITS IN MILIMETERS (mm)
PRIOR TO ANY LAND-DISTURBING ACTIVITIES.
1000
C B C (MIN)
OUTLET
INLET
TOP WATER LEVEL
2
1
SECTION A-A
L 300mm THK. RIVERSTONE
PLAN B
WIDTH
SAND LAYER
EARTH CHANNEL
2 2
1 1
WIRE BOX GABION
WITH ROCKFILL
SECTION B-B
GEOTEXTILE
300mm THK.
SAND LAYER
SECTION C-C
DETAIL A
SCALE N.T.S
COMPACTED
BACKFILL
JOINTS - SECTION B
SCALE N.T.S
2. ANCHOR TRENCH SHALL BE EXCAVATED WITH TRENCHER, OR WITH SILT FENCE INSTALLATION MACHINE, NO ROAD
GRADERS, BACKHOES ETC. SHALL BE USED TRENCH SHALL BE COMPACTED BY HAND WITH "JUMPING JACK" OR BY THE
WHEEL ROLLING, COMPACTION SHALL BE SUCH THAT SILT FENCE RESISTS BEING PULLED OUT OF ANCHOR TRENCH BY
HAND.
3.SILT FENCE INDICATED INITIAL E.S.C.P PLAN SHALL BE INSTALLED PRIOR TO ANY LAND DISTURBING ACTIVITIES.
1. THE E.S.C.P MANAGER SHALL INSPECT SILT FENCE DAILY, DURING AND AFTER ANY STORM EVENT AND MAKE REPAIRS
OR CLEAN OUT UPSTREAM SEDIMENT AS NECESSARY.
2. SEDIMENT ACCUMULATED UPSTREAM OF SILT FENCE SHALL BE REMOVED WHEN THE UPSTREAM SEDIMENT REACHES A
DEPTH 150mm.
3. SILT FENCES SHALL BE REMOVED AT THE UPSTREAM DISTURBED AREA IS STABILIZED AND GRASS COVER IS APPROVED
BY THE COUNTRY. IF ANY DISTURBED AREA EXISTS AFTER REMOVAL, IT SHALL BE SEEDED AND MULCHED OR
OTHERWISE STABILIZED.
SEDIMENT FENCE
100.0
101.0
A
A
STOCKPILE
EARTH BANK
CONSTRUCTION NOTES
CONSTRUCTION
SITE ACCESS
VTC AT CONSTRUCTION
ENTRANCE (SEE DETAIL 24)
1. SEE PLAN VIEW FOR GENERAL LOCATION OF STAGING AREA, CONTRACTOR MAY MODIFY
LOCATION AND SIZE OF STABILIZED STAGING AREA WITH COUNTRY APPROVAL.
3.STAGING AREA SHALL BE STABILIZED PRIOR TO ANY OTHER OPERATIONS OF THE SITE
1. THE ESCP MANAGER SHALL INSPECT STABILIZED STAGING AREA DAILY, DURING AND
AFTER ANY STORM EVENT AND MAKE REPAIRS OR CLEAN OUT UPSTREAM SEDIMENT AS
NECESSARY.
1. Qpre (Before Construction or Existing Condition) , Qduring (During Construction Period) and Qpost (Post Construction Condition)
Determination:-
Cpre = 0.5 (Grass Cover) for >10 year ARI Major System
*Recommended Runoff Coefficients for Various Landuses (MSMA 2nd Edition)
Cduring = 0.6 (Bare Soil ) for >10 year ARI Major System
*Recommended Runoff Coefficients for Various Landuses (MSMA 2nd Edition)
Cpost = 0.5 (Grass Cover) for >10 year ARI Major System
*Recommended Runoff Coefficients for Various Landuses (MSMA 2nd Edition)
th L /3
Overland Flow, tc =
S /5
Tk
Rainfall Intensity, i =
(d+θ)ŋ
Coefficients
Roughness
IDF Fitting
Constants
Gradient
Horton's
Runoff
Slope
Section 2 ARI 5 ARI 10 ARI 50 ARI 100 ARI
Symbol λ Ϗ θ ŋ C n s tc ὶ Q tc ὶ Q tc ὶ Q tc ὶ Q tc ὶ Q
Unit - - - - - - % min mm/hr m3/s min mm/hr m3/s min mm/hr m3/s min mm/hr m3/s min mm/hr m3/s
59.06 0.202 0.128 0.66 0.5 0.045 0.31 28.25 95.30 0.016 28.25 114.68 0.019 28.25 131.91 0.022 28.25 182.59 0.030 28.25 210.03 0.035
Qpre
59.06 0.202 0.128 0.66 0.6 0.0275 0.05 24.87 101.73 0.020 24.87 122.41 0.024 24.87 140.81 0.028 24.87 194.91 0.039 24.87 224.20 0.045
Qduring
59.06 0.202 0.128 0.66 0.5 0.045 0.01 56.14 65.23 0.011 56.14 78.49 0.013 56.14 90.28 0.015 56.14 124.97 0.021 56.14 143.75 0.024
Qpost
PROJECT SITE
PROJECT SITE
RECONNAISSANCE SOIL MAP FOR JOHOR
PROJECT SITE
APPENDIX H : PAGE 1
CALCULATION SHEET : SOIL LOSS ESTIMATION / EROSION RISK Calculation by: M Johari A Malik
1. Qpre (Before Construction or Existing Condition) and Qpost (During Construction Condition)
Determination:-
b) K Factor :
Kpre = 0.051 (represents top soil or surface soil)
Kpost = 0.051 (represents top soil or surface soil, same soil shall be used for filling and levelling)
c) C Factor :-
Cpre = 0.35 (Bushes / Shrubs 50% Cover)
Cpost = 1.00 (Bare Soil) and 0.05 (Compacted gravel layer)
d) P Factor :-
Ppre = 1.00 (No support practice)
Ppost (No BMP’s) = 1.00 (No support practice)
Ppost (With BMP’s) = 0.50 (To apply Sediment Containment - Silt Trap)
APPENDIX H : PAGE 2
CALCULATION SHEET : SOIL LOSS ESTIMATION / EROSION RISK Calculation by: M Johari A Malik
SOIL LOSS /
Symbol R K s LS C P
EROSION RISK
PROJECT : TANJUNG LANGSAT
CONDITION
(ton/ha) LS Factor from Wischmeier Equation
Unit MJ.mm/ha.yr % - - - Tonne/ha/year
(hr/MJ.mm) SITE Sheet Length, λ (m) Ψ m
Before Construction TANJUNG LANGSAT 17,500.00 0.051 0.31 0.15 0.35 1 48.281 600.00 22.13 0.2
or TANJUNG LANGSAT
Existing Condition
During Construction 17,500.00 0.051 0.05 0.13 1 1 116.242
TANJUNG LANGSAT TANJUNG LANGSAT 600.00 22.13 0.2
(No BMP’s)
1. Ypre (Before Construction or Existing Condition) and Ypost (During Construction Condition)
Y = 89.6 (V × Qp )0.56 (K × LS × C × P)
Determination:-
Before Construction or 1197.37 0.051 0.15 0.35 1 28.250 210.030 0.035 59.325 0.361
TANJUNG LANGSAT
Existing Condition
During Construction 1197.37 0.051 0.13 1 1 24.870 224.200 0.045 67.149 1.103
TANJUNG LANGSAT
(No BMP’s)
During Construction 1197.37 0.051 0.13 0.05 0.5 24.870 224.200 0.045 67.149 0.028
TANJUNG LANGSAT
(With BMP’s)
U
0
270
90
180