Professional Documents
Culture Documents
Rupture of Piping and Fire in Syn Loop
Rupture of Piping and Fire in Syn Loop
As part of the plant upgrade activities, synthesis The fire caused damage to the equipment, pipe-
loop Boiler feed water exchanger (123-C) of Am- lines, instrument and electrical cables, insulation
monia Unit II was replaced in February 2012 etc. in the vicinity, which were assessed and re-
(Figure 1) due to its’ past tube plugging history. stored. The plant operations were fully normal-
The elevation of inlet nozzle of the new 123-C ized by 30th November 2017.
was higher than the previous one. To accommo-
date the change in inlet nozzle elevation of the
123-C, a pipe spool piece of 1.3-meter (4ft)
length was inserted into the vertical leg of piping
Figure 2. Isometrics of pipeline from 123-CA Figure 3. Location of failed spool segment of
exit to 123-C inlet, showing location of spool vertical leg of synthesis gas from 123-CA exit to
piece inserted during revamp in February’2012 123-C inlet
Figure 4. API 941 Nelson Curve showing operating point of three identified pipeline of synthesis loop
and CSB recommendation line (red color) for carbon steel
The materials of construction for these three 123-C outlet to 121-C inlet (ASTM A53 Gr
pipelines are as follows: B).
105-D converter outlet to 123-CA inlet As shown in Figure 4, none of these pipelines are
(ASTM A335 Grade P22). susceptible to HTHA as per Nelson curve for the
material of construction used.
123-CA outlet to 123-C inlet (ASTM A335
Grade P22).
Out of the 3 pipelines subjected to further assess- • 123-CA tubes are of A335 Grade P22 material
ment, only one pipeline (123-C outlet to 121-C and 123-C tubes are of A335 Grade P11
inlet line) was of carbon steel (A53 Grade B) material.
having operating point of 106.5 bar (1550 psi) • 123-CA and 123-C exchanger heads are of
hydrogen partial pressure and 176°C (350°F), A335 Grade P11 material. These operating
which also lies well below the recommended points were also mapped on Nelson curve
curve by CSB. (same points in Figure 4). Both point lies
inside safe region and hence are not
Therefore, none of the pipelines are susceptible susceptible to HTHA.
to HTHA as per CSB recommendations due to
the material of construction used and the • Converter outlet exchanger 122-C is of SS-
particular process parameters operated within. 304 material. Hence, it is also not susceptible
to HTHA.
Parameter Value
Total shell thickness 201 mm
(7.91”)
Shell thickness without outer layer 192 mm
(7.55”)
Thickness required as per ASME 196.1
BPVC Sec VIII Div-2, edition mm
1980 for original design condition (7.72”) Figure 7. Bulged portion of converter was as-
Table 2. Thickness calculation summary sessed, and patch of required grade and dimen-
sion was welded
From Table 2 it is concluded that the available
thickness of inner layers (ignoring outermost Metallography assessment of affected area was
layer assuming all other layers and weld joint of also carried out and no microstructure degrada-
equipment are intact) are: tion was observed.
Adequate for before revamp operating conditions
• One leg of the structure support of the 123-C
of 196 bar (2842.7 psi)
buckled at the area adjacent to the fire (Figure
Adequate for post revamp operating conditions of 8), which was replaced as per existing config-
181.4 bar (2631 psi) uration (Figure 9). Other bracket supports to
Inadequate for original design conditions 234.4 shell weld were checked by NDT methods.
bar (3399.7 psi).
In addition to code calculated thickness, a finite
element analysis (FEA) was carried out to evalu-
ate the portion of equipment remaining after re-
moving the 9mm thick outer layer at the bulge
region. It was observed the linearized stress in-
tensities in the local bulge affected area (without
Positive material identification (PMI) of the in- PMI was also carried out on the remaining line
serted 1.3-meter spool piece revealed that Low segments and elbows of the removed line
temperature carbon steel A333 Grade 6 (incor- wherein it was found that except for the 1.3-me-
rect material of construction for this service) was ter spool, the entire rest of the pipeline parent ma-
inserted. Since the existing material was ASTM terial and weld joints confirmed to A335 Grade
A335 Grade P22, the 1.3-meter spool piece P22.
added should also have been of same material.
LTCS (A333 Grade 6) is not recommended as per Hence in the welding area three different metal-
API 941 and discontinued since 1991 for such lurgies were present which is not a standard en-
service as synthesis gas at the operating temper- gineering practice for such critical high pressure
ature being handled by pipe. piping.
HTHA Corrosion
Visual inspection of failed spool piece revealed
blisters on the surfaces. Since the operating point
of this pipeline lies above the CS line on Nelson
curve (as can be seen from Figure 4) and being in
high temperature and pressure environment of
hydrogen for more than 5 years, HTHA was evi- Figure 12. Blister crack depth on the edge
dent in the form of blistering. Here it is worth where fracture take place
noting that there was no visible effect of HTHA
(like blistering, fissuring) on A335 Gr P22 side
of the pipeline.