Safe Work Method Statement

Project Name: SAR3 PH-1


Company Name: Harsha Vardhan Air conditioning Engineers PVT LTD Activity /Trade: Shaft Duct Installation
Address: Bowenpally Office Contact No:04027796632
Project Manager: ANAND REDDY Contact No: 9100029121

Procedure (in steps) Possible Risk Rating Control Measures Person who
(Break the job down into Hazards (See below) (Describe what action or procedure will be taken to will ensure
steps. Each step should (Identify the hazards associated eliminate or minimize the risk of injury or damage. Use the this happens
accomplish some major with each step. Examine each Hierarchy of Controls below as a guide
tasks and be in logical to find possibilities that could 1. Eliminate the Hazard
sequence.) lead to an accident or potential 2. Substitute the material or equipment
harm arising.) 3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
Manpower Mobilization Untrained worker, unauthorized M 1. Only inducted worker shall be deputed at the work place. Supervisor
entry 2. Given Tool Box Talk to all workers. What are / Engineer
activities to be carried out, what are the hazards, what
are the precautions that are to be taken should be conduct
before start of work.
3. Height Work activity permit shall be taken before start
of work from concern engineer. and HSE Dept.
4. Required PPE's use by workers.
5. Area shall be barricaded to prevent unauthorized entry.
6. Access & egress should be clear, use of required PPE's
only train person deployed for work
7. Job Specific training should be conduct.
Mobilization of Hand Damaged hand tools, M 1. Avoid damaged hand tools for use. Supervisor
tools and power tools Uninspected hand tools, 2. Inspect all tools at the time of entry to site and maintain / Engineer
improper guarded power tools record.
3. Only inspected hand tools shall be use at site.
4. Approved tools should be use.
5. Inspect power tools before entering into site and work
location
Power cable routing & Electrocution, Short circuit, M 1. Proper insulated power cable with industrial plug tops Supervisor
must be used
isolation of power Slip, trip falls, Damaged cable. / Engineer
2. Cable should be at safe height from ground or man
cables movement
3. No cable should be on the ground
4. Power Cable should be free from water
5. Damaged cable shouldn’t be used at work premises
6. ‘S’ hooks with proper insulation
should be used for cable running
from Power source or PDB to Work
Area
7. No two power cables should touch each other

Procedure (in steps) Possible Risk Control Measures Person who


(Break the job down into Hazards (Describe what action or procedure will be taken to eliminate or will ensure this
Rating
steps. Each step should (Identify the hazards associated (See minimize the risk of injury or damage. Use the Hierarchy of happens
accomplish some major with each step. Examine each to below) Controls below as a guide
task and be in logical find possibilities that could lead 1. Eliminate the Hazard
sequence.) to an accident or potential harm 2. Substitute the material or equipment
arising.) 3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
Duct Erection in Shaft Falling of ducts in duct and H Obtain work Permit to enter shaft Engineer in
due to failure of rope on Ensure a good grip before exerting force to lift, push or pull charge
personal head. the material / tool and ensure manual lifts should not
Finger cut
exceed beyond 20kgs on each person.
Cut injury on
arm/head from Only trained and experienced team shall be engaged with
contact with sharp under competent supervisor. Position the Ducts with 4 or
edges of ducts. more operators. Bend and lift with legs/arms, keep back
straight and do not twist (turn with feet) Ensure closing of
Muscle back strain while
shaft just beneath of working floor.
drilling
Person must be stand within the hand rails on working
• Man, and materials falling
platform and keep legs on same platform.
during duct joint.
Ensure use of safety harness with strong anchorage.
Barricaded the areas and posts signage to prevent
entry of others
People should hold the AC units at both ends with proper grip
then lift the Ac unit up to ceiling level using chain pulley block
to support with rods.
Use inspected and green tagged mobile scaffold to ensure
appropriate positioning and easy reach position.
1. Using appropriate PPE’s (Hard Hats, Gloves, Shoes, Reflective
jacket, Full body Harness)
Barricading, Shaft Fall from Hight M • Proper working Platforms to be provided. Supervisor /
closing, Signage Struck in between objects • Sharp Edges of the debris will be removed at regular intervals. Engineer

installation • Regular debris removal from the work location

Removal of Debris Manual Handling Slips, trips M All workers must practice correct manual handling techniques. Supervisor
and falls • All mandatory PPE to be worn, including correct gloves for the / Engineer
Vehicle movement task.
Load shift Falling • All demolished materials to be placed in the designated debris
objects yard
immediately after being demolished.
• Make sure clear pathway to the debris yard is always
maintained
throughout the demolition works.
• Restrict manpower movement during demolition work activity.
• Exclusion zone in place during truck loading

E - Extre me Risk: The hazard has the potential to kill or permanently disable a person M - Medium Risk: The hazard has the potential to cause a LTI <
7 days
H - High Risk: The hazard has the potential to cause an LTI ≥ 7 days L - Low Risk: The hazard has the potential to cause a minor injury that will not
disable a person (ie: Nil LTI)
Safe Work Method Statement

We agree that we have been consulted in the hazards and control measures and agree to complete the work in accordance with our Work Method Statement (WMS).
We have been provided with training in all tasks outlined in our WMS and in the Codes of Practice applicable to our work.

Employee / Worker Signature Date Employee / Worker Signature Date


1. / / 8. / /

2. / / 9. / /

3. / / 10. / /

4. / / 11. / /

5. / / 12. / /

6. / / 13. / /

Reviewed by: Signature: Date:


(Principal Contractor’s Representative)

Any changes, additions or deletions made to this S WMS are to be covered with the above personnel and the Principal Contractor ’s representative at a Toolbox
meeting (Record date and time of Toolbox meeting below):

Date: Time:
Comments:

A copy of the Toolbox Meeting must be attached to this S W M S.