Professional Documents
Culture Documents
(SWMS) Shaft Work Duct Erection
(SWMS) Shaft Work Duct Erection
Procedure (in steps) Possible Risk Rating Control Measures Person who
(Break the job down into Hazards (See below) (Describe what action or procedure will be taken to will ensure
steps. Each step should (Identify the hazards associated eliminate or minimize the risk of injury or damage. Use the this happens
accomplish some major with each step. Examine each Hierarchy of Controls below as a guide
tasks and be in logical to find possibilities that could 1. Eliminate the Hazard
sequence.) lead to an accident or potential 2. Substitute the material or equipment
harm arising.) 3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
Manpower Mobilization Untrained worker, unauthorized M 1. Only inducted worker shall be deputed at the work place. Supervisor
entry 2. Given Tool Box Talk to all workers. What are / Engineer
activities to be carried out, what are the hazards, what
are the precautions that are to be taken should be conduct
before start of work.
3. Height Work activity permit shall be taken before start
of work from concern engineer. and HSE Dept.
4. Required PPE's use by workers.
5. Area shall be barricaded to prevent unauthorized entry.
6. Access & egress should be clear, use of required PPE's
only train person deployed for work
7. Job Specific training should be conduct.
Mobilization of Hand Damaged hand tools, M 1. Avoid damaged hand tools for use. Supervisor
tools and power tools Uninspected hand tools, 2. Inspect all tools at the time of entry to site and maintain / Engineer
improper guarded power tools record.
3. Only inspected hand tools shall be use at site.
4. Approved tools should be use.
5. Inspect power tools before entering into site and work
location
Power cable routing & Electrocution, Short circuit, M 1. Proper insulated power cable with industrial plug tops Supervisor
must be used
isolation of power Slip, trip falls, Damaged cable. / Engineer
2. Cable should be at safe height from ground or man
cables movement
3. No cable should be on the ground
4. Power Cable should be free from water
5. Damaged cable shouldn’t be used at work premises
6. ‘S’ hooks with proper insulation
should be used for cable running
from Power source or PDB to Work
Area
7. No two power cables should touch each other
Removal of Debris Manual Handling Slips, trips M All workers must practice correct manual handling techniques. Supervisor
and falls • All mandatory PPE to be worn, including correct gloves for the / Engineer
Vehicle movement task.
Load shift Falling • All demolished materials to be placed in the designated debris
objects yard
immediately after being demolished.
• Make sure clear pathway to the debris yard is always
maintained
throughout the demolition works.
• Restrict manpower movement during demolition work activity.
• Exclusion zone in place during truck loading
E - Extre me Risk: The hazard has the potential to kill or permanently disable a person M - Medium Risk: The hazard has the potential to cause a LTI <
7 days
H - High Risk: The hazard has the potential to cause an LTI ≥ 7 days L - Low Risk: The hazard has the potential to cause a minor injury that will not
disable a person (ie: Nil LTI)
Safe Work Method Statement
We agree that we have been consulted in the hazards and control measures and agree to complete the work in accordance with our Work Method Statement (WMS).
We have been provided with training in all tasks outlined in our WMS and in the Codes of Practice applicable to our work.
2. / / 9. / /
3. / / 10. / /
4. / / 11. / /
5. / / 12. / /
6. / / 13. / /
Any changes, additions or deletions made to this S WMS are to be covered with the above personnel and the Principal Contractor ’s representative at a Toolbox
meeting (Record date and time of Toolbox meeting below):
Date: Time:
Comments: