Professional Documents
Culture Documents
WMS For Management Washroom
WMS For Management Washroom
displayed.
j. All the material properly inspected through client
k. Only competent person for task
l. Material will be shifted by tractor trolley, wheel barrow and manually
m. More than 20kg will be handle two or more person
n. 20 feet length of scaffolding pipe will be highlighted with barricading tape
during shifting.
o. All the tools will be inspected by orient
5.Demolishing Work
a. Wall will be demolished manually with the help of hammer and worker will be
wearing face shield during hammering work.
b. No worker will be working or standing within the line of fire.
c. Dismantling of existing reinforced beam, slabs and masonry walls will be done
as proposal
d. Ms grill will be removed manually by wearing leather gloves to avoid any hand
injury.
e. After removal of all item re-useable material will be placed at IBEX area in the
custody of PMI
f. Work at height will be done as per requirement.
g. Dismantling of floor, walls and slab will be done as per requirement.
h. Safe Distance will be maintained from cables and equipment.
i. Activity will be performed under the site and EHS supervision. 19. End
of the day, Area issuer and owner will ensure the safe working before
permit closer.
j. Activity will be performed under the supervision of Site and EHS
supervision.
k. No PMI property will be damaged during the job.
l. Align with area owner and issuer at the end of the days before closer
of permit to ensure working according to the plan.
Revision: 0.0
Niaz
construction METHODSTATEMENT Issue date: MOC#
company For GENTS’ Washroom 28-09-2022
a. Excavation work will be started and will be done with Hilti machine and hoe
b. Excavation work will be done for main hole and pipe installation.
c. Excavated material will be kept at 2 feet from excavated area.
d. Excavation depth /specs will be as per requirement.
7.Debris Shifting
A. Brick work will be done after plinth beam & column installation
B. The quality of bricks to be used in masonry construction should be of standard
specifications (good brick earth, thoroughly burnt and deep cherry red or
copper in color).
C. Bricks are shifted at site with the help of tractor trolley.
D. Mortar should be of the specified grade and materials used for mortar should
be of standard specifications.
E. Necessary and suitable scaffolding should be provided to facilitate the
construction of a brick wall
F. All workers will follow the covid.19 protocols.
G. Social distancing will be maintained.
Revision: 0.0
Niaz
construction METHODSTATEMENT MOC#
FOR GENTS’ WASHROOM Issue date:
company
28-09-2022
A. Providing and carrying out termite proofing under and all sides of
foundations and over 1:4:8 floor concrete layer or prior to laying of 1:2:4
concrete floor, using BIFLEX - FMC (U.S.A.) or AGENDA 25EC
manufactured by Bayer with a pressure ensuring at least 3" penetration in
the soil of the area to be treated. The Contractor will provide a guarantee for
a period of fifteen years against infestation of termite in the shape and mode
approved by the Consultant stating that incase of infestation, additional
treatment will be provided by the contractor at no extra cost to the Owner as
per specifications and/or as directed and approved by the Engineer.
Revision: 0.0
Niaz
construction METHODSTATEMENT MOC#
FOR GENTS’ WASHROOM Issue date:
company
28-09-2022
All required material will be making outside factory will be installed at desired
point according to drawing
Aluminum door, window, roller blinds with channel of approved shade and
color will be fixed by competent worker
18.Paint work
20.Plumbing work
A. PPR AND UPVC Piping fixing complete plumbing system will be done by
Revision: 0.0
Niaz
construction METHODSTATEMENT MOC#
FOR GENTS’ WASHROOM Issue date:
company
28-09-2022
competent plumber
B. Fixing of European wall hung water closet with wall concealed type tank
C. Fixing of vanity like bottle tarp, drain pipe with complete accessories
D. Fixing of Muslim shower with bib cock with complete accessories
E. Fixing of shower set complete in rest with satisfaction of entire project
F. Mixer, wash room accessories, multi floor tarp with S.S floor drain
21.Night activity
a) Use proper lighting for best visibility
b) Prevent noise and vibration when possible
c) Make sure workers get proper rest take a way for your construction night your
plan
d) No work will be done lonely
e) Reflective jacket will be provided to workers
Prepared By Reviewed By
M.BaqiBillah Javeed Hussain
Signing Authority Niaz Co.
Reviewed By Approved by