Kolar Saleble Area (Sft) 574,841 FFV Saleable Area (Sft) 759,911
Sl
Particulars Amount
No Unit Qty Rate Amount Cost/Sft Cost/Sft Remarks
Spent
1 Civil Works
Main Gate, Security Cabin & Association Office Sft 800 2,500 2,000,000 3 2,387,987 3
Compound Wall (Precast Compound Wall - 7' ht) Rft 3,950 850 3,357,500 6 11,242,806 15
2 Site Marking
Site Name Boards No's 380 1,500 570,000 1.0 263,199 0.3
Sub Total for Site Marking Works 620,000 1.1 353,199 0.5
3 Road Works