Professional Documents
Culture Documents
Hoshiarpur
Hoshiarpur
Hoshiarpur
Closure formats
Name of District(s) : Hoshiarpur Project Implementing Agency (PIA) : Punjab State Power Corporation Ltd.
Name of Scheme : DDUGJY-New Project Management Agency (PMA) : Medhaj Techno Concept Pvt. Ltd.
3 Total funds reeceived under the Project(s) 1689.812 10.469 1700.281 From Format-F
4 Total completion cost (excl State Taxes) 1873.999 10.212 1884.211 From Format-F
5 State Taxes (to be borne by State Govt) 168.395 0.000 168.395 From Format-F
6 Total completion cost (incl State Taxes) (4+5) 2042.393 10.212 2052.605
B. Physical Details:
Covered in Final
Quantities as per Quantities Balance Reasons for variation
S. No. Particular addition to Completed
Sanctioned DPR Executed Quantity agreed by State Govt.
Sanction Quantities
1 2 3 4 5=3-4 6 7=4+6 8
It is certified that the infrastructure created under other State/Central schemes has not been claimed under present proposal and vice versa.
(#) As per decision of Monitoring Committee meeting held on 12.12.2018, villages covered in the list circulated by Ministry of Rural Development (MORD) have
only been considered under SAGY component.
(*) As per Saubhagya guidelines (Chapter -II, Clause no.2.7), "in case entities are not able to find adequate number of BPL households in the project area under
DDUGJY, to meet the target of BPL households electrification already sanctioned under DDUGJY, PIAs are allowed to release electricity connections to
equivalent nos. of remaining households in accordance with Saubhagya. Such Households shall not be claimed under Saubhagya.
** As per Saubhagya Guidelines, any un-electrified Household not found eligible as per SECC data, would also be provided Electricity connection. An amount of Rs.
500 per HH would be recovered for release of connection by the Discom/Power Deptt in ten (10) installments of Rs. 50 each. An amount equivalent to such recovery of
applicable charges from the Households shall be deducted from the eligible Grant from Govt of India payable to Discom / Power Deptt.
3 Only those SAGY villages that are listed by Ministry of Rural Development (MORD), are covered under SAGY component Yes
DISCOM/PIA has ensured necessary arrangements for maintenance of the assets created under the scheme, revenue sustainability at the
4 Yes
DISCOM level.
All willing BPL households have been given free electricity connections in connections for other than BPL Households (if any) have been given
5 No household
as per Saubhagya Guidelines.
electrification work
Access to electricity to all rural households has been ensured. The Service Connections released duly segregating BPL & other than BPL (SECC has been covered
6 under DDUGJY
poor and non-poor as per Saubhagya Guidelines) has been submitted and will not be claimed under Saubhagya again.
Technical specification of Standard Bidding Documents (SBD) / REC Construction standards have been followed generally during
7 Yes
implementation of DDUGJY project. The deviations, if any, are approved by Competent Authority of PIA.
Quality Assurance Mechanism has been implemented as per the guidelines issued by REC. All observations/defects under Quality Control
Mechanism have been complied with/rectified. If there are any pending rectifications/ compliances, appropriate deductions shall be made from
8 Yes
the payment to be made to the contractor and the balance rectification works shall be completed by PIA. The amount so deducted shall utilised
by PIA for this rectification work and no additional amount shall be claimed from REC against the same
The interest earned on unutilized subsidy has been remitted to Ministry of Power Bank Account on regular basis. Also, Accrued interest on final
9 Yes
release of capital subsidy (if any) shall be remitted to MoP’s account
3 Interest income towards initial advance, penalties, permanent deduction, LD have been credited to project account. Yes
In case any liabilities to the Contractor arise in future, the same shall be dealt according to the Contract and shall not be claimed from REC.In
4 case any amount is to be recovered from the Contractor in future viz. CPBG, LD etc., the same shall be remitted to REC/MoP. Yes
All payments including Taxes & Duties and Fees (both central & state) have been claimed on actual basis. REC shall not be liable for non-
5 payment of any bills to contactor and taxes & duties to any statutory authority. Yes
Final time extension has been determined and Liquidated damages, if any, has been settled as per contract and with approval of competent
6 Under process
authority of the PIA.
Accounts Officer,
M/S PP industries Pvt Ltd. Bathinda Non-APDRP, PSPCL, Patiala
1 2 3 4 5 6 7 8 9 10 11 12 16 17 18
1 Village Covered Nos. 252 386 386 386
a.UE Villages Nos. NA NA NA NA
b. IE Villages Nos. 250 384 384 384
c. SAGY Villages Nos. 2 2 2 2
2 Total HHs Electrified Nos.
A. Electrification of UEV - - 0 - - 0 - - 0 - - 0
Total Cost of (A) Electrification of UEV 0 0 0 0
B. Feeder Separation Nos. - - 0 - - 0 - - 0 - - 0
Total Cost of B. Feeder Separation Nos. - - 0 - - 0.000 - - 0 - - 0
ii
Augmentation of 11 kv Feeder With 50sq.mm. (Rabbit) Ckt. Km. - - 0 - - 0.000 - - 0.000 - - 0.000
Page 4 of 16
Project cost as per executed work Total Project cost as per completion
Sanctioned Parameters Awarded Parameters
(Turnkey Execution) Proposal
Sr. No. Item of Work Unit Cost per unit Cost per unit Cost per unit Cost per unit
Qty Total Cost Qty Total Cost Qty Total Cost Qty Total Cost
1 2 3 4 5 6 7 8 9 10 11 12 16 17 18
v Conversion of Existing overhead line to ABC
Ckt. KM 5.883 3.50 20.591 - - 0.000 0.000 -
3Cx95+70sq.mm. (bare messanger cum neutral)
Total (6): Aug of LT Line 20.591 - - 7.067 0.382 0.382
7 Distribution Transformer-R&M (Earthing) Nos. 0.039 11 0.429 0.064 18 1.145 - 0.000 -
Total (6): Distribution Transformer-R&M (Earthing) 0.429 1.145 0.000 0.000
E Metering
1 Feeder Metering Nos - - 0 - - 0 - - 0 - - 0
2 DTR Metering Nos - - 0 - - 0 - - 0 - - 0
3 Consumer Metering - - 0 - - 0 - - 0 - - 0
i. New meters Nos - - 0 - - 0 - - 0 - - 0
ii. Shifting of meters Nos - - 0 - - 0 - - 0 - - 0
iii. Replacement of meters Nos. 0.025 60,872 1521.800 0.007 35,268 245.076 0.007 35,226 244.784 0 35,226 244.784
Total Cost of E. Metering (In Rs.) 1521.800 - 245.076 244.784 244.784
-
F. System Strengthening -
1 New 33 KV or 66KV or 22 KV s/stn Nos. -
Total (1): New S/stn -
2 11KV Bay With VCB Nos. 5.432 - 0.000 - - 0 - - 0 - - 0
Total (3): (In Rs.) -
Page 5 of 16
Project cost as per executed work Total Project cost as per completion
Sanctioned Parameters Awarded Parameters
(Turnkey Execution) Proposal
Sr. No. Item of Work Unit Cost per unit Cost per unit Cost per unit Cost per unit
Qty Total Cost Qty Total Cost Qty Total Cost Qty Total Cost
1 2 3 4 5 6 7 8 9 10 11 12 16 17 18
7 New LT Line -
i 3.960 - 0.000 0 0 0
New LT Line With 50sq.mm. (Rabbit) Ckt. Km. - - - - - -
G. Total (A to F) (incl all taxes) Rs. In Lakhs 2,407.086 2,365.956 1,996.884 1,996.884
(i) Others (Cost Of GSM and GPRS Modems) Nos. - - - 0.047 502 23.638 0.047 330 15.539 0.047 330 15.539
H. (ii) CEI Fees - - - - - - - - 6.052 6.052
(iii) Price Variation - - - - - - - - 23.918 - - 23.918
Total Cost of H. Rs. In Lakhs - 23.638 45.509 45.509
I. State Taxes (to be borne by State Govt) - - - - - - - - - - - -
a. SGST - - 183.591 - - 180.454 - - 165.908 - - 165.908
b. VAT - - - - - - - - - - - -
c. Works Contract Tax (WCT) - - - - - - - - - - - -
d. Entry Tax - - - - - - - - - - - -
- - - - -
e. Building & Other Construction Workers Welfare Cess - - - 2.487 - - 2.487
Page 6 of 16
Project cost as per executed work Total Project cost as per completion
Sanctioned Parameters Awarded Parameters
(Turnkey Execution) Proposal
Sr. No. Item of Work Unit Cost per unit Cost per unit Cost per unit Cost per unit
Qty Total Cost Qty Total Cost Qty Total Cost Qty Total Cost
1 2 3 4 5 6 7 8 9 10 11 12 16 17 18
2. Individual item in each component executed under the project are as per guidelines of the scheme. No item which is not part of the project, has been claimed under the proposal
3 The cost of DT meters is already included in the cost of activity of Installation of DT, so no separate head for Dt meters activity was made.
Project Manager JE/Non APDRP Cell AE/Non-APDRP Cell Sr.XEN/Non-APDRP Cell Engineer-in-chief
M/S PP Industries Pvt.Ltd. Bathinda PSPCL Jalandhar PSPCL Jalandhar PSPCL Jalandhar RE & APDRP, PSPCL, Patiala
Page 7 of 16
Format F
Details of Expenditure / Fund received in of the project
It is Confirmed that the account has been linked with PFMS and all the entries have been
made on the PFMS
(*) i. Applicable portalsupply of materials as per SBD.
on direct
Ii. There is no cost overrun due to grant of extension of time for execution due to
Financial Advisor
PSPCL, Patiala
Page 12 of 16
Format-G
UTILISATION CERTIFICATE
Financial Advisor
PSPCL, Patiala
Page 13 of 16
Format-G
UTILISATION CERTIFICATE
Financial Advisor
PSPCL, Patiala
Page 14 of 16
Annex. 4
Undertaking
With regards to closure of above mentioned project and release of final installment as per closure cost, Punjab State
Power Corporation Limited(PSPCL), hereby undertakes that:-
a).
Accrued interest on final release of capital subsidy (if any) shall be remitted to MoP’s account.
b). Village-wise infrastructure created under the project shall be uploaded in online web portal i.e.,
ddugjy.gov.in by PIA/DISCOM.
c). In case any liabilities to the Contractor arise in future, the same shall be dealt according to the Contract
and shall not be claimed from REC.
d). In case any amount is to be recovered from the Contractor in future viz. CPBG, LD etc., the same shall be
remitted to REC/MoP.
e).
3-Tier Quality Control Mechanism has been implemented as per the guidelines. All observations/ defects
under Quality Control Mechanism have been complied with/rectified. No any rectifications/compliances
are pending.
Engineer-in-chief
RE & APDRP, PSPCL
Patiala
Format-G
UTILISATION CERTIFICATE
Financial Advisor
PSPCL, Patiala
Page 16 of 16