Indiana Gratings Pvt. Ltd.

D7 Unit
INSPECTION REPORT DURING WELDING
Client Date
Drawing No. : Report no
WO. NO. : Rating :

Material WPS No
Material Thk. WPQ No
Welder Name Welder No
Acceptance Standard

EXAMINATION

Sr. No. Observation Remarks

Required observed ok/not ok

1 Essential variables
2 Current
3 Voltage
4 Travel speed
5 Wire feed speed
6 sheilding gas flow
7 backing gas flow for root
8 Pre heating temperatue
9 Interpass temperature
10 Cleaning between passes
11 No of layers/ Passes
12 Back gouging/chipping/grinding
13 Welding sequence as per weld Map
14 Weld size as per WPS
15 correct use of consumables
16 Distrotion controls
17 any other non sepcified parameters
stiffners/ temp supports/ cleats

Remarks : Weld Visual found SATISFACTORY [ √ ] / UNSATISFACTORY [ ]

Checked By Verified / Witness By

SIGNATURE

NAME

DATE

QC IGPL RWC

FORM NO. : QC/BM/F/30/R0