Professional Documents
Culture Documents
TG Chapter 7
TG Chapter 7
1. AA Co. enters into a construction contract with a customer. PFRS 15 requires AA to do all of the following
at contract inception, except
a. assess the customer’s ability and intention to pay the contract price on due date.
b. assess whether the promised goods and services in the contract are individually distinct.
c. determine if the performance obligation(s) identified in the contract is(are) satisfied over time or at a
point in time.
d. estimate the total construction costs at completion.
2. “Step 2” of the revenue recognition principles of PFRS 15 requires an entity to identify the performance
obligations in the contract at the inception of the contract. Which of the following statements is not
correct regarding this step?
a. An entity shall treat each promise in the contract to transfer a distinct good or service as a separate
performance obligation.
b. An entity shall treat a promise to transfer a distinct bundle of goods or services as a separate
performance obligation.
c. An entity shall treat a promise to transfer a series of distinct goods or services that are substantially the
same and have the same pattern of transfer to the customer as a separate performance obligation.
d. An entity shall treat all promises in a single contract as a single performance obligation regardless of
the nature of those promises, if those promises are negotiated with the customer as a single
package.
4. At contract inception, AA Co. determines that its performance obligation in the contract is a single
performance obligation that is satisfied over time. AA Co. uses the cost-to-cost method to measure its
progress in the contract. How much is the profit recognized in 20x1?
a. 118,000 c. 122,000
b. 120,800 d. 132,200
5. AA Co.’s performance obligation in the contract is satisfied over time. However, the outcome of the
performance obligation cannot be measured reasonably but contract costs incurred are recoverable. How
much is the revenue recognized in 20x1?
a. 708,000
b. 590,000
c. 118,000
d. 0
6. AA Co.’s performance obligation in the contract is satisfied at a point in time, i.e., when the construction is
completed and control over the promised good is transferred to the customer. How much is the revenue
recognized in 20x1?
a. 708,000
b. 590,000
c. 1,200,000
d. 0
no revenue is recognized until the project is completed and turned over to the customer
7. AA Construction Co. entered into an ₱80M fixed price contract for the construction of a private road for
BB, Inc. The performance obligation on the contract is satisfied over time. AA measures its progress on the
contract using the “cost-to-cost” method. The estimated total contract cost is ₱40M. AA incurred the
following costs in the first year of the construction:
a. 180,000
b. 200,000
c. 220,000
d. 240,000
(a)
Costs incurred to date (1) 120,000
Estimated costs to complete 240,000
Estimated total contract costs (2) 360,000
Percentage of completion (1) ÷ (2) 33 1/3%
9. What amounts are presented in Contractor Co’s. statement of financial position under <List A: Traditional
accounting> and <List B: PFRS 15>?
Gross amount due from (to) cust. Contract asset(liability)
a. (20,000) (20,000)
b. 20,000 20,000
c. 20,000 (20,000)
d. (40,000) (40,000)
Traditional accounting:
Construction in progress
Costs
incurred 120,000
Gross profit (b) 80,000
12/31/x1 200,000
(b)
Revenue for the year (see previous solution) 200,000
PFRS 15:
Contract liability
180,000 Progress billing
Revenue in 20x1 (see prev. sol.) 200,000
Debit balance - Asset 20,000
10. In 20x1, Silverchair Co., a construction company, enters into a contract with a customer for the
construction of a building. The contract states a fixed fee of ₱8,700,000. Silverchair’s performance
obligation in the contract is satisfied over time. Silverchair uses the ‘cost-to-cost’ method in measuring its
progress in the contract. Information on the contract follows:
20x1 20x2
Estimated total costs at completion 6,525,000 6,960,000
Page |4
20x1 20x2
Contract price 8,700,000 8,700,000
Estimated total costs at completion (6,525,000) (6,960,000)
Expected total gross profit 2,175,000 1,740,000
Percentage of completion 15% 65%
Profit to date 326,250 1,131,000
Profit in prior yr. (326,250)
Profit for the yr. 326,250 804,750
Revenue to date in
20x1 (3,000,000)
Revenue in 20x2 3,000,000
Since the contract is 100% complete in 20x2, the transaction price must be equal to the ‘revenue to date in
20x2’ of ₱6,000,000 (see previous solution).
In 20x1 and 20x2, it was not highly probable that the project will be completed on time. However, in 20x3,
ABC assessed that the project will be completed earlier than originally expected and thus it is now highly
probable that the incentive payment will be received.
(1)
The costs incurred each year are computed as follows:
20x1: 2.4M costs incurred to date – 0 costs incurred in previous yrs. = 2.4M
20x2: 4.575M – 2.4M = 2.175M
20x3: 6.125M – 4.575 = 1.55M
Salamagi Co. estimated a ₱5,000,000 gross profit from the project. The percentage of completion method will
be used. In 20x1, Salamagi billed the customer for 50% completion of the project. The customer accepted all
the billings, except one for 10% which was accepted on January of the following year. All the accepted billings
were collected during the year except an 8% billing which was due January of the following year.
15. What is the amount of profit recognized from the contract in 20x1?
a. 2,500,000 c. 2,720,000
b. 2,650,000 d. 2,900,000
20x1
Expected gross profit (given) 5,000,000
Multiply by: % of completion (given) 50.00%
Profit to date 2,500,000
Profit in previous years -
Profit for the year 2,500,000
16. What is the total amount of collections from the billings in 20x1?
a. 5,760,000 c. 6,760,000
b. 6,400,000 d. 7,400,000
The entity uses an input method based on costs incurred to measure its progress towards complete
satisfaction of the performance obligation. The customer obtains control of the elevators when they are
delivered to the site in December 20X2, although the elevators will not be installed until June 20X3. The costs
to procure the elevators are significant relative to the total expected costs to completely satisfy the
performance obligation. The entity is not involved in designing or manufacturing the elevators.
As of December 31, 20X2, the entity has incurred total costs of ₱500,000, excluding the cost of the elevators.
Page |7
Control over the elevators is already transferred to the customer (as stated in the problem). However, the
incurrence of the cost of the elevators does not properly reflect the percentage of completion of the contract
because the elevators are not yet installed. Accordingly, the entity shall adjust its measure of progress to
recognize revenue only to the extent of the costs of the uninstalled elevators. The cost of goods sold
recognized in 20X2 will also include this cost. As a result, the entity recognizes zero profit from the elevators
in 20X2.
Percentage of completion = (500,000 costs incurred, excluding cost of elevators) ÷ (2.5M ‘other costs’ only,
excluding costs of elevator)
Percentage of completion = 20%
[(5M transaction price – 1.5M cost of elevators) x 20%] + 1.5M cost of elevators = ₱2,200,000 revenue in 20X2
Or
(5M transaction price – 1.5M cost of elevator) x 20% = 700K revenue excluding elevator – 500K costs excluding
elevator = 200K
19. An entity, a construction company, enters into a contract to construct a commercial building for a
customer, on customer-owned land, for a promised consideration of ₱1 million and a bonus of ₱200,000 if
the building is completed within 24 months. The entity accounts for the promised bundle of goods and
services as a single performance obligation satisfied over time because the customer controls the building
during construction. At the inception of the contract, the entity expects the following:
Transaction price ₱1,000,000
Expected costs 700,000
Expected profit (30%) 300,000
At contract inception, the entity does not expect to receive the bonus because it cannot conclude that it is
highly probable that a significant reversal in the amount of cumulative revenue recognized will not occur.
Completion of the building is highly susceptible to factors outside the entity’s influence, including weather and
regulatory approvals. In addition, the entity has limited experience with similar types of contracts.
The entity determines that the input measure, on the basis of costs incurred, provides an appropriate measure
of progress towards complete satisfaction of the performance obligation.
The entity reassesses the variable consideration and concludes that the amount is still constrained.
In the first quarter of the second year, the parties to the contract agree to modify the contract by changing the
floor plan of the building. As a result, the fixed consideration and expected costs increase by ₱150,000 and
₱120,000, respectively. In addition, the allowable time for achieving the ₱200,000 bonus is extended by 6
months to 30 months from the original contract inception date. At the date of the modification, on the basis of
its experience and the remaining work to be performed, which is primarily inside the building and not subject
to weather conditions, the entity concludes that it is highly probable that including the bonus in the
transaction price will not result in a significant reversal in the amount of cumulative revenue recognized. In
assessing the contract modification, the entity concludes that the remaining goods and services to be provided
Page |8
using the modified contract are not distinct from the goods and services transferred on or before the date of
contract modification; that is, the contract remains a single performance obligation.
How much is the cumulative catch-up adjustment to revenue recognized on the date of contract modification?
(round-off percentage of completion to one decimal place only)
a. 89,200 c. 92,800
b. 91,200 d. 93,400
20x1 20x2
Original contract price 1,000,000 1,000,000
Bonus - 200,000
Contract modification 150,000
Total 1,000,000 1,350,000
Percentage of completion (a) 60% 51.20%
Revenue to date 600,000 691,200
Revenue in prior yr. (600,000)
Revenue for the year 600,000 91,200
(a)
20x1 20x2
Costs incurred to date 420,000 420,000
Total expected costs 700,000 820,000(b)
Percentage of completion 60% 51.20%
(b)
700,000 + 120,000 increase due to contract mod. = 820,000
20. ABC Co. started work on a construction contract in 20x1. The contract price is ₱10M. However, the
contractual agreement stipulates that if the cumulative inflation reaches or exceeds 26%, the contact price
shall be adjusted upwards by 10%. Additional information on the contract is shown below:
20x1 20x2
Costs incurred to date 2,400,000 4,500,000
Estimated costs to complete 3,600,000 1,500,000
Cumulative inflation rate 18% 27%
20x1 20x2
10,000,00 11,000,00
Total contract price 0 0 *
(a
) Costs incurred to date 2,400,000 4,500,000
Estimated costs to complete 3,600,000 1,500,000
(b Estimated total contract
) costs 6,000,000 6,000,000
Expected profit (loss) 4,000,000 5,000,000
Multiply by: % of completion
(a) ÷ (b) 40% 75%
Profit (loss) to date 1,600,000 3,750,000
Profit recognized in prior (1,600,000
years - )
Profit (loss) for the year 1,600,000 2,150,000