WEEK 1 WEEK 2

Permist & Licences


GENERAL
REQUIREMENTS Mobilization & Delivery of Materials
Temporary Facilities
COLLECTION AND Adjustment of Indoor Units as Temporary ACU for the area
MARKETING
OFFICES Troubleshooting and Reactivation
Dismantling of old system units
Installation of hangers and supports
Refrigerant pipe layout (for new system)
Delivery and installation of REFNET/Y-branch
Communication wiring
Power supply wiring
Flushing of refrigerant pipes
Leak testing of refrigerant line
Drain pipe layout
Leak testing of drain line
INSTALLATION OF
Delivery of indoor units
Installation of indoor units
Connection of drain to indoor units & catch basin
Dismantling of temporary ACUs at Collection & Marketing Office
Delivery of outdoor units
Installation of outdoor units
Pipe finishing works
Machine connection
Field wiring
Installation of ACCU deflector ducts
Testing & Commissioning