Area

No of FDV Line
Manpower Total Cooling tower Hr without
running FDV Capacity Running
Per shift Manpower Capacity (KL) water
Shifts (KL) Hr
Wooshin 3 200 600 135 6 12 2 24
SFC 1 15 15 50 3 6 3 8
LP 1 30 30 80 2 2 2 8
Prima 2 40 80 70
EDAG 2 100 200 6 9 2 16
FAT 2 20 40 50
Tilt 1 50 50 80 6 7 3 8
1015
Equipment Rate of Flow Demand

Water Projection Projection


Spot gun Robot Intercooler Spot gun Robot Intercooler Spot gun
Consumed Welding Welding
144 72 1 6 3 12 30 20 30 864
16 20 2 6 6 120
8 8 1 8 8 64
87 27 10 10 870
72 60 1 6 7 7 7 420
27 10 270
19 65 3 6 6 390
259
Demand Total

Projection
Robot Intercooler LPM KL/Hr
Welding
30 120 90 1104 66.24
12 0 0 132 7.92
8 0 0 72 4.32
0 270 0 1140 68.4
7 42 0 469 28.14
0 0 0 270 16.2
18 0 0 408 24.48