Professional Documents
Culture Documents
PTS 60.0108 HSE Construction and Commissioning
PTS 60.0108 HSE Construction and Commissioning
(GUIDELINE)
PTS 60.0108
JUNE 2006
PTS 60.0108
JUNE 2006
2
PREFACE
Petronas Technical Standards (PTS) are based on the experience acquired during the involvement with the
design, construction, operation and maintenance of processing units and facilities. Where appropriate they are
based on, or reference is made to, national and international standards and codes of practice. The objective is to
set the recommended standard for good technical practice applied by PETRONAS in oil and gas production
facilities, oil refinery, gas processing, chemical plants, marketing facilities or any other such facility, and
thereby to achieve maximum technical and economic benefit from standardisation.
The information set forth in these publications is provided to users for their consideration and decision to
implement. This is of particular importance where PTS may not cover every requirement or diversity of
condition at each locality. The system of PTS is expected to be sufficiently flexible to allow individual
operating units to adapt the information set forth in PTS to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for the quality of work
and the attainment of the required design and engineering standards. In particular, for those requirements not
specifically covered, the Principal will expect them to follow those design and engineering practices which will
achieve the same level of integrity as reflected in the PTS. If in doubt, the Contractor or Manufacturer/Supplier
shall, without detracting from his own responsibility, consult the Principal or its technical advisor.
2) Other parties who are authorised to use PTS subject to appropriate contractual arrangements.
Subject to any particular terms and conditions as may be set forth in specific agreements with users,
PETRONAS disclaims any liability of whatsoever nature for any damage (including injury or death) suffered
by any company or person whomsoever as a result of or in connection with the use, application or
implementation of any PTS, combination of PTS or any part thereof. The benefit of this disclaimer shall inure
in all respects to PETRONAS and/or any company affiliated to PETRONAS that may issue PTS or require the
use of PTS.
Without prejudice to any specific terms in respect to confidentiality under relevant contractual arrangements,
PTS shall not, without the prior written consent of PETRONAS, be disclosed by users to any company or
person whomsoever and the PTSs shall be used exclusively for the purpose they have been provided to the user.
They shall be returned after use, including any copies, which shall only be made by users with the express prior
written consent of PETRONAS. The copyright of PTS vests in PETRONAS. Users shall arrange for PTS to be
held in safe custody and PETRONAS may at any time require information satisfactory to PETRONAS in order
to ascertain how users implement this requirement.
PTS 60.0108
JUNE 2006
3
PTS 60.0108
JUNE 2006
4
1. Introduction 6
1.1 Background 6
1.1.1 Level of risk exposure 6
1.1.2 Transient nature of construction activities 6
1.1.3 Hazardous nature of construction sites 7
1.1.4 Hazardous nature of construction activities 8
1.1.5 Hazards specific to commissioning 8
1.2 Objectives of this document 9
1.3 Scope 10
1.4 User Guide 11
2. Overview 12
2.1 Links with Other Sections of the HSE Manual 12
2.2 Summary of HSE-Critical Activities in Construction and Commissioning 13
2.3 Construction and Commissioning Activities Framework 14
PTS 60.0108
JUNE 2006
5
PTS 60.0108
JUNE 2006
6
1. INTRODUCTION
1.1 BACKGROUND
Construction industry, in general, has one of the worst accident records of any
industrial sector. A number of factors, specific to the construction industry,
contribute to this poor record and thus require focused management attention. This
situation is being recognised at government level and some countries have introduced
legislation that imposes specific duties on OPU/JVs and contractors. In the UK, for
example such legislation involves compliance at each stage of construction. Amongst
other things, it targets planning aspects of construction projects (particularly the co-
ordination and management of health and safety aspects of design and the pre-tender
stage and the preparation of a 'health and safety file' or HSE Case). OPU/JVs that
have appropriate procedures which integrate HSE throughout the various stages are
likely to find that they already do what such regulations require. However, they will
need to be aware of the format of any documentation that has to be provided to
demonstrate legislative compliance.
Although the duration of the construction phase for a typical production facility is
much shorter than the facility's subsequent operational life, the nature of the activities
involved and the total manhours expended in a typical construction project can
expose the construction workforce to a level of risk higher than that of the personnel
involved in the subsequent, longer operational phase.
The nature of the circumstances under which construction contracting is carried out
often results in:
• pressure to work in short time horizons and comply with the "fast-track"
approach, often exacerbated by the need to include additional work scope due to
late changes
PTS 60.0108
JUNE 2006
7
• inadequate training (e.g. workers unaware of hazards). Often this is because the
value of training is seen as low priority by the contractor when the incentive to
have a well-trained workforce is nullified by individuals leaving to work with
other organizations. Similarly short mobilization timescales may preclude
adequate training periods
• poor 'team' dynamics. Team dynamics and group 'norms' are generally more
difficult to form and retain on construction sites compared with situations where
team stability has a longer time horizon within which to develop
The potential for the occurrence of injuries and fatalities can be high due to:
• working in locations that present extra risk (e.g. at height, over water,
underwater, in confined spaces, close to live power lines or other live services,
etc)
PTS 60.0108
JUNE 2006
8
• building in accordance with designs that can involve the existence of interim
stages before the permanent construction is completed
• communicable diseases
Under such conditions, there may be a propensity for the following situations to
dominate:
Specialized individual tasks, such as major heavy lifts, etc are specifically recognized
as being potentially hazardous and are normally planned and executed under close
supervision. Generally, a large proportion of injuries and fatalities occur, not during
such targeted tasks, but rather during the performance of normal, routine general
workplace practices (e.g. scaffolding, welding, use of power tools, etc). The HSE
management of these routine activities should be given equal treatment with special
tasks and not overlooked.
The commissioning period can be a time of increased risk due to the occurrence of
some, or all, of the factors listed below:
PTS 60.0108
JUNE 2006
9
• unfamiliarity
• time pressure
The timing of commissioning is often dictated by the need to fit in with the
limited availability of shutdowns or to meet contractual hydrocarbon delivery
deadlines with third parties and shareholders
• personnel constraints
This can often arise because of differences in sense of time perspectives and
ownership.
• transfer of responsibility
Responsibility for the plant is often transferred from one group of individuals to
another at this time
PTS 60.0108
JUNE 2006
10
• describe how to compile an effective HSE Plan that will anticipate potential
problem areas and help to provide a structured method of control
1.3 SCOPE
• construction completion
• pre-commissioning
• hook-up
• commissioning
• handover
PTS 60.0108
JUNE 2006
11
This section does not cover detailed guidance on all specific construction and
commissioning activities.
Transport and materials handling is also a key part of construction activities and
guidance on these subjects is given in PTS 60.0110 Logistics Handling (see
Appendix II for the list of subjects covered).
The principles within this document are intended to apply to all sizes of construction
project, for example, from a simple refurbishment of part of an office block, through
to a major oil and gas processing facility, utilising a large multi-disciplined
workforce.
Chapter 2 indicates the links between this section and other sections of the HSE
Manual. It also defines the Construction and Commissioning activities framework
used to ensure a comprehensive Hazards and Effects Management Process (HEMP)
throughout this document.
Chapter 4 provides guidance on the steps necessary to ensure HSE issues are
adequately addressed during the commissioning phase of any project.
PTS 60.0108
JUNE 2006
12
2. OVERVIEW
The guidance in this section utilizes the structure of a number of other associated
sections of the HSE Manual. These are listed below (together with the key elements
utilized in parentheses):
PTS 60.0101 Group HSE Management System (HSE Management System structure)
The links between PTS 60.0108 Construction and Commissioning and these sections
are shown in Figure 2.1.
Fig 2.1
Links with Other Sections of the HSE MS
PTS 60.0408
Construction
and
Commissioning
PTS 60.0302
PTS 60.0410 General
Logistics Workplace
Practises
PTS 60.0108
JUNE 2006
13
These activities can be summarized under the following stages (associated project
management phase shown bold in parentheses):
• define the general construction HSE requirements to be met in the detailed design
stage (Project Specification)
• define the contracting strategy, the OPU HSE MS and contractor HSE
prequalification criteria (Project Execution Plan)
PTS 60.0108
JUNE 2006
14
• develop the framework for the HSE Plan and specify the requirements of the
contractors in developing the HSE Plan (Project Execution Plan)
• execute construction and commissioning in accordance with the HSE Plan (by
construction and commissioning contractor and vendor representatives)
(Construction and Commissioning)
In this document, reference is made to the 'HSE Plan' which essentially defines the
combination of the HSE MS and a description of how the HSE-critical activities are
to be managed. The term 'HSE Plan' has deliberately been retained for a wider
understanding of the management of construction HSE, since this inevitably involves
the management of contractor HSE. It should be recognised that in many situations,
particularly for larger contracts, this HSE Plan will effectively form a significant part
of a full HSE Case.
• to analyse the work and enable identification of hazards during the front-end
engineering phase
This will provide a focus for the elimination of hazards wherever possible and
allow information about remaining hazards to be included in the tender
documents.
PTS 60.0108
JUNE 2006
15
• the workplace
• hazardous substances.
To source the relevant location in PTS 60.0101 the appropriate reference is obtained
by omitting the initial 3 from the references in this document, i.e. 3.6.2 has an
equivalent 6.2 in PTS 60.0101
The key essentials in demonstrating the appropriate leadership and commitment are:
PTS 60.0108
JUNE 2006
16
3.2.1 Policy
The policy should be translated into all relevant native languages and if necessary
PTS 60.0108
JUNE 2006
17
The application of specific policies (e.g. drug and alcohol abuse) should be consistent
for all personnel.
• development of an HSE framework by the OPU/JV (or the project team) for the
construction and commissioning contract
G development of the HSE Plan by the contractor before site work execution.
The framework for the HSE Plan should be included in the tender documents
and subsequently used and built upon by the contractors in their bids. This
should then be expanded in further detail by the successful contractor as a
comprehensive plan for managing the construction and commissioning
hazards before work is started. The framework should include any limitation
on working practices imposed as a result of environmental assessment (EA)
reports (e.g. hours of work, noise limitation, waste management, etc).
There is a need to ensure that all areas of the HSE Plan are strictly followed and
appropriate quantifiable measurement criteria should be identified. Any areas where
deviations are unavoidable must be managed effectively by use of the principles of
PTS 60.0108
JUNE 2006
18
change control. In the commissioning phase, there are a number of additional specific
objectives which reflect the transition from building a plant safely to building and
operating a safe plant:
G to ensure that all potential hazards have been identified and assessed during
the initial commissioning and that necessary controls have been put in place,
resulting in a safe startup of production operations
G to demonstrate that the facility operates in accordance with the intent of the
design and within the design envelope.
HSE objectives should be achievable. To this end HSE aims should be consistent
with other project management objectives of time and cost. It may be necessary to
amend the time and cost parameters of an element of work in order to achieve the
HSE objectives.
The key aspects of concern for construction and commissioning HSE are:
G interface management
Clear definition of responsibilities is particularly important in managing the
many interfaces from construction execution through construction testing,
pre-commissioning, commissioning, to handover and operation.
G authorization
Authorized signatories should be defined for each step in the construction and
commissioning sequence and for each party involved (e.g. OPU/JV, specialist
contractors, vendors, certifying authority, etc).
G delegation of authority
Ensure that individual responsibilities are matched by the delegation of the
necessary authority.
The HSE responsibilities for typical key positions in construction and
commissioning are given in Appendix IV.
PTS 60.0108
JUNE 2006
19
The Management Representative(s) for both the OPU/JV and the contractor are the
focal points for the overall co-ordination of HSE management activities within their
respective organizations.
3.3.3 Resources
3.3.4 Competence
The systems devised for ensuring competence of personnel for both OPU/JV and
contractor should consider the following factors:
G evidence of training
PTS 60.0108
JUNE 2006
20
For a number of trades and skills (e.g. driving, radiography, scaffolding, first-
aid, crane driving, electrical installation, etc) recognized levels of competency
result in formal certification. Evidence of training should be controlled
through the checking of relevance and currency of certificates of recognized
training boards, etc.
Construction and commissioning relies a great deal on the use of contractors. The
arrangements for carrying out these activities (and the potential impact on HSE) can
vary significantly. Amongst the most important criteria are:
Service contracts are a familiar and often-used means of executing many small
packages (often in different locations, several contractors working together, etc).
Initially such contracts often have no defined scope beyond a general description of
the services, skills, plant, etc that the contractor must be able to provide. However,
the ability of the contractor to manage HSE on a job-by-job basis is an essential
requirement. For example, he should be able to make hazard assessments, apply and
enforce controls to manage residual HSE hazards and effects, apply correctly local
HSE legislation, respond effectively to emergency situations, etc. All these elements
must be demonstrated prior to contract award.
PTS 60.0108
JUNE 2006
21
G timespan of project(s)
Projects can range from major construction ventures lasting several years to
small packages accomplished in a matter of weeks and the extent of HSE
management varies accordingly. Major projects follow a recognizable
sequence as described above.
For short duration projects, HSE planning is equally important and must not
be ignored or treated superficially. The potential risk for causing a serious
incident in a small, short-duration task (e.g. the fabrication of pipe spools and
making tie-ins to live plant) may be just as high as that for the construction of
a major stand-alone new facility. In such cases, the work is likely to include
the use of basic practices (e.g. scaffolding, welding, excavating, erecting
formwork, etc) and the contractor should be able to demonstrate good general
HSE management in each of these basic practices plus the ability to
understand and carry out hazard assessment when these practices are put
together in different combinations, particularly in association with the hazards
of the workplace (e.g. working in confined spaces, over water, etc) and live
plant (e.g. presence of H2S, isolating electrical systems, etc).
G the approach, format and structure of HSE Plans (and where relevant HSE
Cases)
G HSE assessments
What methods of assessment are available and when to apply them.
PTS 60.0108
JUNE 2006
22
For example, an OPU/JV might wish to employ several small local contractors via
service contracts to carry out a programme of work over two years on distributed
sites, requiring civil, mechanical, instrumentation, etc construction skills. In the
planning and invitation to tender stage, the OPU/JV would be required to provide a
broad description of the type of work expected, locations, resources to be provided
(e.g. personnel, equipment, consumables, etc) and to indicate in general the hazards
likely to be encountered. Prequalification of contractors (or selection from an
approved list of registered contractors) would follow the same approach as for a
major project. The OPU/JV would in addition need assurance that the contractor is
competent to make hazard assessments from the details in the construction packages
supplied at a later date. The OPU/JV might therefore seek this assurance in the tender
documents by providing a typical construction pack and asking each contractor to
provide an HSE assessment as part of his bid.
PTS 60.0108
JUNE 2006
23
PTS 60.0108
JUNE 2006
24
The key HSE issues for construction and commissioning contractors are provided
under each of the main headings below.
G determine the HSE impacts on scope, schedule and strategy for the contracts
required
G assess HSE content of each contract
G confirm suitability of contract scope, schedule and strategy against HSE
assessments
G prepare HSE-related contract documents
G prequalify potential contractors for HSE suitability, having reviewed their
past HSE performance
G prepare the outline contract with appropriate milestone hold points.
Definition
G prevailing influence Prevailing influence allows the OPU to impose its own
HSE requirements. In contrast, negligible influence only allows the
imposition of relevant national HSE legislation.
PTS 60.0108
JUNE 2006
25
It is preferable for the Construction Manager to have been nominated by this stage
but where this is not the case the Project Manager should consider whether to co-opt
someone with the relevant experience. This list may be expanded to suit, e.g. to
include specialist support, training department, etc.
The assessment should utilize in its approach:
G the standard HSE MS headings and the guidance given in PTS 60.0101 and
this document for HSE Management requirements
G the six element framework for job hazard analysis in construction and
commissioning tasks and operations.
PTS 60.0108
JUNE 2006
26
It should also define specific requirements associated with the job activities, such as:
G timing and sequence of the work with any restrictions or time windows
G phasing requirements to interface with delivery of large equipment items
G impact of any other concurrent OPU operations on construction and
commissioning and vice versa
G constraints on the methods of working
G constraints on the areas of work
G specific shutdown limitations
G provision for suspending construction and commissioning operations.
Appendix VII provides a checklist of items for inclusion in the Contract HSE
Specification.
Prequalify Contractors
Key points to address in contractor prequalification are:
G status of contractor's HSE MS
G management of subcontractors
G use of local contractors with limited exposure to HSE MS
G use of Register of Approved Contractors
G experience with previous similar projects
G availability of typical HSE assessments and method statements
G availability of HSE procedures for the common construction and
commissioning practices.
G his own hazard assessment of the work described for the contract
G his execution proposals
G awareness and familiarity with the type of work
A demonstration of awareness, familiarity and experience with the hazards and the
application of controls in the type of construction and commissioning work involved
is essential. This could be demonstrated by the existence of generic internal control
procedures (HSE manual) that covers routine construction activities.
G working conditions
Where there is no or inadequate legislation concerning the conditions of
employment for the contractor's labour force, their terms of employment
should be reviewed to ensure that adequate combinations of working hours
and social provisions (e.g. catering, transport, laundry, cleaning, etc) are
made. Consideration should also be given to what provisions are made for
expatriate workers, working remote from their families, to alleviate
psychological pressures (e.g. leave periods, telephone facilities, etc).
HSE Costs
Evaluation
PTS 60.0108
JUNE 2006
28
PTS 60.0108
JUNE 2006
29
Kick-off meetings
The kick-off meeting with the contractor should be held immediately after
contract award, before the execution of any work and should ensure that the
contractor's personnel are aware of the site hazards and familiar with HSE
regulations, working procedures and emergency response procedures.
Depending on the size and complexity of the project, additional topics may
need to be covered in more detail (e.g. HSE performance objectives, HSE
rules on site, HSE induction, third party involvement in emergency response,
briefing of subcontractors etc).
Mobilization
The OPU/JV should begin its supervisory role of the contractor's pre-
execution activities and ensure that the contractor has deployed his
supervisory staff and is implementing the briefing and training that are
required for his supervisors and employees.
Pre-execution Audit
PTS 60.0108
JUNE 2006
30
G project team (both OPU/JV and contractor) not yet fully conversant
with all key HSE issues
G vehicles and equipment being mobilized both subject to recent
inspection and maintenance
G long distances involved in delivery of personnel, equipment and
materials to site (often well away from operational base, etc)
G remoteness from first-aid/medical facilities.
The pre-execution audit should include such factors as part of the audit terms
of reference.
3.3.5.5 Execution
Objectives
The extent to which each of these points should be addressed will depend on
the size and complexity of the contract.
Supervision
PTS 60.0108
JUNE 2006
31
Competence Assurance
The OPU/JV should monitor the competence assurance (and any associated
training programme) of the contractor (e.g. adherence to recruitment
standards, provision of induction courses, effectiveness of job-related
training, etc).
For construction and commissioning contracts, hazard hunt (or PSAP) and
near-miss reporting should be used to facilitate the early identification of
potential incidents and to determine the appropriate remedial action.
G all action items from earlier, relevant assurances to assess that follow-
up has been completed
G all design and construction is complete, that all change control has
been managed in accordance with the HSE Plan and the facility is fit
for operation
G testing already completed (or still planned) demonstrates technical
integrity of the facility
G precommissioning is proceeding in accordance with the HSE Plan.
3.3.5.6 Demobilisation
The contractor's HSE Plan continues to be the vehicle for monitoring his HSE
activities in this phase. In construction and commissioning, this may include
such issues as disposal of waste or surplus materials, site clean-up and
restoration.
PTS 60.0108
JUNE 2006
32
3.3.5.7 Close-out
3.3.6 Communication
when people from a number of nationalities are present on the one site. In
such situations, repeat messages/displays and simplicity of the message is
all important.
toolbox meetings
The HSE Plan should specify requirements where the use of toolbox
meetings is considered essential (e.g. prior to specialised tasks such as
heavy lifts, as a review and reminder for routine general practices, tasks
involving interfaces with other parties such as operations, etc).
PTS 60.0108
JUNE 2006
33
G HSE Plan
G method statements
G material certificates
G fabrication reports
G vendor documentation
G preservation programmes
G Acceptance/handover certificates.
PTS 60.0108
JUNE 2006
34
A checklist for key HSE issues to be examined as part of the early appraisal of
construction and commissioning process is given in Appendix VI.
3.4.2 Evaluation
The methods required for recording should be stated and would typically be as
follows:
PTS 60.0108
JUNE 2006
35
Application of each of the stages of the hazard and effects management process
should result in the generation of a set of objectives and performance criteria and
frequently these become part of the subsequent contract specification. Examples of
such objectives and performance criteria include:
G by choice of design
Remove or reduce the exposure to the construction and commissioning HSE
risk. For example, the necessity for working at heights in bolting up structural
components could be avoided or reduced by making more use of offsite
prefabrication or pre-assembly at ground level and lifting into position. The
choice of safe materials is also part of this exposure reduction (for example
by avoiding fragile materials in roofing construction). Such requirements are
increasingly featured in legislation.
PTS 60.0108
JUNE 2006
36
design must ensure that such an intermediate stage is still safe under all
foreseen conditions (e.g. weather conditions, adjacent construction activities,
etc).
G by using and enforcing controls where operational systems are released for
construction work Where live systems are de-commissioned to enable
construction work to proceed, details such as status of system/equipment
items at handover (e.g. hydrocarbon-free, de-energised, etc), isolation
schedule, etc should be provided. Where de-commissioning involves removal
of essential systems (e.g. plant protection instrumentation, utilities, etc), then
alternative, temporary systems must be planned and implemented. All such
controls form part of a permit-to work (PTW) system.
G occupational health
PTS 60.0108
JUNE 2006
37
3.5.1 General
In construction and commissioning, there are two levels at which planning has to be
carried out:
G process level
This covers the normal HSE MS elements (e.g. organisation, roles,
competence, contractor management, etc).
G task level
This covers the factors necessary to carry out work activities safely (e.g.
adequate resources, a safe work-place, safe methods of work, adequate
timescale, etc).
Planning must satisfy legislative requirements but are often set in the absence
of such legislation.
Procedures and work instructions for construction and commissioning activities that
are essential for HSE management include:
G method statements
List each activity where the OPU/JV expects the contractor to develop a
detailed construction procedure (method statement) from the OPU/JV's
PTS 60.0108
JUNE 2006
38
The OPU/JV should define those areas where change control management is
essential. These include:
G (pre)commissioning sequence
The (pre)commissioning sequence should be carried out in accordance with
the defence hierarchy sequence (see 4.5.1). No change to this should be
permitted unless an adequate risk assessment has been made and suitable
controls implemented.
PTS 60.0108
JUNE 2006
39
PTS 60.0108
JUNE 2006
40
Activities and tasks should be carried out in accordance with formal procedures. In
the case of general construction practices, these should have already been produced
by the contractor and accepted by the OPU/JV (as the contractor's general
procedures) as part of the contractor's tender submission and form part of the formal
contract documents. Procedures for exceptional or unusual activities (i.e. method
statements) may have only been listed or outlined prior to contract award. These
should now be prepared in detail by the contractor and agreed with the OPU/JV,
before construction work starts. Method statements typically include the sequence of
events, a complete description of each of the steps in the activity (supported by
descriptions of the personnel resources, plant and equipment to be used) and any
intermediate checks to be made.
3.6.2 Monitoring
See outline activity sheets and hazard sheets in PTS 60.2115 General
Workplace Practices for target areas in such assurances.
3.6.3 Records
PTS 60.0108
JUNE 2006
41
Where incidences of failure to comply with HSE requirements occur (and where
considered appropriate) formal notices should be issued to advise corrective actions,
changes to procedures etc. Such notices may require temporary suspension of a
construction-related activity until the deficiency has been rectified or the hazard
eliminated.
Actions to be undertaken for incident follow-up should be included in the HSE Plan.
3.7.1 Assurance
An assurance programme should be based on the size, location and nature of the
project. It should form part of the HSE MS. Assurances can be selected and
structured in a number of ways including:
For construction and commissioning contracts, hazard hunt (or PSAP) and near-miss
reporting should be used to facilitate the early identification of potential incidents and
to determine the appropriate remedial action.
There are two specific areas where assurances during construction and
commissioning are most likely to be required.
The HSE Plan should specify the minimum pre-execution requirements. The main
objective of a pre-execution assurance is to verify compliance with these
requirements. It has an additional benefit in demonstrating the profile of HSE issues
PTS 60.0108
JUNE 2006
42
to the contractors at an early stage. The terms of reference for such an audit would
normally include verification that:
G the HSE plan is in place and addresses the site specific hazards
G the condition of equipment is satisfactory
G key personnel are available
G general procedures are available and known
G personnel have completed training prior to starting work
G personal protective equipment (PPE) is available
G site infrastructure has been set-up satisfactorily (including medical emergency
response).
The HSE Plan should specify the pre-startup assurance requirements. The main
objectives are to verify that:
G the original design was suitably checked to verify design integrity and that
any changes required have been suitably followed-up (e.g. HAZOP action
items)
G the facility is constructed as designed, including any agreed design changes
G checks to be performed during commissioning are adequate to demonstrate
the system integrity
G the Asset Holder is sufficiently prepared to undertake the running of the
facility. Subsidiary objectives are to check that:
G commissioning activities are compatible with Environmental Impact
Assessment (EA) results
G hardware and procedures are in accordance with standards and local
legislation
G all hardware and software changes were subject to change control procedures
G construction is in accordance with approved design and fit for introduction of
hydrocarbons
G HSE aspects of interfaces with other facilities have been reviewed
G precommissioning and commissioning procedures are complete and adequate
G handover arrangements are clearly defined
G emergency procedures are available and demonstrably suitable
G design drawings, as-built drawings and vendor manuals are available
G concurrent operations procedures (where other activities proceeding
concurrently with construction or commissioning) are available and suitable.
3.7.2 Review
Completion of the project should include the assembly and issue of a close-out
report. HSE issues for feedback should be highlighted in this report, such as site
rehabilitation, waste management conclusions, deviations required from original HSE
Plan, design change control list, etc).
It should also provide feedback on the performance of the contractor to any internally
held database of contractor HSE performance for future contract considerations.
PTS 60.0108
JUNE 2006
43
4. COMMISSIONING
This chapter provides guidelines for the preparation of Commissioning Plans taking
into account all relevant HSE issues.
PTS 60.0108
JUNE 2006
44
The content of the Commissioning Plan should be in proportion to the size and
complexity of the project, although each of the elements outlined in this chapter
should be covered.
The stages of the development of the main elements of the Commissioning Plan are
summarized below in Table 4.1, under the headings of the phases from a typical field
development.
Table 4.1 Stages of development of Commissioning Plan
PTS 60.0108
JUNE 2006
45
G commissioning dependencies
The requirements of all existing systems essential for the commissioning
process (e.g. existing utilities to support new process facilities, emergency
services, etc) should be defined.
PTS 60.0108
JUNE 2006
46
The commissioning sequence should be carried out in the following order (i.e. in
relation to the defence hierarchy):
Within each system the order in which the commissioning sequence proceeds
(precommissioning, hook-up, commissioning) should be agreed and defined (this is
particularly relevant to utilities and process systems). The description of how each
step is to be completed should address the following principles:
G step-by-step working
Proceed with each step only when all necessary documentation from the
previous step is available and complete.
G documentation
Document each step by a rigorous discipline of completing checklists, logs
and commissioning test results as work progresses.
4.5.3 Requirements of commissioning procedures
PTS 60.0108
JUNE 2006
47
4.6.2 Onsite
PTS 60.0108
JUNE 2006
48
The following should be available at the end of construction and the start of the
commissioning process:
4.7.2 Pre-commissioning
4.7.3 Hook-up
4.7.4 Commissioning
PTS 60.0108
JUNE 2006
49
Once commissioning activities have been completed and the responsible person has
performed final inspections/tests etc, the system should be identified as being
commissioned in a suitable way (e.g. by tagging, log sheets, etc). Permission to work
on such a system must then be subject to permission of the responsible person via
PTW.
4.7.5 Handover
The process of handover is essentially the transfer of responsibility for the facilities
from the construction and commissioning team to the operations Asset Holder and
the associated operations personnel. The circumstances under which handover takes
place need to be managed carefully if HSE is not to be compromised, particularly as
there is often significant pressure for the Asset Holder to accept the facilities.
There may be a tendency for the construction and commissioning team to want to
complete their work as quickly as possible. This may be exacerbated by such factors
as:
Personnel in the construction and commissioning team by this time are usually very
familiar with the facilities and the strength of this position can be overlooked. In
contrast, the operations Asset Holder and his personnel, unless they have had a strong
and early involvement prior to handover, may be subject to the following:
The choice of team leader for the operations side must be someone who has the
strength and ability to resist pressure to accept facilities prematurely and to ensure
that HSE is not being compromised due to key factors like those described above.
Final as-built drawings and final issue of the OPM should be provided to the facility
PTS 60.0108
JUNE 2006
50
PTS 60.0108
JUNE 2006
51
G (for used or surplus items) disposed of only in accordance with proper waste
management practice (see 4.9 below).
4.8.2 Consumables
Consumables includes materials such as liquids used for cleaning, pickling, drying,
lube oils, empty containers and packaging, etc. Used or surplus items, should be
disposed of only in accordance with proper waste management practice (see 4.9
below)
Special tools, required for precommissioning and commissioning tasks, may present
hazards:
All items of test equipment should be defined, including item serial numbers,
calibration frequencies and use of calibration certificates. All items should then be
used only within a strict calibration log system.
The commissioning period poses special demands on the need for effective
PTS 60.0108
JUNE 2006
52
The first requirement is to satisfy all legal requirements. Thereafter, the key principle
in waste management is to reduce pollution by elimination, change or reduction of
practices that result in discharges to land, air or water. Where elimination of a waste
is not possible, then the amount should be minimized by the application (in order) of
the following:
G source reduction
G reuse
G recycling
G recovery
G treatment and responsible disposal.
G dedicated storage for individual types of waste according to classification
G storage facilities should be limited to dedicated areas
G individual containers/skips etc should be clearly manifested and labelled in
accordance with local regulatory requirements.
Facilities should be provided for the storage of disposable waste according to the
following principles:
General workplace hazards that are commonly encountered as a result of the tasks
that take place in commissioning include:
G fluids under pressure, e.g. during leak testing and initial start-up
G hazardous substances used in cleaning, etc
G contact with hot and cold surfaces and fluids
G contact with rotating parts of machinery
G noise and vibration exposure
G electric shock
G radiography
G non-life-supporting conditions (including toxic gas)
G chemical/caustic substances
G slips trips and falls around plant site
G effects on personnel resulting from thermal stress.
These hazards and appropriate controls are described in PTS 60.2115 General
PTS 60.0108
JUNE 2006
53
Workplace Practices.
PTS 60.0108
JUNE 2006
54
PTS 60.2115 General Workplace Practices provides details on HSE management of the
following list of general activities/substances occurring in construction.
Tasks and Operations
Scaffolds
Suspended access
Mobile platforms
Ladders and Lightweight Staging
Rope access
The workplace
Work space
Light
Heat stress
Cold stress
Noise and vibration
Working in confined spaces
Working at heights
Working over water
Working in excavations
Office HSE
Laboratory HSE
Workshop HSE
Electricity
Compressed Air
PTS 60.0108
JUNE 2006
55
Steam
Consumables (LPG, automotive fuels)
Working with hazardous substances
PTS 60.0108
JUNE 2006
56
PTS 60.0110 Logistics provides details on HSE Management of the following list of subjects
in the transportation of personnel and materials by land, sea and air and the handling of
materials.
Transport HSE management
Land Transport
Drivers
Competence and selection
Driving permits
Induction Training
Driver improvement
Responsibilities of the individual
Vehicles
Correct selection
Specification
Passengers
Freight
Marine Transport
Marine Personnel
Competence and selection
Certification
Induction Training
Vessels
Correct selection
Specification
Surveys
Electrical Equipment
Cargo
Anchoring handling
Towing
Operations management
Need and approval
Journey routing and scheduling
Journey management
Roles and responsibilities
Contracting Procedures
Performance measurement
Emergency services
Air transport
PTS 60.0108
JUNE 2006
57
Aircraft
Correct selection and specification
Maintenance
Cargo
Air fields, runways and the operation of fixed wing aircraft
Aircraft performance and runways
Technical accommodation
Personnel accommodation
Fuel storage and delivery systems
Communications and navigation
Meteorological information
Emergency services Security
Operations Management
Need and approval
Aircraft numbers and availability
Personnel numbers and flight time/duty time limitations
Journey routing, scheduling and monitoring
Roles and responsibilities
Refueling operations
Contracting
Physical characteristics of airfields and runways
Compilation of statistics and records
Helicopter facilities onshore/offshore
Helicopter facilities onshore
Helicopter facilities offshore
Support Facilities
Materials handling
Materials handling personnel
Competence and selection
Induction Training
Materials storage
Layout
Traffic routes (personnel and vehicles)
Escape routes and exits
Lighting
Telephones/PA
Firefighting equipment
Drainage
Decontamination equipment
First aid
Ventilation
Storage areas S
Storage systems
Operations management
Planning and authorization
Execution
PTS 60.0108
JUNE 2006
59
The key HSE issues and objectives addressed in these documents are tabulated below
Table III.1 Expanded elements in construction and commissioning
PROJECT SPECIFICATION
Section Number Scope
Part I General Project General project information Parties involved Summary
Information, Scope of Work and scope of work:
Local Information Gscope of contractors' work
Gscope of project
Gsite preparation
Gtie-ins
Glist of activities indicating responsible parties
PTS 60.0108
JUNE 2006
60
During the Construction and Commissioning Activities described below the key HSE
activities are as follows:
PTS 60.0108
JUNE 2006
61
EXECUTION
PTS 60.0108
JUNE 2006
62
The HSE responsibilities for typical key positions in Construction and Commissioning are
given below:
Table IV.1 HSE responsibilities for key positions in construction and commissioning
PTS 60.0108
JUNE 2006
63
PTS 60.0108
JUNE 2006
64
PTS 60.0108
JUNE 2006
65
PTS 60.0108
JUNE 2006
66
PTS 60.0108
JUNE 2006
67
Table VII.1 shows typical HSE issues to be considered in the planning stage of construction
and commissioning projects. Environmental issues will also be covered in EA. See
Appendices I and II for subjects under General Workplace Practices and Logistics.
PTS 60.0108
JUNE 2006
68
Tasks and operations GActivities involving high risk (eg heavy lifts, demolitions or plant
modifications adjacent to live plant) or unfamiliar operations
GActivities involving critical timing or sequencing, integration
with other concurrent activities
GActivities involving specialised skills and/or training
Table VII.1 shows typical HSE issues that should be described as part of the planning stage
of construction and commissioning projects and which should be included as information for
the contractors in the invitation to tender. These issues would normally arise from expanding
the level of detail set out in the Project Specification Checklist (see Appendix VI).
PTS 60.0108
JUNE 2006
69
This appendix should be used by the Contract Holder to check the coverage described in the
contractor's Construction and Commissioning Contract HSE Plan, in the context of and in
response to the invitation to tender. The detail should be in keeping with the scope,
complexity and size of the contract. For the contractor's HSE Management System, PTS
60.0305 Management of Contractor HSE, Appendices IV and V provide checklists for
general HSE management aspects (large scale and small projects respectively). The appendix
addresses HSE issues based on the suggested framework of headings used throughout this
document. Environmental issues should be checked against the EA.
PTS 60.0108
JUNE 2006
70
PTS 60.0108
JUNE 2006
71
The list below summarizes the documentation necessary at formal handover of facilities to
Operations to demonstrate technical integrity and functioning of the facilities in accordance
with design. The contents list described below is appropriate for a major facility. Smaller
projects or those involving modifications to existing facilities may not need documentation
of this detail. However, the contents provide a checklist for determining whether to include
an item in the dossier or whether it is adequately documented elsewhere.
PTS 60.0108
JUNE 2006
72
GLOSSARY
A Glossary of commonly used terms in HSE is given in both PTS 60.0101 Group HSE
Management Systems and PTS 60.0401 Hazards and Effects Management Process.
PTS 60.0108
JUNE 2006