Professional Documents
Culture Documents
Pes CVS PC22 0912 D1TS01 SLD
Pes CVS PC22 0912 D1TS01 SLD
Outlines
Introduction
Theoretical Background
Distribution Network
Simulation Analysis
Summary
RMIT Classification: Trusted
Introduction
RMIT Classification: Trusted
Introduction
In recent years, residential photovoltaic (PV) panels and battery energy storage systems
(BESSs) are installed in many households.
Theoretical Background
RMIT Classification: Trusted
Theoretical Background
Power consumption of each customer
Theoretical Background
Voltage drop in a distribution feeder
Rk k P + X k k Q
Vk −1 − Vk =
Vk
The impedance of the The total power at
distribution cable between downstream of k
busbar k-1 and k (including k)
Rk+jXk ΣkP+jΣkQ
DER DER
Vk-1 Vk
RMIT Classification: Trusted
Distribution Network
RMIT Classification: Trusted
415V busbar
• 415 V 3-phase distribution network
P0257 P0258 P0276
• 56 customers in total Representative
upstream customers
• Each customer is connected to a 6kW 4kW 6kW 6kW 1.5kW 1.5kW
Customer
PV system
6kW 5kW
RMIT Classification: Trusted
Simulation Analysis
RMIT Classification: Trusted
Simulations Scenarios
Scenario Details
No PV BESS charging BESS discharging Load (kW) BESS Penetration
(scale) (kW) (kW) PF=0.95
1 1.8
2
0 0 N/A
3.4
0 Load only
3 20% 0 N/A 3.4 0
4
100% 0 N/A
0
0
Load and PV
5 3.4
6 100% 2.5 N/A 3.4 All customers
7 100% Rest PV power N/A 3.4 PV customers
Load, PV and BESS
8 All customers
9 0 2.5 N/A 3.4 Upstream customers charging
10 Downstream customers
11 100% N/A 3 0 All customers
12 0 All customers
13
0 N/A 3
All customers Load, PV and BESS
14 3.4 Upstream customers
15 Downstream customers
discharging
16 0 N/A 3.4 3.4 All customers
17 0 5 0 3.4 All customers
18 100% 0 5 0 All customers Future assumption
RMIT Classification: Trusted
VUF (%)
V (p.u.) P0279
1.016
1.016
0.060.06 P0259 P0278
V (p.u.)
VUF (%)
Load 1.012
P0291
P0277
P0258
6
1.012
0.04 0.04 415V
busbar P0257 P0256 P0274 P0276
1.8 kW P0255
1.008
1.008
0.020.02
1.004
1.004
0 100 200 300 400 500 0.000.00
2 Phase A Feeder length
Length (m)
Phase B Phase C 415V busbars
415V Busbars
1.0151.015 0.200.20
1.0101.010 0.160.16 P0290
VUF (%)
P0279
8
V (p.u.)
VUF (%)
P0291
P0276
4
0 3.4100
kW 0.995
200 0.995 300 400 500 0.040.04
200 300 Length (m)
400 500
Phase
Length
400 (m)A 500 0.9900.990 0 Phase
100 B 200 300 Phase C
400 500 0.000.00 415V Busbars
Phase B Phase
Phase A B Phase C
5 3.4
1.02
1.01 Scenario 2: The terminal voltage in [0.99,1.01] p.u.
1.00 Scenario 3: PV power is less than load.
Customer power consumption is reduced.
0.99
Scenario 5: Some customers’ PV power is higher than load.
0.98
-8 -6 -4 -2 0 2 4 The terminal voltage in [0.99,1.03] p.u.
Generation Customer Power (kW) → Consumption Scenario 4: The worst case.
The terminal voltage in [1.02,1.06] p.u.
RMIT Classification: Trusted
V (p.u.)
2 N/A N/A 3.4 N/A
1.01
8 2.5 N/A 3.4 All customers 1.00
12 N/A 3 0 All customers 0.99
13 N/A 3 3.4 All customers 0.98
0.97
Scenario 2: The terminal voltage of each customer is in [0.99, 1.01] p.u. -4 -2 0 2 4 6
Scenario 8: Total load of each customer increases, and the terminal voltage Generation Customer → Consumption
decreases. Also, the distribution line loss increases. Thus, the terminal Power (kW)
voltage differences between each customer are larger than in scenario 2.
Scenario 13: Total load of each customer decreases from 3.4 kW to 0.4 kW. Therefore, the terminal voltage increases,
and distribution line loss decreases. Consequently, the voltage differences between customers are small.
Scenario 12: Customers generate power for the network. Thus, the terminal voltage is higher than in other scenarios
RMIT Classification: Trusted
V (p.u.)
1.02
Scenario 7: The customers with PV and BESS are
1.00
islanded, and their power is 0 kW. For other
customers, the power consumption is 3.4 kW. 0.98
1
Scenario 2 to Scenario 10: The voltage deviation of the
0.995 customer with the lowest terminal voltage is 0.0052 p.u.
1
Scenario 2 to Scenario 15: The voltage deviation of the
0.996 customer with the lowest terminal voltage is 0.0061 p.u.
0.992 When BESSs in discharging mode locate downstream of
the network, the terminal voltage of customers increases
0 1 2 3 4 more significantly
Customer Power (kW) →Consumption
Scenario Details
No PV BESS charging BESS discharging Load (kW) BESS Penetration
(scale) (kW) (kW) PF=0.95
2 0 N/A N/A 3.4 N/A
14 0 N/A 3 3.4 Upstream customers
15 0 N/A 3 3.4 Downstream customers
RMIT Classification: Trusted
1.000
Transformer- P0257 73.22 78.77
0.9875
upstream P0257-P0256 49.18 52.50
V (p.u.)
downstream
P0277-P0278 37.28 38.86
P0278-P0279 12.36 12.94
1.07
V (p.u.)
Scenario Details
1.05 1.05
BESS
V (p.u.)
1.03
No PV BESS charging BESS discharging Load (kW) Penetration
1.01 1.01
(scale) (kW) (kW) PF=0.95
0.99
17 0 5 0 3.4 All customers
0 100 200 300 400 500
Phase A
Length (m)
Feeder length Phase B Phase C 18 100% 0 5 0 All customers
RMIT Classification: Trusted
Summary
RMIT Classification: Trusted
Summary
• In this paper, a series of simulations are conducted to explore the influence of distributed power
sources on a power network.
• Investigation including the influence of: PV generation power, BESS charging and discharging
power, and locations of BESS.
• PV generation and BESS discharging can reduce customer load and the terminal voltage of the
customer increases. When the power generation is higher than the customer's power consumption,
the terminal voltage increases further.
• BESSs located downstream can lead to a more significant influence on the network performance.
• The cluster can operate within the standard range with both existing PV penetration and expected
100% PV and BESS penetration in the future.
Forecasting Solar Irradiance using Hybrid SWT– QVNN
with a Softplus AMSGrad Learning Algorithm
We combined the stationary wavelet transform and quaternion
valued neural networks (SWT-QVNN) to forecast solar irradiance
Dr. Hasan AlMarzouqi
Khalifa University
INTRODUCTION
INTRODUCTION
• Solar forecasting allows grid
managers to estimate and balance
energy system operations
Literature review
System models
Problem formulation
Coot algorithm
Results
Conclusion
References
Research Background
What is Microgrid?
• Loads
✓ Constant/intermittent
• Immediate storage
✓ Batteries, fuel cells, capacitors…
• Controller
✓ Load leveling, charge control, power point tracking Fig.: Microgrid components
9
12
11
• BESS functions as both a generator to deliver energy 7
2 G
• Wind: The output power of a wind turbine can be expressed using the following
equation
v k − vctk ,i
Prp k (vct ,i v vrp )
v rp − v k
ct ,i
Pw (v) = Prp (vrp v vct ,o )
0 (v vct ,i and v vct ,o )
where Prp is the rated power, vct ,i and vct ,o are the cut-in and cut-out wind speeds, vrp is the rated wind speed, and k is the
Weibull shape parameter.
System Models
Gas Turbine Generator and BESS Modelling
• Gas: The fuel costs Fd for gas turbine can be expressed as follows
Fd ( Pdt ) = d + d Pdt + d ( Pdt ) 2
• BESS: The battery unit runs as a generator when it is discharging and as a load when it
is charging.
1) Discharging state: The energy transferred from the BESS can be expressed using the
following equation
CBt − T dcrate
t
C t +1
= max , CB,min
B
dc
where CBt is the current battery capacity; is the time; CB ,min is the minimum battery capacity; t
dcrate and dc are the
discharging rate and discharging efficiency.
The battery SOC after discharging for a period T can be expressed as follows
SOCt +1 = max ( SOCmax − (C BES,max − C BES
t
) (T / C BES,max )), SOCmin
where is the SOC at time t+1; SOCmax is the max SOC; is the battery capacity at t; is the max battery capacity.
System Models
BESS Modelling
The incremental cost factor (Cf) for BESS while discharging at minimum SOC can be
expressed as follows
SOCt C f ,t + (SOCt − SOCt +1 ) EtS
C f , t +1 =
SOCt +1
where EtS is the electricity selling price, C f ,t is the incremental cost factor at hour t.
2) Charging state: The energy transferred from the BESS can be expressed using the
following equation
(
CBt +1 = min CBt − T Crate
t
)
c , C B ,max
where CBt is the current battery capacity; C B,max is the maximum battery capacity; t
Crate and c are the charging rate and
charging efficiency.
The incremental cost factor for battery charging can be expressed as follows
SOCt C f ,t + ( SOCt +1 − SOCt ) Etb
C f , t +1 =
SOCt +1
where Etb is the electricity buying price.
System Models
Load Model
• The load model can be presented as a stable power absorber using the following equation
S = P + jQ
where P and Q are the active and reactive power. The power factor of the load should be kept between 0.85 to 1.
(P X
d =1
d
t t
d + BESS t X t ) =PDm
t
where t
PDm is the net power demand, BESS t is the available battery energy storage.
(P
d =1
d ,max X dt + BES X t ) =PDm
t
+ SRt
where SR is the spinning reserve; Pd ,max is the maximum real power generation of unit d.
Problem Formulation
III. Minimum up and down constraint:
1, if Td ,on Td ,up
X dt = 0, if Td ,off Td ,down
0 or 1 otherwise
where Td ,on and Td ,off are the duration of "on" and "off" of unit d; Td ,up and Td ,down are the minimum uptime and downtime of unit
d.
1) Random movement:
𝑄 = 𝑟𝑎𝑛𝑑(1, 𝑛).∗ (𝑢𝑏 − 𝑙𝑏) + 𝑙𝑏
where n is the number of dimensions, ub and lb are the upper and lower limits.
The coot changes locations in the search space. Coot's new position is defined by the
following equation
𝐶𝑜𝑜𝑡𝑝𝑜𝑠(𝑘) = 𝐶𝑜𝑜𝑡𝑝𝑜𝑠(𝑘) + 𝐴 × 𝑟𝑎𝑛𝑑 × (𝑄 − 𝐶𝑜𝑜𝑡𝑝𝑜𝑠(𝑘))
where iter and MaxIter are the current iteration and maximum iteration.
Coot Algorithm
2) Chain movement:
Cootpos(k ) = 0.5 (Cootpos(k − 1) + Cootpos(k ))
where Cootpos(k-1) is the previous (second) coot.
3) Position adjustment based on the group leaders: The leader is chosen utilizing the
following equation
D = 1 + (k MOD L)
where k and D are the index number of the current coot and the leader, and L is the number of leaders.
The coot’s next location is determined using the equation below following the best leader.
Cootpos(k ) = Leaderpos(d ) + 2 rand
cos(2 R ) ( Leaderpos(d ) − Cootpos(k ))
where R is the random numbers in the range of [-1,1].
Coot Algorithm
4) Leader movement:
B rand cos(2 R ) rand 0.5
( pBest − leaderpos(k )) + pBest
Leaderpos(k ) =
B rand cos(2 R ) rand = 0.5
( pBest − leaderpos(k )) − pBest
Initialize parameters
• For finding the best UC scheduling, coot algorithm Find the best coot/leader as global
optimum (pBest)
is applied to reduce the objective function while Update the position of the coot
All No
constraints
satisfy?
•
Increase Yes
After evaluating the fitness function, the constraints iteration Update leader position
Yes
Update global optimum (pBest)
No
Max
iteration?
Yes
Global optimal output
End
•
14 207.85 0 0 18.90 4087.13
The total operating cost a day with and without 15 202.88 0 0 18.44 3984.73
16 191.22 0 0 17.38 3750.94
BESS are $120409 and $124193, and simulation 17 227.07 0 0 20.64 4500.63
times 527.877012s and 519.725659s, respectively. 18
19
185.86
202.00
65
0
0
81.25
22.81
25.75
5845.78
6479.98
20 235.66 0 81.25 28.81 7207.12
21 202.00 0 81.25 25.75 6479.98
22 248.05 0 0 22.55 4981.80
23 207.24 0 0 18.84 4074.55
24 175.89 0 0 15.99 3458.25
Conclusion
• The obtained outcomes show that a small BESS unit can substantially minimize the
running costs up to 6% when allocated to supply power in the UC stage.
References
1. S. S. Fazlhashemi, M. Sedighizadeh, and M. E. Khodayar, "Day-ahead energy management and feeder reconfiguration for microgrids with CCHP and energy
storage systems," Journal of Energy Storage, vol. 29, p. 101301, 2020/06/01/ 2020, doi: https://doi.org/10.1016/j.est.2020.101301.
2. M. A. Matos and R. J. Bessa, "Setting the Operating Reserve Using Probabilistic Wind Power Forecasts," IEEE Transactions on Power Systems, vol. 26, no. 2, pp.
594-603, 2011, doi: 10.1109/TPWRS.2010.2065818.
3. P. Nikolaidis and A. Poullikkas, "A novel cluster-based spinning reserve dynamic model for wind and PV power reinforcement," Energy, vol. 234, p. 121270,
2021/11/01/ 2021, doi: https://doi.org/10.1016/j.energy.2021.121270.
4. H. Jiang et al., "Dynamic reserve demand estimation model and cost-effectivity oriented reserve allocation strategy for multi-area system integrated with wind
power," IET Generation, Transmission & Distribution, vol. 12, no. 7, pp. 1606-1620, 2018, doi: 10.1049/iet-gtd.2017.0868.
5. J. Wang et al., "Wind power forecasting uncertainty and unit commitment," Applied Energy, vol. 88, no. 11, pp. 4014-4023, 2011/11/01/ 2011, doi:
https://doi.org/10.1016/j.apenergy.2011.04.011.
6. S. Yuan, C. Dai, A. Guo, and W. Chen, "A novel multi-objective robust optimization model for unit commitment considering peak load regulation ability and
temporal correlation of wind powers," Electric Power Systems Research, vol. 169, pp. 115-123, 2019/04/01/ 2019, doi:
https://doi.org/10.1016/j.epsr.2018.12.032.
7. H. Quan, D. Srinivasan, A. M. Khambadkone, and A. Khosravi, "A computational framework for uncertainty integration in stochastic unit commitment with
intermittent renewable energy sources," Applied Energy, vol. 152, pp. 71-82, 2015/08/15/ 2015, doi: https://doi.org/10.1016/j.apenergy.2015.04.103.
8. A. Rezaee Jordehi, "An improved particle swarm optimisation for unit commitment in microgrids with battery energy storage systems considering battery
degradation and uncertainties," International Journal of Energy Research, https://doi.org/10.1002/er.5867 vol. 45, no. 1, pp. 727-744, 2021/01/01 2021, doi:
https://doi.org/10.1002/er.5867.
9. A. Rezaee Jordehi, "A mixed binary-continuous particle swarm optimisation algorithm for unit commitment in microgrids considering uncertainties and
emissions," International Transactions on Electrical Energy Systems, https://doi.org/10.1002/2050-7038.12581 vol. 30, no. 11, p. e12581, 2020/11/01 2020,
doi: https://doi.org/10.1002/2050-7038.12581.
10. P. Harsh and D. Das, "Energy management in microgrid using incentive-based demand response and reconfigured network considering uncertainties in
renewable energy sources," Sustainable Energy Technologies and Assessments, vol. 46, p. 101225, 2021/08/01/ 2021, doi:
https://doi.org/10.1016/j.seta.2021.101225.
11. M. Islam, H. Shareef, and A. Mohamed, "Optimal siting and sizing of rapid charging station for electric vehicles considering Bangi city road network in
Malaysia," Turkish Journal of Electrical Engineering and Computer Sciences, vol. 24, pp. 3933-3948, 2016.
Thank you for your attention