M.O.

M points

Date: 08/08/2023

Attend:

Mr. Aditya Sir (HO)

Mr. Vijay Sir (HO)

Mr. Parag Sir (HO)

Mr. M Sakib Ansari (JDISG)

Mr. Amit (JDISG)

Scan copies for level Sheet

 RA Bill measurements to be cleared by tomorrow 12:00PM


 Mobile tower will be arrived on site on date 10.08.2023
 Daily site meeting for Progress, Material, Manpower & bill status
 Vendor selection for compound wall sample.
 Written Instruction & approval needed for black japan from JLL.
 65 mm Cover block making (Total stock Qty at site & Mfg start date & todays status)
 Waller material procurement status
 Site store will be ready by the Date -
 Quality cube reports required on daily basis.
 Column shuttering schedule to be given to Parag sir
 Daily basis cost sheet to be mail to HO
 GFC general drawing to be mail to JLL by tommorow
 Long lead items to be provide by Friday on Dated 11.08.2023
 Labour report(Carpenter & fitter) to be maintain
 Raj Karan labour requirement to be increased.
 Make delay register(As like as FAME site) & mail by tomorrow 09.08.2023 HO
 Paver block completion work for pathway.
 DDS & DLS to be fill by site team & submit to planning team
 Plan vs Achieved & next day planning required on daily basis at the EOD
 Footing casting to be increased.
 For reinforcement checking mail to client to reduce the delay in casting work.
 Avoid sharing planning documents like DPR, DLR, WPR, MPR etc. direct to client (without
approval from HO team , Vijay sir, Parag sir & Aditya sir)
 20 no’s footing & 7 no’s columns should be cast till Saturday by Dated 12.08.2023
 6 footings & 6 PCC per day target to be achieved anyhow.
 Mail to MEP department for CCTV installation.
 Make RFI & mail to client regarding 8mm steel in Plinth beam top bar.
 Make trial mix for another RMC plant nearby ISPAT Gate plant by 09.08.2023