Professional Documents
Culture Documents
01 - RAP Vol-I - Main Report-CASA 1000 PAK TL
01 - RAP Vol-I - Main Report-CASA 1000 PAK TL
01 - RAP Vol-I - Main Report-CASA 1000 PAK TL
EXECUTIVE SUMMARY
ES.1 Introduction and Overview
Central Asia-South Asia (CASA-1000) is a cross-border electricity transmission project.
The project development objective is to create the conditions for sustainable electricity
trade between the Central Asian countries of Tajikistan and Kyrgyz Republic and the
South Asian countries of Afghanistan and Pakistan. Surplus energy available with
Kyrgyzstan and Tajikistan Republic will be exported to Afghanistan and Pakistan, under
the project. The CASA-1000 project will facilitate the first electricity trade of 1,300
megawatts (MW) of planned summer time hydropower surplus between the two regions.
The Pakistan component of the CASA-1000 project consists of approx. 113 km of 500
kV High-Voltage Direct Current (HVDC) line crossing Peshawar, Nowshera and Khyber
Pakhtunkhwa province. The Government of the Islamic Republic of Pakistan has been
allocated grant funds from the World Bank (WB) for the implementation of the proposed
project.
The National Transmission and Despatch Company (NTDC) is the Executing Agency
(EA) of CASA-1000 Project, Pakistan. NTDC has undertaken an environmental and
social assessment of the proposed transmission line project (thereafter referred to as ‘the
Project’) in accordance with the national regulatory requirements and World Bank
Environmental Assessment Policy OP 4.011. This Resettlement Action Plan (RAP)
addresses the resettlement impacts of the Project in accordance with the requirements of
World Bank Involuntary Resettlement Policy OP 4.12. An ESIA for the project has also
been prepared in parallel.
This RAP presents the socioeconomic baseline conditions of the project area, identifies
potential resettlement impacts, and proposes appropriate mitigation measures. Eligibility
and compensation entitlements are described, as is the resettlement budget, the
stakeholders’ consultation and information disclosure, as well as the institutional
arrangements and monitoring & evaluation plan.
The project route alignment is located in the jurisdiction of three Districts (Peshawar,
Nowshera, and Khyber) of Khyber Pakhtunkhwa (KP) Province. The transmission line
route generally traverses in the areas of relatively low population density. In the
Nowshera district the route passes through 14 villages, in the Peshawar district has 14
and the Khyber district has 24 villages.
1 This was conceived and planned prior to the World Bank ESF and therefore governed by the previous safeguard policies – i.e.,
OP4.01 Environmental Assessment and OP4.12 Involuntary Resettlement Policy.
2 Access roads or tracks are rarely built for transmission line construction in Pakistan. In steppe areas, temporary tracks are used to
access the RoW from the nearby existing road. In mountainous areas, access is more difficult and building access tracks/roads is not
always possible or feasible.
C. Affected structures
Loss of residential
Residential structures Nos. 4 4
structures
D. Affected trees
Severely affected
3 These persons are severely affected, e.g., having to relocate, or losing more than 10% of productive land or other
assets.
4 Resettlement impacts have been identified and presented in the RAP based on the route alignment of the transmission line, i.e., land under conductor & towers), the land under access routes,
borrow areas etc.) will be identified at final design. Presently, temporary impacts/ temporary land acquisition (i.e., access to road and camping site etc.) have not been demarcated yet.
5 Compensation for all assets will be paid to the owner of the asset.
4. Trees Trees affected will need All PAPs owning trees For timber/wood trees, the compensation will be at market value of
to be felled in the tower (including squatters) tree's wood content.
footprint. Fruit trees: Cash compensation based on lost production for the
entire period needed to re-establish a tree of equal productivity
(assumed to be 10 years).
5. RESETTLEMENT &
RELOCATION
Relocation allowance Transport and transitional All PAPs affected by The project will facilitate all entitled PAPs in relocating their
livelihood costs relocation affected structures at the place of their choice and a self-relocation
allowance in lump sum equivalent to PKR 25,000 per household
for one time will paid as project-based support.
The disrupted facilities and access to civic amenities like water
supply, sewerage and electricity will be restored when PAPs are
relocated.
Transport allowance All types of structures All asset owner/tenant For residential structure a lump sum amount of PKR 15,000 to
requiring relocation PAPs requiring to relocate PKR 20,000, depending upon case-by-case situation on the
due to lost land and ground.
structures For commercial structure or agricultural farm structure a lump sum
amount of PKR 10,000 to PKR 15,000, depending upon the
situation on ground.
6 The below poverty line (BPL) using the minimum wages that are fixed by the Government Gazette, Extraordinary, 31st May, 2021.
may be raised by PAPs or community members regarding impacts resulting from project
activities that are performed and/or undertaken by the PMU.
During deliberations, the PMU can call representatives from any other Department for
consultation and advisory services for resolution of grievances. There will be a
Complaint Box at the Project Implementation Unit (PIU) office on site and a dedicated
telephone number for registration of any complaints. The PMU Office will also designate
a person, not below the rank of an Office Assistant, who shall record the complaints and
immediately report them to CO Head/Executive Engineer and concerned officials.
The Grievance Redress Committee Headquarters (GRC-HQ), through an authorized
representative, will acknowledge the complaint, scrutinize the record of the GRC,
investigate the remedies available and request the complainant to produce any record in
favor of his claim. After a thorough review and scrutiny of the available record on
complaint, they will visit the field and collect additional information, if required. Once
the investigations are complete, the GRC-HQ shall give a decision within 21 days of
receipt of the complaint. If the complainant is still dissatisfied with the decision, they can
go to the court of law, if they wish to.
All records of GRC cases shall be properly maintained by the PMU Office, including
minutes of meetings and decisions made by the GRC. The complaints received in writing
or received verbally (or by phone) will be entered and properly recorded and
documented. The meeting minutes at various GRCs will be recorded and decisions made
will be as part of the input in the case record document and filed properly by respective
GRCs.
List of Tables
Table 1.1: List of villages located under the towers along the CASA-1000 T/L route 1-4
Table 2-1: Typical Activities for Overhead T/L Construction 2-6
Table 3-1: Household socioeconomic survey by District 3-1
Table 3-2: Villages and Districts along CASA-1000 TL Route 3-2
Table 3-3: Population of Districts along CASA-1000 TL Route 3-2
Table 3-4: Average Family Size and Gender Composition of Sample Households 3-3
Table 3-5: Gender Disaggregated Age Distribution 3-3
Table 3-6: Methods for Dispute Resolution/Decision making in the Project Area 3-4
Table 3-7: Literacy Rate of the Sample Households 3-4
Table 3-8: Access to School along the TL Route 3-5
Table 3-9: Housing Conditions of Surveyed Households 3-5
Table 3-10: Access (%) to Amenities in Project Area 3-6
Table 3-11: Major Occupations of Sample Households 3-6
Table 3-12: Average Annual Income of Earning Family Members of Households 3-7
Table 3-13: Average Annual Expenditure of Surveyed Households 3-7
Table 3-14: Average Annual Income and Expenditure of Sample Households 3-7
Table 3-15: Average Amount of Credit Obtained by Sample Households 3-7
Table 3-16: Sources of Credit Obtained by Sample Households 3-8
Table 3-17: Purpose of Credit Obtained 3-9
Table 3-18: Land within the RoW of CASA-1000 TL 3-10
Table 3-19: Land Holdings in Project Area 3-10
Table 3-20: Cropping Pattern in Project Area 3-10
Table 3-21: Average Yield of Major Crops in Project Area 3-11
Table 3-22: Livestock Inventory of Sample Households 3-11
Table 3-23: Cultural and Religious Sites 3-11
Table 3-24: Women’s Involvement (%) in Household and Other Activities 3-13
Table 3-25: Women Involvement in Income Generation Activities 3-13
Table 3-26: Ranking of Development Needs of the Surveyed Households 3-14
Table 3-27: Vulnerable PAPs 3-15
Table 4.1: Number of affected households by district 4-1
Table 4-2: Land required for the Towers and Conductor in RoW 4-3
Table 4-3: Impacts on Land Due to Towers Installation 4-4
Table 4-4: Impacts on Land Due to Installation of Conductors in RoW 4-5
Table 4-5: Affected Cropped Area 4-6
Table 4-6: Privately Owned Wood/Timber Trees located within the RoW 4-6
Table 4-7: Privately Owned Fruit Trees Located within RoW 4-6
Table 4-8: Forest Wood/Timber Trees Located within RoW 4-7
Table 4-9: Affected Residential Structures located within the RoW 4-7
Table 4-10: Project Impact on Livelihood & Severely Affected Persons 4-8
Table 4-11: Community and Public Structures 4-8
Table 4-12: Summary of the Project Resettlement Impacts 4-10
Table 5.1: Key Clauses of Land Acquisition Act 5-1
Table 5.2: WB Involuntary Resettlement & Pakistan Land Acquisition Act 5-5
Table 6-1: Entitlement Matrix 6-5
Table 8-1: Overview of Consultations 8-5
Table 8-2: Consultations with Government Officials 8-6
Table 8-3: Consultations with the PAPs/ Local Communities 8-6
Table 8-4: Community Consultations Stakeholder Feedback along the Proposed CASA-
1000 Route Alignment 8-8
Table 8-5: Institutional Consultation Feedback 8-12
Table 11.1: Unit Rates of Non-land Assets 11-2
Table 11.2: Compensation for the Loss of Land under Towers 11-3
Table 11.3: Compensation for the Loss of Cropped Area 11-3
Table 11.4: Compensation for Loss of Wood Trees 11-3
Table 11.5: Compensation for Loss of Fruit Trees 11-4
Table 11.6: Compensation for Loss of Structures 11-4
Table 11.7: Relocation Assistance 11-5
Table 12.1: Resettlement Compensation Estimates 12-1
List of Figures
Figure 1.1: Proposed Route of Transmission Line (CASA-1000) Project 1-3
Figure 2.1: Alignment of Transmission Line (CASA-1000) by locations 2-2
Figure 2.1: Typical Design of 500 kV DS1 Angle Tower 2-3
Figure 4.1: Line route of 500 kV HVDC 4-2
Figure 8.1: Communications Framework and Levels of Engagement 8-14
Figure 10.1: Institutional Setup for RAP Implementation 10-2
Figure 10.2: RAP Implementation Schedule and Tentative Timeframe 10-8
Main Report:
Photographs of Selected Events
Currency Equivalents
(As of 19st October, 2021)
List of Acronyms
AoI Area of Influence
ACSR Aluminum Conductor, Steel Reinforced
BPL Below Poverty Line
C&W Communication & Works (Department)
CAS Compulsory Acquisition Surcharge
CASA Central Asia South Asia
CASAREM Central Asia-South Asia Regional Electricity Market
CO Camp Office
CSO Civil Society Organizations
CSP Community Support Program
DC District Collector’s
DFO District Forest Officer
DMS Detailed Measurement Survey
DO (R ) District Office, Revenue
EA Executing Agency
Measuring Units
MW Megawatt
KW Kilowatt
MWh Mega Watt Hour
KWh kilo Watt Hour
Ha Hectare
km kilometer
m meters
kg kilogram
Glossary of Terms
Asset Inventory A complete count and description of all property that may be affected due
to the project.
Resettlement Allowance Cash paid to cover resettlement related expenses other than losses of
immoveable assets. For example, tenants can be provided with a cash
allowance to support their effort to secure alternative housing. A moving
allowance can be paid to people who have to relocate as a result of
Project land acquisition. An allowance is distinguished from
compensation, which reimburses the loss of an immoveable asset
Baseline A set of pre project conditions used as a benchmark for the project.
Resettlement Compensation Payment in cash or in kind for an asset or resource acquired or affected by
the project.
Cultural Heritage Attributes of a group or society that are inherited past generations,
maintained in the present.
Customary Law A law passed down through oral tradition, which has now been adopted by
the community as riwaj (presently two different types of traditional laws
operate in the project area with reference to use rights and management of
natural resources).
Cut-off-Date The date of start of census for all non-land related entitlements and for
land, it is the date for announcement of Section 4 notification under the
LA Act of 1894. Any person entering the project area after the cut-off date
is not eligible to receive the agreed upon entitlements.
Disclosure Openly available for public (website & public libraries and project offices)
Economic Displacement A loss of productive assets or usage rights or livelihood capacities because
such assets, rights or capacities are located in the directly affected area.
Economic Rehabilitation Economic rehabilitation implies the measures taken for income
restoration or economic recovery, so that the affected population can
improve or at least restore its previous standard of living.
Entitlement Range of measures comprising compensation, income restoration,
transfer assistance, income substitution, and relocation, which are due to
displaced persons, depending on the nature of their losses, to restore their
economic and social base.
Eligibility The criteria for qualification to receive benefits under the resettlement
plan.
Encroachers/ squatters People who have trespassed onto private/community/public land to
which they are not authorized. If such people arrived before the
entitlements cut-off date and identified during the census, they are
eligible for compensation for any structures, crops or land
improvements that they will lose.
Grievance Mechanism This is an extra-legal and project-specific mechanism by which project-
affected persons (PAPs) or general public can raise their concerns to
project authority. The processes established by local regulations and
administrative decision to enable affected people to their rights as per the
approved policy matrix. This is in addition to existing legal processes that
allow owners of assets acquired to redress any grievances (by the formal
court).
Inventory of Lost Assets Descriptive list of all assets lost to the project, including land, immovable
property (buildings and other structures), and incomes with names of
owners.
Involuntary Resettlement Land and/or asset loss which results in a reduction of livelihood level.
These losses have to be compensated for so that no person is worse off
than they were before the loss of land and/or assets.
Jirga Jirga refers to the assembly of local elders to resolve the community
concerns.
Kharif Summer cropping season of the year (15 th April – 15th September)
Katcha House or building made of un-burnt bricks and/or mud with
wooden/thatched roof. Not made of brick and mortar.
Livelihood restoration Specific activities intended at supporting displaced peoples’ efforts to
restore their livelihoods to pre-project levels. Livelihood restoration is
distinguished from compensation. Livelihood restoration measures
typically include a combination of cash or other allowances and support
activities such as training, agricultural assistance or business
enhancement. Livelihood restoration is often referred to as economic
rehabilitation.
Rabi Winter cropping season of the year (15 September – 15 th April)
Mouza (Village) A demarcated territory, for which separate revenue record (Cadastral
map) is maintained by the Revenue Department.
Market Value It is more broadly defined as "the price which a willing vendor would
reasonably expect to obtain from a willing purchaser. It is the value to the
seller of the property in its actual condition at the time of expropriation
with all its existing advantages and with all its possibilities excluding any
advantage due to the carrying out of a scheme for which the property is
compulsorily acquired”.
Pacca A house/ structure is considered ‘pacca’, if both the walls and roof of the
house are made of material that includes bricks, cement, sheets, slates,
corrugated iron, zinc or other metal sheets, bricks, lime and stone or
RBC/RCC concrete. Made of brick and mortar.
Patwari Revenue record keeper at village level. Revenue Clerk
Project Affected Household All members of a project affected household residing under one roof and
operating as a single economic unit, who are adversely affected by the
Project or any of its components; may consist of a single nuclear family
or an extended family group with multiple married couples.
Project Affected Persons Any person adversely affected by any project related change or changes in
use of land, water or other natural resources, or the person/s who loses
his/her/their asset or property movable or fixed, in full or in part including
land, with or without displacement, after the commencement and during
execution of a project.
Rehabilitation Compensatory measures provided under the WB Policy Framework on
Involuntary Resettlement other than payment of the replacement cost of
acquired assets.
Relocation The physical resettlement of PAPs from his/ her pre-program place of
residence.
Resettlement Strategy The approaches used to assist people in their efforts to improve (or at
least to restore) their incomes, livelihoods, and standards of living in real
terms after resettlement.
Resettlement Action Plan A resettlement action plan (RAP) is the planning document that describes
what will be done to address the direct social and economic impacts
associated with involuntary taking of land.
Resettlement Entitlements Resettlement entitlements with respect to a particular eligibility category
are the sum total of compensation and other forms of assistance provided
1. Introduction
1.1. Overview
Central Asia-South Asia (CASA-1000) is a cross-border electricity transmission project
that aims at establishing an electricity trade involving the transfer of surplus hydropower
available in Central Asia to electricity-deficient countries in South Asia. Surplus energy
available with Kyrgyzstan and Tajikistan Republic will be exported to Afghanistan and
Pakistan, under the project agreements. The CASA-1000 project will facilitate the first
electricity trade of 1,300 megawatts (MW) of the upcoming planned summer time
hydropower surplus between the two regions. The Pakistan component consists of about
113 km of the 500 kV HVDC line passing through Nowshera, Peshawar and Khyber
(Torkham) in Khyber Pakhtunkhwa province of Pakistan.
The Government of the Islamic Republic of Pakistan has received grant funds from the
World Bank (WB) for the implementation of the proposed project. National Transmission
& Despatch Company (NTDC) has been mandated with the construction and operation of
Pakistan component of this project. NTDC has undertaken an environmental and social
assessment of the proposed transmission line (CASA-1000 TL) Project in accordance
with the national regulatory requirements and World Bank operational policies. 7 The
Resettlement Action Plan (RAP) has been prepared as one of the outcomes of the
environmental and social assessment, and addresses the resettlement impacts of the
Transmission Line Project in accordance with the requirement of World Bank
Involuntary Resettlement Policy OP 4.12. The present RAP covers the transmission line
located in the jurisdiction of Khyber Pakhtunkhwa (KP) province of Pakistan.
This RAP presents the socioeconomic baseline conditions of the project area, identifies
potential resettlement impacts, and proposes appropriate mitigation measures. Eligibility
and compensation entitlements are described, as is the resettlement budget, the
stakeholders’ consultation and information disclosure, as well as the institutional
arrangements and monitoring & evaluation. NTDC Pakistan is the Executing Agency
(EA) responsible for the implementation of Resettlement Action Plan (RAP) of CASA-
1000 Project, Pakistan.
In addition to this RAP, the CASA-1000 TL Project has been subject to preparation of
several environmental and social investigations and studies, including:
Land Acquisition and Resettlement Framework (LARF), to cover broad potential
social impacts for all IFIs funded projects to be managed by NTDC, including ADB
and World Bank.
Regional Environmental Assessment (REA), to examine strategic environmental and
social issues and impacts associated with the projects including CASA-1000 TL in
the region.
Social Impact Assessment (SIA), to report potential social impact of the project (in
design, pre-construction and construction stages, as well as long-term), and propose
mitigation and management measures. The report summarized previous work on
social aspects, including community benefit sharing, social aspects and risk
assessment work in Afghanistan and Pakistan.
7 Since CASA was conceived during pre-ESF period, the Project safeguard policies are governed by OP4.12 and other
relevant instruments. ESF guidelines are not applicable.
Ghari Chanden, Churkh, Ghari Maina, Ghari Harchn, Ghari Noor Hasham,
Peshawar Thala Band, Matani Aza Khel, Maryam Zai, Khar Khari, Zang Ali, Sara
Khawar, Sara Khawar Matini, Aka Khel, Matani
Sanzal Khel, Ramga Sanzal Khel, Rustam Khel, Umber Khel, Sultan Khel,
Mada Khel, Masood Khel / Mom Khel, Umer Khel / Mori Khel, Mori Khel,
Khyber Dojangi, Pesho Khawy, Asghr Tulads, Fort Stope, Katia Khel, Mania Khel,
Toor Khel, Sapai, Ali Masjid, Kalah Kusta Gheroba, Niki Khel, Bagi Khel,
Fatinee Khel, Ashraf Khel, Pasoad Khel
This transmission line will be constructed in accordance with NTDC specifications.
Towers generally have a construction footprint of 15 m x 15 m (225 m2) with an average
height of 35m. Foundations are expected to be excavated to a depth of 2-3 m with tower
footings extending a further 1m above ground level as a rule. The typical span between
towers is 350-400m, although this distance increases or decreases depending upon the
topography and geography of the location. In hilly areas, the length decreases while in
populated areas it is generally greater. NTDC policy is to maintain a 52 m (26 m from
either side of the centerline of T/L) Right of Way (RoW) that will need to be cleared.
NTDC undertook detailed engineering survey and in 2019 elaborated the sitting of 500
kV towers along this route and also carried out site investigation. Further details of the
project are presented in Chapter 2 of this document.
1.4. Right of Way (RoW)
The RoW is the strip of land along either side of the centerline. Vegetation within the
RoW is not allowed to grow to a height above 3 m and no permanent structures shall be
constructed within the RoW. Proper clearance to ground and other structures has to be
maintained. The total width of the RoW will be 52 m, (i.e., 26 m on either side from the
centerline). The RoW is not to be used for public road access. Any maintenance road
access should be on the edge of the RoW to avoid encroachment within RoW.
Consultations were carried out with the PAPs/local communities, through village level
meetings to share the project information, to obtain feedback from the communities about
the project and its perceived impacts, and to collect anecdotal information, and
socioeconomic baseline in the study area. Separate consultations were carried out with
women of the study area to obtain their views and concerns regarding the project.
Consultations were also conducted with the concerned government departments and non-
government organizations to obtain their views about the project.
Resettlement impacts/inventory of losses of the project were identified. This was done by
conducting the detailed measurement survey (DMS), e.g., measuring the floor space of
buildings. These included impacts on land, crops, trees, houses, structures/
community/social structures and public infrastructure/ utilities.
An entitlement matrix has been prepared in accordance with the national legislation as
well as World Bank safeguard policies on involuntary resettlement. Based on the
Entitlement Matrix, compensation for each kind of impact was determined and the total
resettlement cost estimates prepared. Finally, the RAP implementation, institutional,
monitoring & evaluation; and documentation arrangements were formulated and
discussed in this RAP.
1.7. Study Team
The RAP study was carried out by the consultant on behalf of NTDC. The Team of
subconsultant (M/s International Development Consultants) consisted of specialists from
various disciplines. The Team members include: Mr. Shaukat Ali Shahid, Mr. Zaffer Ali
Bhatti, Mr. M. Saeed Khan, Mr. Sadaam Hussain, Mr. Nadeem Ahmed, Mr. Fahem
Khan, Mr. Javeed Khan, Ms. Gulnaz, Ms. Shazia Zubair, Mr. M. Hanif, Mr. Mudassar
Hassan & Ms. Alia Arshad.
2. Project Description
2.1. Background
Under the first phase of Central Asia-South Asia Regional Electricity Market
(CASAREM), CASA-1000 envisages the construction of a transmission line to enable
electricity exports from the Kyrgyz Republic and Tajikistan to Afghanistan and Pakistan
with the financial assistance of the World Bank.
2.2. CASA-1000 Alignment
The CASA-1000 TL, alignment is shown in Figure 2.1; a more detailed series of maps
(based on Google Earth imagery) is presented in Annex A. The project route alignment is
located in the jurisdiction of three districts (Nowshera, Peshawar and Khyber of KP
province of Pakistan. The transmission line route generally traverses in the areas of
relatively low population densities. The present RAP has been prepared as an outcome of
the social assessment and addresses the land acquisition and resettlement impacts
associated with the proposed Project in accordance with the requirement of World Bank
Involuntary Resettlement Policy OP 4.12.
2.3. CASA-1000 TL Design
The salient information on CASA-1000 TL design is presented in this Section. This
includes tower design, their foundations, transmission conductor and insulators, and
minimum clearance requirements.
2.3.1. Transmission Line Towers and their Outline Design
The proposed transmission line requires five tower types; these include tangent
suspension tower used for no line angle/small line angle up to 2degree, small angle tower
used for line angles from 2 degree to approx., 15 degree, medium angle tension tower
used for line angles from approx., 15 degree to approx. 30 degree, heavy angle tension
tower used for line angles from 30 degree to 60 degree and the remaining are terminal
towers used at the line terminals and as anti-cascade towers at intervals along the line.
The proposed TL will require about 374 towers. The average size of each tower footing
will be 15 m x 15 m (225 m 2). The length is approximately 113 km. The right of way
(RoW) of the transmission line will be 52 m wide. The distance between towers will be
between 350 m and 400 m. The average height will be about 35 m. Tower design is
illustrated in Figure 2.2.
The requirement is to construct the 500 kV transmission line featuring self-supporting
lattice steel towers conforming to NTDC’s suite of standard +/- 500 kV line towers
comprising (Type PA-0; (ii) Type PHB-15, and (iii) Type PHC-30 and (iv) Type PHD-
60, Type PHDS-60 tower designs.
The Bi-poles are in horizontal geometric arrangement with four bundle conductor. The
tower features twin optical ground wires (OPGW) providing shielding against lighting
strikes along with overhead continuity of the earth connections between towers while also
establishing optical communication links between converter stations.
These towers are designed for a quad bundle Cardinal Aluminum conductor steel-
reinforced (ACSR). The towers will be of lattice steel design, similar to the ones which
are commonly used for high voltage transmission lines in Pakistan.
Figure 2.1: Typical Design of 500 kV DS1 Angle Tower
8 This optical fiber is meant for Supervisory Control and Data Acquisition (SCADA) system.
based on the conductor technical performance as well as its impact on the construction
cost and the impact of losses over the life of project.
For the construction of 500kV double circuit TL, all the parameters with respect to
electrical performance and environmental effects for this TL have been examined and
applied based on the international standards and experience of Utilities that have adopted
500kV system in the world.
Guaranteed protection of TLs against over-voltages is virtually impossible. However, line
insulation must have enough strength to meet the stresses produced by over-voltages. In
all cases (power frequency, switching and lighting), the insulation should be able to
withstand failure or disruptive discharges.
The minimum clearances will have to be maintained at the specified maximum conductor
temperature with the phase conductors and suspension insulators hanging vertically or
deflected to any angle up to 70° from the vertical.
2.4. Alternatives for Minimizing the Project Impacts
The following steps were considered by the NTDC to minimize the social impacts of the
proposed transmission line project:
Impacts on settlements/ villages were avoided to the extent possible while
selecting the route alignment for installation of the transmission line;
In consultation with local people/community, efforts were made to select an
alignment avoiding as much as possible private and public structures/
infrastructure requiring resettlement.
A wider corridor for the CASA TL was selected with the primary objective to avoid
populated areas. This corridor was further refined by analyzing three alternative TL
routes (Option-I, Option-II and Option-III). The parameters used for this analysis
included; economic aspects, construction related issues, accessibility issues; social
aspects and environmental aspects. Based on detailed analysis, Option-I was selected as
the preferred one from all aspects. It has a total length of 113 km, it is easily accessible
from the existing road network, and it does not cross any environmentally designated or
otherwise sensitive areas, while it generally avoids populated areas. In this way, the most
appropriate route alignment of the proposed transmission line was selected with
minimum social impacts. The details of analysis of alternatives is presented in the ESIA.
2.5. Social Impact Assessment
The social impacts of the project were assessed within both Corridor of Impact (COI) and
Area of Influence (AOI).
The COI is confined to the RoW of the transmission line. The RoW is a 52 m
wide corridor along the transmission line–26 m on either side from the centerline
of the transmission line. The resettlement impacts are limited to the COI.
AoI is a 2-km wide corridor along the transmission line, one kilometer on either
side from the centerline of the transmission line. This area is likely to receive
indirect impacts of the project activities; no resettlement impacts are likely to take
place in this area. The sample-based socioeconomic survey, to collect the baseline
conditions of the area, has been carried out in this AoI.
Activity Description
For tower locations where it is determined vehicle access is
required, access will be via existing access tracks
The RoW/surrounding land with no new access track
construction
In certain circumstances, where ground conditions prevent
normal access, it may be necessary to construct a
temporary access track.
In mountainous areas, cable trolleys may also be used to
access the site and to transport material to the tower
location and other parts of the RoW.
3 Civil Works Tower foundations will be constructed first, either four or
one foundations per tower depending on the final tower
design. The foundations will be mechanically excavated
and filled with concrete. Piled foundations may be required
in some areas where ground conditions are unstable. The
dimensions of the excavation will differ depending on the
type of tower to be installed and the quality of soil/rock.
Concrete would be delivered by ready mixed concrete
trucks from batching plants strategically located along the
route. However, if the access road is not available, the
concrete will be mixed at the tower location by small mixer
machines.
Foundation strengthening works typically require
increasing the bulk of concrete in the foundation,
depending on the additional tower loads that are expected.
This normally involves excavation around the existing
foundation and application of additional concrete.
4 Steel Erection Steelwork sections for the towers will be delivered by
access track, cable cars/trolleys and helicopter (if possible).
The assembly of each tower at ground level would proceed
as far as possible until the utilization of a crane becomes
necessary to enable the higher sections of the tower to be
completed. It is normal practice to use cranes to erect
steelwork, subject to good access being available.
Otherwise, tripod and chain-pully are employed for this
purpose. In very rare cases where terrain is difficult and to
minimize disturbance, steelwork may be delivered by
helicopter.
5 Conductor Stringing is undertaken using a winch to pull the conductor
Stringing along the towers and a ‘tensioner’ at the other end to keep
the conductor above the ground. Typically, the sections
depend on the requirement of angle towers decided during
the construction phase. These winch locations are not fixed
and can be selected to minimize impact at sensitive
locations.
6 Testing of Overhead line components including conductors,
Activity Description
Equipment insulators, towers, joints and fittings are designed and
tested to prove compliance with structural, mechanical and
electrical requirements.
7 Reinstatemen At completion, the area would be cleared and tidied up.
t of Tower Fences and hedges would be repaired, and access routes
Construction and disturbed land would be reinstated in agreement with
Area the land users and title owners. Any site security fences
would be retained throughout the dismantling and
construction process.
others. Preference will be given to establishing these camps within the WAPDA or
NTDC owned premises. Otherwise the land for these camps will be obtained on a rental
or lease basis in accordance with the Entitlement Matrix as specified in this RAP.
In addition to the construction camps, the contractor may establish temporary
construction camps near the tower locations (away from the nearby villages, and
preferably near some towns). Construction of each tower requires about eight days (four
days for foundation and four days for erection) per one gang (a group of workers).
2.8.3. Machinery Yard
A machinery yard will also be needed for each construction team; it can be combined
with the construction camp or established separately. The machinery yard will be parking
bays, maintenance and washing bays, fueling arrangements, oil and fuel storages,
firefighting arrangements, and tools and parts storage.
2.8.4. Batching Plants
The contractors may need to establish concrete mixing and batching plants for tower
foundation construction. These plants will be established at appropriate places based
upon the distance from and accessibility to the tower locations. The batching plants will
be completed with dust control arrangements.
2.9. Project Implementation Time Frame
The commencement of civil work will be subject to the satisfactory implementation of
this RAP including payment of compensation and R&R assistance/allowances for the loss
of crops, trees and structures, as well as redress of community complaints. It is expected
that the construction of the Transmission Line (CASA-1000) Project will be completed
over a period of about 2 years (2022-2024). The disbursement of payment of
compensation and allowances will be carried out in parallel with the project
implementation and will be completed till the end of 2023. Moreover, the implementation
of CSP including benefit-sharing component will also continue simultaneously with the
project implementation.
2.10. Operational and Maintenance Requirements
The power evacuation facilities will be operated and maintained by NTDC in accordance
with its general system maintenance procedures. This involves an inspection regime
which requires access to the towers from time to time and visual inspection of the line
corridor. Where defects or repairs are noted, maintenance crews will be mobilized to
undertake the corrective works. Land users and title holders are required to keep tree
heights within the 3m limits and this requirement is enforced by the NTDC inspection
teams. Also, the ability to access the right of way is ensured.
There should larger scale works be identified, then this will generally be undertaken by
suitable call-off contractors under individual contracts.
3. Socioeconomic Baseline
3.1. Overview
This Chapter describes the socioeconomic baseline conditions of the project area. This
description has been prepared on the basis of on the detailed field surveys including
interviews, focus group discussions, impact assessment and measurements, community
consultations and information disclosure, stakeholder consultation meetings, transact-
walk, physical observations, gender survey to accomplish this RAP document. In
addition, photographs were also taken of selected events of field surveys and consultative
meetings.
3.2. General
The socioeconomic conditions of PAPs were derived from primary data through
conducting field survey, and supplemented through secondary data obtained from NTDC,
local community including PAPs, other concerned departments and websites. The
primary data include a socioeconomic survey of the affected families/ PAHs. The
socioeconomic profile of the area has been developed based on the interviews of 322
households selected randomly from the project area.
3.3. Data Collection Approach
The socioeconomic baseline data was collected from both primary and secondary
sources. Most of the primary data was collected through a sample-based survey carried
out along the CASA-1000 transmission line route, which passes through three districts of
the Khyber Pakhtunkhwa. For the socioeconomic survey, a sample of 322 households
was selected randomly from the project area. The survey covered the entire length of this
area and the survey results can be considered as being representative of the entire project
area/project alignment.
The detailed socioeconomic description field surveys, interviews, and public
consultations have been carried out to collect the baseline data, which provide the basis
for subsequent monitoring and evaluation studies. The sample size and its distribution by
district is presented in Table 3.1.
Table 3-2: Household socioeconomic survey by District
Number of Households
Districts
Villages surveyed
Nowshera 14 216
Peshawar 14 66
Khyber 24 40
Total 52 322
districts have a more urban lifestyle with greater access to education and healthcare
facilities, and much better livelihood opportunities compared with the rural parts of the
CASA-1000 TL route.
The TL route has been selected to avoid large towns and human settlements to minimize
technical as well as social issues during TL construction and operation.
The Nowshera district has 14 villages, Peshawar district has 14 and the Khyber district
has 24 through which the route will pass as listed in Table 3.2.
Table 3-3: Villages and Districts along CASA-1000 TL Route
Districts Villages
Aza Khel Bala, Ishar Sari, Steen Kana, Speen Kalal Cand, Jaba Tar, Jaba Tar
Nowshera Miara, Zaokala, Bakhi Khel, Shaikhan Jhalazai, Pannah Kot, Khelq Banda,
Wazir Abad, Dag Ismail Khel, Speen Khak
Ghari Chanden, Churkh, Ghari Maina, Ghari Harchn, Ghari Noor Hasham,
Peshawar Thala Band, Matani Aza Khel, Maryam Zai, Khar Khari, Zang Ali, Sara
Khawar, Sara KhawarMatini, Aka Khel, Matani
Sanzal Khel, Ranga Sanzal Khel, Rustam Khel, Umber Khel, Sultan Khel,
Mada Khel, Masood Khel / Mom Khel, Umer Khel / Mori Khel, Mori Khel,
Khyber Dojangi, Pesho Khawy, Asghr Tulads, Fort Stope, Katia Khel, Mania Khel,
Toor Khel, Sapai, Ali Masjid, Kalah Kusta Gheroba, Niki Khel, Bagi Khel,
Fatinee Khel, Ashraf Khel, Pasoad Khel
Source: Socioeconomic survey of CASA-1000 TL Route
The field surveys have revealed that more than 90% of the population located within
RoW is rural in nature, while the remaining 10% is urban or semi-urban.
3.5. Demographic Profile
According to District Census Report of Khyber Pakhtunkhwa, the population of the
districts located along the CASA-1000 TL route was approximately 5.7 million in 2017
as shown in Table 3.3.
Table 3-4: Population of Districts along CASA-1000 TL Route
Population
Districts Census Census
(1998) (2017)
Nowshera 419,549 727,749
Peshawar 2,026,851 4,269,079
Khyber 430,898 718,812
Total 2,877,298 5,715,640
Source: District-wise provisional results of Census of Khyber Pakhtunkhwa (2017)
The overall average family size of households in the project area is 8.7 persons, out of
which the proportion of male and female is 52.2 percent and 47.8 percent respectively as
shown in Table 3.4.
Table 3-5: Average Family Size and Gender Composition of Sample Households
Average Gender Composition (%)
Districts
Family Size Male Female
Nowshera 7.0 53.7 46.3
Peshawar 11.0 50.5 49.5
Khyber 14.0 50.6 49.4
Overall 8.7 52.2 47.8
The data in Table 3.5 shows that overall, 38.7% of the population is in the age cohort
that is the most economically productive between 15 to 40 years old. The vulnerable
elderly people above 60 years old in the districts of Nowshera, Peshawar and Khyber are
5.4%, 4.3% and 1.6% respectively, and children 10-15 years old are 8.0%, 7.6% and
8.7%, respectively.
Table 3-6: Gender Disaggregated Age Distribution
Gender Composition (%)
Age Bracket
Male Female Both Sexes
Nowshera
10-15 Years 3.3 4.7 8.0
>15 - 30 Years 15.7 13.2 28.9
>30 - 40 Years 6.3 4.2 10.5
>40 - 60 Years 9.0 7.9 16.9
Above 60 Years 3.6 1.8 5.4
Peshawar
10-15 Years 2.1 5.5 7.6
>15 - 30 Years 13.3 14.0 27.3
>30 - 40 Years 7.8 4.3 12.1
>40 - 60 Years 5.9 5.4 11.3
Above 60 Years 2.5 1.8 4.3
Khyber
10-15 Years 3.7 5.0 8.7
>15 - 30 Years 12.5 13.9 26.4
>30 - 40 Years 6.1 3.2 9.3
>40 - 60 Years 6.1 6.1 12.2
Above 60 Years 1.4 0.2 1.6
Overall
10-15 Years 3.1 5.0 8.1
>15 - 30 Years 14.5 13.6 28.1
>30 - 40 Years 6.6 4.0 10.6
>40 - 60 Years 7.6 6.9 14.5
Above 60 Years 2.9 1.5 4.4
Khel, Kohi Khel, Khokha Khel, Zaka Khel, Sanzal Khel and Shinwari. During the
several field data collection activities carried out for the project (census, socioeconomic
survey, focus group discussions, walk-through inspections), no conflicts related to land
were observed.
3.7. Community Governance
Informal and traditional governance institutions and methods are preferred by the
villagers to resolve social disputes in between ethnic and tribal groups, relatives,
neighbors, and other villagers. Table 3.6 summarizes.
Table 3-7: Methods for Dispute Resolution/Decision making in the Project Area
Methods of Decision (%)
Districts Jirga Within the
Court (assembly of local Tribal
elders) Groups
Nowshera 3.7 95.4 0.9
Peshawar 1.5 98.5 0.0
Khyber 2.5 97.5 0.0
Overall 3.1 96.3 0.6
These above systems are also used to determine land disputes and could play their role
during the RAP implementation.
3.8. Education
The educational level in most of the project areas is very low. The reasons are lack of
schools and madrasas (religious schools) in their villages. Students often travel far from
their houses to access education. The literacy rate at district level is 52.5%, 55.9% and
53.7% in Peshawar, Nowshera and Khyber respectively). For the overall project area, the
literacy rate is 54.7%.
Gender disaggregated education details have been summarized in Table 3.7
Table 3-8: Literacy Rate of the Sample Households
Household
Districts Educational
Members (%)
Male Female Total
Attainment/ Literacy
(n=971) (n=865) (n=1836)
Nowshera Tertiary 10.2 1.8 12.0
Secondary 26.2 6.7 32.9
Primary 5.9 5.1 11.0
Overall 55.9%
Peshawar Tertiary 13.4 0.9 14.3
Secondary 21.5 5.7 27.2
Primary 4.8 6.2 11.0
Overall 52.5%
Khyber Tertiary 10.4 0.3 10.7
Secondary 16.6 5.2 21.8
Primary 13.2 8.0 21.2
Overall 53.7%
Overall Literacy Tertiary 11.1 1.3 12.4
Household
Districts Educational
Members (%)
Male Female Total
Attainment/ Literacy
(n=971) (n=865) (n=1836)
Rate for the project Secondary 23.3 6.2 29.5
area Primary 6.9 5.9 12.8
Overall 54.7%
A 91.3% of the surveyed population has access to boys’ primary schools, 68.4% have
access to girls’ primary schools, 67.4% and 60.6% respectively have access to boys’ and
girls’ middle schools, and 62.4% and 42.9% has access to boys’ and girls’ high schools,
as detailed in Table 3.8. There are also several small madrassas where students receive
religious education.
Table 3-9: Access to School along the TL Route
% of Surveyed Villages
Districts Primary Primary Middle Middle High High
school for school for school for school for school for school for
boys girls boys girls boys girls
Nowshera 95.8 53.4 77.3 77.8 74.1 56.9
Peshawar 92.4 92.4 51.5 30.3 43.9 18.2
Khyber 65.0 62.5 40.0 17.5 30.0 7.5
Overall 91.3 68.4 67.4 60.6 62.4 42.9
3.9. Healthcare
There are few facilities for general healthcare in most villages. Government hospitals are
far away and the quality of services provided by these hospitals is poor as some of the
staff remains absent from their duties. The paramedic staff do not provide an adequate
level and quality of care to patients. Only in rare cases, Lady Health Visitors (LHV) and
medical technicians are available in the villages, and if present, they charge very high for
their services and were using low quality of medicines on very high prices.
3.10. Housing Conditions
The better-off households have concrete houses, the middle-income households live in
semi-‘pacca’ houses made of cement, mud and stone and the families from lower income
households live in ‘katcha’ houses made of stone and mud. The survey results show that
100% of the sampled households are living in self-owned houses. About 43.5% of these
houses are pacca (made of brick and mortar), 30.3% of semi-pacca and about 26.2% are
katcha (made of mud, stones, wood, and or thatch) (see Table 3.9 for details).
% of Surveyed Households
Districts
Pacca Semi Pacca Katcha
Khyber 22.3 52.9 24.8
Overall 43.5 30.3 26.2
The assessment of annual household income is one of the important indicators to measure
the well-being of the household. Income of the households comes from farming,
livestock rearing, service/jobs, business, labour and working abroad. The average annual
per capita income of the sample households in the project area is PKR 45,151 , whereas
annual average household income is PKR 392,894. Details are provided in Table 3.12.
The average monthly expenditure and pattern of expenditure provides an indication of the
quality of living standards of project affected households. The expenditure on food items
include wheat or maize flour, cereals, pulses, sugar, cooking oil, and milk; while the non-
food items include fuel, education, health, clothing, shoes, cosmetics, utility charges, and
other miscellaneous expenditures. Total average annual expenditure of the surveyed
households on both food and non-food items is estimated at PKR 314,594 as given in
Table 3.13.
Table 3-14: Average Annual Expenditure of Surveyed Households
Total Expenditure
Food Expenditure
Food Expenditure
Non-Food Expenditure
Non-Food Expenditure
Districts
(PKR) (PKR) (%) (PKR) (%)
Nowshera 281,153 163,576 58.2 117,577 41.8
Peshawar 369,378 206,471 55.9 162,907 44.1
Khyber 404,786 245,303 60.6 159,483 39.4
Overall 314,594 182,520 58.0 132,074 42.0
Total average annual income of the sample household is PKR 392,894. On average,
80.1% of the income is spent on food and non-food items. A comparison of income and
expenditure levels in the project area is presented in Table 3.14.
Table 3-15: Average Annual Income and Expenditure of Sample Households
Average (PKR/ Annum)
Districts
Income Expenditure
Nowshera 343,352 281,153
Peshawar 453,364 369,378
Khyber 560,650 404,786
Overall 392,894 314,594
Access to credit from banks is limited due to high repayment interest rates. The 33.2% of
sample households who have obtained credit have borrowed above PKR 50,000 and
7.45% sample households obtained credit within the range of PKR 20,000 - PKR 50,000.
Details are given in Table 3.15.
Table 3-16: Average Amount of Credit Obtained by Sample Households
HHs Obtained Credit
Amount of Credit Bracket
No. %
Nowshera
PKR 20,000 8 3.70
PKR 20,000 - 50,000 16 7.41
PKR 50,000 56 25.93
The results of the survey have shown that people take credit despite the fact that on
average they make savings (as per Table 3.14). This paradox can be explained due to the
following:
People make savings on average, i.e. some of them will not make savings while
others will make more savings than average.
The majority of those who resort to credit are in need of relatively larger amounts of
money, i.e. PKR 50,000 or more, which seems to be the average amount of savings
made. In other words, the savings may not be enough to cover the needs of the
households.
The average savings made are in the order of USD 455 per annum, which are not
adequate to cover needs such as the purchase or repair of houses, the opening or
maintenance of a business or the purchase of household appliances, etc.
Approximately 44.1% of people obtain credit from their relatives, friends, and
landowners; as formal institutions charge high interest rates. The details regarding
sources of credit have been presented in Table 3.16.
Table 3-17: Sources of Credit Obtained by Sample Households
HHs Obtained Credit
Sources of Credit Obtained
No. %
Nowshera
Relatives 43 53.8
Private money lender 8 10.0
Other 29 36.3
Peshawar
Relatives 30 75.0
Private money lender 1 2.5
Other 9 22.5
Khyber
Relatives 9 40.9
Private money lender 1 4.5
Other 12 54.5
Overall
A total 29.8% of people possess less than 1 acres of land, 40.7 % possess between 1 and
5 acres, 15.2 % possess between 5 and 12.5 acres, 6.8 % possess between 12.5 and 25
acres and the 7.5% remaining possess more than 25 acres of land. (Table 3.19)
The major rabi (winter) and kharif (summer) crops are wheat and maize having cropping
pattern of about 56.7% and 56.2%, respectively. The cropping pattern in the project area
is given in Table 3.20
Table 3-21: Cropping Pattern in Project Area
Summer Crops Winter Crops
Cropping (15th April – 15th (15 September –
Districts Intensity September) (%) 15th April) (%)
(%)
Maize Wheat
Nowshera 118.8 57.3 61.4
Data on average yield of the major crops of the project area presented in Table 3.21
reveals that on the whole, the average yield per hectare of maize and wheat, is 2,214 kg,
2,965 kg, respectively.
Livestock is a major source of livelihood for the households and includes milk production
and animal sale and purchase. The data presented in the Table 3.22 shows that
approximately half of households raise an average of 2 animals per household. The
average numbers of poultry birds per household is 5.
Table 3-23: Livestock Inventory of Sample Households
Districts Type of Animal
Buffaloes Cows Donkey Goat Poultry
Nowshera
No. of AHs, who kept animals - 51 - 72 57
No. of total animals - 70 - 154 214
Average No. of Animals/AH - 1 - 2 4
Peshawar
No. of AHs, who kept animals 3 39 9 22 28
No. of total animals 6 60 9 42 106
Average No. of Animals/AH 2 2 1 2 4
Khyber
No. of AHs, who kept animals - 21 - 16 23
No. of total animals - 37 - 47 193
Average No. of Animals/AH - 2 - 3 8
Overall
No. of AHs, who kept animals 3 111 9 110 108
No. of total animals 6 167 9 243 513
Average No. of Animals/AH 2 2 1 2 5
Distance from
Name Description RoW Centerline Location/ Village
(km)
Mast Baba Mazzar 5 Speen Kana Kalan
Akhoon Ghani Baba Mazzar 0.5 Jabba Tar
Mazzar (Punj Peer) Ziart 0 Zawo
Marza Khan Mazar Mazzar 1 Shekhan
Sheikh Babar Mazzar Mazzar 2 Daagismail
Peer Rahmat Kareem Mazzar 4 Daagismail
Peshawar
Sarfaraz Gul - 4 Mazar
Tarake - 4 Desert
Tarake Hill - 4 Hill
Gulidana Diri Mazzar 2 Diri
Khyber
Jrando Kalay Picnic Spot - RustamKhel
Spera Dam Dam 2 ManaKhal
Bab-e-Khyber - - Guli Shah
Awal Khan Kale Zero point Border Line 1 Paisad Khel
Mazara Hamza (Poet) Poet 1 Sultan Khel
Due to heavy load of household work it is very difficult for women of the area to have
leisure time. Some women are involved in embroidery, stitching and sewing of clothes,
but this is typically to supplement household incomes rather than recreation. Some girls
make hand fans or decorative items in different designs for trading purposes. Some have
expertise in glass painting and making candles after learning these skills from non-
governmental organizations (NGOs) working in the area. Other income generating
activities of women include livestock rearing, milking cattle and other paid employment.
The percentage of these skills being practiced are given in Table 3.25.
Table 3-26: Women Involvement in Income Generation Activities
Nowshera
Stitching/Embroidery 21 9.7
Livestock/ Milking 28 13.0
Job - -
Peshawar
Stitching/Embroidery 15 22.7
Livestock/ Milking 27 40.9
Job - -
Khyber
Stitching/Embroidery 12 30.0
Livestock/ Milking 15 37.5
Job - -
Overall
Stitching/Embroidery 48 14.9
Livestock/ Milking 70 21.7
Job - -
Due to the hard terrain of most of the project the area, lack of transport facilities, non-
affordability of transport and social and cultural barriers, female’s access to education is
not prioritized. There is also a perception of some of the parents that women’s education
is not a worthwhile expenditure as they have to leave their parents’ house after their
marriage. In some areas, civil society organizations (CSO) and non-governmental
organizations (NGOs) are involved in skill enhancement activities for young women
including candle making, decoration items, embroidery, and dress making.
Access to healthcare for women is also worse than it is for men. Few women receive
treatment form ante-natal care centers or any form of post-natal care from skilled birth
attendants. The majority or people consider it unnecessary and cost prohibitive. As with
education affordable transport and cultural barriers are also restrictive factors.
During the household survey the community prioritized their development needs such as
roads, electricity, water supply and health facilities. The respondents were asked to rank
their needs on the scale of 1 to 5, with 1 being the highest priority and 5 being the lowest
priority. The responses of the sample respondents reflecting their priorities are given in
Table 3.26. Some of the highest priorities were primary school and middle schools for
girls, showing that attitudes are slowly changing, and that people are increasingly seeing
the importance of female education.
Table 3-27: Ranking of Development Needs of the Surveyed Households
% of Sample Respondents
Rank their needs on Health Primary Middle Primary Middle
the scale Water
Road Electricity care school school school school
supply
center for girls for girls for boys for boys
Nowshera
Less than 1 Km 1.0 - - - - - - -
Between 1 and 5 km 4.2 1.0 - 11.5 2.1 5.2 2.1 4.2
5 km and above - - - - - - - -
Peshawar
Less than 1 Km - - - - - 1.8 - 1.8
Between 1 and 5 km 3.6 3.6 - 8.9 1.8 25.0 1.79 17.9
5 km and above - - - 1.8 - 5.4 - -
Khyber
Less than 1 Km - - - - - - - -
Between 1 and 5 km 7.14 - - 10.7 14.3 25.0 14.3 16.1
5 km and above 3.57 - - 5.4 - - - -
Overall
Less than 1 Km 0.7 - - - - 0.7 - 0.7
Between 1 and 5 km 6.6 2.0 - 14.5 7.2 21.7 7.2 15.1
5 km and above 1.3 - - 2.6 - 2.0 - -
9 Poverty and Vulnerability estimates: Pakistan, 2017-2018 by Social policy and Development Centre. RR 99.
10 This figure is based on the below poverty line (BPL) using the minimum wages (i.e., PKR 21,000/month) that are
fixed by the Government Gazette, Extraordinary, 31st May, 2021
4. Resettlement Impacts
4.1. Overview
The resettlement impacts of the Project are discussed in this Chapter. These include
impacts on land, crops, trees, structures and livelihood. The Chapter quantifies and
characterizes these impacts and describes how PAPs are expected to be affected. The
selected line route of 113.752 km of the 500 kV HVDC line passing through settlements
belonging to district Nowshera, Peshawar and Khyber of KP province of Pakistan is
depicted as Figure 4.1.
4.2. Total Project Affected Persons
The total number of affected households as per the 100 percent census is 668 PAHs. The
breakdown per district is provided in the following table.
Table 4.29: Number of affected households by district
Number of
Number of Project
Districts
Villages Affected
Households
Nowshera 14 247
Peshawar 14 260
Khyber 24 161
Total 52 668
Details on the impacts to these households are presented in the Annexes (Volume II) and
are further analyzed below.
4.3. Impact Assessment and Cut-off Date
The resettlement impacts of the TL (CASA-1000) project have been assessed based on an
inventory of losses (IOL) survey of 100 percent of all 668 PAHs, the socioeconomic
survey of 322 households of the project area, 75 consultations with PAPs and members of
the local community, and 48 consultations with the district level officials (line-
departments/ agencies). The inventory assessment and census survey were conducted
between December 11, 2020 – 17 March 2021. After completing the census/ impact
assessment survey/IOL, the cut-off date was shared with the PAPs and local community
through consultative meetings (as detailed in Chapter 8). Thus, the “cut-off date” has 11
been set as of March 17, 2021. This cut-off date applies to all those affected without
land titles. For those with land titles, the cut-off date will be the date of notification by
DC as per the provisions of LAA 1894.
11 Normally, this cut-off date is the date when the census begins. The cut-off date could also be the date the project
area was delineated, prior to the census, provided that there has been an effective public dissemination of information
on the area delineated, and systematic and continuous dissemination subsequent to the delineation to prevent further
population influx.
Other information on relevant issues will be disclosed to PAPs and other stakeholders in
the project area through installing hoarding boards in National and/or Urdu language at
appropriate places near settlements and by distributing leaflets to the PAPs and local
communities will disclose ES of RAP after approval from the World Bank. Any people
who settle or move in the area after the Cut-off-date will not be eligible and entitled to
any compensation under this CASA-1000 TL project. The project impact assessment has
been carried within the limits of the RoW and accordingly, census survey of the affected
households was carried out. The details regarding land and affected crops are provided in
Annex B&C respectively of Volume-II. The details regarding affected trees
(timber/wood & fruit) are given in Annex D and E. The list of affected structures and
infrastructure is provided in Annex F and G respectively.
4.4. Impacts on Land and Crops
The resettlement impacts which will take place within the RoW include decrease in value
and use of land, damaged crops, felling of trees, and removal demolition of buildings and
structures.
Table 4.2 presents the project impacts on land because of the installation of towers and
the transmission line and conductors (details are presented in Annex B; Table 4.3
provides data for the land required for the tower installation, whereas Table 4.4 provides
details of the land falling under the TL). The PAPs using land under the towers will be
severely and permanently impacted after construction and the land will be useful only for
limited cultivation; no structures and tree could be allowed on such land.
The land under the TL’s RoW will also be impacted but not as severely as for the land
under the towers because in addition to cultivation, some orchards (without tall trees)
could also be grown. However, no new structure (s) can be built within the jurisdiction of
towers. A list of these households is presented in Annex B.
Table 4-30: Land required for the Towers and Conductor in RoW
Project
Total Total
Affected
Sr. Required Required
Land Use Category HHs and
No. Land Land
Persons
(Acres) (Ha) (Nos.)
A Private
i) Agriculture (Cultivated land) 438.84 177.60 408
(3,549)
ii) Barren/ Hilly (Un-cultivated land) 101.26 40.98 61
(531)
iii) Commercial/ Residential land 3.470 1.40 10
(87)
B Communal/ Shamlat land
i) Agriculture (Cultivated land) 121.35 49.11 54
(470)
ii) Barren/ Hilly (Un-cultivated land) 703.12 284.55 135
(1,174)
C Community/ Communal land
i) Graveyard, mosque etc. 0.578 0.23 -
ii) River, Stream/ nullah bed 34.63 14.01 -
Project
Total Total
Affected
Sr. Required Required
Land Use Category HHs and
No. Land Land
Persons
(Acres) (Ha) (Nos.)
D Govt. land
i) Forest land 21.640 8.76 -
ii) Canal, Roads, grid stations, tracks 4.50 1.82 -
Total 1,429.38 578.46 668
(5,810)
Note: i) RoW the Transmission Line (CASA-1000) is 52m wide; ii) Figures in parentheses indicate the family members.
Source: Impact assessment and Census Survey of the project Area.
The total area in the RoW of Transmission Line (CASA-1000) project will be
approximately 1,429.38 acres. Of this land, about 20.794 acres will be covered by the 374
towers to be erected (on an average, each tower will take 15m x 15m (225m2) as part of
the CASA-1000 T/L project. This land is owned by a total of 668 PAHs; a list of these
PAHs is presented in Annex B. Details of this land are summarized in Table 4.3.
Table 4-31: Impacts on Land Due to Towers Installation
Project
Affected Affected Affecte
Sr. Towers
Land Use Category HHs and Landa d Land
No. Persons
(Nos.) (Nos.) (Sq. M) (Acres)
A Private
i) Agriculture (Cultivated land) 127 260 28,469 7.035
ii) Barren/ Hilly (Un-cultivated land) 29 34 6,623 1.636
B Communal/ Shamlat land
i) Agriculture (Cultivated land) 22 35 4,962 1.226
ii) Barren/ Hilly (Un-cultivated land) 185 119 41,555 10.268
B Community land
i) Graveyard, mosque etc. - - - -
ii) River, Stream/ nullah bed 6 - 1,416 0.350
C Govt. land
i) Forest land 3 - 675 0.167
ii) Canal, Roads, grid stations, tracks 2 - 450 0.111
Total 374 448 84,149 20.794
(3898)
a
Each tower will require on average 15m x 15 m (225 m2) of area.12
Source: Impact assessment & census survey along the project alignment.
The PAPs using land under the towers would be most severely and permanently impacted
because once the tower is erected, the potential use of the land under it will be limited to
some cultivation only. The tower size and design is such that cropping is possible under
the towers, even an agriculture tractor can access the land under the towers and do
operations. However, although this land is usually not actually acquired and instead is
leased, the landowner cannot build any structures on it. Hence, the utility and value of
this land will be greatly reduced. This impact is permanent in nature.
12 As per NTDC practice, tower footing size is 100 square meters (i.e. 10m x 10m = 100m 2). As per the preliminary design
drawings, the construction area for tower erection is 15m x 15 m = 225m2 as presented in Chapter 2 of the RAP.
This permanent impact reducing the value of land impacts 20.794 acres of land under the
towers that is owned by 448 PAHs.
The land under the conductor’s right of way (RoW) will also be impacted but not as
severely as for the land under the towers because in addition to cultivation, some
orchards (without tall trees) could also be grown.
The land under the TL conductors (but not under the towers) will be about 1,408.587
acres. This land is owned by a total of 220 PAHs; a list of these households is presented
in Annex B. Details of the land under the conductors is in Table 4.4.
Table 4-32: Impacts on Land Due to Installation of Conductors in RoW
Project
Affected Affected Affected
Sr.
Land Use Category HHs and Land Land
No.
Persons
(Nos.) (Sq. M) (Acres)
A Private
i) Agriculture (Cultivated land) 148 1,747,447 431.803
ii) Barren/ Hilly (Un-cultivated land) 27 403,158 99.623
iii) Commercial/ Residential land 10 14,043 3.470
B Communal/ Shamlat land
i) Agriculture (Cultivated land) 19 486,116 120.122
ii) Barren/ Hilly (Un-cultivated land) 16 2,803,877 692.853
C Community land
i) Graveyard, mosque etc. - 2,339 0.578
ii) River, Stream/ nullah bed - 138,727 34.280
D Govt. land
i) Forest land - 86,899 21.473
ii) Canal, Roads, grid stations, tracks - 17,749 4.386
Total 220 5,700,356 1,408.587
(1914)
Source: Impact assessment and Census Survey of the project Area
The nature of impacts on the land under the TL conductor (but not under the tower) will
be less severe than the impacts on land under the tower because it can be used for
cultivation purposes without any restriction keeping in view the safety measures.
However, plantation of tall trees and the construction of structures will not be allowed
within the jurisdiction of towers and the conductors as per NTDC practice. Hence the
value of this land will also decrease, although to a lesser degree than the land under
towers. This impact is also permanent in nature.
The land losses are likely to take place over an area of 560.186 acres. This includes:
i) permanent land losses and crop damage to 8.261 acres of land under the towers that is
owned by 295 PAHs; and ii) 551.925 acres owned by 167 PAHs under the TL
conductors, as shown in Table 4.5. A list of these households is presented in Annex C.
The construction activities are likely to damage any crops grown over this land. This
impact is associated with construction phase only hence it is temporary in nature. The
operation and maintenance activities may also cause some crop damages; however, such
damage is very infrequent and quite nominal.
A total of 3,928 fruit grown exist within RoW, including 1,696 at the tower locations and
the remaining 2,232 under the TL conductors. Details of these trees are presented in
Tables 4.7; further details are given in Annex D.
Table 4-35: Privately Owned Fruit Trees Located within RoW
Type of Tree Project
Total
(under the Towers and Age (years) Affected
Quantity
Conductors) HHs
Up to 5 5 to 10 Above10 (Nos.)
Apricot 962 790 730 2,482 9
Beri 58 62 429 549 17
Guava 4 - - 4 1
Lemon - - 250 250 1*
Orange - - 25 25 1*
Mulberry 3 - 25 28 3
Peach - 150 440 590 4
Total 1,027 1,002 1,899 3,928 34
* Some owners also owned more than one type of fruit trees
A total of 9,920 government-owned trees grown within RoW, including 1,523 at the
tower locations and the remaining 8,397 under the conductors. These trees are owned by
the Forest Department. Details of these trees are presented in Tables 4.8; further details
are given in Annex E.
Table 4-36: Forest Wood/Timber Trees Located within RoW
Type of Tree Girth Range (Feet)
(under the Towers and Total
Conductors) Up to 2 >2 to4 >4 to 6 Above 6 Quantity
13 As per government departments, the unit rates are provided in square feet, so that for true and actual calculations, size of
structures for the calculation compensation has been considered as square feet, while in case of measurement survey, the inventory of
losses of structures has been followed metric unit (i.e. meters) as referred in Annex O of RAP Volume-II.
this context, the required land under the tower will be compensated in negotiation with
the land owners. The details are given in Table 4.10.
Table 4-38: Project Impact on Livelihood & Severely Affected Persons
Severely
affected
Description Remarks
HHs
(Nos.)
These PAHs will lose residential
PAHs Losing of Residential Structures 4* structures and will need to be
relocated at nearby available space.
These will permanently lose more
Severely Impacted HHs 295
than 10% of their productive land
Total PAHs 295
* Some owners have more than one type of impact
incorporated to safeguard the specific needs and problems of women during project
implementation:
Any female-headed households if identified will be considered as the recipients of
compensation and rehabilitation assistance to be paid to their households;
Titled eligible women will be paid compensation if their assets are lost or
damaged by the project activities;
Women will be included in the consultation process during the project
implementation after the formation of women project affected committees;
Project Affected Persons Committees (PAPCs) will be established for female
members, as appropriate, along the route alignment; and
Due consideration will be given to complaints and grievances lodged by women
following the procedures given in the grievance redress mechanism of the project.
Specific targeted vocational skills training for women will be included in the social
development plan and livelihood restoration entitlements too.
4.11. Impacts of Establishing Construction Camps and
Access Routes
The TL (CASA-1000) project will be divided in three segments and construction of each
segment will be assigned to a separate construction team. Hence temporary construction
camps will also be required at three separate locations. The prospective places of these
construction camps include CASA-1000. However, the exact location of these camps will
be decided by contractors as per their work plan. Preference will be given to establishing
these camps within the WAPDA/ NTDC-owned premises. Otherwise the land for these
camps will be obtained on a rental or lease basis. Preference will be given to uncultivated
land away from communities.
Access roads or tracks are rarely built for TL construction in the Pakistan. In steppe
areas, temporary tracks are used to access the RoW from the nearby existing road. In
mountainous areas, access is more difficult and building access tracks/roads is not always
possible or feasible. For the TL (CASA-1000) construction, it has been assumed that on
average, 200 m of access roads will be used for each tower location though it may not be
possible for the earlier part of the route because of very steep slopes. Preference will be
given to barren land while selecting these access routes.
Though exact locations and hence ownership of the land under these access tracks is not
known at this stage, it can however be estimated that about 110.456 acres of cultivated
land may be temporarily impacted by the access tracks (200m long x 15 m wide x 149
towers located in cultivated areas).
4.12. Summary of Resettlement Impacts
The inventory of losses and census results represent that in total 668 PAHs consisting
5,810 family members are facing loss of their assets located within the RoW. In total 295
PAHs with a total population of 2,566 persons will face significant impacts due to the
impact of more than 10% of their productive resource due to the installation of towers.
This includes 4 PAHs whose houses will be physically relocated. In total, 92 PAHs are
assessed as vulnerable as their household income is below the poverty line. The project
affected households (668 nos.) are termed as titled users of the RoW land who are
eligible and entitled for the compensation as per entitlement matrix. The resettlement
impacts discussed in the earlier sections are summarized in Table 4.12 below.
Table 4-40: Summary of the Project Resettlement Impacts
Sr. Resettlement and livelihood No.
Unit Quantity Remarks/ Description
No. Impacts PAHs
A. Land along CASA-1000 TL Route Alignment for Towers and Conductors
Decrease in the value of land
expected due to the
Arable land (cultivated) with
i) Acres 560.19 462 installation of towers and
residential structures other associated
utilities/uses.
Barren/hilly14 (un-
Barren/hilly
Cattle grazers and land
ii) Acres 804.38 196
cultivated land) owner PAH affected
Decrease in the value of
private land expected due to
iii) Commercial and residential land Acres 3.470 10 the installation of towers and
other associated utilities
iv) Graveyard, mosque etc. Acres 0.578
Government land
Government land15
Forest land is owned by the
i) Government/forest land Acres 21.640 - Forest Department.
Government land: motorways, Land is owned by National
ii) roads, tracks (unpaved) and Acres 4.500 - Highway Authority,
railway track Pakistan Railways.
Land is owned by the
Government land: river,
iii) Acres 34.63 - Government Irrigation
Stream/nullah bed Department
Total 1,429.38 668
B. Affected area under crops
There will be damage of
crops due to the installation
i) Total area of agriculture land Acres 560.186 462 of towers/ conductors etc.
(see tower locations in
Annex A).
Total 560.186 462*
C. Affected structures
Loss of residential structures
of 4 PAHs (35 family
members) who will
reconstruct the structures
i) Residential structures Nos. 4 4 outside RoW limits. These
households also use the
buildings for livelihood
activities.
4 PAH in total consisting of
Total affected structures 4 4* residential households that
will need to relocate.
D Affected trees
Privately owned wood/timber
i) Nos. 1,419 30* -
Trees
ii) Privately owned fruit trees Nos. 3,928 34* -
Barren/hilly
14 As land is barren/hilly terrain (un-cultivated), there will not be any impact, however, the land is being used for
cattle/livestock grazing, so that there might be impact due to ‘electromagnetic field. Are you proposing any mitigation
measure for this?
Government land
15 The land located under the conductor (TL), there will be the impact on crops, while in case of land located under
the towers, there will be devaluation of land and the land use will be limited.
Severely affected
16 The persons are severely affected, e.g. having to relocate, or losing more than 10% of productive land or
other assets.
The Telegraph Act (1885) was enacted to define the authority and responsibility of the
Telegraph Authority. The law covers, among other activities, installation and
maintenance of telegraph lines and posts (poles). The Act defines the mechanism to
determine and make payment of compensation associated with the installation of these
lines and posts. Under this Act, the land required for the poles is not acquired (or
purchased) from the owner, nor the title of the land transferred. Compensation is paid to
the owner for any structure, crop or tree that exists on the land; cost of the land is not
paid to the owner. NTDC has been following this act for building transmission line
towers throughout the country.
The WAPDA Act of 1958 is the other relevant legal instrument, which allows “right of
entry” for the purpose of construction - for instance, (i) survey of any land, erect pillars
for the determination of intended lines of works, make borings and excavations and do all
other acts which may be necessary for the preparation of any scheme; and (ii) pay or
tender payment for all necessary damage to be done as aforesaid. The Act further states
that “in case of dispute as to the sufficiency of the amount so paid or tendered, the dispute
shall be referred to the Deputy Commissioner (DC) of the district whose decision shall be
final.”
Regulatory Authorities: A number of national and provincial governmental agencies
perform functions relevant to the RAP as summarized below.
Revenue Department is responsible for the acquisition of land (permanent or
temporary) including assessment, valuation, disbursement of compensation, and
mutation in favor of NTDC
Fisheries Department will be involved in case of any damage to any fish resources
and fishponds caused by the project activities.
Forest Department is responsible for the assessment and valuation of losses of wood
trees.
Agriculture Department is fully responsible for the assessment and valuation of losses
of crops and fruit trees.
Communication & Works (C&W) Department: the C&W Department will be
involved for the assessment and valuation of losses in case of project impact on
structures/ buildings and roads.
5.3. NTDC Practices, Framework for Land Acquisition and
Valuation
The Telegraphic and the WAPDA Act mentioned above provide the basis for the legal
framework used in the CASA-1000 Project. The use of the Telegraphic Act of 1885 as
the legal instrument is justified by the fact that there is no land acquisition foreseen for
the CASA-1000 transmission line project. Compensation is paid for loss of structures,
crops and trees, allowances are foreseen to restore the livelihood of affected people and
vulnerable groups but no land ownership change takes place. The entitlements,
compensation rate, etc. have been determined through consultation and negotiations,
taking into consideration of the market value and other associated costs.
NTDC will constitute, as per the NTDC Guidelines, a committee to compensate impacts
through negotiation. The processes are as per the following steps:
i) The NTDC Committee engages with the owners.
ii) NDTC has qualified technical and field staff mostly on deputation from the
revenue department to carry out measurement of loss of land based assets
(building, crop, fruit bearing trees or any other immovable structure on the land)
iii) The valuation of the loss is then prepared by the same NTDC field staff in
coordination with the concerned district administration/departments followed by
the verification of the committee members.
iv) Following the completion of the valuation of assets (includes crops, trees, and
other assets) as well as compensation package and entitlements; the compensation
payment is dispersed to the PAPs directly through NTDC account.
Finally, in case the negotiations fail, and parties do not agree on rates, the LAA (1894)
will be used to acquire the land.
In the case of married couples/households, the compensation (through cross cheques) will
be paid to the one who owns the assets. If these assets are jointly owned by couple, then
the amount is paid to both the parties. However, when assets are owned by
single/unmarried/separated women, they will receive compensation directly. These
provisions for payments were also discussed during consultation with women.
5.4. International Requirements of WB OP 4.12 IR Policy
World Bank OP 4.12 encourages the purchase of land and assets through negotiation
based on pre-displacement market value through full compensation at market value,
independently with advance public notice, negotiation and right of appeal. The processes
undertaken complies with OP 4.12 IR Policy guidelines.
In this project, the determination of compensation for land (if any) will be based on
negotiations with the affectees, based on recent market data as the basis; and the rates are
eventually above market value. For other land-based assets (trees and crops), consultation
with the relevant government departments (forestry, agriculture) was done. Finally, in
case of delay in RAP implementation, the compensation will be updated based on the
GDP deflator.
Further, to minimize the gaps and to comply with the OP 4.12 requirements, the RAP
policy has taken measures - for example, analysis of gender issues, consultation with
women and other vulnerable groups, grievances/dispute resolution, and livelihood
restoration measures to that affected persons can regain and restore their livelihood in
post-project period.
5.5. Gap Analysis between National and International
Requirements
The LAA 1894 and OP 4.12 are compared in Table 5.2 below to show the gaps between
the national and international requirements and how they are addressed in this RAP.
The aim of this payment is to assist severely affected persons to overcome the short-term
adverse impacts of land and asset loss and help them to readjust to their changed
circumstances while they are making replacement earning arrangements. There will be a
need to closely monitor such severely displaced persons. The one-time payment should,
at the absolute minimum be adequate to provide them with equivalent level of livelihood
than they had previously.
Other options have been considered, including non-cash-based livelihood support and
employment, both temporary and permanent. Additional income restoration measures
will be considered during project implementation.
Residential and Commercial Land Entitlements: Residential and commercial land will
be compensated at replacement value for each category of the PAPs. Residential and
commercial landowners will be entitled to the following:
Legal/ legalizable owners will be compensated by means of either cash
compensation for lost land at replacement cost based on the market value of the
lost land plus a 15% CAS, free of taxes and transfer costs; or in the form of
replacement land of comparable value and location as the lost asset.
Renters are compensated by means of cash compensation equivalent to three
months of rent or a value proportionate to the duration of the remaining lease,
including any deposits they may lose.
Encroachers/squatters are compensated through either a self-relocation allowance
covering six months of income or the provision of a leased replacement plot in a
public owned land area. They will be compensated for the loss of immovable
assets, but not for the land that they occupy.
All other Assets and Income Loss Entitlements
Structures will be compensated in cash at replacement cost plus 15% CAS. There
will also be a 10% electrification allowance and any transaction costs will be paid.
Materials that can be salvaged can be taken by the owner, even if compensation
has been paid for them.
Renters or leaseholders of a house or structure are entitled to cash compensation
equivalent to three months’ rent or a value proportionate to the duration of the
remaining lease period.
Crops will be compensated for owners, tenants and sharecroppers based on their
agreed shares. The compensation will be the full market rate for one year of
harvest including both rabi and kharif seasons.
Fruit and other productive trees will be compensated based on rates sufficient to
cover income replacement for the time needed to re-grow a tree to the
productivity of the one lost. Trees used as sources of timber will be compensated
for based on the market value of the wood production, having taken due
consideration of the future potential value.
Businesses will be compensated for with cash compensation equal to one year of
income for permanent business losses. For temporary losses, cash compensation
equal to the period of the interruption of business will be paid up to a maximum
of six months or covering the period of income loss based on construction
activity.
Workers and employees will be compensated with cash for lost wages during the
period of business interruption, up to a maximum of three months or for the
period of disruption.
Relocation assistance is to be paid for PAPs who are forced to move from their
property. The level of the assistance is to be adequate to cover transport costs and
special livelihood expenses for at least 1 month or based on the severity of
impact.
Community structures and public utilities, including mosques and other religious
sites, graveyards, schools, health centers, hospitals, roads, water supply and
sewerage lines, will be fully replaced or rehabilitated to ensure their level of
provision is, at a minimum, to the pre-project situation.
Vulnerable people are defined as households who have monthly income20 of less
than PKR 21,000 (BPL).
The entitlement matrix has been developed keeping in view the project impacts and
consistent with the entitlement matrix. The compensation and rehabilitation entitlements
are summarized in the Entitlement Matrix presented in Table 6.1.
20 This figure is based on the below poverty line (BPL) using the minimum wages that are fixed by the Government
Gazette, Extraordinary, 31st May, 2021.
21 Resettlement impacts have been identified and presented in RAP based on the route alignment of transmission line, i.e., land under conductor & towers), the land under access routes, borrow
areas etc.) will be identified at final design. Presently, temporary impacts/ temporary land acquisition (i.e. access to road and camping site etc.) not demarcated yet.
22 Compensation for all assets will be paid to the owner of the asset.
23 The below poverty line (BPL) using the minimum wages that are fixed by the Government Gazette, Extraordinary, 1st May, 2021.
Public consultation and information disclosure plays a vital role in studying project
effects and their successful mitigation. This provides an opportunity for the potential
PAPs and other stakeholders to share their views associated with the project and propose
possible solutions. Public involvement is an essential element of RAP preparation,
leading to a better and more acceptable RAP implementation.
8.3. Stakeholder Identification and Analysis
Stakeholders’ are individuals or organizations which have an interest in the proposed
project or knowledge that would provide insight into issues or affect decision making
related to the proposed project.
On the basis of interest and role criteria there are two types of stakeholders for the
proposed project as described below.
The primary stakeholders (also called direct stakeholders) are the grass-root stakeholders,
such as PAPs and general public including women residing in the project area (people
living in the project area particularly the RoW). These people are generally, directly
affected by project
The secondary stakeholders (also called institutional stakeholders) are the people,
department, institutions, and/or organizations that may not be directly affected by the
project however, they may influence the project and its design. They include project
proponent (NTDC in case of the present project), other concerned departments such as
WAPDA that may have a role during various phases of the project and other relevant
departments such as Forest, Agriculture and CSO/NGOs, the broader interested
communities including academia and journalists, and general public. The list of
stakeholders considered for the preparation of this RAP is as below:
NTDC
WAPDA
Irrigation Department
Revenue Department
Agriculture Department including Horticulture Wing
Forest Department
Building Department (C&WD/PWD)
District administration/DC/AC
Civil society organizations (CSOs)
Non-governmental organization (NGOs)
Other concerned (Contractors, consultants)
A total of 48 interviews/consultations were carried out with the district level government
officials (line-departments/ agencies at tehsil as well as union council level) to ensure
their participation and cooperation while preparing the RAP, but also during the project
implementation. The breakdown of interviews/consultations per district is presented in
Tables 8.2, while the details are given in Annex I (Volume-II) and signed copies of
Government Officials are in Annex J (Volume-II). The pictorial presentation of officials’
consultation events is provided at the RAP Main Report (Volume I). The issues raised
during the interviews and the responses of the project team are presented in Table 8.5.
Table 8-43: Consultations with Government Officials
District No. of Interviews with officials
Nowshera 23
Peshawar 18
Khyber 7
Total 48
The RAP team conducted a series of 75 consultations and FGDs covering 465
participants that included 373 men and 92 women from the villages located along the
project route alignment. These consultations were carried out in different villages
belonging to the province Khyber Pakhtunkhwa. A list of consultations including the
date, venue/ location and number of participants is summarized in Table 8.3, while the
feedback/concerns are presented in Table 8.4 as well as Annex K (Volume-II) and the
signed copy or thumb print of the PAPs and local community members including women
is given in Annex L (Volume-II). The pictorial presentation of consultation events is
provided in Main Report (Volume I).
Table 8-44: Consultations with the PAPs/ Local Communities
District No. of meetings with PAPs
Nowshera 33
Peshawar 20
Khyber 22
Total 75
In addition, consultation with NGOs/CSOs was carried out, including the (i) Society for
the Protection of the Rights of Child (SPARC), (ii) National Integrated Development
Association (NIDA), (iii) Sustainable Peace and Development Organization (SPADO).
The key findings of the consultations with NGOs/CSOs comprise the following:
Local norms should be honored, privacy of the locals should be given priority and
construction work should be completed in time.
All safety practices/measures should be adopted by management during all
activities of the transmission line to ensure safety of the local public/peoples.
Community welfare projects/CSP, i.e., access roads, school and hospitals for the
local community should also be completed.
Employment to local skilled and unskilled persons in the project should be
provided to increase the livelihood and household well-being. Local community
PAPs should be preferred to engage in the project execution & operation.
Generally, in the project area, availability of drinking water is scarce and the
government/project management should provide drinking water facilities such as
water supply system, tube-wells /wells and hand pumps under the on-going CSP.
Table 8-45: Community Consultations Stakeholder Feedback along the Proposed CASA-1000 Route Alignment
Concerns Response/Redress
Consultations with PAPs/ Local Community (Male members)
Opportunities should be given to the locals especially small Contractor will maximize employing local small contractors of material supplying.
contractors of material supplying.
Employment to local skilled and unskilled labor in the project should Contractor will maximize employing local laborers.
be provided to increase the livelihood. Local community especially Preference will be given to the PAPs.
PAPs should be engaged in the project related jobs.
The impact of electromagnetic induction increases during the A safety plan to be provided in the communities along the project.
rainy days. The CASA-1000 TL design includes safety measures to protect communities from risks such
as electrocution.
RoW clearance for installation of towers and transmission line should Cultivation fields have been avoided to the extent possible while selecting the CASA-1000 TL
be minimized at the best possible extent. route. If unavoidable, compensation will be paid as detailed in the present RAP.
The contractor will minimize the RoW clearance through astute planning.
Installation should be done after harvest of crops. Liaison with the community will be maintained during construction activities.
Construction activities will be commenced after the harvest to the extent possible. Otherwise
compensation will be paid in accordance with the present RAP.
Compensation should be fair and should be delivered before start of Compensation for any loss to crops, trees, and structures will be paid in accordance with the
work. Payment of compensation for project affected person especially rates given in the present RAP. These rates have been established based upon the official
vulnerable PAPs should be ensured. rates.
The compensation will be provided to all PAPs before the start of construction in all project
areas
PAPC will be established to ensure that compensation is fair and paid in a timely manner.
Impacts on the structures should be avoided and relocation of Settlements, houses, and other structures have been avoided to the extent possible while
settlements should be minimized by changing the design, where selecting the CASA-1000 TL route. If unavoidable, compensation will be paid as detailed in
possible. the present RAP.
Transport for relocation of assets and timely compensation to all the Transition/ shifting assistance will be provided to the eligible/ entitled persons in addition to
affectees should be provided. the compensation for the lost assets.
Policy framework should be made and ensured to project affectees for Compensation against losses of crops, trees, structures and other assets will be paid to the
resettlement and compensation. PAPs in accordance with the present RAP.
Concerns Response/Redress
Damaged lands should be rehabilitated/ restored after the construction Contractor will rehabilitate/ restore the lands damaged by the construction activities.
work is completed.
Local norms should be honored, Privacy of the locals should be given Construction activities will be completed in the shortest possible time.
priority and construction work should be completed in time The construction staff will be provided trainings regarding local norms.
The construction staff will comply with code of conduct.
Liaison with the community will be maintained during construction activities.
The value of land above which the transmission line is passing Compensation against the losses of land which the transmission line is passing and installation
depreciates in value; hence, compensation should also be given for the of Tower
land under the transmission line. Community support project is also being implemented to share benefits of projects with
communities.
The CASA-1000 transmission line project must include the Facilitate will be considered under the community support program
development schemes such as schools for boys and girls, livestock,
BHU, hospitals and sui-gas etc., for the area
Resistance will be observed by the local community as experienced in Compensation will be paid before start of civil works in any area.
the past. They should be paid compensation prior to the Extensive consultations have been carried out with the local community.
commencement of work in order to run the project smoothly The present RAP has identified PAPs and their losses, and has estimated the amount of
The participants of (Ghari Mina) were non supportive and too much compensation to be paid to them.
rigid. They have a lot of concern about the transmission line because RAP will be implemented in a participatory manner involving PAPs themselves.
they have already fought with PHA on another project.
Transmission line will be of high voltage which can be caused various The CASA-1000 TL design includes safety measures to protect communities from risks such
health risks such as brain cancer, breast cancer and cardiovascular as electrocution.
disease to the local dwellers. A safety plan has been developed in the communities along the project.
Payment to affectees should be made through jirga or tribes Liaison will be maintained with the local community during project implementation. However,
representative and compensation process should not be lengthy and payments will be made directly to the PAPs.
complicated and should be discussed with all concerned communities
jirga/tribes located along the TL rout.
Some of area along the transmission line was deprived of electricity Community support project being implemented along the TL route and converter station is
and water supply and if possible these basic needs should be provided. designed to share benefits and to assist communities in meeting their basic needs.
For the protection of community, Safety measures such as wall/fence A safety plan to be provided in the communities along the project.
around towers should be adopted in this project. Construction of
towers/poles of transmission line should be far from residential houses.
Concerns Response/Redress
Consultations with PAPs/ Local Community (Female members)
Male family members should be employed in the project related jobs Contractor will maximize employing local laborers.
so that they could get the jobs in their own city/village instead of Preference will be given to the PAPs.
moving towards other cities for jobs. In this way their social safety
could be enhanced
Girls after completing primary education cannot go for higher Government Girls High school will be considered under the community support program
education as the village has no high school. Government should (CSP).
provide high school in the area
Women involvement in the activities outside the home is limited. Compensation will be provided to the eligible and entitled PAPs including women and
However, in case of loss of any property/ assets, crops/ trees, vulnerable people in accordance with the entitlement matrix of compensation given in the
compensation should be provided. present RAP.
The participant mentioned that we cannot work outside home alone Liaison with the community will be maintained during construction activities.
during construction activities. In some cases, local women are working The construction staff will comply with code of conduct which will be developed by the
in agricultural fields, so their routine activities should not be disturbed Contractor
due to the construction activities. A GRM will also be established to address community complaints.
The construction staff will be provided trainings regarding local norms.
They demanded that some skills development programme initiated for Facilitation will be considered under the community support program
the improvement of women therefore vocational center, personal skills
trainings should be included in this project
Resettlement issues should be discussed in the presence of whole local Extensive consultations have been carried out while preparing the present RAP
community/ local population involving female. RAP implementation will be carried out in a participatory manner as explained in the present
RAP.
PAPCs will be established to ensure PAPs participation in the process.
Finalized RAP will be disclosed and an Urdu translation will be shared with the communities
also.
We are unable to construct our home buildings near the high voltage Settlements, houses, other structures, and cultivation fields have been avoided to the extent
power line. They said that radiations are very dangerous for pregnant possible while selecting the CASA-1000 TL route. If unavoidable, compensation will be paid
women and the child can be disabled after birth. as detailed in the present RAP.
Basic health facilities are not available in the area, they demanded for Such facilities will be considered under the community support program
BHU and hospital at village/town level and sui-gas and electricity
supply in the area should be included in this project.
Concerns Response/Redress
TL carries large quantities of electricity at a very high voltage; A safety plan has been developed in the communities along the project.
TL should be covered by an insulating sheath. They suggested The CASA-1000 TL design includes safety measures to protect communities from risks such
underground system of TL of this project. as electrocution.
The participants (Tela Band and Khan Kari) said that they will not give These concerns will be shared with the senior NTDC management.
their lands/ assets and also, they are not agreeing for this project
implementation. Therefore, no interest shown regarding the
transmission line.
Concern Redress
Local norms should be honored, privacy of the The project will comply to all national
locals should be given priority and construction regulations and standards as well as WB ESHS
work should be completed in time. safeguards
All safety practices/measures should be adopted A CSP is currently implemented which is in line
during all activities to ensure safety of the local with the needs and priorities of the project area as
public/peoples. these have been identified through community
Community welfare projects/CSP should also be consultations
completed. Preferential employment to local skilled and un-
Employment to local skilled and unskilled skilled staff will be included as a condition to
persons in the project should be provided. Local construction contracts
community PAPs should be preferred.
Drinking water facilities such as water supply
system, tube-wells /wells and hand pumps
should be provided.
Periodically, the Project will also hold formal workshops to consult a wide range of
stakeholders/members of Grievance Redress Committee (GRC) on project activities.
These workshops will involve members from the GRC, PAPs from communities,
WAPDA, NTDC, concerned organizations/departments and World Bank representatives
to share the progress and elicit the views of all the stakeholders for the improvement. The
Consultation and Participation Framework for the entire project cycle is provided in
Table 8-6.
Table 8-47: Consultation and Participation Framework
Description Target Stakeholders Timing Responsibility
Establishment of GRM and PAPs/ Communities within Before PMU and RAP
GRCs RoW of CASA-1000 TL commencement Consultants
Location: various places in of project
project area activities and
quarterly during
implementation.
Grievance redress CO staff; consultants; Implementation PMU and RAP
Location: various places in relevant line departments; Stage Consultants
project area and APs (as needed).
Consultations with the APs/ PAPs/ Communities within Construction CO and RAP
communities during internal RoW of CASA-1000 TL Stage Consultants
monitoring
Location: various places in
project area
Fortnightly meetings at project PMU staff; consultants; and Construction PMU and RAP
sites APs (as needed). Stage Consultants
Location: Site offices
Consultations with the PAPs/ PAPs/ Communities within Construction M&E Consultants
Communities during the RoW of CASA-1000 TL Stage
Independent Monitoring
Location: various places in
project area
Consultation workshops to PAPs/ Communities within Six-monthly PMU and RAP
review RAP implementation, RoW of CASA-100 TL; during Consultants
any outstanding issues and relevant line department; implementation
grievances, views and relevant NGOs phase
concerns of PAPs; and actions
needed to address them
Location: site offices within
project area.
Consultations with the PAPs/ PMU; Project consultants; Construction/ PMU;
Communities during the site PAPs Operation Stage WB Mission
visits by the WB Review
Missions.
Location: various places in
project area.
GRC-P has provision for representatives (both male and female) from the community.
These will be nominated by PAPCs and selected by the PMU-NTDC in consultation with
them. However, the area is conservative and culturally sensitive and female involvement
will be limited in activities outside from their homes. Keeping this in view, female
representation in GRC-P will be difficult. If there are any specific grievance(s) lodged by
any female in the project area, the gender specialist in the project will facilitate the
process.
2. NTDC has constituted a Grievance Redressal Committee (GRC-HQ) at HQ
level. The committee has the following composition:
General Managers Projects Delivery North/South (as relevant) as member,
being the convener
Additional Director General ESIC as member
Gender Focal Point or NTDC female manager as member
Representative of the Land Directorate as member
Representative of the Legal Department as member
The GRC-HQ, through authorized representative, will acknowledge the complainant
about his complaint, scrutinize the record of the GRC-P, investigate the remedies
available and request the complainant to produce any record in favor of his claim. After
thorough review and scrutiny of the available record on complaint, visit the field and
collect additional information, if required. Once the investigations are completed, the
GRC-HQ shall give decision within 21 days of receipt of the complaint. If the
complainant is still dissatisfied with the decision, he can go to the court of law, if he/she
wishes so.
Gender representation will be ensured by appointing a female member in both GRCs.
The mechanism will ensure the access to PAPs to a GRM that openly and transparently
deals with the grievances and makes decision in consultation with all consultation with
all concerned that are consistent with foreign lenders’ requirements and country
safeguard system.
9.2. Grievance Redress Procedure
The intention of GRM is to resolve a complaint as quickly and at as low a level as
possible to avoid a minor issue becoming a significant grievance. Irrespective of the stage
of the process, a complainant has the option to pursue the grievance through the court as
his or her legal right in accordance with law. The details of the process are given below:
ii. Information that necessary action will be taken within the specified
working days from the date of receipt of the grievance by the authorized
representative concerned.
d) If the office receiving the grievance/complaint is not the one designated to consider
and resolve it, the receiving office will forward it to the designated office, but
after having complied with the requirements at (b to c) above;
e) The GRC will provide an opportunity of hearing to all the concerned parties and
examine the relevant record before making the final decision;
f) The GRC or its representative designated to consider the matter will make every effort
to ensure that grievances/appeals are considered and resolved preferably within the
stipulated period; and
g) The complete records of all activities will be kept and filed into the grievance database
maintained by both GRCs. The GRCs will also be responsible to compile records of
the GRM and make quarterly reports to the WB or any other concerned Authority.
The complaint will be considered as resolved and closed when:
Where the complainant has not responded to the Grievance Redress staff within
one month of being sent the final decision of the grievance officer on his
grievance/complaint;
Where the Complainant fails to attend the proceedings of the GRC within the
stipulated period of the resolution of the complaint; and
Where the Complainant withdraws his/her complaint.
9.3. Documentation of GRC Cases
All records of GRC cases shall be properly maintained by the PMU Office, including
minutes of meetings and decisions made by the GRC. The complaints received in writing
or received verbally (or by phone) will be entered and properly recorded and
documented. The meeting minutes at various GRCs will be recorded and decisions made
will be as part of the input in the case record document and filed properly by respective
GRCs. The log frame for recording the grievances and the minutes of the GRC meetings
is attached as Annex H.
The outcomes of GRC deliberations and decisions will be notified in written form by the
Chair of the GRC within a week from the date of the meeting. The decisions taken are
mandatory on the NTDC with regard to any additional awards or compensation to be paid
to the disputants. The records of all GRC cases must be available for review and
verification by NTDC, WB, Independent monitoring consultants and other interested
stakeholders.
NTDC
World Bank
PMU-CASA-1000
(CE/ PD)
Project Consultants
(including RAP
implementation
team)
Contractor
Independent
Environmental and Social
Monitoring Agency Impact Cell (ESIC)
(PMU- CASA-1000)
- Deputy Manager
- Assistant Manager (Social)
- Assistant Manager
(Environment)
- Assistant Manager (OHS)
-
For the RAP implementation, the ESIC will have the following specific functions and
responsibilities:
Assist and supervise the Project Consultants for the implementation of the
approved RAP, in accordance with the procedure and schedule given in this
document. The ESIC will hold monthly meetings with the Project Consultants and
PIU to review the RAP implementation progress, to identify related gaps and
issues, and to determine corrective actions needed;
Maintaining close liaison and coordination with various project entities including
PIU, Project Consultants, project affected persons and Grievance Redress
Committee (GRC);
Maintaining liaison with regulatory agencies/authorities and WB specialists, as
needed;
Preparation and dissemination of RAP implementation progress reports in
coordination with the Project Consultants;
Assist and supervise the Project Consultants for updating RAP, if required, in
case of any change in the design. This will involve additional inventory surveys,
measurements, assessment, and valuation in coordination with concerned
departments.
10.5. Field-Level Construction Camp Offices
Under the PMU-Director, the Project will establish a Field-level Construction Camp
Office for project implementation purposes. The main function of the Camp Office (CO)
will be to coordinate and supervise the construction activities in the field. For the purpose
of RAP implementation, the CO will include the following, in addition to its own
technical staff including an Executive Engineer: (i) Representative of ESIC or a relevant
staff designated by NTDC at CO; (ii) Representatives of contractor; (iii) Representatives
of the Project Consultants; (iv) NTDC (Patwari). The responsibilities of CO ESIC Team
include the following:
Maintain liaison and interaction with the PAPs and local communities to address
their concerns;
Provide proper guidance to PAPs for the submission of their requests for
compensation as per eligibility and entitlement;
Help the PAPs to forward their complaints, if any, to the GRC;
Maintain close liaison with PMU, ESIC, contractor, and relevant government
departments for RAP implementation;
Distribute the notices to the entitled PAPs regarding payment of compensation;
and
Facilitate the PAPs for completing the necessary documentation to receive their
entitled payments.
10.6. Project Consultants
The Project Consultants will be responsible to supervise the construction contractors.
They will also be responsible to support for RAP implementation team27. A
representative of the consultants will be needed at each CO to support this with one
senior specialist with supervision and reporting responsibilities. They will also be
responsible for RAP implementation; their key responsibilities in this context will
include:
27 RAP implementation is a specific and specialized job involving various experts, including Resettlement
specialist, Grievance redress specialist, Gender specialist, M&E specialist, Database/ MIS specialist and Social
Mobilizers (both males and females). These experts will need to be engaged directly by the NTDC or through
CSC or project consultants to ensure this RAP implementation and to comply with the WB social
safeguard/operation manual.
In summary, the primary purpose to PAPC is to facilitate the implementation of the project with
inputs from the affected communities and to develop a sense of ownership of the
project.
10.8. Independent Monitoring Consultants (IMC)
NTDC will engage the Independent Monitoring Consultants (IMC) to periodically
monitor the project activities to ensure compliance with the design and other
requirements such as social safeguards. The IMC will also be responsible to validate and
monitor the RAP implementation. For this purpose they will periodically visit the site,
have meetings with the PMU, CO, ESIC, Project Consultants, and most importantly, the
PAPs. IMC will review the documentation relating to RAP implementation and
particularly review the GRM record; and status of redress of community complaints.
After one year of RAP implementation, the IMC will carry out a post-implementation
evaluation of the RAP to ensure that the RAP has achieved its intended purpose.
10.9. Grievance Redress Committee (GRC)
The project specific GRC has been notified for addressing conflicts and appeal procedures regarding
eligibility and entitlements during RAP implementation. GRC will receive and facilitate
the resolution of PAPs concerns and grievances. It will ensure that the procedures are
accessible by PAPs and are gender sensitive. However, aggrieved people have the right to
access the country's judicial system as and when required. The details have already been
discussed in the earlier Chapter.
10.10. Government Departments
The line departments which are relevant for RAP implementation include the Forest
Department in case of damage to any forest trees; Agriculture Department for valuation of
crop damages & fruit trees (horticulture wing), Revenue Department for land related
impacts; Public Health Engineering Department in case of any government-owned
tube-wells are affected; C&W Department in case of any damage to local roads as well
as valuation of affected buildings and structures and National Highway Authority in case
of crossing of any national highway/motorway. The CO will be responsible to contact
the concerned departments in a timely manner and maintain liaison during the
construction works.
10.11. District Governments
District-based departments/ offices have jurisdiction over land acquisition and compensation
activities. Land acquisition functions rest with the Board of Revenue represented at
District level by the Deputy Commissioner/LAC. LAC maintains official records and also
possesses the Legal/Administrative authority for land titling and therefore assuring
eligibility of PAPs for compensation.
Other staff members of the Revenue Department, most notably Qanoongo and Patwari, carry out
specific roles such as titles identification and verification of the ownership. Functions
pertaining to compensation of non-land assets rest on other line-agencies and their
District level offices. Crops, fruit trees, compensation pertains to the Department of
Agriculture and timber tree to forest Department and building structure by the Building
and Repair Department.
During the implementation process, the LAC may engage other staff to assist in establishing the
identity of the owners of the affected properties and process the documents for
compensation payment.
The LAC will receive funds from the Project Management and payment will be made directly to the
PAPs without any delay, by way of crossed cheques, following issuance of notices as
required by LAA 1894.
10.12. Capacity Building and Safeguard Training
The ESIC staff, including those to be recruited from the market for project implementation under the
PMU in Construction Camp Office, will be provided with at least one-week training for
social and resettlement capacity building prior to mobilizing to the field. The training will
be conducted by reputed trainers and professionals with experience in resettlement
implementation experience in Pakistan and internationally.
The Project will periodically organize study tours and exposure trips of ESIC/Project staff within
and outside the country. As a start, the ESIC Team will be taken to the Transmission Line
(CASA-1000) Project for training and exposure to see, observe and learn hands-on how
Transmission Line (CASA-1000) Project has been managing the massive resettlement
and social development programs and the implementation challenges. Post-training de-
briefing sessions will be held in seminar form to discuss the learnings and application in
the context of the Transmission Line (CASA-1000) Project.
10.13. RAP Implementation Schedule
The commencement of civil work will be subject to the satisfactory implementation of
this RAP including payment of compensation for the loss of crops, trees and structures,
as well as redress of community concerns. It is expected that the construction of the
Transmission Line (CASA-1000) Project will be completed over a period of about 2 years
(2022-2024). The disbursement of payment of compensation and allowances payment will
be carried out in parallel with the project implementation and will be completed till the end
of 2023. Moreover, the implementation of CSP including benefit-sharing component will
also continue simultaneously during the project implementation. The status of progress will
be reflected both in internal and external monitoring report, as these semi-annual reports
will be prepared by the PMU and independent monitoring consultant respectively. Thus, a
timely implementation of the RAP is essentially important for the successful completion
of the project itself.
The RAP implementation process is presented in Table 10.1 and the implementation
schedule is illustrated in Figure 10.2.
Establish Grievance Redress Committee NTDC PMU will need to notify the GRC at field
Updating of RAP (if any change in design) PMU/NTDC If there is any change in design, then RAP
and accordingly submit to WB will be updated and accordingly get
for approval. approval from WB.
Contract Award (expected date March NTDC/ Date will be finalized based on the
2022) PMU/Contractor construction plan of the project
Hiring of IMC (Independent monitoring NTDC/ PMU Independent monitoring consultant to be
consultant/ agency) engaged by the PMU for the validation of
RAP implementation.
Employment to the PAPs in the project Contractor/ CO Preference will be given to the PAPs/locals
related jobs. in the project related jobs.
Full Implementation of RAP PMU/PIU/ESIC/ RAP implementation to be carried out by
Project the PMU through CO/ ESIC with the
Consultants assistance of project Consultants’ team.
As per LAA 1894, the land compensation cost is assessed as per provisions of section 23
by considering market value of land, damages sustained due to lost asset (crops, trees)
and severing of acquired land, incidental costs in income losses due to change of
residence or place of business. The replacement costs for the structures, trees and crops
are based on the updated scheduled rates provided by the respective government
departments. The unit rates applied in determining the resettlement costs are elaborated
as follows:
Valuation of acquired Land: Under the law (LAA 1894) respective district land
revenue officer/designated land acquisition collector is required to follow the process for
land valuation and assessment of compensation by considering provisions of section 23
of LAA and prevailing instructions issued by the BOR. To ensure, the compensation
determined by the district price assessment committee or land revenue officer/land
acquisition collector is consistent with the provisions of section 23.
Valuation for non-land assets: For compensating affected assets within the ROW limits
of CASA 1000 TL, the following procedures / methods have been used:
For compensating the affected structures of different types and dimensions, the
updated construction rates have been collected for the year 2021 from the
Executive Engineer (Buildings), W&S Department, Peshawar. These scheduled
rates applicable for new construction of similar types of structures have been
used to calculate compensation on replacement cost basis for all affected
structures. The depreciation for age will not be deducted and the salvage will be
28The affected structures will be dismantled (if required) and accordingly re-assessment of the payment of
compensation will be made based on the latest rates provided by C&WD/NTDC civil department. This activity will be
started as the RAP implementation of CASA-1000 TL project initiates.
29. The land owners who will be affected due to erection of towers will be compensated for the land under tower at rates that could
be ranged from 0.100 Million PKR to 0.500 Million PKR per tower location subject to negotiation between NTDC and landowner
depending upon site conditions/location of tower. Both the ceiling will be flexible depending upon site conditions.
Amount
Sr. PAHs Unit Rate Amount
Resettlement Activity Unit Quantity (USD in
No. (Nos.) (PKR) (M. PKR)
million)
Government owned timber
iii) Number 9,920 Various - -
trees
Sub-Total (C) 18.102 0.105
D Residential Structures
Square
i) Pacca structures (1 structure) 1 645.90 2,300 1.486 0.009
feet
Square
ii) Mud structures (3 structures) 3 4252.16 1,800 7.654 0.044
feet
Sub-Total (D) 9.139 0.053
E Support allowances and livelihood restoration
For loss of Residential Structures
i) Relocation Assistance 4 Number 4 25,000 0.100 0.0006
ii) Transport/Shifting Allowance 4 Number 4 15,000 0.060 0.0003
Sub-Total (E) 0.160 0.001
Income restoration
F
allowances30
Entitled Severe Impact
i) Allowance for Significantly 295 Ha 3.343 205,542 0.687 0.004
affected owners
Productivity enhancement
ii) 295 Number 295 25,000 7.375 0.043
support (PAH/ PKR. 25000)
Sub-Total (F) 8.062 0.047
G Vulnerability Allowances
i) PAHs with income Below PL 92 Number 92 63,000 5.796 0.034
Sub-Total (G) 5.796 0.034
Total (A to G) 284.045 1.645
Benefit-Sharing and
H Community Support
Program
Social Development Plan (A
i) Community Support Program is - -
funded by a separate project)
Sub-Total (H) - -
I RAP Implementation
Project Consultants (RAP Lump
i) 2.400 0.014
Implementation Team31) sum
Training and Capacity Lump
ii) 1.500 0.009
Building sum
Independent Monitoring Lump
iii) 1.500 0.009
Agency sum
30 To comply with the WB OP 4.12, compensation and allowances for the livelihood restoration to be paid as per entitlement matrix.
However, during the construction phase, the project impacts will be re-examined/ re-assessed by the NTDC Revenue staff and
accordingly the payment of compensation as well as entitled allowances/livelihood restoration assistance will be paid to the eligible
PAPs/PAHs (see Entitlement matrix table 6.1).
31 It is further suggested that for this RAP implementation, and Independent Committee (IC) will be constituted to avoid the
grievance (s)/ and or to resolve complaint (s) concerns of the PAPs/ and or local community.
Amount
Sr. PAHs Unit Rate Amount
Resettlement Activity Unit Quantity (USD in
No. (Nos.) (PKR) (M. PKR)
million)
Sub-Total (I) 5.400 0.031
J Total (A to I): 289.445 1.677
K Contingencies @ 10% 28.945 0.168
Grand Total (J+K) 318.390 1.844
Note: (i) 1 USD=172.63 Pakistani Rupees as of 19th October 2021.
(ii) During the initiation of RAP implementation, re-assessment of impacts (type and magnitude) based on final design and
construction activities will be made by the NTDC revenue staff and accordingly the payment of compensation will be made to the
eligible and entitled PAPs/PAHs
The internal monitoring by PMU will identify the key bottlenecks and problems in implementation
of the RAP. The Project Director of PMU and ESIC of NTDC will review these reports
and take necessary actions to address the concerns associated with the proposed project to
ensure successful implementation of the RAP.
13.3. External Monitoring by IMC
External monitoring will be carried out twice a year, i.e., semiannual external monitoring and its
results will be communicated to all concerned PAPs, PMU and World Bank through
semi-annual external monitoring reports. Subprojects whose implementation timeframe
will be under 6 months will be monitored only once. Indicators for External Monitoring
tasks include:
a) Review and verify internal monitoring reports prepared by ESIC and its field
offices;
b) Review of the socio-economic baseline census information of pre-displaced
persons;
c) Identification and selection of impact indicators;
d) Impact assessment through formal and informal surveys with the affected persons;
e) Consultation with PAPs, officials, community leaders for preparing review report;
and
f) Assess the resettlement efficiency, effectiveness, impact and sustainability,
drawing lessons for future resettlement policy formulation and planning.
The IMC will also assess the status of project affected vulnerable groups such as female- headed
households, disabled/elderly and families below the poverty line. The following will be
considered as the basis for indicators in monitoring and evaluation of the project:
a) Socio-economic conditions of the PAPs in the post-resettlement period;
b) Communication and reactions from PAPs on entitlements, compensation,
options, alternative developments and relocation timetables etc.;
c) Changes in housing and income levels;
d) Rehabilitation of squatters;
e) Valuation of property;
f) Grievance procedures;
g) Disbursement of compensation; and
h) Level of satisfaction of PAPs in the post resettlement period.
13.4. Post-Project Evaluation by IMC
The IMC will carry out a post-implementation evaluation of the RAP about a year after completion
of its implementation. The compelling reason for this study is to find out if the objectives
of the RAP have been attained or not. The benchmark data of socioeconomic survey of
severely affected PAPs conducted during the preparation of the RAP will be used to
compare the pre- and post-project conditions. The IMC will recommend appropriate
supplemental assistance for the PAPs should the outcome of the study shows that the
objectives of the RAP have not been attained.
13.5. Disclosure of IMC Reports
The results of semiannual external monitoring will be communicated to all concerned
PAPs, PMU and World Bank through semi-annual external monitoring reports. The
reports will be uploaded to NTDC web-page while electronic copies will be made
available to WB and the communities affected by the project.
The results of the post-implementation evaluation of the RAP will also be communicated
to all concerned parties through the same channels, including any likely recommended
supplemental assistance for the PAPs.
PHOTOLOG
OF SELECTED EVENTS
1. PHOTOGRAPHS.............................................................................................2
Stakeholders’ Consultations..........................................................................2
2. PHOTOGRAPHS.............................................................................................6
Consultations with Local Women/Stakeholders Consultations.................6
3. PHOTOGRAPHS Impact Assessment Surrey/IOL.................................15
PHOTOGRAPHS
Stakeholders’ Consultations
Pictorial Presentation
Plate 2: A view of consultative meeting with EDO KPK being held at her
Plate 1: A view of consultative meeting with Ex-Governor KPK being held at office Peshawar
his office Peshawar
Pictorial Presentation
Plate 7: A view of consultation meeting with XEN Warsak canal at Irrigation Plate 8: A view of consultation meeting with ADEO being held at District
Department Peshawar Education office, Nowshera
Pictorial Presentation
Plate 13: A view of consultation meeting with NGO (SPARC) Plate 14: A view of consultation meeting with NGO (NIDA)
Representative at Peshawar Representative at Peshawar
PHOTOGRAPHS
Consultations with Stakeholders including women
Pictorial Presentation
Plate 17: A view of Consultation with community at Zawo Banda, Tehsil &
Plate 16: A view of Consultation with locals at Zawo Banda, Tehsil & District
District Nowshera
Nowshera
Pictorial Presentation
Plate 23: A view of Consultation meeting with Locals at Jaba Khushk (Meera),
Plate 22: A view of Consultation at Jaba Khushk (Meera), District Nowshera Tehsil & District Nowshera
Plate 25: A view of Consultation with locals at Zawo Banda, Tehsil & District
Plate 24: A view of Consultation with Locals at village Jaba Khushk (Meera), Nowshera,
District Nowshera
Plate 26: A view of Consultations with local community at Ghari Churkh, Plate 27: A view of Consultations with local community at Ghari Churkh,
Tehsil& District Peshawar Tehsil & District Peshawar
Pictorial Presentation
Plate 28: A view of Consultation with at Jaba Khushk (Meera), Tehsil Plate 29: A view of Consultation with at Jaba Khushk (Meera), Tehsil
&District Nowshera &District Nowshera
Plate 33: A view of consultation with locals at Shaddi Bag UC: Shah Kot Tehsil
Plate 32: A view of consultation with locals at Shaddi Bagh UC: ShahKot Tehsil
&District Nowshera
& District Nowshera
Pictorial Presentation
Plate 34: A view of Consultation with locals at Zawo Banda, Tehsil & District
Plate 35: A view of consultation at Gari chandan Faqeerabad
Nowshera,
Plate 36: A view of Measurement at chainage 60+538 Plate 37: A view of Measurement at chainage 00+060
Plate 38: A view of Measurement at chainage 000+712 Plate 39: A view of consultations at Jaba Khushk (Meera), Tehsil & District
Nowshera
Pictorial Presentation
Plate 40: A view consultation Meeting at Lundikotal, District Khyber Plate 41: A view consultation with local induvial at Speen Khana Tehsil &
District Nowshera
Plate 42: A View of consultation with locals at Azakhul Bala, UC: Azakhul Plate 43: A View of consultation with local community at Azakhul Bala, UC:
Bala Tehsil & District Nowshehra Azakhul Bala Tehsil &District Nowshehr
Plate 44: A view consultation at Spean Khana Khulan, Tehsil &District Plate 45: A view consultation meeting with individual at Speen Khana
Noweshera Khulna, Tehsil & District Noweshera
Pictorial Presentation
Plate 46: A view of consultation with locals at Sara khura (Maryam zai), Plate 47: A view of Community Consultation with locals at Umber khel,
Tehsil& District Peshawar Tehsil Bara & District Khyber
Plate 48: A View of consultation at Taila band, Tehsil &District Peshawar Plate 49: A View of Community consultation at Sipha, Tehsil Bara & District
Khyber
Plate 51: A view consultation at pak Shekhan jalozai, Tehsil Pabbi, &
Plate 50: A view consultation meeting Aza lkhel, Tehsil and District District Nowshera
Nowshera
Pictorial Presentation
Plat 52: A view of consultation with locals at Aza khel. , Tehsil & District
Nowshera
Plate 53: A view of Consultation with locals at Jabba tar, Tehsil & District
Nowshera
Plate 54: A View of Community consultation at Speen kana Kalan, Tehsil &
Plate 55: A View of consultation at pak meri khel Bara District Khyber
District Nowshera
Plate 56: A view consultation Meeting at Tehsil pabbi & District Nowshera Plate 57: A view consultation Meeting at Taila band, Tehsil & District
Peshawar
Pictorial Presentation
Plate 58: A of consultations meeting with women about Casa 1000 at Speen Plate 59: A view of consultation with women about T/L Sara Khura,
Khana , Nowshera Peshawar
Plate 61: A view of consultations with Locals women about T/L at Lundi
Plate 60: A view of consultation Meeting with women at Sipai, Nowshera Kotal
PHOTOGRAPHS
Impact Assessment Survey/IOL
PICTORIAL PRESENTATION
Plate 62: A view of affected structure, at Churkh at chainage 00+710 Tehsil Plate 63: A view of Affected crops at Jaba Khushk (Meera), Tehsil
& District Peshawar &District Nowshera
Plate 64: A view of affected structure, at Churkh as chainage 00+71 Tehsil Plate 65: A view affected area at Dojangi canal, Tehsil Bara, and District
& District Peshawar Khyber
Plate 66: A view of affected Area at Zow kaly, Tehsil & District Nowshera Plate 67: A view of Transmission Line Crossing at Garhi Chandan,
Faqerabad
PICTORIAL PRESENTATION
Plate 68: A view of along the Existing Transmission line at Aazakhel Bala,
Tehsil & District Nowshera Plate 69: A view of centerline of Transmission line at Tawar 147
Plate 70: A view of affected land at Aazakhel Bala, Tehsil & District Plate 71: A view of Grave Yard in the Row at Ranga, Tehsil Bara, District
Nowshera Khyber.
Plate 72: A view of Affected Tress along the Route alignment Plate 73: A view of Affected Area at chainage 27+975