Professional Documents
Culture Documents
004 - ITP Asphalt - Revision 0
004 - ITP Asphalt - Revision 0
Project Number and Name: Ampol Lytton Refinery Future Fuels Project Bulk Prime & Asphalt
Inspection Title:
Earthworks
Sign-Off
Name: Signature: Date:
HEQ-TPE-00396
Rev. 6 (15/06/2018) Page 1 of 5
Inspection and Test Plan (ITP)
Verification
Inspection / Reference/ Hold Points/
Item Work Step Conformance Criteria Frequency Sign Date
Test Method Clause Witness Points
BMD Kent
1.0 Preliminary Requirements
SWMS to be submitted prior to permit being issued. Prior to
1.1 Documentation Submission establishment Hold Point
on site
HEQ-TPE-00396
Rev. 6 (15/06/2018) Page 2 of 5
Verification
Inspection / Reference/ Hold Points/
Item Work Step Conformance Criteria Frequency Sign Date
Test Method Clause Witness Points
BMD Kent
3. Aggregate Particle Size Distribution - BCC S330
4. Binder Content CL2.5
5. Filler Content
6. Mixing Temperature
For Prime/Primer seal:
1. Binder Class
2. Cover Aggregate Size
3. Design Method
4. Designed Spray & Spread Rate
2.0 Construction
The prime or primer seal the granular base before any asphalt
is placed. BCC S330
All Areas with
2.1 Prime / Primer Seal Monitoring Clause 6.6 and
Prime
The prime curing time is to comply with the specific prime type Clause 6.7.
requirements (cutback, emulsion, etc.)
Submit a delivery docket at the time and place of delivery for
each truckload of material showing:
1. Empty and loaded mass of the vehicle
Documentation/ 2. Dispatch Date and Time BCC S320 All Areas with
2.2 Delivery Dockets Report 3. Mixing Plant Supplier and Location CL2.4. Asphalt
Submission 4. Vehicle Registration
5. Asphalt Mix – Size and Type
6. Binder Class
7. Mixing Temperature
Geotechnical The asphalt compaction standards to be achieved are listed in BCC S120 Table All Areas with
2.3 Asphalt Compaction BCC S120 Table 7.2.
Testing 7.1 Asphalt
The asphalt layer thickness to be adhered to are listed in BCC All Areas with
Monitoring
S320 Table 5.1. Asphalt
HEQ-TPE-00396
Rev. 6 (15/06/2018) Page 3 of 5
Verification
Inspection / Reference/ Hold Points/
Item Work Step Conformance Criteria Frequency Sign Date
Test Method Clause Witness Points
BMD Kent
Edges abutting kerb and channel: Within + 5 mm or flush - BCC S320 Vertical: 1 test
with the level of the actual lip of channel. CL3.0 every 20m
Crossfall: As-constructed levels are not to depart from the - Min 3 points on
corresponding design crossfall by more than 0.2% absolute. each cross-
Maintain positive drainage slope towards pavement drainage section.
system. (i.e. 1 at the crown
Primary vertical tolerance: +10 mm, -0 mm at any point on and offsets
the surface layer. spaced evenly at
Deviation from a 3 m straightedge: Maximum 5 mm except not more than 3m
where due allowance for design shape dictates otherwise. from the crown.)
HEQ-TPE-00396
Rev. 6 (15/06/2018) Page 4 of 5
HEQ-TPE-00396
Rev. 6 (15/06/2018) Page 5 of 5