Professional Documents
Culture Documents
002 - ITP Earthworks - Revision 2.0
002 - ITP Earthworks - Revision 2.0
002 - ITP Earthworks - Revision 2.0
Project Number and Name: AMPOL Lytton Refinery Future Fuels Project Bulk Earthworks & Pavements
Inspection Title:
Earthworks
Sign-Off
Name: Signature: Date:
3.0 Excavation
All excavation and filling shall be made to the
lines, grades and elevations shown on the
All Areas Survey
Drawings and in accordance with AMPOL
Excavation Procedure PROC 4.10.02.001. STD
3.1 Excavation and Fill
Geotechnical 40.06.Q.004 CL4
Any excess excavation to pipe and cable Testing
trenches shall be backfilled with Type 1 fill As Required
material. STD 40.06.Q.004
CL4.5.1
4.0 Subgrade
The Subcontractor (BMD) is to conduct
subgrade CBR testing and provide the results
to the Principal Contractor / Company & a FYFE - CIVIL
All Subgrade Geotechnical
4.1 Subgrade In-situ CBR Testing suitable qualified Geotechnical Engineer for TYPICAL
Surfaces Testing
assessment. DETAILS
5.0 Filling
Medium Duty Crushed Rock Pavement,
Heavy Duty Crushed Rock Pavement &
Light Duty Crushed Rock Pavement:
The Subcontractor, BMD, is to engage a
suitably qualified Geotechnical Engineer to
witness and approve the (1) combi-grid and (2)
crushed rock starer layer preparation works. All Pavement
The Geotechnical Engineer is to visually Areas where
Geotechnical Engineer Visual Inspection /
5.1 Witness Point assess the subgrade surface for perceptible the Topsoil
Supervision Proof Roll
surface deformation by undertaking proof Remained In-
rolling to: situ
1. Ensure the subgrade is suitable for
the placement of fill, OR
2. (b) Provide the Subcontractor
(BMD) with direction and details to
perform additional subgrade
treatment.
The fill material shall be placed and spread in
STD
uniform near-horizontal layers, which do not
5.2 Placing Fill All Areas Visual Inspection 40.06.Q.004
exceed the thickness specified for the various
CL4.5 &CL4.8
grades of fill listed in the STD 40.06.Q.004.
The Subcontractor (BMD) is required to
achieve compaction testing results in the
following order:
1. Compaction testing requirements
listed in the FYFE CIVIL DETAILS STD
As per Figure Geotechnical
5.3 Compaction of Fill DRAWING 40.06.Q.004
2 Testing
a. A1 Structural Fill @ 98% CL4.4
standard compaction.
b. Rock Starter Layer @
98% standard
compaction; &
STD
Fill Material - Type 3 (Crushed Geotechnical
5.3 40.06.Q.004
Rock - Road Base Course) Testing
CL4.5.3
Class 2.3 Material The Class 2.3 Material is to comply with the FYFE - CIVIL
As per Figure Geotechnical
5.6 MRTS-05 - Section 7.2 Type 2 Unbound TYPICAL
MRTS 05 3 Testing
Material (excerpts on Page 12-13). DETAILS
The minimum size pieces shall be 75mm and STD
5.7 Rock Pitching thickness when places shall not exceed As Required Visual Inspection 40.06.Q.004
150mm. CL4.5.7
Figure 2: Testing Frequencies (Extracted from AMPOL Earthworks Specification - Table 8 - Testing Fill Guide)