Professional Documents
Culture Documents
IPMT Weekly Report 27 Jan 17 DRAFT (MH)
IPMT Weekly Report 27 Jan 17 DRAFT (MH)
694012004.docx Page 1 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
h. Contractor has issued a Claim for Scaffold costs of $10.2m USD. h. Reviewed by IPMT and discussed with Allens. Next steps agreed.
694012004.docx Page 3 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
694012004.docx Page 4 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
694012004.docx Page 5 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
694012004.docx Page 6 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
U-111 Flue gas Desulphurization: Designer (Hamon) inspected & gave initial Line condensate header up to main header & send to U-102
findings, will submit schedule & plan after verifying with Head Office, Demineralised Water for recovery
targeted 27 January. PSSR held with 36 observations made.
U-112 GTG: GTG # 1 operating below 152 NOx, GTG # 2 exhaust used for
steam production HRSG # 2.
U-112 HRSG: HRSG # 2 @ 51 bar & producing 50-55 ton HPS/hr
U-113 Steam Turbine Generators: STG # 4-3-2-1 MRT & over speed trip
tests completed. STG # 5 continues with control oil flushing, Turning gear
test on STG # 5 suspect turbine condensate lines back flushed to each STG
U-122 Nitrogen: Liquid N2 production ongoing building level
U-190 ETP: MRT of systems for rotating equipment ongoing, target
completion 11 February
694012004.docx Page 7 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
Abbreviations
A ABD Amine Blow Down
AG Above Ground
ASNT American Society for Non Destructive Testing
AFR Audit Finding Report
B BBS Behavioural Based Safety
BFW Boiler Feed Water
BTM Baseline Thickness Measurement
BOQ Bill of Quantities
C CAR Corrective Action Report
CC Contract Change
CCN Contract Change Notification
CIF Cost Insurance and Freight
COC Continually Oily Contaminated Wastewater
COW Change of Work
CRD Construction Required Date
CCB Central Control Building
CBD Closed Blow Down
694012004.docx Page 8 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
O OC Operating Centre
OTDR Optical Time Domain Reflectometer
OM Operating Manual
OVHD Over Head
P PSA Pressure Swing Adsorber
PM Project Manager
PO Purchase Order
PIM Pre-Inspection Meeting
PAF Personnel Approval Form
PLEM Pipeline End Manifold
PMSO Project Management Support Officer
PSS Production and Schedule System
PCSR Pre Commissioning Safety Review
PSSR Pre Start Up Safety Review
PVD Post Order Vendor Deviation Request
R2R Reactor & Two Regenerators
R RCM Report Reliability Centred Maintenance
RFA Recommendation For Award
S SAT Site Acceptance Test
SCR Selective Catalytic Reduction
SIS Safety Instrumented System
SDAS Supervisory Date Acquisition System
SIMOPS Simultaneous Operations
SMP Steel Mechanical Piping
SSU Successful Start Up
694012004.docx Page 11 of 12
NSRP LLC NSRP Complex Project Executive Summary Report Week Ending 27 January 2017
(New Activities are in Blue text – existing/ongoing activities in Black Text)
694012004.docx Page 12 of 12