Professional Documents
Culture Documents
VSHydro 142
VSHydro 142
┌ ┐
Seilkranbau VSHydro
Cable way systems
Costruzione teleferiche Mr. Prabodha Sumanasekera
Managing Director
└ ┘
Phone:+254786221877
Fax:+256775582275
E-mail: prabodhaks@yahoo.com
Trodena, 2016.04.26
we were very pleased to received your inquiry and now we send you our offer n.142/2016 for the SEIK
GmbH/srl products requested:
Article code 01 Carrier Seik type SFM30/60 motorized Unit price EURO
000099136 Engine Diesel-Turbo 42hp
Power transmission full hydraulic with negative brake
Line pull single traction 3000 kg
double traction 6000 kg
Heave speed from 0,5 to 1,6 m/s
Operation radio control system with two
transmitters
Load line length 170m – Ø 12mm
Unit price 52.004,00
Special Features:
Third transmitter for radio control system
Unit price 1.570,00
Seilkranbau
Cable way systems
Costruzione teleferiche
B(1)
F
M G H
A(*)
SFM 30/60 2.740 1.570 630 2.050 420 980 2.100 420 220
(*) – Owerall length. (1) – Dimension depending of the size of the roller (Diameter of suspension cable). (2) –
Owerall width of the carrier.
Tab. 1 – Principal dimensions
Seilkranbau
Cable way systems
Costruzione teleferiche
9 16 13
11
14
5 4
6
10
2
15
7 1
12
Seilkranbau
Cable way systems
Costruzione teleferiche
Traction
60 kN Article Nr. 410700030 Weight 124 kg
Traction
40 kN Article Nr. 410700031 Weight 119 kg
Seilkranbau
Cable way systems
Costruzione teleferiche
Quantity need tot. Description Unit price EURO Tot. price EURO
Cable support (saddle) for high
04 mainline guidance 1.200,00 4.800,00
Seilkranbau
Cable way systems
Costruzione teleferiche
Quantity need tot. Description Unit price EURO Tot. price EURO
02 Bar for double skyline support 1.000,00 2.000,00
Seilkranbau
Cable way systems
Costruzione teleferiche
Steel elements for braced masts - Series 80, with the following heights:
Quantity need tot. Description Unit price EURO Tot. price EURO
02 Headelement 3 m 1.120,00 2.240,00
02 Headplate small 540,00 1.080,00
02 Footelement 3 m 1.120,00 2.240,00
02 Footplate small 520,00 1.040,00
09 Interimelement 6 m 1.520,00 13.680,00
01 Headplate special for double mast 2.500,00 2.500,00
01 Footplate special for double mast 1.500,00 1.500,00
B A
B A
3 1 1 2
"Z"
Sezione A - A
Schnitt A - A
(1:5) Sezione B - B
Schnitt B - B
(1:5)
4
Scala 1:5
Dettaglio "Z"
Einzelheit "Z"
(1:2.5)
4 5
2 1
6
Seilkranbau
Cable way systems
Costruzione teleferiche
01 Anchor plate
BLOCKS
Quantity need tot. Description Unit price EURO Tot. price EURO
03 Block URA50 386,00 1.158,00
Quantity need tot. Description Unit price EURO Tot. price EURO
02 Block URA100 1.012,00 2.024,00
Seilkranbau
Cable way systems
Costruzione teleferiche
Quantity need tot. Description Unit price EURO Tot. price EURO
02 Turnbucklets at 8-pulleys 40t 3.000,00 6.000,00
Quantity need tot. Description Unit price EURO Tot. price EURO
01 Anchoring points 40t for rope 38-48mm 2.000,00 2.000,00
01 Small material necessary for cable way system like cable hoists, shackles, forged wire
ropes clipes, loop and since to a value
For installation of the cable way system the firm Seik the client will provide skilled personnel, to
assist at the installation.
The daily rate of one expert amounts to 850,- Euro with 10 hours working time exclusive per diems,
accommodation, fly etc., which is to be supplied by the client.
(Travel time is to be considered working time)
Seilkranbau
Cable way systems
Costruzione teleferiche
PLANNING
Our planning contain all the calculations of the anchor powers, the rope power, the pressure on
brached masts and on which point you have to put up the brached masts. It also gives out the type
of the necessary ropes, the diameters of the ropes, except the anchor ropes. The planning also
give as the necessary interfaces between anchor, halftimbered brached masts and so on.
CONCRETE ANCHORAGES
All required anchorages including earth works, drillings, rock anchors, reinforcements, construction
steel, etc. for the cable way system are not in the scope of delivery and are to be supplied by the
client.
The static of the anchorages will be planed for you, by a civil engineer on construction side, and
then, in case of conclusion of a transaction, we will help you with plan examples for anchorages, to
realize them.
Conditions of delivery:
Payment: to accordate
Delivery time: to accordate
Terms of delivery: EXW Seik, Zona artigianale San Lugano, I-39040 Trodena
Validity offer: 30/11/2016
Best regards,
Lantschner Michael
Director