Professional Documents
Culture Documents
Risk Management and Use of Risk-Based Approaches in Inspection, Maintenance and HSE ... (PDFDrive)
Risk Management and Use of Risk-Based Approaches in Inspection, Maintenance and HSE ... (PDFDrive)
Risk Management and Use of Risk-Based Approaches in Inspection, Maintenance and HSE ... (PDFDrive)
Additional
contract info:
NIS, petroleum industry, risk management, API 581, risk based inspection,
Keywords:
reliability centered maintenance, Seveso, Safety report
© Steinbeis Advanced Risk Technologies GmbH, Willi-Bleicher-Str. 19, 70174 Stuttgart, Germany
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Table of Contents
List of Figures ................................................... vi
List of Tables ................................................... viii
1 Management Summary Report .................... 1
2 Detail Technical Report .............................. 2
2.1 General part............................................. 2
2.1.1 Introduction ................................. 2
2.1.2 General about NIS a.d. .................. 3
2.1.2.1 Activities ........................................... 3
2.1.2.2 History of the company ....................... 4
2.1.2.3 NIS in numbers.................................. 4
page ii
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page iii
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page iv
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page v
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
List of Figures
Figure 1: RiskNIS packages - Scope of the work ............. 2
Figure 2: Refineries of NIS a.D. .................................... 3
Figure 3: Structure of shares on NIS a.d. ...................... 5
Figure 4: Geographical position of Pancevo in Serbia ....... 6
Figure 5: Google view of Pancevo in Serbia .................... 7
Figure 6: Industrial zone of Pancevo ........................... 10
Figure 7: Industrial zone of Pancevo - Location of
Refinery .................................................. 10
Figure 8: Wind Rose for Pancevo ................................ 16
Figure 9: Years of construction................................... 20
Figure 10: Second phase of expansion ........................ 21
Figure 11: Bombing 1999 .......................................... 22
Figure 12: Oil refinery in Novi Sad .............................. 27
Figure 13: Position of Novi Sad .................................. 28
Figure 14: Position of Novi Sad Refinery ...................... 28
Figure 15: Location of Zrenjanin in Serbia ................... 41
Figure 16: Location of Zrenjanin and Elemir ................. 41
Figure 17: Map of roads ............................................ 42
Figure 18: Distribution of relative wind frequencies per
year (%) ................................................. 45
Figure 19: Seismic activities ...................................... 46
Figure 20: Elemir Gas refinery ................................... 46
Figure 21: Framework of RIMAP procedure within the
overall management system ....................... 51
Figure 22: Methodology and application of detailed RBI . 52
Figure 23: CEN CWA 15740 (RIMAP) Risk Matrix........... 55
Figure 24: NIS risk matrix ......................................... 55
Figure 25: Flowchart of HAZOP Process ....................... 62
Figure 26: Results of API Qualitative Analysis Component
based applied on RGE equipment ................ 65
Figure 27: Results of API quantitative (detailed) Analysis
Component based applied on selected RGE
equipment ............................................... 65
Figure 28: Component count for RBI analysis of Elemir
Refinery .................................................. 66
Figure 29: Project web site – Tools and analysis ........... 68
Figure 30: Flow diagram of the refinery, Part 1 of 3 ...... 72
Figure 31: Flow diagram of the refinery, Part 2 of 3 ...... 73
page vi
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page vii
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
List of Tables
Table 1: List of blocks in Pancevo Refinery ..................... 8
Table 2: Medium monthly and annual values of the
precipitation quantity ( mm) in Pančevo ....... 14
Table 3: Medium monthly and annual air temperatures in
Pančevo reduced recording to the data for
Belgrade .................................................. 14
Table 4: Medium monthly and annual values of the air
humidity in Pančevo, reduced according to
data for Belgrade ...................................... 16
Table 5: List of commercial products of Pancevo refinery 17
Table 6: Storage capacities of Refinery........................ 19
Table 7: Qualification structure of employees in Pancevo
Refinery .................................................. 25
Table 8: Number of employees in Pancevo Refinery by
type of work ............................................. 25
Table 9: Maximum concentration of employees, first shift26
Table 10: List of units in Novi Sad Refinery .................. 29
Table 11: Average temperatures (Source: Republic
Hydrometeorology Service of Serbia) ........... 31
Table 12: Novi Sad region - Frequency of the winds ...... 32
Table 13: Average value of cloudiness in sky/10 ........... 32
Table 14: Key units in Novi Sad Refinery - characteristics34
Table 15: Number of personnel in Firefighting unit of
Novi Sad refinery ...................................... 36
Table 16: Firefighting equipment ................................ 36
Table 17: Available fire extinguishing means ................ 37
Table 18: Dangerous substances in U 100 ................... 38
Table 19: Dangerous substances in U 200 ................... 40
Table 20: Statistical data on monthly weather
parameters for Zrenjanin region .................. 43
Table 21: Statistical data on seasons weather
parameters for Zrenjanin region .................. 43
Table 22: Temperature distribution in the region - July .. 45
Table 23: Temperature distribution in the region -
December ................................................ 45
Table 24: Frequency and velocity of wind .................... 45
Table 25: RGE supplies ............................................. 47
Table 26: Employees structure in Elemir Refinery ......... 47
Table 27: List of NIS-Naftagas certificates and scope of
certification .............................................. 47
page viii
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page ix
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page x
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 1
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
A. Basic package:
C. * Full coverage
• Feasibility study (all identified equipment)
• Basic implementation for RBI, RCM and Basic package INCLUDED
RCFA: Software Licensing and first
B. Suggested package: • 12871 pieces of equipment for Level 1
year maintenance cost
analysis
Travel and subsistence Basic package INCLUDED
• 5148 pieces of equipment for Level 2
Project Management FULL training INCLUDED analysis
• 2529 pieces of equipment • 1287 pieces of equipment for Level 3
• 200 Equip. RBI level 1
for Level 1 analysis analysis
• 80 Equip. RBI level 2 • 1012 pieces of equipment • 12058 pieces of equipment for RCM
• 20 Equip. RBI level l3 analysis for Level 2 analysis analysis
• 20 components analyzed by • 253 pieces of equipment • 250 pieces of equipment / systems for
RCM for Level 3 analysis RCFA analysis
• 1268 pieces of equipment Introduction of the full scale CMMS (Aopt) is a
• 10 components analyzed by for RCM analysis necessary precondition for this Package.
RCFA • 38 pieces of equipment /
• Implementation of HSE, HAZOP and systems for RCFA analysis
Seveso II Directive
Basic training for RBI, RCM/RCFA and
HSE/HAZOP/Seveso II, first instance of the
training/certification
Kick of meeting for Package B was held on September 28, 2008 in Elemir Refinery and
preparation for data collection started immediately. Templates for data collection for RBI,
RCM / RCFA analysis have been developed and agreed with experts from three refineries.
page 2
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Order of refineries to be treated with analysis has been agreed as RGE, RNS, RNP, according
to availability of experts to collected / verify data.
Data collection started by the end of December 2008 with Refinery Elemir and for other two
refineries in the first quarter of 2009. First preliminary RBI report prepared for RGE and
delivered in March 2009.
Several meetings were held in order to review the work progress (May 4, June 12, December
12, 2009) and to present plan for the further work. Two workshops were held as well in
Stuttgart (April 2010) with the aim to verify input data and to agree the type and contents of
the reports expected by NIS management.
Analysis have been done as required by the contract for Package B; based on their results
recommendation for improvement / optimization of inspection, maintenance and HSE
practice have been given.
Training, education and certification of NIS a.d. employees started in November 2008 and
finished in January 2010. Training has included both, theoretical courses in the field of risk
management and on-the job training in German companies.
page 3
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 4
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 5
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
the crude oil and dispatching the derivatives by barges. Crude oil and its derivatives can also
be loaded and unloaded at the Refinery's own railway transport facilities. There are also
tank-truck loading & unloading facilities.
Head office of the refinery is in Pancevo, Spoljnostarcevacka b.b and legally it is a part of the
joint-stock company NIS - Petroleum industry of Serbia owned Serbia and JSC Gazprom
Neft. Total number of employees is 2300.
Some of planned development projects are:
• meeting EU standards on product quality
• reconstruction of the units and infrastructure in order to improve the process
efficiency and crude oil valorization
• reduction of energy costs
• improvement of environmental protection
• joint projects with neighboring petrochemical company HIP-Petrohemija on better
valorization of by-streams.
page 6
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Pančevo is an industrial town with a population of about 130,000 people; 86,000 live in the
city, the remainder in outlying settlements and villages. The largest companies on the
territory of the town Pančevo is represented by an industrial complex (Figure 5a) which
includes the petrochemical plant HIP Petrohemija, Pancevo Refinery of NIS and the chemical
fertilizer plant HIP Azotara.
The industrial complex lays on the city’s southern edge, southeast of Vojlovica (Figure 5b), a
major residential area. The three factories, which cover about 290 hectares, employ about
6,600 people and represent the major employer for the entire Pančevo area. The map of
industrial zone is given in Annex 2 (scale 1:25000).
Micro location
Pancevo Refinery is located in the southeastern and eastern part of the southern industrial
zone, located about 4 km from the town of Pancevo, between settlements Vojlovica and
Starcevo. To the West of the refinery, at a distance of 2.5 km, runs Danube river, with docks
owned by the refinery. Channel Nadel flows to the East of the Refinery.
Residential area of Starčevo is located to the Southeast at a distance of 1 km of Refinery
while residential area of Vojlovica located northwest at a distance of 350m. Several small
villages lie directly to the south of the industrial complex. Sensitive public buildings like
schools are in a distance of about 3 km. Furthermore no traffic routes or major transport
centers are nearby the establishment yet.
The refinery is surrounded by agricultural land. The nearest industrial facilities are located on
the northwestern edge of the refinery and plant Messer-Tehnogas and Petrochemical
Complex Petrochemical HIP-Pancevo.
Pancevo refinery covers an area of 145 hectares. Port on the Danube, area of 3.5 hectares,
and pipeline bridge connecting the port and the refinery, about 2.5 hectares, are located
outside of the refinery.
Refinery itself consists of 24 blocks where production and power units are settled, as well as
necessary infrastructure. Schema of blocks in Refinery is given in Annex 3 and list of blocks
in Table 1.
page 7
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
No Description
Headquarter
Mashing workshop
Storage and garage
Block I
Technical security center
Trafo F
Entrance gate 2
Central wardrobe
Restaurant
Block II Laboratory
Sample house
Trafo C
Flare I and II
Storage tanks for slop and oil water
Block IV API separator
Pumpe house PK-4 with annex
Vessels with hydrogen and nitrogen
page 8
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
No Description
Trafo ST-35/6
Block XXIII
Gate 1
Railway building
Garage for locomotives
Loading installation for derivate
Block XXIV Unloading installation for crude oil and semi-products
Oil terminal with the building
Wagon
Sludge sediment
page 9
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 10
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 11
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Fauna of Fauna of the area comprises more than 280 species approximately. Some of these
species are threatened, according to IUCN categorization.
Population
According to the census in 2002. in the municipality of Pancevo lived 127,162 people and 23
different nationality, which speaks of a turbulent history and demographic situation of the
people in this region. About 8,000 reside in the Vojlovica and Topola quarters in the close
vicinity of Pancevo Refinery.
page 12
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
can not receive all the water from Tamis, thus creating backwater at Tamis that floods the
surrounding area. At minimal water level in its upstream parts at some points it almost dries
completely. West of the Tamis river there is the Sibnica River and a network of natural and
artificial canals, which are all directly dependent on the Danube regime.
The narrow area of Pančevo, South Industrial Zone of Pancevo, next to the flood plain, and
the SZIC were built on backfilled material, by which the ground level was raised to an
altitude of around 75 masl. This had to be done because of the high groundwater level
especially during the maximum water level in Danube and the influence of “Djerdap” dam.
This caused the creation of an artificial aquifer under the zone (Azotara and Petrohemija) in
its inner parts practically independent from the Danube River, which was the purpose of
these amelioration works. Between the city of Pančevo and the South Zone Industrial
Complex two parallel open canals have been constructed for industrial purposes. The
northern wider canal connects the fertilizer plant to the Danube. This is a navigable canal,
used by ships to carry bulk of raw materials and products, and is itself used as a raw water
source by the fertilizer and the petrochemical industries.
The southern canal is a wastewater canal that is used for discharging industrial effluent. Both
canals are approximately 2 km long. They are divided and surrounded by embankments all
the way from the plants to the Danube. The two canals both originate from the fertilizer
plant HIP Azotara. Those two canals are of great importance for the hydrology and
hydrogeology of SZIC. One the main purposes of canals is to drain the backfilled area, the
shallow aquifer, of the Industrial Complex making a local underground (hydro geological) sub
watershed. At the same time, the canal waters infiltrate the lower alluvial deposits of the
Danube, which means that those canals connect the artificial shallow aquifer with the main
alluvial aquifer.
Geology and Hydrogeology
The wider region around Pančevo is composed entirely of significantly thick quaternary
deposits settled on older Neocene sediments, which are found
only in deep research boreholes. Geology of South Zone Industrial Complex area can be
divided into:
• Oil Refinery region, and
• Region of Petrohemija and Azotara.
The Oil Refinery region belongs to the Banat loess terrace, southeast from Petrohemija. The
altitude of this first terrace from loessoide silt is higher then alluvial plain so there was no
need for backfilling as in case of Petrohemija and Azotara. There was just backfilling with the
purpose of levelling of original ground, which was slightly uneven. Oil refinery was
constructed on backfill heterogeneous material. Regarding the grain size analyses of this
heterogeneous material it is similar with sediments found beneath. The thickness of
backfilled material vary from 0 to 3,5 m. The altitude of Oil Refinery after backfilling is
around 74,21-76,93 masl, with slope from north to south. Sediments found beneath are
mostly presented by loessoide silt, since Refinery was built on Banat loess terrace made of
loess and loessoide silt. Thickness of this sediments, together with backfilled material, goes
from 4,5-12,5m, usually around 7-9m. Under this sediments starts the main aquifer made of
alluvial sands. Altitude of main aquifer overlying is on 61,72-70,94 m.a.s.l
Hydrogeology of Oil Refinery region do not have any specific characteristics comparing with
data given in chapter Hydrogeology of Pančevo area. As it is mention before, backfilling of
this terrain has been done only to level the previous surface of the ground. There is two
underground waters with different hydrodynamic characteristics: aquifer with free water level
(formed in loessial loam) and confined aquifer formed in Quaternary and Neocene sediments.
Hydraulic conductivity of loessial loam is around 2x10-6 cm/s, and for main aquifer around
1,5x10-2 cm/s [RADUS doo, 2004]. Underground water level, for the period September
2001-August 2002, vary from 70,1-72,1 m.a.s.l. General direction of groundwater flow is
from north to south.
Terrain Tectonics
From geotectonic aspect, the investigation area of Pančevo belongs to the south part of
Banat depression on the very border (Danube river) with the Zone of Uncover Neocene. The
oldest sedimentary rocks of Cretaceous age are folded and faulted during the Laramian
stage, between Senonian and Paleogene. During this period the basic tectonic framework
was formed. The tectonic movements in Neocene are weaker.
page 13
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Meteorological data
Pančevo is characterized by a continental to a moderate continental climate. The local
climatic conditions in this area are mostly affected by the presence of rivers Danube and
Tamiš, geographic latitude, distance from Mediterranean and Atlantic seas, as well as by its
isolated position in the Pannonian Basin surrounded by high-altitude mountains (Alps, Dinaric
Alps, Carpathian Mountains and Rodhopes). Moreover, significant forest belt located along
the two rivers could also influence on a local scale the municipal climate.
Rainfall
Precipitation distribution in Pančevo area is characterized by an alternation of rather humid
and rather dry periods. Generally, years with lower precipitation show two rainfall seasons
during spring and autumn, characteristic for the continental climate.
During years with high precipitation the spring rainy season extends through the summer
period, showing the influence of the Mediterranean climate regime. Table 2 shows data on
rainfall for the period 1961 do 2003.
Table 2: Medium monthly and annual values of the precipitation quantity ( mm) in Pančevo
J F M A M J J A S O N D Ann.
Mean
38.2 35 42.2 53.1 62.2 84.6 60 50.7 54.7 41.2 48.8 51.8 662.5
value
Maximum 103 100.1 128.8 132.9 171.5 195 227.7 259.7 189 164.4 89.8 146.4 927.8
Year of
max. 1987 1978 1981 2001 1987 1969 1999 1975 2001 1974 1980 1969 1999
value
Minimum 2.2 3.4 2.2 14.4 12.9 7.6 0 0 0 0 4.2 0.3 334.5
Year of
1990 1987 1972 1968 1988 2000 1989 1992 1986 1965 1986 1972 2000
min. value
Lightning is high frequency event in summer. The level of underground water is about one
meter deep. The surface is brick earth covered with concrete.
Air Temperature
Data on medium monthly and annual air temperatures for the period 1961 - 2002 is shown
in Table 3. Mean long-term air temperature value for the period 1962-2002 is 11.3 °C.
Analysis of the average monthly air temperature shows that January is the coldest month
with an average of –0.4 °C while July is the hottest month with an average of +21.8 °C.
Table 3: Medium monthly and annual air temperatures in Pančevo reduced recording to the
data for Belgrade
J F M A M J J A S O N D Ann.
Mean
-0.4 2.0 6.3 11.7 17.1 20.2 21.8 21.5 17.2 11.7 6.0 1.2 11.3
value
16.31
Maximum 3.7 7.3 10.7 15.5 171.5 19.7 22.8 24.8 26.4 21.2 5.0 13.4
1.3
Year of
max. 1983 2002 2001 2000 2002 2000 1988 1992 1994 1966 1963 1985 2000
value
Minimum -6.7 -4.0 0.6 0.6 7.5 18.1 19.3 17.7 13.6 8.5 0.8 -3.0 10.2
Year of
1964 1985 1987 1997 1991 1974 1979 1976 1996 1974 1988 2001 1978
min. value
page 14
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
High temperatures during the hot period of the year cause turbulences in the atmosphere
and strong vertical circulation that can favourably effect the dilution of emitted pollutants. It
is known that at a relative humidity higher that 55% and a temperature higher than 25°C,
photochemical smog is formed.
In Pančevo, these conditions are met on a couple of days of July and August. During the
winter period low temperatures and poor turbulences in the atmosphere enable temperature
inversions in Pančevo. Under these conditions dispersion of polluting substances is poor and
concentration of polluting substances in the lower part of the atmosphere occurs. During this
period, therefore immission measurements can detect pollutants concentrations higher than
the law limit values.
Wind
Wind has an important and significant influence on Pančevo climatic characteristcs and air
quality condition, since it could effect the transport and dilution of polluting substance.
Moreover, in specific climatic conditions, it could affect also the city of Belgrade. Wind profile
in the lowest layers of the atmosphere is greatly influenced by local topography, distribution
of water bodies and land ect.
The wind profile in the non-urbane part of Pančevo is under the influence of relatively
smooth terrain. In case of break-through of large atmospheric systems – cyclones, the
movement above Pančevo is in accordance with the circulation in the system of synoptic
scales. At such times a medium to strong wind usually blows. In the urbane part of Pančevo
we have increased ruggedness of urbane units that lead to modifications in wind speed and
wind direction. Meteorological station in Pančevo doesn’t have anemograph, so all the data
about wind are given from the Belgrade observatory. Frequency of winds from various
directions for Pančevo – wind rose - is given in
Figure 8.
page 15
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The dominant wind is the south-eastern wind, called Kosava. It is most frequent during
autumn, winter and early spring. The least frequent are north-eastern, easterly and south-
westerly winds. Southeastern winds are the fastest – higher than 3.5 m/s. Predominant wind
mean speed is 2,9 m/sec and annual average wind speed is 2,3 m/sec. Wind speed
influences the degree of smoke rise from the chimneys. Higher speeds are favourable for
dilution of pollutants from lower sources, but cause smoke rinsing from chimneys in case of
high-point sources2. The less frequent winds in Pančevo have the lowest speeds. These
winds have a detrimental effect on dispersion of polluting substances from ground sources
but enable rising of smoke from high sources to higher altitudes enabling significant
dispersion, that is high degree of dilution of emitted polluting substances from higher
sources.
Air Humidity
The mean annual value of relative humidity for the Pančevo region is around 78%, as shown
in Table 4. The highest monthly average values are recorded during winter season, in
December (88%) and January (88.1%), while the lowest average values are recorded during
summer period, in July and August (around 72%).
Table 4: Medium monthly and annual values of the air humidity in Pančevo, reduced
according to data for Belgrade
J F M A M J J A S O N D Ann.
Mean value 88.1 84.3 76.1 72.0 71.4 73.0 72.7 72.7 75.6 78.1 84.3 88.0 78.0
Maximum 98 94 93 81 83 86 84 86 85 91 94 97 85.5
Year of max. value 1971 1971 1962 1966 1961 2002 2002 1975 1975 1975 1975 1970 1970
Minimum 81 75 62 65 61 56 61 56 63 66 71 79 71.2
Year of min. value 1985 1998 1972 1968 1992 2000 2000 2000 1986 1961 1963 1989 2000
page 16
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Activities
Commercial
Product Standard
Code
page 17
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Commercial
Product Standard
Code
Gases
Propane PN SRPS B.H2.130
Butane BN SRPS B.H2.132
Isobutene IBN PS RNP 36/99
Propane - Butane mixture PBS SRPS B.H2.134
Diesel
Diesel fuel D1 D1 SRPS B.H2.410/1
Bitumen
Bitumen for road BIT 200 BIT 200 SRPS U.M3.010
Bitumen for road BIT 60 BIT 60 SRPS U.M3.010
Polymer bitumen PMB 50/90
Other products
page 18
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Commercial
Product Standard
Code
Product m3
LPG 5000
Naphtha 100000
Middle distillates 220000
page 19
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 20
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Upon completion of the first phase of expansion and increase in primary processing in the
Refinery, it became necessary to build secondary units that provide “deeper“ crude oil
processing, i.e. better crude oil yield.
Construction of the secondary units was implemented as the second phase of Refinery
expansion. However, before that, in 1982, Vacuum Distillation and Bitumen Units were
completed and commissioned. Design and equipment for both units were made in USSR.
Equipment and material for Vacuum Distillation and Bitumen were financed bythe guarantees
of banks from the loan of ex USSR to the Government of SFRY, and the funds in dinars were
provided by the Refinery.
page 21
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
By the end of nineties, it was already possible to compare the Refinery with the modern
world refineries. The built Refinery units enabled production structure in the ration 80% of
white, highly valuable products, to 20 % of black products.
Sanctions
Security Council introduced at the end of May 1992 sanctions to FR Yugoslavia. Embargo had
very serious consequences for the entire Petroleum Industry of Serbia, and thereby for the
Refinery as well. Direct damages from embargo are estimated to several billion dollars, and
indirect damages, in the form of delayed development, lost profit, and the like, can only be
assumed.
The last barges with the imported crude oil arrived in Refinery on 18 June 1992, and from
that moment on, Refinery was only processing domestic crude oil. Only about one sixth of
the available primary processing units were in operation, under the conditions of dinar and
foreign currency insolvency, multiple limitations in terms of procurement of spare parts and
chemicals, and the like.
At the time of embargo, S-100 was in operation, a small primary processing unit, and the
average processing capacity was 2.400 tons per day. This unit, before the sanctions, was
almost discarded – it was used for occasional processing of slop as well as a spare unit. In
1991, this unit was revitalized and put on stand-by. It proved that the Refinery would not
have been able to operate without it during the sanctions. Namely, there was not enough
crude oil for the operation of big Atmospheric Distillation Unit. All through the sanctions, S-
100 operated without major shut-downs. During embargo, Platforming, Gas Concentration
and Udex with auxiliary units were in function, in addition to S-100.
Even in these conditions, continuity of crude oil processing was preserved, while the
development was not entirely neglected either. This time was used for reparation of process
equipment that had not been in operation, for the preparation of investment and
development projects, professional training and education of personnel, development of
information system.
Because of that, Refinery was ready when the sanctions were lifted: Primary processing units
were ready as early as November 1995. Immediately upon the arrival of greater quantities of
crude oil, the processing capacity was increased to 8.000 tons per day.
In 1996 and 1997, revitalization of all the Refinery units was carried out, and these were
successively being put into operation. This is without precedent that a refinery was
successfully restarted, after most of its units have been out of operation for almost 4 years.
Bombing and reconstruction
In the course of seventy-seven days of NATO bombing of Serbia, the Refinery was bombed
seven times. The first time it was bombed on 4 April 1999, when the Refinery Power Plant
was hit with two missiles. The following attacks took place on 12 April (twice), 13 April, 16
April, 18 April and 7 June. About 60 percent of Refinery units was destroyed, and almost all
of the units and facilities were damaged, to a greater or smaller extent. Direct damages from
the bombing were estimated to more than 400 million dollars, but considerable indirect
damages should be added to the final sum.
page 22
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Refinery, with its own resources and means, with the employment of domestic contracting
companies, started reconstructing the damaged parts right away.
In the first phase of reconstruction, in less than three months, overhaul and reparation of the
damaged equipment on the major primary processing unit (AD-1) and on some of the units
in Block 5 were completed. In Handling Department and Power Plant, units and facilities
necessary for the operation of process units, acceptance of crude oil and dispatch of finished
products were made operational again. Derivative production was restarted as early as 26
September 1999.
The second phase, which implied a future modernization, was commenced right away.
Bitumen Production and Vacuum Distillation Units were reconstructed and commissioned. By
commissioning Boiler 1 in the Power Plant, Refinery repaired the unit that had been almost
completely destroyed. This resulted in the renewal of the Refinery's own generation of
steam.
The most complex and significant unit for a better crude oil yield in the Refinery, Fluid
Catalytic Cracking Unit (FCC), started operation on 1 September 2000.
In parallel with the reparation, reconstruction and modernization of many units also took
place. Some of the most important are as follows: replacement of the old control systems on
almost all units with the new ones that are used in EU countries, reconstruction of Vacuum
Distillation Unit in accordance with the design by Greek company Asprofos, for the purpose
of increasing the yield, improving the bitumen feed quality, more reliable operation and
easier unit management. FCC was modernized for the purpose of improving yield, and more
reliable and longer operation.
Refinery today
Pančevo Oil Refinery is significant organizational part of and the biggest oil processing
company in NIS-Petrol, which is the biggest branch of shareholding company - Petroleum
Industry of Serbia. That is a fuel-type refinery which produces fuels, paraffinic and aromatic
solvents, feed for Petrochemical Complex, bitumen and sulphur. Primary and secondary units
for crude oil processing were constructed in such a way as to enable the processing of
various types of crude. With the processing capacity of 4,8 million tons per year, it is the
biggest factory of this type in Serbia, meeting the domestic market demand for oil
derivatives, with the possibility of exporting 20% of its production.
Crude oil (domestic and imported) is delivered to the Refinery by oil pipeline and river barge,
and the derivatives are dispatched by product pipeline, tank truck, railway and barge.
Refinery is situated at exceptionally favourable location - 14 kilometers from Belgrade, the
biggest consumer center in Serbia. It has its own Jetty on the Danube and pipeline that
connects them, also truck loading facilities and railway station with the facilities for
derivative dispatch and crude oil acceptance.
Top priority for all employees in Pančevo Oil Refinery is crude oil processing and production
of sufficient quantities of oil derivatives according to the European standards for domestic
requirements and creation of conditions for export, at the same time meeting all
environmental standards. That is achieved by constant upgrading of operation process
quality, better crude oil yield, power optimization and reduction in production costs, and for
that purpose, it has been planned to implement development projects defined in cooperation
with the foreign engineering companies (JGC, SHELL, ABB).
Particular attention is paid to environmental protection. During units reconstruction from
1999 to 2001, by investing into modernization and overhaul of the existing units,
reconstruction and construction of storage tanks and facilities, as well as the preparation of
basic designs for the future modernization, environmental component was integrated into the
entire production cycle: starting from crude oil storing, derivative production, to derivative
dispatch into transport means. Implementation of the planned development technological
projects is of common interest both for industrial zone and for Pančevo town as a whole.
These projects aim at reaching European standards by restricting and controlling detrimental
substance emission into the air, soil and water.
2.1.3.4 Safety of the plant
Management system
Pancevo Refinery has established the quality management system in accordance with ISO
9001:2000 standard, for all its operations. The system is certified by Lloyd’s Registrar
page 23
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Quality Assurance. Internal audits and management reviews are conducted once in a year in
accordance with written procedures.
Top management has establish policy of improving the quality of products, services and
environmental protection, which is achieved in the following manner:
• by permanent development of the company, by introducing state-of-the-art
technologies and processes in oil processing areas
• by delivery of products and services to meet buyers' needs with minimum costs
• by delivery of products and services in accordance with the requirements defined by
standards and regulations for petroleum industry
• by consistent implementation and continuous improvement of designed quality
management system, in all operations, by employees
• by continuous and planned specialized education of all employees and in accordance
with the requirements of modern business activities
• by cooperation with scientific research and project organizations, regarding product
and process development projects
• by motivation of employees and improvement of working conditions
• by establishing and maintaining the documented environmental management system,
in accordance with the requirements of ISO 14000:2004 standard.
Environmental Protection Policy consists of the following:
Pančevo Oil Refinery, being the biggest oil processing company in the Republic of
Serbia, for the purpose of its long-term successful business activities and assurance
of sustainable development, within its business policy, places considerable emphasis
on systematic approach to the environmental protection improvement activities.
For that purpose Pančevo Oil Refinery performs the following:
• introduces the environmental protection policy, programs and practice into every
activity, as an important element of managing all business operations.
• Identifies all environmental aspects and puts under control the important ones.
• Operates in accordance with the environmental protection laws and regulations.
• Pursues permanent improvement in environmental protection.
• Systematically reduces detrimental substance emission into the surroundings (air,
water, soil), saves resources and energy, minimizes use of detrimental substances
and the quantity of dangerous waste.
• Minimizes the possibility of detrimental effect on the environment by preventive
measures and the measures to be taken in case of an accident.
• Increases employees’ awareness of environmental protection significance, by
constant education and professional training, as well as by providing information in a
timely and proper manner.
• Develops cooperation with the institutions of local and communal self-government,
responsible for environmental protection, as well as with all other interested parties.
• Procures products not having or having minimum effect on the environment, and
induces suppliers to actively apply all the environmental protection measures,
including application of ISO 14001 in their business activities.
Safety Management System is a part of quality and environment management system and
includes some principles to identify and to evaluate possible hazards and principles to
identify and to realize technical organizational and management activities for the mitigation
and consequence reduction of accidents. Responsible organizational unit for Health, Safety
and Environment issues is Risk Management division.
Critical situations, preparation for emergency situations
The Pancevo Refinery has for many years a fire protection plan, made according to the
requirements of fire protection regulation in Serbia. Existing plan prescribes in details the
behavior of workers in the event of fire and have been made for the following cases:
• protection plan for unplanned production stop
• fire protection plan
o technological preventive plan
o fire distinguishing tactical plan
In 2009 Pancevo Refinery has developed a risk assessment of chemical accidents separately
for all relevant production and technological units. Based on this, protection plan in the case
page 24
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
of chemical accidents was developed on the level of production units as well as for the whole
plant. Elements of the plan are:
• Forces and assets of the Plan
• Scheme for response to accident
• Training and education program
• Control program
• Other instructions and information.
Total number of employees in the refinery is 1625. Qualification structure of employees is
given in Table 7 and number of employees in different section in
Table 8. Maximum concentration of employees in first shift during working days is given in
Table 9.
General Plan of Refinery Pancevo is given in Annex 1, map in scale of 1:2000, within which
are listed and identified the process unit and storage. The specific plans for individual
facilities are included in the vChapter V of the report.
Table 7: Qualification structure of employees in Pancevo Refinery
Number of
Qualification
employees
PhD 1
MSc 1
BSc 202
College 68
Highly skilled 201
High-school 953
Skilled 137
Elementary school 3
Semiskilled 3
Unskilled 56
page 25
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Total: 1625
Number of
Location
employees
Headquarter 441
Block V building 69
FCC building 82
S-3600 building 17
S-0250 building 18
Laboratory 126
HSE building 35
page 26
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The pressure vessels will have an inside inspection every three years and every six years the
pressure will be tested. This inspection is based on a national law which is connected with EU
regulations.
It is not an obligation in Serbia but regarding the topic explosion protection the Risk
Management division has started to consider the requirements of the ATEX Directives. An
explosion protection document has been developed which has been submitted to the
Ministry. The exchange of the equipment in regard to the requirements of the ATEX Directive
will be done step by step. Furthermore the German TA Luft will be implemented.
The inspection is in the responsibility of the production and maintaining department of RNP
and planning of safety aspects is in the responsibility of the Risk Management department.
No public utilities are affected by accident consequences as the line connections are
underground.
Lightning is high frequency event in summer and has lead to two accidents in the past. About
10 years ago a safety valve has been fired by lightning and last year a burning flare has
been addressed by lightning.
The normal protection measure is earthing. The maintenance period for the control of the
protection measure is once a year as required by law. The measurement of the resistance
and continuity will be done. All safety valves are protected by steam extinguishers. This task
is from 2007. in the responsibility of Risk Management division and will be done by an
external party.
Internal communication will be done by phone, radio and mobile phone.
Macro location
Novi Sad Refinery is situated about 1 km away from the town Novi Sad and about 80 km
from Belgrade, on the left bank of the Danube River.
Novi Sad is located in the northern Serbian province of Vojvodina (Figure 13 and Figure 14),
with land area of 699 km², while on the city's official site, land area is 702 km²; and the
urban area is 129.7 km². The city lies on the river Danube and one small section of the
Danube-Tisa-Danube Chanel.
page 27
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 28
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
not active, except in the Ribnjak neighborhood (between Sremska Kamenica and
Petrovaradin.
Refinery Novi Sad (NIS-RNS) is located in the economic zone of the city of Novi Sad - North
4. This zone is foreseen for building large commercial facilities and covers area of 1735
hectares. Refinery itself covers about 256 hectares of industrial space. The site is in north-
eastern part of the city of Novi Sad, south the site flows channel Danube-Tisa-Danube, while
on the north side is the street Put Šajkaškog odreda, the road for settlement Shanghai
(distance about 2 km). On the west side of the refinery are main storage are of NIS
NAFTAGAS-TRAFFIC with installations for filling oil and petroleum products.
On the south side are the production plants and warehouses, factories for the production of
artificial fertilizers "AGROHEM.
On the north-west side is located filling stations with storage tanks for liquid petroleum gas.
Distance from the bottling and storage space is about 250 meters. Along the east side lie the
pipeline installation.
This site has convenient traffic conditions. On the north side of the refinery site is a highway
E-7 (Belgrade - Novi Sad - Subotica) while on the west side is the main road M-7 (Backa
Palanka - Novi Sad - Zrenjanin). On the south side are lying waterways, the river Danube
and Novi Sad channel Savino Selo.
Micro location
Novi Sad Refinery is a complex of process and auxiliary facilities for processing crude oil,
storage facilities, transportation and manipulation utilities, research and laboratory space
and other supporting facilities. In the north part of the refinery there are pipeline
installations.
Refinery is fenced and secured, and the only access is possible from the street Put Šajkaškog
odreda where entrance gates are locating enabling access to the refinery from the road.
Inside the area of Novi Sad Refinery are located 13 production, manipulation and storage
units, including necessary infrastructure. General plan of the refinery is given on Annex and
list of units in Table 10. There are two main production lines in RNS:
page 29
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 30
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Novi Sad has a moderate continental climate, with four seasons. Autumn is longer than
spring, with long sunny and warm periods. Winter is not so severe, with an average of 22
days of sub-zero temperature. January is the coldest month, with an average temperature of
-1.9 °C. Spring is usually short and rainy, while summer arrives abruptly. The coldest
temperature ever recorded in Novi Sad was -30.7°C (-19.3°F) on January 24, 1963; and the
hottest temperature ever recorded was 41.5°C (110.7°F) on July 6, 1950. Average
temperatures are given inTable 11.
The southeast-east wind Košava, which blows from the Carpathians and brings clear and dry
weather, is characteristic of the local climate. It mostly blows in autumn and winter, in 2-3
days intervals. The average speed of Košava is 25-43 km per hour but certain strokes can
reach up to 130 km/h. In winter time, followed by a snow storm, it can cause snowdrifts.
Also it can cause temperatures to drop to around -30°C.
Table 11: Average temperatures (Source: Republic Hydrometeorology Service of Serbia)
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year
Avg. 2.5 5.7 11.5 17.2 22.5 25.2 27.2 27.2 23.7 18 10.3 4.5 16.3
high °C (36) (46) (57) (67) (76) (81) (85) (85) (77) (68) (54) (44) (65)
(°F)
Avg low -4.4 -2.3 1.2 5.8 10.6 13.6 14.7 14.2 11.2 6.3 2.2 -1.9 5.9
°C (°F) (29) (32) (38) (46) (55) (60) (62) (62) (56) (47) (40) (33) (47)
Rainfall 38 35 41 47 57 82 61 55 36 35 46 44 577
mm (1.5) (1.4) (1.6) (1.8) (2.2) (3.2) (2.4) (2.2) (1.4) (1.4) (1.8) (1.7) (22.7
(in.) )
Winds
The presence of winds opposites directions is characteristic of this region (Figure 14). Most
dominant winds are from two different directions; south-east (18.2%) and north-west
direction (17%). The third kind of wind is western and the least one which can be seen on
this area is Sothern wind. These winds are characterizing the whole Pannonia Basin.
The dominant south-east wind KOSAVA is blowing from December to March, in winter part of
the year. North-west wind is dominating from June to September, in summer part of the
year. The calm weather without the wind is mostly presented in June, July, August and
September. Strength of the wind is between 0,81 – 1,31 m/s.
page 31
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
J F M A M J J A S O N D Ann.
Novi Sad 7.1 7.8 6.2 6.1 5.6 5.1 4.4 3.9 4.2 4.7 7.1 7.7 5.7
page 32
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
On the loess terrace the level of the underground water rises from October to April.
Oscillations are within 1 to 1.5 m, while the deepness is mostly more then 4 m.
Freatske water are high polluted. Not treated waste water go to the open sewage line, cricks
from the mountain Fruska Gora and drain to the underground, to the not deep water layers
which are use for individual or public water supply. All human facilities in Backa and partly
Novi Sad are drained using open channels.
Areas of seismic activities
In the region seismic activities are possible with intensity 6 - 8 MCS. On location of Novi Sad
Refinery possible earthquake with intensity of 7 MCS.
Geological and hydrological characteristiques
Environment of Novi Sad is characterized by presence of two different morphological units:
Fruska Gora mountain and the Pannonian basin. Their genesis is related to strong orogenic
movements with the participation of deflection. Fruska Gora is an area of erosion, and the
Pannonian plain area reservoirs (lake sediments, les, sand) and erosion (alluvial plain).
Novi Sad Refinery lies on the oldest alluvial carbonate coat that is sandy clay and to some
extent consolidated. In the area of Novi Sad shallow groundwater and deeper ones, up to
300m are of the great importance. The water level in alluvial area is directly related to the
water level of the Danube. High groundwater show significant amplitude, in contrast to the
deep groundwater, which show greater stability.
Wastewater is directly discharged in an open canal network, creeks of Fruska Gora and
further drained in underground, in the shallow water-bearing layers, which are used for
individual and public water supply.
The entire area is Refinery fill-reflux sand thickness from 1:50-2.00m.
Flora, fauna and protected natural and cultural properties
Natural advantages for plant species in the area of Novi Sad and surrounding are not the
same. They are primarily caused by differences in relief, the differences in the amount of
underground water, in geological and pedological soil composition, anthropogenic influence
and other factors.
Biographical characteristics of the area corresponding to the rim of the Pannonia regions.
Observing the physical and geographical distribution of fauna, flora observed the following
characteristic areas:
• region of Bačka with complex agro eco systems
Population
Novi Sad iis Serbia's second-largest city, after Belgrade. In its most recent official census
from 2002, the city had an urban population of 216,583, while its municipal population was
299,294. But according to the data from April 2010, the city had an urban population of
286,157, while its municipal population was 372,999. Shanghai, nearby village, occupies an
area of 13 ha, and lives about 1,600 inhabitants.
2.1.4.3 Description of the plant
Activities
The main activities in Novi Sad refinery are:
page 33
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Capacity Constructe
Unit License
(t/year) d
Atmospheric Distillation AT-500 Pritchard 500.000 1968
Atmospheric distillation I Naphtha Stabilization
USSR 2.000.000 1985
U-2100
Vacuum Distillation U-2200 USSR 1.200.000 1985
Naphtha Hydro treating U-2300 UOP (TPL) 560.000 1985
Platforming U-2400 UOP (TPL) 430.000 1985
Gas treatment (LPG) U-2500 UOP (TPL) 60.000 1985
HDS Unibon (Kerosine /VGO) U-2600 UOP (TPL) 240.000 1985
Atmospheric Distillation U-100 Badger 500.000 1974
Vacuum Distillation U-200 Badger 550.000 1974
Bitumen Badger 200.000 1974
Hydro finishing U-400 Texaco 240.000 1981
Acid Treatment U-500 Texaco 89.000 1985
Lube Oil Blending, Filling and Packaging Texaco 56.000 1981
page 34
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
First phase of Lube Oil Plant I program in 1973 involved construction of the following
production units:
• Atmospheric Distillation Unit (500.000 t/y)
• Vacuum Distillation Unit (550.000 t/y)
• Bitumen Production Unit (160.000 t/y).
In 1975 realization of the most elaborate RNS program, called Fuel II Plant was started
parallel with the commencement of Yugoslav pipeline construction, the founder of which,
amongst others, was RNS.
Fuel II Plant Process Units involved construction of following production units:
1. Primary Process Units with
• Atmospheric Distillation unit, capacity 2.000.000 t/y
• Gasoline Stabilization Unit, capacity 580.000 t/y
• Vacuum Distillation Unit, capacity 1.200.000 t/y
2. Secondary Process Units with
• Hydro Treating Unit, capacity 500.000 t/y
• Platforming Unit, capacity 430.000 t/y
• HDC Unibon, capacity 230.000 t/y
• LPG Processing Unit, capacity 66.000 t/y
In 1976 Atmospheric Distillation Unit, Vacuum Distillation Unit and Bitumen Production Unit
(Lube Oil Plant I program) were commissioned.
Second phase of Lube Oil Plant II program involved construction of the following production
units:
• Hydro Finishing Unit (240.000 t/y)
• Acid Treatment Unit (80.000 t/y)
• Lube Oil Blending Unit (56.000 t/y).
1979 Fuel II Plant process units construction was started and 1980 Lube Oil Blending Plant
was constructed and started up. 1981 Start-up of Hydrofinishing Unit and other
accompanying units. 1984 Fuel II Plant program Primary Process Units were started up with
the delivery of the first quantity of imported crude oil via Yugoslav pipeline 1986 Fuel II Plant
program Secondary Process Units were started up.
2.1.4.4 Safety of the plant
Measures to prevent or mitigate the hazards
Preventive measures
There is no major maintenance period as the different establishment is only running between
20% and 50% or their normal capacity (missing feed).
The pressure vessels will have an inside inspection every three years and every six years the
pressure will be tested. This inspection is based on a national law which is connected with EU
regulations.
Safety valves and gas installations have an inspection period of once per year. Gas
installations will also be inspected if the duration of the shut down period is more than one
month.
Preventive constructional measures
No public utilities are affected by accident consequences as the line connections are
underground.
Preventive technical measures
Lightning is high frequency event in summer and has lead to some initial fires (each time fire
on the top of a column). This part is also protected by earthing. In general the normal
protection measure is earthing. The maintenance period for the control of the protection
measure earthing is once a year as required by law. The measurement of the resistance and
continuity will be done.
Additional measures
Internal communication will be done by radio, phone and mobile phone.
Measures to reduce the consequences of an accident
page 35
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The whole staff has a yearly fire extinguishing training and exercise. Evacuation training has
been only done for parts of the establishment. Rescue and emergency plans has been
establishment now. Sub contractors have to pass training (fire protection and workplace
safety) and to do an exam.
There is only one drainage system for fire extinguishing water and normal water. The fire
water retention (shown in Error! Reference source not found.) will be done by hydrants
connected to basins.
Fire extinguishing by foam can be down by fire brigade.
An automatic gas detection system does not exist. A fire detection will be done by optical
control. An automatic fire extinguishing system does not exist. A system for automatic
cooling of the tanks.
Fires will be detected by optical control. Fire sensors do not exist. A new sensor system for
gas detection and continuous measurement has been installed last year.
An alarm plan in the establishment exist. In the case of an accident or a fire the workers will
be informed by radio to leave the establishment.
Operating Fire fighting unit within the Fire protection Service is located on two locations on
refinery territory. Staffing of the unit, 82 persons, is designed by the Plan of Fire protection
of OD RNS, and approved by MUP of Serbia. Actually there are 69 persons working in this
unit, as shown in Table 1.
Table 15: Number of personnel in Firefighting unit of Novi Sad refinery
Position taken
Working position Planned Workers of Workers of Total
the refinery subcontractors number
Manager of operating
1 - - -
unit of fire brigade
Chief of operating unit
1 - - -
of fire brigade
Shift leader of
operating unit of fire 10 9 - 9
brigade
Fireman, department
16 13 - 13
leader
Driver, fireman 16 10 10 20
Fireman, operator 25 7 9 16
UKUPNO 69 39 19 58
page 36
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Beside the above mentioned mobile equipment, operating firefighting brigade has the
following multipurpose equipment:
- fire extinguishers ( type S-6A, S-9A, S-25A, S-50A, CO2-5, CO2-10 )
- suction and discharge pipes (Ø52 mm, Ø75 mm, Ø110 mm )
- water/foam nozzles
- manifolds / collectors
- mixers for foam
- vatrogasne armature
- insulation facilities
- personal protection equipment (suits for fire approaching, suits for entering
into fire, fire helmets
Systems for storage area extinguishing and cooling
The refinery is provided with ring hydrant net with over 500 hydrants, as well as hydrant
facility for continual maintenance of water pressure in hydrant net.
Firefighting system is separated in 5 stations with suitable capacity of firefighting substances
and utilities (motor and electrical pumps, regulating equipment…). The reason for this
separation is the size of refinery. There are following stations:
• Stara vatrogasnica
• MIX-stanica
• Mešaona Blending benzina
• Terminal JP „Transnafta“
• Mešaona Goriva II
Table 17 shows means for fire extinguishing and capacities.
Table 17: Available fire extinguishing means
Almost all tanks are provided with stabile firefighting and cooling systems.
Fire protection of Lube oil I and Lube oil II units
These units are provided with ring hydrant net, stable and mobile monitors, as well as with
numerous fire fighting devices of different types. A fire on process units segments is
extinguished from station „MIX-stanica“, with additional water pressure provision from
station „Stara vatrogasnica“ (and if necessary from Mešaone - Goriva II). Station „MIX-
stanica“ is equipped with two tanks with extracte for fire extinguish, each with capacity of 16
m3, pumps and devices for extracted mixture, as well as with the piping for emulsion
distribution for fire extinguish on of process unit segments and related storage area.
The whole refinery is connected with Fire alarms system, with 24 hours service on both
locations.
2.1.4.5 Description of processes
Main units in Lube oil part of Novi Sad refinery are:
page 37
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
For the analysis within the project, units U 100 and U 200 are considered.
Product Flammable
Crude gasoline Cancerous Water organism 2.200
liquid
Flammable
Kerosene Cancerous Water organism 16.000
liquid
Flammable
Gas oil Cancerous Water organism 41.200
liquid
Flammable
Atmospheric residue Cancerous Water organism 140.600
liquid
By-product -
page 38
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Chemicals No data
Sodium hydroxide Irritant corrosive
available
Irritant,
Risky for water
Deemulgator Potential stable
organism
cancerous
Irritant,
Anticorrosion Harmful for
Dangerous to corrosive
inhibitor water organism
drink
Ammonium Very toxic for
Toxic, Irritant Toxic
hydroxide water organism
From the list of specified materials following dangerous materials are present: H2S in waste
gas, SO2 – in flue gas
page 39
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Flammable
Vacuum gas oil Cancerous Water organism 12.000
liquid
Flammable
VD1 Cancerous Water organism 13.000
liquid
Flammable
VD2 Cancerous Water organism 20.000
liquid
Flammable
Product VD3 Cancerous Water organism 20.000
liquid
Flammable
VD4 Cancerous Water organism 20.000
liquid
Flammable
Paraffin’s slop Cancerous Water organism 15.000
liquid
Flammable
Vacuum residue Cancerous Water organism 60.000
liquid
By-product
Irritant,
Anticorrosion Harmful for
dangerous to corrosive
Chemical inhibitor water organism
drink
Neutralizer
From the list of specified materials following dangerous materials are present H2S in waste
gas and SO2 given in U 100 while they have the common chimney.
page 40
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 41
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Legend:
page 42
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
JAN FEB MAR APR MAJ JUN JUL AVG SEP OKT NOV DEC
Tsr(°С) 0.3 2.0 6.5 11.7 17.5 20.8 22.3 22.3 16.8 11.9 6.3 0.8
Tx(°С) 3.3 6.6 12.2 17.3 23.4 26.7 28.3 28.9 23.1 17.7 10.3 3.8
Tn(°С) -2.5 -2.0 1.7 6.4 11.4 14.7 16.0 16.1 11.6 7.3 3.0 -1.9
ApsTx(°С) 17.7 20.2 27.7 30.1 33.5 38.0 38.7 38.7 34.2 30.0 23.6 14.9
ApsTn(°С) -24.6 -17.9 -12.6 -6.7 -0.2 6.0 6.5 7.2 2.2 -8.6 -10.5 -23.1
b.d.mraz 20.9 17.6 11.2 2.2 0.1 0.0 0.0 0.0 0.0 2.7 8.2 19.1
b.d.trops. 0.0 0.0 0.0 0.1 1.9 7.4 11.8 12.6 1.8 0.1 0.0 0.0
U(%) 84 76 67 66 63 65 65 64 71 75 80 85
SS(h) 65.9 120.6 164.3 187.4 251.4 285.4 287.3 284.4 204.0 158.1 89.1 58.6
b.d.vedrih 2.9 5.9 5.4 4.2 5.6 6.5 9.1 11.9 6.0 6.2 4.1 2.8
b.d.tmurnih 14.7 8.4 7.6 8.9 6.4 4.3 4.1 3.8 5.6 6.9 12.0 16.0
RR(mm) 34.3 24.1 26.1 45.9 51.0 81.9 66.5 39.3 62.2 51.5 52.8 50.4
maxRR(mm) 30.7 20.4 22.9 30.4 52.5 62.5 72.3 49.1 60.0 45.9 47.5 44.2
rr>0.1(mm) 10.9 8.7 8.8 11.4 11.4 11.7 10.2 7.7 11.0 8.9 10.8 11.8
rr>10(mm) 1.1 0.3 0.7 1.3 1.0 2.5 1.7 1.2 2.0 1.1 1.8 1.3
b.d.sneg 5.0 5.3 2.1 0.4 0.0 0.0 0.0 0.0 0.0 0.1 1.9 5.1
b.d.s.p. 11.3 7.6 1.5 0.1 0.0 0.0 0.0 0.0 0.0 0.0 2.9 8.4
b.d.grad 0.0 0.1 0.0 0.1 0.1 0.4 0.1 0.1 0.1 0.0 0.1 0.0
Table 21: Statistical data on seasons weather parameters for Zrenjanin region
page 43
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Legend:
Tsr (°С) air average temperature (°С)
Tx (°С) average max. air temperature (°С)
Tn (°С) average minimal air temperature (°С)
ApsTx (°С) absolute max air temperature (°С)
ApsTn (°С) absolute minimal air temperature (°С)
b.d.mraz number of ice days Tn< 0°C
b.d.trops. number of tropical days Tx≥30°C
U (%) relative air humidity u %
SS (h) sunshine in hours
b.d. vedrih number of clear days
b.d. tmurnih number of sunshade days
RR (mm) precipitation (mm)
maxRR(mm) daily max. precipitation (mm)
rr>0.1(mm) number of days with precipitation ≥ 0.1 mm
rr>10(mm) number of days with precipitation ≥10.0 mm
b.d.sneg number of days with snow
b.d.s.p. number of days with show ?
b.d.grad broj dana sa gradom
Fog
The average number of fogy days in a year in Zrenjanin region is 22.4 days or 6.1%. Fog
appears in every month but the most often it appears in December, average 5.6 days
(probability is 18%). Ice days, days with average daily temperature is under 0 o C, most
often appear in January. The average number of icy days in January is 14. t
page 44
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The average yearly air humidity value in the Zrenjanin region is 78.5%; the lowest monthly
value of daily relative air humidity in July is 69% and the highest in December 85%.
Table 22: Temperature distribution in the region - July
Air pressure
In Zrenjanin and wider surroundings the air pressure decreases in the period January – April,
and increases. The average value of the air pressure in a year is about 1006 mbar, the
highest is in January, 1010 mbar and lowest in April, 1003 mbar. In October this value is
about 1008 mbar (81 m of see-height).
Precipitation
Average frequency of days with strong precipitation (9.5 mm) is 16,4 days per year, e.g.
13,1% of total number of days with precipitation, what is very law value.
The most of those days appear in May, average 2.2 days, with probability of 7%, and the
lowest number of those days is in October. The highest value was recorded in July. In
summers it happens that one day precipitation is higher then in winter period or in transition
seasons.
Wind
Frequency (%o) and velocity of wind (m/s) are given in Table 24. Weather with no wind
appears mostly in July (91%o), and the lowest freqancy is in February (63%o). The Figure
18 shows “wind rose” for Zrenjanin and this applies for Elemir as well.
Table 24: Frequency and velocity of wind
N NE E SE S SW W NW
page 45
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Activities
Elemir Refinery (Figure 20) is a gas-type refinery which produces natural gas, LPG and
gasoline. It is designed by J.F. PRICHAR COMPANY, 4625 ROANOKE PARKWAU, CANSAS
CITY, MISSOURI, USA and delivered by EDWIN COMPANY (OLDBURY) LIMITED BIRMINGHAM
ENGLAND Desing-Engineering Job No IN-1776.
The refinery was commissioned in 1963. It was the first unit of the kind built in the country,
thus the design standards were the standard of the country that has designed the unit. The
delivery has included: Know-how, license, patents, base engineering and other services. In
the year 1988 reconstruction took place (equipment replacement) with no changes in
technological process. The major outside supplies for RGE and the connected safety
problems are shown in Table 25.
page 46
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Type of
Safety problem
supply
There are no safety problems if no electricity will be
delivered. Within less than 5 minutes the internal
Electricity
generator system will take over the supply of
electricity.
Fuel gas No safety problems as the production will stop if no
gas will be delivered
Nitrogen
It will only be used for maintenance
Number of employees
Qualification
RGE Naftagas
PhD /
M.Sc. /
B.Sc. 10 1
College 3
Highly skilled
High-school 43
Skilled 14 45
Elementary school /
Semiskilled /
Unskilled 7
Total 77 46
Responsible for safety aspects in the whole NIS a.d. is the central HSE department of NIS
a.d. and NIS Naftagas Safety department (Department for systematic support - EMS, Safety,
QMS, IMS) and this department is delegating one person to the RGE for HSE duties.
Nevertheless safety is one of the major points of the philosophy of the company.
Management systems are certified and scope of certification is shown in Table 27. Policy
established by top management withing integrated management system is presented in
Annex 12.
Table 27: List of NIS-Naftagas certificates and scope of certification
page 47
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 48
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Type Description
3
1. Stable hydrant system 1100 m
2. Stable system for foam 2 m3 of foam
3. Portable systems with S-9 30
4. Portable systems with S-50, 250 10
5. Portable systems with S250 5
6. Portable systems with CO2 10
7. Water guns with foam 3
page 49
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
6)
35. Flamable gases 10
7)
36. Slef flamable 50
8)
37. Solid flamable 50
38. Materije koje u dodiru sa vazduhom i vodom 50
9)
39. Verry flamable liquids 1000
10)
40. Flamable liquids 5000
page 50
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Figure 21: Framework of RIMAP procedure within the overall management system
page 51
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 52
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 53
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
consequence of each type of failure is calculated and combined with the probability for that
failure; to calculate the overall risk associated with each piece of equipment.
The basic method of risk analysis as presented in API RBI is not changed for the financial risk
analysis. The risk is still calculated as the consequence of failure (now expressed as cost in
dollars) times the probability of failure.
For a rigorous and flexible analysis, the consequences (costs) are evaluated at the hole size
level. Risk is also evaluated at the release hole size level by using the probability of failure
associated with each release hole size. The total risk is calculated as the sum of the risks of
each release hole size.
page 54
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The overall ranking is then done according to the RIMAP risk matrix, shown in the Figure 23.
Alternatively, the risk can be represented in the NIS risk matrix, as shown in Figure 24.
page 55
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Tech Software iRIS-Petrol has been used for the analysis. It accounts for both internal
thinning and external corrosion rates. The remaining life is calculated as follows:
1. First, determine the Minimum Wall Thickness (tmin) to be used.
There are 3 options available for specifying this tmin:
• using the Design Corrosion Allowance taken from design documents (which is a
default option)
• using User-defined Minimum Thickness taken from local codes or other
considerations such as structural stability.
• using Calculated Minimum Thickness which is based on ASME code formula:
in which,
Whereby
State i = 1, is when the thinning rate is as given by the user
State i = 2, is when the thinning rate is 2 times the given rate
State i = 3, is when the thinning rate is 4 times the given rate
Pi is the probability of state i.
(Nominal Remaining Life)i is the remaining life calculated for state i.
A more complex equation is used when external thinning is included or where liner is
involved.
page 56
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Since an inspection needs to be tailored to fit the particular type of damage expected at a
particular piece of equipment, the key considerations are:
• High total Likelihood Factors
Inspection
Effectiveness Intrusive Inspection Non-intrusive Inspection
Category
50-100% examination of the
50-100% ultrasonic scanning
A surface (partial) internals
coverage (automated or manual)
Highly Effective removed) and accompanied by
or profile radiography
thickness measurements
Normally 20% ultrasonic scanning
Normally 20% examination (no
coverage (automated or manual),
B internals removed), and spot
or profile radiography, or external
Usually Effective external ultrasonic thickness
spot thickness (statistically
measurements
validated)
2-3% examination, spot external
C Visual examination without ultrasonic thickness
Fairly Effective thickness measurements measurements, and little or no
internal visual examination
Several thickness measurements,
D External spot thickness readings
and a documented inspection
Poorly Effective only
planning system
Several thickness measurements
E taken only externally, and a
No inspection
Ineffective poorly documented inspection
planning system
Inspection
Effectiveness Intrusive Inspection Non-intrusive Inspection
Category
50-100% coverage using
100% visual examination (with
automated ultrasonic scanning, or
A removal of internal packing,
profile radiography in areas
Highly Effective trays, etc.) and thickness
specified by a corrosion engineer
measurements
or other knowledgeable specialist
20% coverage using automated
100% visual examination (with ultrasonic scanning, or 50%
B partial removal of the internals) manual ultrasonic scanning, or
Usually Effective including manways, nozzles, etc. 50% profile radiography in areas
and thickness measurements specified by a corrosion engineer
or other knowledgeable specialist
page 57
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Inspection
Effectiveness Intrusive Inspection Non-intrusive Inspection
Category
Nominally 20% coverage using
automated or manual ultrasonic
Nominally 20% visual scanning, or profile radiography,
C
examination and spot ultrasonic and spot thickness measurements
Fairly Effective
thickness measurements at areas specified by a corrosion
engineer or other knowledgeable
specialist
Spot ultrasonic thickness
measurements or profile
D
No inspection radiography without areas being
Poorly Effective
specified by a corrosion engineer
or other knowledgeable specialist
Spot ultrasonic thickness
measurements without areas
E
No inspection being specified by a corrosion
Ineffective
engineer or other knowledgeable
specialist
Table 33: CUI for Carbon and Low Alloy Steels Inspection Categories
Inspection
Insulation Insulation Not
Effectiveness
Removed Removed
Category
Remove >95% of the insulation
AND For the total surface area:
A
Highly Effective visual inspection of the exposed >95% profile or real-time
surface area with follow-up by radiography
UT, RT or pit gauge is required
For the total surface area:
> 95% external visual
inspection prior to removal
For the total surface area:
of insulation
> 95% external visual inspection
AND
B AND
remove >60% of total surface
Usually Effective area of insulation including follow-up with profile or real time
suspect areas radiography of >60% of total
surface area of insulation
AND
including suspect areas
visual inspection of the exposed
surface area with follow-up by
UT, RT or pit gauge as required
For the total surface area:
> 95% external visual
inspection prior to removal
For the total surface area:
of insulation
>95% external visual inspection
AND
C AND
remove >30% of total surface
Fairly Effective area of insulation including follow-up with profile or real time
suspect areas radiography of >30% of total
surface area of insulation
AND
including suspect areas
visual inspection of the exposed
surface area with follow-up by
UT, RT or pit gauge as required
D >95% external visual inspection For the total surface area:
page 58
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Inspection
Insulation Insulation Not
Effectiveness
Removed Removed
Category
Poorly Effective prior to removal of >95% external visual inspection
insulation AND
AND follow-up with profile or real time
remove >5% of total surface radiography of >5% of total
area of insulation including surface area of insulation
suspect areas including suspect areas
AND
visual inspection of the exposed
surface area with follow-up by
UT, RT or pit gauge as required
<5% insulation removal and
inspection No inspection or ineffective
E
OR inspection technique or <95%
Ineffective
no inspection or ineffective visual inspection
inspection technique
Inspection
Intrusive Non-intrusive
Effectiveness
Inspection Inspection
Category
For the total surface area:
No inspection techniques yet
A 95% dye penetrant or eddy available meet requirements of
Highly Effective current test with UT follow-up of "A".
relevant indications.
For the total surface area:
For the total surface area: > 95% automated or manual
B 60% dye penetrant or eddy ultrasonic scanning
Usually Effective current testing with UT follow-up OR
of all relevant indications. AE testing with 100% follow-up of
relevant indications.
For the total surface area:
> 30% dye penetrant or eddy For the total surface area:
C
Fairly Effective current testing with UT >67% automated or manual
follow-up of all relevant ultrasonic scanning
indications.
For the total surface area: For the total surface area:
>5% dye penetrant or eddy >30% automated or manual
D current testing with UT ultrasonic scanning
Poorly Effective follow-up of all relevant OR
indications
>60% radiographic testing
Less than “D” effectiveness or Less than “D” effectiveness or no
E
no inspection or ineffective inspection or ineffective inspection
Ineffective
inspection technique used technique used
Inspection
Effectiveness Inspection
Category
A Visual inspection of >95% of the exposed surface area with
Highly Effective follow-up by UT, RT or pit gauge as required
page 59
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Table 36: Guidelines for Assigning Inspection Effectiveness for Furnace Tube
Inspection
Effectiveness Inspection
Category
Visual inspection, UT thickness measurements of all tubes and
A
strapping at UT measurement locations. FMR at various
Highly Effective
locations
B
Visual inspection, UT thickness measurements of all tubes
Usually Effective
C Visual inspection with UT thickness measurements of 75% of the
Fairly Effective tubes
D
Visual inspection with spot UT measurements
Poorly Effective
E
Visual
Ineffective
page 60
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
what should be done. It is useful if a simple risk estimate can be provided for each problem
in order to provide a basis for deciding on the best allocation of resources to address key
problems. Consequently HAZOP-PC provides a means for qualitatively estimating the
likelihood and severity of each problem identified in order to develop a risk estimate.
HAZOP studies can be performed for new plants where the design is nearly firm and
documented, or for existing plants where a significant redesign is planned, or where no
previous study has been performed. HAZOP studies can be conducted not just for processes
but also for storage, transportation, and other systems.
While the HAZOP technique is the most comprehensive hazard analysis method of those
available, it cannot provide complete assurance that all hazards have been identified.
HAZOP Team
HAZOP team members need to be knowledgeable of the process and its operation, at least
some of the team should come from the operating facility. A typical team may consist of the
following members:
• Team Leader
• Process Engineer
• Operations Supervisor
• Safety Engineer
• Maintenance/Inspection Supervisor
• Facilities/Mechanical Engineer
HAZOP Process
Typical HAZOP process is illustrated on the Figure 25.
page 61
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Item
Section heading Summary Comments
No.
Summary of findings and
Executive
1 intended methods of control of
summary
accidents and hazards
Must cover the plant features,
process and layout, and if
Description of plant, special
Introduction and nearby to populated areas
2 features and any limits to the
overview must describe issues in local
scope of the Seveso assessment.
communities that may impact
hazard management.
Methodology – the
Outline of the approach taken by
hazards and This section describes the
the assessment team to
3 effects assessment methodology
illustrate a rigorous approach
management undertaken.
and use of appropriate data.
process
A listing of the hazards that
apply to the plant under
assessment.
In addition to the identification A key first step to describe
Hazard of the major accident hazards, what accidents and hazards
4
identification study the safety-critical elements and apply to the plant being
performance standards (i.e. the assessed.
manner in which the “safety
critical” elements perform in the
context of the major hazard).
page 62
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Item
Section heading Summary Comments
No.
Many HAZID exercises are
A supporting list of typical
carried out using a
hazards to assist the
5 Hazard checklist “brainstorming” team review,
comprehensive review of
the checklist is a very useful
applicable hazards.
element to support this review.
A term used in the UK as a
short-hand description but the
A further description of the
step to identify the “safety
safety critical elements (those
Safety-critical critical elements” (SCEs) is a
6 items that help to protect the
elements key identification of the
plant and adjacent
valuable systems used to
communities).
prevent, detect, control or
mitigate the incidents.
A collation exercise of the
Setting of Formal statement of the performance measures
7 performance performance required for the required to be in place to
standards “safety systems” for this plant. enable the SCEs to do their job
effectively.
Usually making use of a generic
Qualitative risk risk matrix, a risk ranking table Assigning risk levels against
8
assessment of the identified risk associated each identified hazard.
with the plant.
Often based on corporate
A section stating the grouped
standards adopted by the plant
acceptance criteria, covering not
operators.
just safety issues but also,
May be already completed,
9 Risk tolerability ecological and amenity
otherwise will require a
consequences criteria plus
“search” of standards accepted
environmental performance and
by the plant operator and
manageability criteria.
collating values.
The means by which the plant
A section describing the manner
operators demonstrate to their
in which the plant’s
regulators and corporate
Demonstration of management intend to manage
management that the hazards
10 major hazards the identified major hazards and
foreseen on the plant will be
management identifying a range of HSE
able to be controlled in some
critical tasks, (in order to
manner by the HSE
prioritise effort and budgets).
management systems in place.
Noting that the management
approaches will require effort to
Escape, be assigned to manage escape,
11 evacuation and evacuation and rescue of
rescue affected personnel on the plant
and adjacent affected
communities.
page 63
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
List of components
2.5 RBI / RCM Analysis and results for Novi Sad Refinery
page 64
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Figure 26: Results of API Qualitative Analysis Component based applied on RGE equipment
5 0 - 0%
1 0 - 0%
A B C D E
CONSEQUENCES
Figure 27: Results of API quantitative (detailed) Analysis Component based applied on
selected RGE equipment
page 65
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
2.6.2 Introduction
2.6.2.1 Objective
The objective of the study was to assess the risk profile of the RGE equipment through the
application of the Risk based inspection methodology and to prioritize equipment for
inspection. Moreover, the goal was to demonstrate the applicability of the overall approach
to the NIS units.
2.6.2.2 Scope
The scope of the RBI study covered all the equipment items and related piping as originally
agreed prior to the project.
Number of
Component type
items
Pressure vessel 41
Condenser, Shell 17
Heat Exchanger, Shell 13
Column Top 10
Filter 7
Furnace Tubes (general) 6
Other Equipment 5
Heat Exchanger, Tube Side 4
page 66
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
2.6.3 Methodology
General details on applied RBI / RCM methodology and HAZOP are presented in Chapter 2.2
of this report.
A HAZOP study is performed by a HAZOP team, consisting of experienced engineers and
operating personnel from appropriate disciplines, facilitated by an independent chairman
experienced in the use of the HAZOP methodology. The team may include representation
from both the design contractor and from their client who is to operate and maintain the
facility. Typically the team may include process engineers, project engineers, electrical &
instrument engineers, maintenance engineers and senior operating personnel. Other
specialists may be drafted in to the meeting when appropriate.
The HAZOP review is normally based on P&IDs of the planned facility, while PFDs, Cause and
Effect Diagrams, Hazardous Area Classification drawings and Layout Drawings may also be
used to provide additional information. During a HAZOP, the P&IDs will be broken down in to
logical sub-systems (nodes), which may be a vessel, a line interconnecting equipments, or
some other logical sub-system.
The HAZOP technique involves the following steps:
1. Identify the node to be studied.
2. Define the design intent of the node and the normal operating parameters.
3. Apply a HAZOP deviation (e.g. NO/LESS FLOW) to the node.
4. Identify all possible causes for the deviation.
5. Identify for each cause all possible consequences, without regard for the
safeguards in place.
6. Identify all available safeguards to prevent the cause or to limit the
consequences.
7. Recommend any new safeguards where judged necessary.
8. Repeat steps 4 to 7, using the next HAZOP deviation.
9. Repeat steps 3 to 8 until all HAZOP deviations have been applied to the
node.
10. Select the next node to be studied, repeating steps 1 to 9.
Steps 3 and 4 are repeated until all the guide-words have been applied and discussed and
the team is satisfied that all meaningful deviations have been considered. The team then
goes back to Step 1 and repeats the process for the next section or node. Figure 3illustrates
the normal workflow of a HAZOP study.
When a recommendation was proposed, the risk was ranked based on consequences and
frequency, using the COMPANY Risk Ranking Matrix.
page 67
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 68
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 69
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
• Propane leakage on the compressor, and auto-ignition of the fluid. Apart from
material damage, there was no other damage to the people or environment mainly
due to an early detection of the incident and fast fire extinguishing
• Leakage of propane, butane and gasoline from the underground lines due to the
corrosion of the underground lines. Consequences – propane and butane was easily
spotted, and quickly fixed. Gasoline leakage was discovered at a relatively late stage,
due to the fact that it did not evaporate. Soil remediation has been done by pumping
up the gasoline from the soil, the whole operation lasted 2,5 months
• Problems at the furnace firing – the firing process is manual and can in some cases
lead to the explosive concentrations inside the furnace and consequent injury of the
person performing firing. So far no serious injuries have happened.
Safety and relief valves: the process is inherently clean, there is a potential for some
corrosion mainly from the outside. No significant fouling of the RV has been registered,
however, in the general process of control, some of the valves have been found not to be
functioning.
Fluid information:
Present fluid in the system are:
• Natural and refined gas - 3,8-17,0% vol explosive concentration, Auto ignition
temperature 640-645°C, gas with no smell or color, flammable and explosive, in
higher concentration might cause suffocation. Danger mark 23, F+, Risk mark R12,
information marks S9,S16,S36/37/39
Approx. fluid composition: methane ~ 93%, ethane ~ 2,50%, propane ~ 0,30%,
butane ~0,03%, other carbon and nitrogen maximum 3,50%,mostly containing
fractions C1-C4, daily throughput of 1200000 m3 per day (or 500t)
• Propane - 2,1-9,5% vol explosive concentration, Auto ignition temperature 465°C,
gas with no smell or color, flammable and explosive, in higher concentration might
cause suffocation. Danger mark 23, F+, Risk mark R12, information marks
S9,S16,S36/37/39
Present quantities on site:
o Process 12m3 as liquid, 8m3 as gas
o Storage: maximal 926 m3(as liquid) and 232 m3(as gas)
• Butane - 1,5-8,5% vol explosive concentration, Auto ignition temperature 365°C, gas
with no smell or color, flammable and explosive, in higher concentration might cause
suffocation. Danger mark 23, F+, Risk mark R12, information marks
S9,S16,S36/37/39
Present quantities on site:
o Storage: maximal 892 m3(as liquid) and 224 m3(as gas)
• Debutanized gasoline - 1,3-7,6% vol explosive concentration, Auto ignition
temperature 257°C, liquid with no color, flammable and polluting for soil and water.
Danger mark 33 Xn,F, Risk marks R11,R22/21,R52/53,R58,R65, information marks
S36/39,S45,S61,S62
Present quantities on site:
o Storage: maximal 355 m3(as liquid) and 89 m3(as gas)
• Heavy gasoline - 1,3-8,0% vol explosive concentration, Auto ignition temperature
205-220°C, liquid with no color, flammable and polluting for soil and water. Danger
mark 33 Xn,F, Risk marks R11,R22/21,R52/53,R58,R65, information marks
S36/39,S45,S61,S62
Present quantities on site:
o Storage: maximal 36 m3(as liquid)
• Methyl-alcohol – 7,3-36% vol explosive concentration, Auto ignition temperature
455°C, liquid with no color, flammable and poisonous. Danger mark T,F, Risk marks
R11 R11,R23/24,25, information marks S-2,7,16,24
Present quantities on site:
o Process: 50l (as liquid)
• Water and steam
page 70
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Technical problem 1
On the top of column T-5 sometimes a valve has to be opened. In some cases the gas
(Decane) ignites and a flame appears on the top of the valve. In this case the valve will be
closed again.
Discussion: The temperature of the gas is 260 0C. There are two possible ignition sources.
The first possibility is electrostatic ignition. The second possibility is an ignition by hot
surfaces. More probable is the ignition by a hot surface. The gas will heat up the surface of
the gas. Autoignition temperature of Decane is about 210 0C. By turbulence at the end of the
valve an explosive air/Decane mixture will be formed which ignites at the hot surface and
lead to the flame.
Technical solution: This has not been discussed during the meeting. A possibility to mitigate
the formation of an explosive air/Decane mixture is to use a three way valve instead of the
existing one. The third line will be connected to a steam line. Both lines have to be opened
instead of only the Decane line. This will have two effects. The surface will be cooled down
under the autoignition temperature and the explosive atmosphere will be inerted. Therefore
an ignition on the surface will not took place.
Technical problem 2
In combination with a pressure drop it may be that there is no liquid phase of Decane at the
bottom of T4 (distillation unit). This will lead to a gas flow to the connected pumps instead of
a liquid flow. The gas will be ignited in the pumps. Same problem will arise if no cooling is
available for the pumps (will be cooled by water and cold oil). Normally two pumps are in
operation and one is stand by. A flow indicator for Decane is responsible for the flow of the
cooling liquids to the pumps.
Discussion: The reason for the ignition is the hot surface of the pumps where an air/Decane
mixture will be ignited.
Technical solution: This has not been discussed during the meeting. A possible solution is as
first a temperature measurement at the pumps. In the line between distillation T4 and pump
a valve can be integrated. This has to be opened if the flow indicator for Decane and the
temperature indicator at the pump indicate that there is no flow of liquid Decane. The open
line can be connected to the flare. The valve can be closed again if the flow indicator gives a
signal for liquid Decane flow.
Technical problem 3
Once per year the gas pipelines outside the establishment will be cleaned. Different kind of
liquids and dusts has been accumulated over the period of one year. The Naftagas plant is
responsible for the collecting of these wastes. The waste is delivered by a pressure wave
through the incoming line for gas and is collected in the separator D-300. The technical
problem is twofold. In the loop1 discussed during the Hazop analysis a pressure surges occur
(e.g. water hammer, cavitational hammer). These pressure surges can lead to damages of
plant's equipment (valves, pumps, pipe bends) up to leakage of the pipe system. After the
cleaning the gaseous line will be opened again. Again pressure surges occur and parts of the
equipment can be obstructed completely or partly by remaining particles. This is actual the
case for the heat exchanger E-110.
page 71
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 72
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 73
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Feed
No safety problem, shut down or Two Safety valves
1 entrance to Flow Less Less Gas Supply FALSE
continuation depending on flow on D-300
D-300
Feed
No Supply Cleaning gas Two Safety valves
2 entrance to Flow No No safety problem TRUE
line on D- 300
D-300
Feed
No safety problem, shut down or Two Safety valves
3 entrance to Pressure Lower Less Supply TRUE
continuation depending on flow on D-300
D-300
Feed
Supply changes, More Valve (LCV 301) to F301 will be partly or Two Safety valves
4 entrance to Composition Higher TRUE
C1-C2 Gas completely closed on D- 300
D-300
Feed
Supply changes, Less PV 401 is an overflow valve and will mitigate Two Safety valves
5 entrance to Composition Less TRUE
C1-C2 Gas increase of level. Storage tank D-27A. on D- 300
D-300
Feed
Filter has to be cleaned. Indication: Pressure Two Safety valves
6 entrance to Pressure Higher Filter in F-301 dirty. . TRUE
increase continuously on D- 300
D-300
page 74
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 75
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Discussion: There was only a general discussion on the hammer effect on the lines where the
liquid phase is in. A more detailed discussion was about the pressure wave which took place
when the gaseous line will be reopened. As the heat exchanger is not really working at the
moment based on pollution with dust particles the questions raised up what can happen
furthermore in other parts of the plant.
It has been proposed not to concentrate on the possible damages and instead to concentrate
of a mitigation of the pressure wave. At the moment a valve in a 12 inch line with a 3 inch
pipepass will be opened, It has been proposed to include another valve in a 6 inch line with a
2 inch bypass to reduce the pressure wave.
The following proposals have not been discussed in this meeting.
The typical scenarios for the origin of pressure surges are fast closing valves triggered by the
breakdown of auxiliary power and fast acting control devices. The fast deceleration of the
liquid results in high pressure surges upstream the valve, because kinetic energy is
transformed into potential energy. This effect is called water hammer that is explained by the
following example. In a horizontally installed 500 m long pipeline of the size DN 200 which
transports water with a velocity of 3 m/s at ambient temperature, the pressure increases by
a fast closing valve from a stationary pressure of 6 bar up to 40 bar. Hereby the forces
induced to pipe supports exceed the design criteria from 1-5 kN to 125 kN. Due to liquid
inertia, the transported liquid continues to flow downstream the valve with the initial speed,
the pressure decreases and a large expanding vapour bubble is formed directly downstream
the valve. The pressure falls up to saturation pressure of the liquid and is thus lower than the
pressure in the system. Thereby the liquid stream is decelerated and finally accelerated
towards the closed valve (back flow). As a result of fast re-condensation of the vapour
bubble, the liquid flows against the closed valve and is stopped rapidly. The resulting
pressure surge is referred to as cavitational hammer. The amplitude of the first cavitational
hammer downstream the valve is nearly as high as the amplitude of the first water hammer
upstream the valve.
Well-known methods for the prevention of water hammer in pipeline systems are e.g. the
application of air vessels, surge shafts, bladder accumulators, as well as the prolongation of
closing and opening times of valves. The latter is the easiest and the most favourable
method. Due to technical and legal requirements for pipeline operation within the chemical
industries and power plants it is not always possible to decelerate the closing process
undefined.
Air vessels, surge shafts or bladder accumulators are used if the pipeline system is not
designed on the same level. These applications are installed upstream the closing valve in its
immediate proximity. When shutting off the medium flows in to the loft and is braked by
this.
Another possibility is the expansion of valve gears with facilities which decelerate the closure
as soon as the last third of the flow cross section is nearly reached. These can be dampers
(often used with swing check valves) or programmable positioners..
Technical problem 4
There is a leakage in the product lines C3 and C4 to the tanks. As the lines are underground
the leakage and the size of the leakage can not be detected. There is no leak detection
system installed.
Discussion: Leakage is visible by bubbles on the ground if it is raining and by parts of non
growing grass.
Technical solution: This has not been discussed during the meeting. As the amount of gas is
unknown there is the hazard of an explosion. The only possible solution is to repair or to
exchange the lines or to build new lines on the ground and to close the old ones.
Technical problem 5
There is a compressor in use where gaseous Propane will be compressed from 1.7 to 13-15
bars. There are two problems. The first problem is in the case of a leakage in the compressor
(Jet fire, explosion). Hot surfaces near by have a temperature of 500 0C. The volume of the
compressor is about 0.5 cbm. The second problem may occur if liquid propane flows into the
page 76
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
compressor. This will normally be mitigated by a measurement of gaseous and liquid phase
in the separator before. If this is not working an explosion is possible.
Discussion: This has not been discussed during the meeting.
Technical solution: There will be possibilities by using quick closing valves. This will mitigate
the flow of liquid Propane to the compressor. Further technical specification possible but not
done.
2.6.6.3 Management Systems Evaluation
According to the API 581, Management system evaluation (self-assessment) has been
performed. After this, an audit of the results has been performed in order to revise the
scores achieved.
The results are given in the table below and shown on Figure 34.
Table 39 Management System Evaluation results with audit comments
page 77
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 78
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
4
L
I
K
E
L RGE-1 Procesno
3
I postrojenje
H
O
O
D
2
A B C D E
CONSEQUENCES
Figure 35: Risk matrix showing the position of the RGE in qualitative unit analysis matrix
page 79
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The corresponding inspection plan (Annex 25) results in increase of inspection on equipment
identified as critical (6 pieces of equipment), while decreasing the number of equipment to
be inspected each year (i.e. in 2009 from 99 to 51).
5 0 - 0%
4 D-101 D-102 2 - 2%
1 0 - 0%
A B C D E
CONSEQUENCES
Figure 36: API 581 Qualitative risk matrix for component level, for year 2009
page 80
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
5 0 - 0%
1 0 - 0%
A B C D E
CONSEQUENCES
page 81
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
5,000,000 Din.
4,000,000 Din.
Costs RSD
3,000,000 Din.
1,000,000 Din.
RBI optimized
0 Din.
2009 2010 2011
Inspection year
3,500,000 € 100%
90%
3,000,000 €
80%
2,500,000 € 70%
2,000,000 € 60%
50%
1,500,000 € 40%
1,000,000 € 30%
20%
500,000 €
10%
0€ 0%
E‐1A/B
E‐101/B
E‐101/A
D‐27A
D‐28A
D‐29A
D‐27C
D‐28C
D‐27B
D‐28B
D‐29C
T‐7
D‐2
T‐9
T‐4
D‐4
T‐8
D‐7
D‐6
T‐6
T‐5
D‐1
T‐1
E‐2
D‐5
E‐110
E‐102
T‐3
D‐27D
D‐27F
D‐28D
D‐28F
D‐29B
D‐27E
D‐28E
D‐102
T‐2
T‐101
JI‐1
JI‐2
D‐300
SP‐1
HP‐1
HP‐2
C1A/B (potis)
(usis)
C1A/B(potis)
C2A/B (usis)
C2A/B
page 82
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Corresponding
Minimum data and information to be included in
paragraph of the
the safety report referred to in Article 9
Safety report
Information about management system and organization
of the establishment in relation to the prevention of
I
major accidents, this information must consider the
items listed in Annex III
II Surrounding of the establishment
Description of site and its surrounding, including the
geographical location, meteorological, geological,
A
hydrographic conditions and, where appropriate, its
history.
Identification of installations and other activities of the
B establishment which could present a risk of a major
accident.
Description of areas that may experience a major
C
accident.
III Description of the establishment
Description of main activities and products of major
parts of the plant in terms of safety, sources of major
A accident hazards and the conditions under which such a
major accident could occur including a description of
proposed preventive measures.
Description of processes, in particular the operating
B
methods.
C Description of hazardous substances:
page 83
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
This Safety Report is updating the Safety report prepared in May 2008. It therefore
incorporates the organizational changes and technological changes occurring in plant and
refinery from that date.
page 84
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 85
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Some accidents took place in the past. 1986 there was a fire in a pressure vessel and a
separator of fuel gas. In 1989 an accident caused by abrasion occurred. The result has been
a small steam leak in a reactor. In 2003 a slide valve was closed caused by a cut cable. The
pressure inside the regenerator increased and cyclones were damaged.
2.7.2.3 Policy the company is pursuing
RNP has established the quality management system in accordance with ISO 9001:2000
standard, for all RNP's operations. Details are given in chapter 2.1.4..
List of RNP QMS and EMS documentation is given in Annex 15.
2.7.2.4 Safety management system
Safety Management System is a part of RNP quality and environment management system
including some principles to identify and to evaluate possible hazards and principles to
identify and to realize technical organizational and management activities for the mitigation
and consequence reduction of accidents. Responsible organizational unit for HSE issues is
Risk Management division.
2.7.2.5 Hazardous materials
FCC ensures deep conversion of vacuum gas oils into gases, gasoline components, diesel
components and fuel oil. Catalytic cracking process breaks or cracks long chain hydrocarbons
into smaller molecules in the naphtha and distillate boiling range to increase gasoline and
diesel production. This process will yield 50-60% gasoline, 20-30% distillate and 30%
butanes and lighter.
Accordingly, hazardous materials in RNP FCC are:
• Propane
• Butane
• Gasoline
• light cracked gas oil
• H2S and
• for internal use fuel gas.
The complete list of hazardous materials is given inError! Reference source not found..
2.7.2.6 Meteorological data
Chapter 2.1.3.2 of this report contains data related to
• Meteorology
• Hydrology
• Geology
• Seismology.
2.7.2.7 External activities
Industrial activities external to the establishment of Refinery Pancevo are described in
Volume I of Detailed Technical Report.
FCC complex is located in Block VI of Refinery Pancevo and it includes following units:
• S-2300: Fluid Catalytic Cracking unit (hereafter FCC)
• S-2500: Gas concentration unit
• S-2550: Merox unit LPG extraction
• S-2600: Alkylation
• S-2750: Merox, Light naphtha sweetening Unit
• S-2850: Merox, Heavy naphtha sweetening
• S-2900: Sour water stripper
• S-2450: Sulphur recovery unit (Klaus)
page 86
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
powdered zeolite catalyst that is kept in suspension in the reactor by the incoming oil feed
from the bottom of the reactor. Upon contact with the hot catalyst, the oil vaporizes and is
cracked into smaller molecules. Vapors from the reactor are separated from the entrained
catalyst and fed into a fractionator, where the desired products are removed and heavier
fractions are returned to the reactor. The catalyst is deactivated by thermal degradation and
through contact with heavy metals in the feed, necessitating regeneration or replacement.
FCC is used in processing of vacuum heavy gas oil which is pumped into the pipe reactor
“RISER” where the actual reaction of cracking is taking place. Unit area is 90 x 100=9000
m2, construction is open and mainly made of concrete. It incorporates also a concrete
chimney with 150m in height and 13m diameter base. This process breaks or cracks long
chain hydrocarbons into smaller molecules in the naphtha and distillate boiling range to
increase gasoline and diesel production. This process will yield 50-60% gasoline, 20-30%
distillate and 30% butanes and lighter. If you do the math you will see that the volume of
products is greater than the volume of the feed.
Capacity of the unit
FCC unit is designed to manufacture 3000t/dan (1.000.000t/year) of heavy vacuum gas oil
that is derived from crude oil Kirkuk. The Pancevo Refinery is mostly processing crude oil of
"REB" and "Kikinda" and processing capacity depends on the availability of supplies and the
market requirements for final products. Flow chart is shown in Figure 42.
Description
Process flow Diagrams Flow through the Unit is shown schematically on the following Process
flow Diagrams:
page 87
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 88
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
instantaneously raises the burning temperature. The "secondary combustion" stage occurs
simultaneously as the CO burns with oxygen to form C02. Combustion of the coke to carbon
dioxide is almost complete at the temperature in the Regenerator. Duri ng start-up the Ai r
Preheater, BC-2301, is used to heat up the Regenerator.
The Air Blower is driven by a condensing turbine, the outlet steam being condensed by the
Surface Condenser, EC-2510. Condensate from the condenser is collected in the Condensate
Drum, FA-2520,and is pumped to the Offsite Deaeration Facilities by the Turbine Condensate
Pump,GA-2520/S,via the Inter/After Condenser, EA-2520. The Inter/After Condenser
condenses the'vapours withdrawn by the steam jet evacuation equipment. Any condensate
formed in the piping between the turbine and the condenser is vaporised in the Re-
evaporatbr, EA-2522.
Hot gases produced by the combustion of coke leave the dense phase of the Regenerator
and enter the dilute phase where entrained catalyst is removed in three twostage
Regenerator Cyclones, FC-2302 A/F and returned to the Regenerator catalyst dense phase
via the cyclone diplegs. The hot regenerated catalyst leaves the Regenerator via the Fresh
Feed Regenerator Catalyst Standpipe and the Recycle Feed Regenerator Catalyst Standpipe
and passes through the slide valves to the FF and RF Risers.
The hot gases leaving the Regenerator Cyclones pass through the Flue Gas Pressure Control
Valve, PA-2305, the Ori fi ce Chamber, PA-2307,and the Fl ue Gas Diverter Valve, PA-
2306,to the CO Boiler, BF-2301,before exhausting to atmosphere via the Stack. CA-230l.
The CO Boiler produces HP steam (44.1 bar g) by recovering sensible heat, and the heat of
combustion of CO when operating with non promoted catalyst, from the Regenerator flue
gas. The CO Boiler is supplementary fired with fuel oil or fuel gas to provide sufficient steam
to meed the demand of the FCC complex. Boi1er feed water enters the CO Boiler under flow
control and passes through a preheater and economiser to improve the overall efficiency of
steam generation. The steam and water mixture produced in the convection bank is
separated in the steam drum and the steam is then passed through a two-stage superheater.
The steam temperature is controlled by taking a slip stream of steam from the fi rst stage of
the superheater and passing it through an attemperator. The attemperator and preheater are
located inside the steam drum.
Fresh catalyst is fed to the Regenerator from the Fresh Catalyst Hopper, FE-230Z, using the
Continuous Catalyst Addition Device, GB-2302. Equilibrium catalyst for start-up is stored in
the Equilibrium Catalyst Hopper, FE-2301.
page 89
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
is cooled in the following four parallel heat exchanger ci rcuits before returning to the
colurnn:
A. Feed/ICGO Refl ux Exchangers, EA-2302 A/B.
B. Deethaniser Reboiler,EA-2502,in the Gas Concentration Unit.
C. Naphtha Splitter Reboiler,EA-2507,in the Gas Concentration Unit.
D. 1CGO Reflux Steam Generator,EA-2307.
The main part of this ICGO Reflux Stream is returned to the Fractionator above the draw off
tray. The remainder is returned to the bubble cap trays below the draw off pan in order to
scrub out any entrained catalyst remaining in the vapour from the baffled section, and also
to provide additional cooling of the vapour.
The balance of the ICGO from the total draw off tray passes to the ICGO Stripper, DA-2302.
The ICGO Stripper is reboiled by circulating ICGO Recycle through the ICGO Recycle Reboiler
Pump, GA-2j07/S, to the ICGO Recycle Stripper Reboiler, BA-2302, under flow control. The fi
red heated serves the dual purpose of stripping and preheating the Recycle Feed. Recycle
feed is pumped from the ICGO Stripper by the ICGO Recycle Pump, GA-2306/S, under flow
control to the RF Riser. The ICGO stripper vapour is returned to the Main Fractionator.
Light Cycle Gas Oil, LCGO, is removed from a partial draw off tray in the Main Fractionator.
Part is circulated by the LCGO Reflux Pump,GA-2308/S, under flow control and is cooled
initially by preheating boiler feed water in the LCGO/BFW Exchanger, EA-230S, and
preheating the Debutani ser Feed in the Debutaniser Feed Preheater, EA-2S03. These
combined streams are then cooled by passing some of the LCGO Reflux through the Lean
Sponge Oil Cooler. EC-2305, before returninq to the Main Fractionator. Some of the LCGO
Reflux from the outlet of the Lean Sponge Oil Cooler is pumped by the Lean Sponge Oil
Pump, GA-2309/S, to the Sponge Oil Absorber, DA-2501, in the Gas Concentration Unit
before returning to the Main Fractionator, and some ;s passed to the Gland and Flushing Oil
Surge Drum, FA-2307, to be used as gland and flushing oil.
The remaining LCGO from the Main Fractionator passes to the LCGO Stripper, DA-2303t
where light ends are stripped from the light cycle gas oil with heat supplied by fractionator
bottoms in the LCGO Stripper Reboiler, EA-2304. The stripped vapours are returned to the
Main Fractionator. The LCGO product is pumped by the LCGO Product Pum~ GA-2310/S,
through the Feed/LCGO Product Exchangers, EA-2301 A/~ to the LCGO Hydrotreating Unit
(Unit 2400) or to storage via the LCGO Product Cooler, EC-2303.
A naphtha sidestream is withdrawn from the Main Fractionator between the LCGO draw-off
and the column overheads. Thi s stream is ci rcul ated under f1 ow control by the Top
Pumparound Reflux Pump, GA-23l1/S,to the Propylene Splitter Reboi1er, EA-2515,in the Gas
Concentration Unit before being returned to the Main Fractionator.
Fractionator overheads are cooled and partially condensed in the Fractionator Overhead
Condenser, EC-2306. Water soluble corrosion inhibitor is injected upstream of the
Fractionator Overhead Condenser using the Fractionator Overhead Corrosion Inhibitor Pump,
GA-2514, to prevent hydrogen blistering. Unstabilised gasoline and vapours are separated in
the Fractionator Overhead Accumulator, FA-2304, with the vapours flowing to the GCU Gas
Compressor, GB-2501. Unstabilised gasoline is pumped under level control by the
Fractionator Overhead Pump,GA-2312/S,to the Raw Gasoline Cooler, EA-2501, in the Gas
Concentration Unit and is also used as pumpback ref1 ux to the Main Fractionator to control
overhead temperature. The condensed water phase and sour water passed into the boot of
the Fractionator Overhead Accumulator from other Units is pumped by the Sour Water Pump,
GA-2313/S,to the Sour Water Stripper Unit (Unit 2900).
page 90
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
B1owdown Drum, FA-2522, where it is quenched with raw water before passing to the oily
water sewer.
Dry plant air, with a water dew point of -40 °C, is provided to supply the power to actuate
the automatic slide valves. The air supplied to each valve passes to an air motor operated
power unit which directs the air supply to drive the valve in either direction, depending on
the signal being received from the automatic controller. Alternatively, the slide valve can be
moved by the manual operation of a local 4-way valve which performs a similar function. The
Slide Valve Air Surge Drum, FA-230l, is provided to operate the valves during an emergency.
The drum is sized to hold sufficient air to close each operating valve once from the wide open
position without the reservoir pressure dropping below 4.1 bar g.
In· the event that any portion of the Regenerator exceeds 730 °c for short periods, spray
water from the Spray Water Drum, FA-2302, should be injected into the Regenerator by the
Spray Water Pump, GA-2301 IS. Spry water should be removed from the Regenerator at the
first opportunity to prevent catalyst deactivation and .to regain optimum combustion air
control.
Light Cycle Gas Oil is normally used as pump gland flush oil and flushing oil for instruments,
the supply being taken from downstream of the Lean Oil Cooler, EC-2305. An alternate diesel
supply is provided at start-up from offsite storage. The LCGO passes into the Gland and
Flushing Oil Surge Drum FA-230~and is continuously circulated around a ring header system
using the Gland and Flushing Oil Pump GA-23l4/S. This system is also used for flushing
equipment which can be taken out of service while the rest of the unit is in operation.
2.7.3.2 Gas concentration unit S-2500
Gas Compression Section
Vapours from the Fractionator Overhead Accumulator, FA-230~ are compressed in the two
stage, turbi ne dri ven GCU Gas Compressor, GB-2501, after passing through the First Stage
Compressor Suction Drum, FA-2501. Liquid removed in the Compressor Suction Drum, flows
under gravity back to the Fractionator Overhead Accumulator. Off gas from the LCGO
Hydrotreating Unit (Unit 2400) is also fed to the First Stage Compressor Suction Drum.
Flashed condensate is injected into the first stage discharge to protect the lines from
hydrogen blistering together with water soluble corrosion inhibitor from the First Stage
Compressar Corrosion Inhibitor Pump, GA-25l5. This stream is then cao1ed and partial1y
condensed by the First Stage Compressor Condenser, EC-2501, befare enteri ng the Second
Stage Compressor Suction Drum, FA-2502. The interstage liquid from this drum is pumped
by the Second Stage Compressor Suction Drum Pump, GA-250l/S to the Deethaniser Feed
Coalescer, FA-2505. Sour water, separated from the hydrocarbon phase in FA-2502,is sent
under level control to the Fractionator FA-2502 are compressed in the second stage of the
GCU Gas Compressor and then injected with steam condensate together with corrosion
inhibitor from the Second Stage Compressor Corrosion Inhibitor Pump, GA-2S16, and routed
to the HP Separator Condenser, EC-2502.
The GCU Gas Compressor is driven by a condensing turbine, the outlet steam being
condensed by the Surface Condenser, EC-2509. Condensate from the condenser i s collected
in the Condensate Drum, FA-2S19, and is pumped to the Offsite Deaeration Facilities by the
Turbine Condensate Pump, GA-25l9/~ via the Inter/After Condenser, EA-2519. The
Inter/After Condenser condenses the vapours withdrawn by the steam jet evacuation
equipment. Any condensate formed in the piping between the turbine and the condenser is
vaporised in the Re-evaporator, EA-2521.
Absorption/Deethaniser Section
The vapours from the compressor second stage are combined w;th liquid from the Raw
Gasoline Absorber,DA-2501 ,and overhead vapours from the Deethaniser ,DA-2502, the C3
Drier Overhead Accumulator,FA-2513,and the Propylene Splitter Overhead Accumulator,FA-
2514,and passed to the High Pressure Separator Airfan Cooler,EC-2502. Flashed condensate
page 91
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
is injected into the inlet of the airfin to protect the exchanger from hydrogen blistering
together The GCU Gas Compressor is driven by a condensing turbine, the outlet steam being
condensed by the Surface Condenser, EC-2509. Condensate from the condenser i s collected
in the Condensate Drum, FA-2S19, and is pumped to the Offsite Deaeration Facilities by the
Turbine Condensate Pump, GA-25l9/~ via the Inter/After Condenser, EA-2519. The
Inter/After Condenser condenses the vapours withdrawn by the steam jet evacuation
equipment. Any condensate formed in the piping between the turbine and the condenser is
vaporized in the Re-evaporator, EA-2521, with water soluble corrosion inhibitor from the
Second Stage Compressor Discharge Corrosion Inhibitor Pump, GA-2516. The combined
stream is cooled and passed to the High Pressure Separator,FA-2504,where hydrocarbon
vapour, hydrocarbon liquid and water are separated. Water i s continuous 1y removed from
the boot and transferred to the Main Fractionator Overhead Accumulator, FA-2304,before
pass ing to the Sour Wate r Stripper.
The vapour stream from the Hi gh Pressure Separator, FA-2504,is introduced at the base of
the Sponge Oi1 Absorber/Raw Gaso1 i ne Absorber, DA-250l ,where i t i s scrubbed with raw
gasoline and then with 1ean sponge oil to remove C3's and heavier. The raw gasoline is fed
from the Maln Fractionator Overhead Accumulator, FA-2304,by the Fractionator Overhead
Pump,GA-23l2/S, via the Raw Gasoline Cooler, EA-250l,to the Raw Gasoline Coalescer, FA-
2503. Water removed i s returned to FA-2304. The raw gasoline enters DA-2501 where it
contacts the vapours from the High Pressure Separator over slotted ring packing. Ouring
winter operation, debutaniser bottoms recycle from the Debutani Sf'r Bottoms Recyc1e
Pump,GA-2504/S, is pumped with the raw gasoline into the Raw Gasoline Absorber. This is
done to provide suffieient liquid loading both in the Raw Gas01ine Absorber and in the
Deethaniser to effect the desired C3 recovery. The raw gasoline leaves the bottom of the
ABsorber and is pumped by the Raw Gasoline Absorber Bottoms Pump,GA-2502/S,into the
inlet of the High Press ure Separator Ai rfan Cool er, EC-2502.
The vapours emerging from the Raw Gasoline Absorber pass up the co1umn through a
chimney tray and are contaeted with 1ean sponge oil aver slotted ring packing. The lean
sponge oil whieh is unstripped LCGO is pumped fram the FCCU by the Lean Sponge Oi1
Pump,GA-2309/S~and enters the top of the Sponge Oil Absorber,DA-2501, where it removes
a major part of the C315 and C4's from the vapour. The rieh spange oi1 1eaving the
Absorber passes to the Rich Sponge Oi1 Surge Drum, FA-2516. Any vapours whi eh di
sengage are returned to the Absorber be10w the top packed bed. Rieh sponge oil is returned
to the coo1ed LCGO reflux stream which passes to the Main Fractionator, DA-2301. Water
removed from the boot of FA-25l6 is returned to FA-2304.
The overhead gases from the Spange Oi1 Absorber,DA-2501, consisting mainly of hydrogen.
Cl's, C2'5 and hydrogen sulphide flow to the Fuel Gas Scrubber KO Drum,FA-2509, and on to
the base of the Fuel Gas Scrubber, DA-2505. where lean amine is used in the countercurrent
extraction of hydrogen sulphide.
Liquid hydrocarbons from the High Pressure Separator, FA-2504,are pumped by the
Deethaniser Feed Pump, GA-2503/S. together with interstage liquid from the Second Stage
Compressor Suction Drum Pump. GA-250l/S. to the Deethaniser Feed Coalescer, FA-
2505.before passing to the top tray, tray 21, of the Deethaniser.DA-2502. Water from the
coalescer boot is passed to FA-2304.
Light ends are stripped out in the Deethaniser, DA-2502, in order to control the C2 content
in the resulting C3 streams. The overheads from the column are returned to the High
Pressure Separator Airfin Cooler,EC-2502. The column is reboiled by circulating hot intermedi
ate cycle gas oil (ICGO) pumped by the ICGO Reflux Pump,GA-2305/S, through the Deethani
ser Reboi1er. EA-2502. Reboiled vapours return to the column and the liquid product is fed
to the Debutaniser.DA-2503. The flow from the bottom of the Deethaniser represents the
total liquids recovery of the sys tem.
Any free water trapped in the Deethani ser i s removed in the Deethaniser Water Draw Off
Pot, FA-2506, which takes liquid from tray 15 of the co1umn.
Debutaniser Section
The Debutaniser DA-2503, is designed to separate C4'5 and 1ighter from C51S and heavier,
with the overhead having less than 0.3 wt.% pentanes and heavier and bottoms containing
less than 0.5 wt.% butanes and lighter. The feed to this tower is the Deethaniser bottoms
stream. This stream is preheated by circulating hot LCGO. pumped by the LCGO Re fl ux
Pump, GA-2303jS. through the Debutaniser Feed Preheater. EA-2503, and by Debutaniser
page 92
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 93
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
is then routed to the LPG Merox Unit (Unit 2550) to remove mercaptans before being
pumped by the Depropaniser Charge Pump, GA-2552/S to the Depropaniser, DA-2508.
Depropaniser Section
C3-C4’s from the LPG Merox Unit (Unit 2550) together with C3-C4 recycle from the
Alkylation Unit (Unit 2600) are fed, through the Oepropani ser Feed/Effl uent Exchanger, EA-
25G8, to the Depropani ser, DA-2507. The feed enters on tray 27 of this 53 tray column.
Reboil heat is suplied to the Depropaniser by the Debutaniser bottoms stream in the
Depropaniser Reboiler, EA-2509. The butane/butylene praduct from the bottom of the
Depropaniser is first cooled in the Depropaniser Feed/Effluent Exchanger, EA-2508) and then
by cooling water in the C4 Product Cooler, EA-25l0 , before being routed to the Alkylation
Unit (Unit 2600) or to offsite storage.
The overheads from the column are tota11y condensed in the Depropaniser Overhead
Condenser, EC-2504, and passed to the Depropaniser Overhead Accumulator, FA-25l0.
Water, separated_ out in the boot of this drum,is passed to the Main Fractionator Overhead
Accumulator, FA-2304. Part of the condensed hydrocarbon stream is pumped by the
Depropani ser Refl ux/Product Pump, GA-2509 IS, as refl ux to the Depropani sero The rema
inder i s routed to the (3 Drier, DA-2508.
C3 Drier Section
Water contained in the overhead product of the Depropaniser is separated fram the C315 in
the C3 Drier, DA-2508, in order to produce a propane cut with a dew pOlnt less than -30 °c.
The feed to the C3 Orier t DA-2508 ,is cooled in the C3 Orier Feed Cool er, EA-2511, and
passed through the C3 Drier Feed Coa1escer t FA-2511 t to remove free water. The feed
enters the 30 tray column on tray 18. The tower overheads are partially condensed by the
C3 Drier Overhead Condenser t EA-2513 and fed to the C3 Drier Overhead Accumulator t FA-
2513. The liquid hydracarbon from the Accumu1ator i5 pumped back to the tower as reflux
by the C3 Drier Overhead Reflux Pump, GA-2511/S, via the C3 Drier Reflux Coalescer, FA-
2512. Vapour from the Accumulator i5 recycled to the High Pressure Separator Airfan Cooler,
EC-2502, in the Absorption/Deethaniser Section.
Propylene Splitter Section
Dried C3’s enter the Propylene Splitter t DA-2509 ton tray 41 of tne 101 tray column. The
co1umn overheads are partia11y condensed in the Propylene Splitter Overhead Condenser,
EC-2508 t and pass to the Propylene Splitter Overhead Accumulator, FA-2514. The liquid
hydrocarbon from this drum is pumped back to the tower as reflux by Propylene Splitter
Overhead Reflux Pump, GA-2513/S, while the vapour is recycled to the High Pressure
Separator Airfan Cooler, EC-2502, in the Absorption/ Deethaniser Section.
Propylene product is withdrawn from tray 91 as a side draw and routed to storage offsite via
the Propylene Product Cooler, EA-2516.
Reboil heat to the co1umn is provided from two separate sources. The majority of the heat is
supplied by a top pump around reflux stream from the FCCU Main Fractionator t DA-2301,
and is circlated by the Top Pump around Reflux Pump,GA-2311/S through the Propylene
Splitter Reboiler/Top Pump around Refl ux Exchanger, EA-2515. The remaining heat is
supplied by the Propylene Splitter Reboiler/Steam Condensate Exchanger, EA~25l4, which
uses high temperature steam condensate from the High Temperature Condensate Drum,FA-
2517, as the heating medium.
The propane product is taken from the bottom of the tower and is pumped by the Propane
Product Pump, GA-25l2/S, through the Propane Product Cooler, EA-2517, to offsite storage.
Condensate Collection System
Steam condensate from the Sour Water Stripper Reboiler, EA-2902, and the Amine
Regenerator Reboiler, EA-2952, together with condensate from the M.P. condensate header
is passed into the High Temperature Condensate Drum, FA-2517.
Flashed steam is fed into the LP steam main. The hot condensate is primari1y used as a heat
source and is passed to the Propylene Splitter Reboiler/Steam Condensate Exchanger, EA-
25l4, before entering the Low Temperature Condensate Drum, FA-2518. Excess condensate
passes directly to the Low Temperature Condensate Drum. If insufficient condensate is
available for reboiling the'Propylene Splitter, boiler feed water is fed into the High
Temperature Condensate Drum.
page 94
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Condensate from the LP condensate header is also fed into the Low Temperature Condensate
Drum, FA-25l 7. Flashed steam is exhausted to atmosphere. Flashed condensate is fed by
the Compressor Condensate Booster Pump, GA-25l8/S, to the First Stage Compressor
Condenser, EC-250l, to the High Pressure Separator Airfan Cooler, EC-2502, and to the
Alkylation Unit (Unit 2600) to be used as water wash in the DP Water Wash Settler, FA-2509,
and the DIS Water Wash Settler, FA-26ll. Additional condensate is supplied by the Process
Condensate Pump, GA-2521/S, vi a the flashed condensate header to theCondensate Surge
Drum, FA-2404, in the Hydrotreating Unit (Unit 2400), to the Spray Water Drum, FA-2302,
in the FCCU, and to other intermittent users. The excess condensate fram this pump is
routed to the offsite deaeration facilities. If insufficient condensate is available, boiler feed
water is fed into the Low Temperature Condensate Drum, FA-2518.
Corrasion Inhibitor System
In order to protect certain items of equipment fram corrosion and hydrogen blistering a
water soluble based corrosion inhibitor system has been provided. The corrosion inhibitor i5
mixed with turbine condensate in the Corrosion Inhibitor Drum, FA-2515. The solution is
mixed using fuel gas which is vented to the flare system. The following items of equipment
and its downstream piping are protected by injecting the material using the following pumps:
Main
Injection Pump
Equipment
GA-2514 Main Fractionator OH Corrosion Inhibitor Pump EC-2304
GA-2515 First Stage Compressor Discharge Corrosion Inhibitor Pump EC-2501
GA-2516 Second Stage Compressor Discharge Corrosion Inhibitor Pump EC-2502
GA-2517 Debutaniser Overhead Corrosion Inhibitor Pump EC-2504
GA-2524 Sour Water Stripper Reflux Corrosion Inhibitor Pump DA-290l
Feed Characteristics
page 95
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Products of FCC
Products from FCC unit are:
• Wet gas
• Raw FCC gasoline
• Light cycle gas oil
• Products from the bottom of fractionators
• Intermediate cycle gas oil for production process in FCC
Characteristics of some products are given in next tables.
Table 44: Quality of wet gas
page 96
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Regime 1 Regime 2
Component
(%mas) (% mas)
H2S 5.84 7,68
H2 0.15 0.38
CH 4 2.24 5.63
C2 H6 2.17 6.66
C2 H4 1.72 2.76
C3 H8 4.86 10.61
Propylene 22.38 16.56
i-butane 24.78 22.23
n-butane 6.67 6.82
Butilene 29.19 20.67
Regime 1 Regime 2
Component
(%mas) (% mas)
Molecular weight 9.41 100.8
o
Specific Gravity at 15.6 C 65.9 58.7
IBP 2.24 5.63
10% 2.17 6.66
30% 1.72 2.76
o
Distillation ASTM C 50% 4.86 10.61
70%
90%
EP
Octane number RON 22.38 16.56
MON 24.78 22.23
paraffin 6.67 6.82
olefins
PONA (%vol)
naphthens
aromats
Total sulfur 0.160 0.169
Major supplies
page 97
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The major outside supplies for FCC and the connected safety problems are shown in Table
46.
The internal electrical distribution system is working now without any problems. In the year
2006. the transformer unit has been completely rebuilt.
Table 46: FCC supplies
Nitrogen No problems
Loss of electricity
One of the most important outside supplies for FCC is electricity. Hazard analysis has never
been done for this case. Loss of electricity could cause safety problem, even may lead to a
Domino effect if something else goes wrong simultaneously. Loss of electricity could affect
differently some types of equipment as shown in the following table.
Table 47: Some effect of loss of electricity
Equipment/
installation Possible safety problem
affected
Reactor Slide valves will close and reaction will stop. Some
valves will opes due to their basic function and the
steam will be released. Result will be steam in the
reactor and the process will stop. (less than 10
seconds).
Temperature will increase as no cooling exists.
Regenerator Regenerator will be a separate unit as all slide valves
are closed. The remaining coke and catalyst will still
react. There are about 90 tons of catalysts in the
regenerator. A balance of the remaining coke and air
is difficult regarding the high reaction speed.
Nevertheless as the concentration of Oxygen is
reduced the concentration of CO may increase and
may cause explosion problems.
Column Temperature and pressure will increase as the
ventilator used for the air coolers are not longer
working. The safety valve at the top of the column
will open.
Air coolers No problem as the temperature will go done very
fast if the feed will not be continued.
Pressure vessel No problem as functioning is not depending on
electrical equipment.
Sensor/
Are still working as using a 24 V line.
Instrumentation
page 98
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 99
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
No flow to the vessel is possible if a valve is closed but will cause no safety problem.
page 100
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 101
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
For a shut down all lines will be cleaned with steam and for a start up all lines will be cleaned
with nitrogen,
page 102
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 103
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The probability and consequences of the accidental scenarios are analyzed in sections 2.7.5.
page 104
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Frequency
Event Fonte
(events/ year)
Leak from Flange seal 4,0 × 10-4 Cremer & Warner, “A report to
the Rijnmond Public Autority”
Leak from pump mechanical seals 6,0 × 10-2 Tab. A 9-2 Lees
Leak from piping diameter
Frequency in /meter (mm)
of pipe/year) Cremer & Warner, “A report to
< 50 9,0 × 10-6
the Rijnmond Public Autority”
50 – 200 5,0 × 10-6
>200 3,0 × 10-6
Piping rupture diameter
Frequency in /meter (mm)
of pipe/year) Cremer & Warner, “A report to
< 50 9,0 × 10-7
the Rijnmond Public Autority”
50 – 200 3,0 × 10-7
>200 9,0 × 10-8
Catatrophic tank rupture 1, × 10-5 Cremer & Warner, “A report to
Leak from tanks 1,× 10-4 the Rijnmond Public Autority
The data above are derived from experience up to the eighties; to date the availability of
tools and procedures specifically dedicated to the improving of safety like Safety
Management Systems, RBI etc makes it realistic to consider that the frequency of failure
should be lower than those experienced up to 20 years ago or more.
To take this into account, a factor of reduction of 0.1 is applied to the all the values given in
the Table 2.
The frequency of occurrence of the final scenario depends on the probability of ignition
(immediate or delayed). From technical literature, the following values for the probability of
ignition are considered:
• Immediate ignition of gas/flashing leaks: 0.3 – 0.01
• Immediate ignition of a liquid pool fire: 0.05 – 0.01
• Delayed ignition of flammable cloud: 0.15 – 0.01
• Probability that the delayed ignition will cause an UVCE: the possibility that an UVCE
occurs depend on the amount of flammable material in the cloud. It is considered
that for a quantity of gas within the flammable limits lower than 1000 kg, the UVCE
can not occur, and only a flash fire is considered. For quantity of gas within the
flammable limits higher than 1000 kg, the probability of having UVCE following
ignition is considered to be 0.3.
The frequency of occurrence of accidental scenarios is calculated by Event Tree analysis, on
the basis of estimation of the above values. The frequency of occurrence of the scenarios can
then be classified according e.g. to the classification given in Table 49.
On the basis of the above classification, events having a frequency of occurrence lower than
10-7 per year are considered to be practically not credible and are therefore not further
analyzed.
The frequency of occurrence of the Hazards identified is assessed as described in the
following sections.
page 105
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Frequency
Classification
(events/year)
Probable > 10-2
Unlikely 10-4 ÷ 10-2
Very unlikely 10-6 ÷ 10-4
Extremely unlikely < 10-6
General model
The scenarios that can derive in general from a release, leading to a given outcome, are
represented in the Figure 50. This path was followed while deriving scenarios for FCC
analysis.
page 106
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Hazardous
substance
Discharge
Liquid Explosion:
pool Condensed phase
Gas 2-phase Liquid
Runaway
reaction
Dust
Physical
Flash and rainout Evaporation
Dispersion
External
fire
Jet Dense Neutral
Outcome
page 107
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 108
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Damage estimates based on overpressure for process equipment (adjusted from CPS 2000)
are given in Table 51.
page 109
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The damage distances obtained by consequence analysis are summarized in the following
Table.
The analysis is done also if all scenarios have frequency of occurrence lower than 1E-7
events/year, practically not credible, to obtain an assessment of the damage distances
associated to a major release case.
Table 53: TOP1 – Release from FA-2514, scenario
page 110
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The damage distances obtained by consequence analysis are summarized in the following
Table. The analysis is done for scenarios having frequency of occurrence higher than 1E-7
events/year, being those having lower frequencies to be considered practically not credible.
Table 55: TOP2 – Release from DA-2503, scenario
page 111
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
(1)
LFL/2 112 LFL/2 -
(1)
Distances not calculated, being the scenario frequency lower than 1E-7 events/year, practically not
credible.
(2)
Damage distances are not calculated. The mass of gas within flammable limits is lower than 1000 kg
and the explosion is to be considered not credible.
The damage distances obtained by consequence analysis are summarized in the following
table.
The analysis is done for scenarios having frequency of occurrence higher than 1E-7
events/year, being those having lower frequencies to be considered practically not credible.
Table 57: TOP3 – Release from DA 2509, scenario
page 112
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
5D
(1)
LFL/2 112 LFL/2 -
(1)
Distances not calculated, being the scenario frequency lower than 1E-7 events/year, practically not
credible.
(2)
Damage distances are not calculated. The mass of gas within flammable limits is lower than 1000 kg
and the explosion is to be considered not credible.
page 113
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The damage distances obtained by consequence analysis are summarized in the following
Table.
The analysis is done for scenarios having frequency of occurrence higher than 1E-7
events/year, being those having lower frequencies to be considered practically not credible.
Table 59: Event 4 – Release from FA-2953, scenario
The damage distances obtained by consequence analysis are summarized in the following
Table.
The analysis is done for scenarios having frequency of occurrence higher than 1E-7
events/year, being those having lower frequencies to be considered practically not credible.
The distances given in the table refer to the concentration of H2S, that is the main
component of the mixture.
Table 61: EVENT 5 – Release from FA-2455, scenario
page 114
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
IDLH 670
• Overpressure of 0.05bar
• Damage of 90% glass
Atmospheric • Instrumentation
500 5 - 10 1200
distillation damage
• In worst case scenario,
about 10% damage
Command center 10 0.0
• Overpressure of 10kPa
(0.1bar).
• Damage of structures of
60%, process equipment
10%
Vacuum
distillation
1100 10 2400 • Metal frames slightly
moved
• Small amount of damage
inside; can be repaired
• Damage of light roof
constructions
• Overpressure of 15 kPa
(0.15 bar)
• Damage, but not
destruction of structures
• Glass and
FCC 11000 30 9000 instrumentation damaged
• Electrical cabling and
control equipment
damaged
• The inner part of the
cooling tower damaged
• Overpressure of 10kPa
(0.1bar).
• Structural damage of
60%, process equipment
of 10%
Sulphurisation 700 10 70 • Metal frames slightly
moved
• Small amount of damage
inside; can be repaired
• Damage of light roof
constructions
Alkylation 1000 100 1000 total damage
Total 14310 13670
page 115
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
VAR (k €) 20.505
The results of the hazard analysis are summarized in Annex 23. The following information
are given:
• initiating event
• accidental scenarios deriving from initiating event
• frequency of occurrence of accidental scenarios
• damage distances.
Organizational measures
The intended major maintenance period is every three years. In reality at the moment there
is a major maintenance shut down per year as the process has been modified to increase the
efficiency of the process. The modification can partly lead to erosion and corrosion. This has
to be controlled at the moment by a yearly inspection.
The pressure vessels will have an inside inspection every three years and every six years the
pressure will be tested. This inspection is based on a national law which is connected with EU
regulations.
It is not an obligation in Serbia but regarding the topic explosion protection the Risk
Management division has started to consider the requirements of the ATEX Directives. An
explosion protection document has been developed which has been submitted to the
Ministry. The exchange of the equipment in regard to the requirements of the ATEX Directive
will be done step by step. Furthermore the German TA Luft will be implemented.
The inspection is in the responsibility of the production and maintaining department of RNP
and planning of safety aspects is in the responsibility of the Risk Management department.
Lighting protection
Lightning is high frequency event in summer and has lead to two accidents in the past. About
10 years ago a safety valve has been fired by lightning and last year a burning flare has
been addressed by lightning.
The normal protection measure is earthing. The maintenance period for the control of the
protection measure is once a year as required by law. The measurement of the resistance
and continuity will be done. All safety valves are protected by steam extinguishers. This task
is from 2007. in the responsibility of Risk Management division and will be done by an
external party.
page 116
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
The exact starting point of the Bowtie Methodology has been lost in time but it is believed
that they were originally called “Butterfly diagrams” and evolved from the Cause
Consequence Diagram of the 1970s. It is then thought that David Gill of ICI plc developed
the methodology and called them bowties in the late 70’s. It is generally accepted that the
earliest mention of the bowtie methodology appears in the ICI Hazan Course Notes 1979,
presented by The University of Queensland, Australia.
Bowtie diagrams for FCC have been created for selected top events which are to be
prevented by
• analyzing threats that could cause the event to occur
• analyzing consequences of the event occurring
• using available controls to prevent the event occurring and
• using available controls to mitigate against the consequences
Table 63: Selected TOP events and scenario
The frequency of occurrence of scenarios is assessed according to the classes given in table :
page 117
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
are experienced. It shall be noted that the definition of severity considers major hazards
having a potential impact on the population, as required by the Seveso II directive.
Table 64: Definition of Frequency Classes
Frequency
Classification Scenario
(events/year)
PROBABLE > 10-2
UNLIKELY 10-4 ÷ 10-2
VERY UNLIKELY 10-6 ÷ 10-4 S10, S11
-6
EXTREMELY UNLIKELY < 10 S1 – S9
Effects limited to the plant personnel are therefore in this context considered as not defining
a major hazards. These are assessed and controlled by Occupational Health procedures and
analyzes.
Table 65: Definition of consequence severity classes
Classification Damage
On the basis of the above definition, the risk associated to each scenario can be assessed as
in the following Risk Matrix, where three levels of risk are sown: an High risk area (in red)
where prevention and protection measures shall be considered to reduce the risk, a Medium
Risk area (in yellow) where prevention and protection measures should be considered to
reduce the risk, a Low risk area (in green) where the risk can be considered to be tolerable
and no further measures are necessary.
Major
Extremely
unlikely Very unlikely unlikely Probable
2.7.6 Conclusions
page 118
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 119
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
4 References
[1] Contract No: 45/609 of September 8, 2006
[2] API RP 581, Risk-Based Inspection Technology, Second edition, September 2008
[3] CEN CWA 15740 RIMAP, 2008
[4] HSE RNP, Implementation of HSE in NIS a.d. Plants NIS RNP Safety report, May 2008
[5] Understanding explosions (2003) By Daniel A. Crowl. Center for Chemical Process Safety of the
AIChE, Journal of Loss Prevention in the Process Industries, Volume 16, Issue 5, Page 449
[6]
page 120
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
5 Annexes
page 121
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 122
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 123
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 124
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 125
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 126
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 127
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 128
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
RNS Director
Director’s Office
Secretariat
Business Coord.
Technical-Technological Department
Department
Information and
Production PR Service
Center for MS
Manipulation
Maintenance
Laboratory Development and Risk Management Legal, personnel and
Investment General Affairs
Power Plant
page 129
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
5.4 Planning
Setting quality objectives at
certain functions and levels
top management, within the organization,
5.4.1 Quality objectives
management representative measuring quality objectives,
compliance with quality policy
and constant improvement
page 130
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
6. RESOURSE MANAGEMENT
Provision of resources
organizational parts
- defining required
managers Defining and providing required
6.1 resources
resources
- provision of required
RNS director
resources
6.2 Human resources
- general provisions, (staff
6.2.1 RNS director Ensuring staff is competent
allocation)
based on adequate qualifications,
top management training, knowledge and
- qualification, awareness
6.2.2 head of the Personnel experience
and training
Section
Infrastructure
- defining required top management
infrastructure and its Operations director Defining, establishing and
6.3 maintenance maintaining infrastructure
- establishment of the
RNS director
required infrastructure
Defining and managing human
6.4 Working environment top management and physical factors of working
environment
7. PRODUCTS REALIZATION
Planning and development of
Planning of products
7.1 top management processes required for products
realization
realization
page 131
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
management
Contrinuous rating of QMS
8.2.2 Internal audit representative,
compliance and effectiveness
MSC manager
Monitoring and measuring Showing processes abilities to
8.2.3 top management
processes performances achieve planned results
Director of technical and
technological operations,
Director of Operations
Verification of requests for
Monitoring and measuring Director of Handling Dept
8.2.4 products (controlling,
products characteristics Director of Laboratory
examination, monitoring)
Director of Department for
Materials Flow Management
(MFM)
Director of technical and
technological operations,
Managing inconsistencies Analysis and treating
8.3 Director of Operations
in a product inconsistencies in a product
Director of Handling Dept
page 132
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
4.3 Planning
top management, Identification of important
4.3.1 Environmental aspects MS management environmental aspects,revision
representative and constant updating.
page 133
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
ISO
Requirement Function/job position Comment
14001
4.5 Revision
Establishing, application and
maintenance of regular
monitoring and measuring
procedures of crucial operations
EMS coordinator characteristics that may have an
(Environmental Dept important influence on
4.5.1 Montoring and measuring manager) environment and information
MS management documentation.
representative, Ensuring that calibrated and
verified equipment is used ofr
monitoring and measuring,
keeping records of related
documentation.
EMS coordinator Establishing, application and
4.5.2 Compliance evaluation
(Environmental Dept maintenance of procedures of
page 134
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
ISO
Requirement Function/job position Comment
14001
page 135
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 136
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 137
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 138
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 139
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
D-300 D-101 T-1 T-101 T-9 D-16 E-102 E-101 A/B E-2 E-1 A/B E-120 D-120 D-102 T-2 E-104 E-3 D-1 E-5 D-104 E-103 E-6 A/B E-7 D-5 D-103 E-15 D-121 D-4 E-116 E-4 C-1,2 A/B C-102 D-122 F-1; F-201 E-24 A/B T-3 E-9 E-11 E-10 E-12 E-16 E-17 D-6 E-18 T-7 D-7 E-20 A/B T-8 E-21 E-22 E-23 D-8 F-302
F-301 E-110 SC-1 T-4 D-2 E-19
TROFAZNI SEPARATOR DEHIDRATACIONA DEHIDRATACIONA KOLONA ZA SEPARATOR PROPANSKI PROPANSKI PROPANSKI SEPARATOR SEPARATOR APSORBER PROPANSKI PRIHVATNI IZMENJIVAC SEPARATOR PROPANSKI PROPANSKI PRIHVATNI PRIHVATNI VODENI CENTRIFUGALNI SEPARATOR ZA PRIHVATNA VODENI VODENI KOMPRESORI KOMPRESOR KOALESCER PEC DEETANIZER RIBOJLER KONDENZATOR IZMENJIVAC RIBOJLER PRIHVATNA IZMENJIVAC PRIHVATNA POSUDA ZA KONDENZATOR DEIZOBUTANIZER RIBOJLER VODENI KONDENZATOR PRIHVATNA FILTER ZA
FILTER ZA IZMENJIVAC IZMENJIVAC IZMENJIVAC IZMENJIVAC IZMENJIVAC PROPANSKI IZMENJIVAC IZMENJIVAC DESTILATOR PRIHVATNA DEBUTANIZER RIBOJLER
SEPARATOR POSUDA KOLONA POSUDA HLADNJAK HLADNJAK HLADNJAK POSUDA POSUDA HLADNJAK SUD TOPLOTE POSUDA HLADNJAK HLADNJAK SUD ZA SUD ZA PARE HLADNJAK RABLJENO ULJE POSUDA ZA HLADNJAK HLADNJAK WEIR KLARK COOPER-BESSEMER TOPLOTE POSUDA ZA TOPLOTE HLADNJAK POSUDA ZA SIROVI
GASNI TOPLOTE KOLONA SUŠENJE TOPLOTE TOPLOTE TOPLOTE TOPLOTE SEPARATOR HLADNJAK TOPLOTE TOPLOTE POSUDA SMEŠU N-BUTANA I
PROPAN PROPANA PROPAN PROPAN IZO-BUTAN GAZOLIN
KONDENZAT KONDENZATA IZO-BUTANA
1
E-103 PRC
PRC
151 3
LC
131 E-20A E-20B
HCV
150
E-12 E-18
HO HO E-1A E-120 I C-102 II 1
1
D-5 PREMA PREMA
E-24A E-8
TIC
T-5 D-9
LCV 4A
FI
2 PIC 200.1 13
7 E-23
210 LC 8 1 1
LCV TRC FI 9
TRC
T-9 152A 152 200.2
PRC PRC
151
LC
4
E-1B TIC 19 9
E-104
204 T-3 FRC PRC 9 TRC
1 1 1 E-6A FRC
6 9 4 10
KA T -3 PC T-6
E-110 5 E-24B E-9
15
HIC
150 PRC
PREMA TS
PRC
T-7 8
PC 1
301 T-101 E-2
PC
TIC 18
16
TS FRC
13
7
E-2 E-3 4B E-110 150 10
T-1 E-7
6 TIC
6
25
PCV FRC
301B E-6B E-11 FRC 13
19 11 29
10 LC od C-2A C-1A C-2B C-1B F-201
T-8
PCV
D-120 151
D-104 LC
E-2
23
19
6 208
301A
C3 E-3 24
CW FRC
C3 C3 E-7 7
26
LC
1
LC
154
E-102 35 D-8
FIQ
E-7 C-2A C-1A C-2B C-1B E-116 T-4 D-7
102
T-2 E-3 LC D-2 F-1 35 D-6 E-22
PCV
24
E-4 29 30 10
OD/PREMA
PRC CW CW TRC
PREMA E-5
152 TRC 9
C-1A/B 8
UV
154
E-101A E-5
C3 C3
D-101 LC LC od E-4
TRC
E-19 E-21
C3 35
5
2 152 TRC CW
3 E-10 LC
LI LC
D-103 E-15 8
LC
101 LC LC
D-16 19 19
13
3 153
LC
E-101B LC CW CW
LG SC-1
LG D-121 D-4 LC 11
155
GS ELEMIR
156 7
20 5 LC
LI TRC SV TRCAH
129 7 7 160
LCV
LC
D-1 6
101 D-102 114 TSH
163 FRC
14
E-102 FRC
FS
8
SV
6
P RCA
160
5
LS
157
FRC
PREMA E-2 PREMA E-3 PREMA E-7 8
TRC PRIHVATNA POSUDA ZA RABLJENO ULJE
LOŽIVI GAS
128 C3
KA D -9
ULAZNA ŠAHTA
PRERAÐENI
FIQ
103
GAS
AS
150
FIQ
D-122 NORMALNI
IZOBUTAN
LCV BUTAN
OD
101 F-302 PS-4 GAZOLIN PROPAN
D-9 SMEŠA SMEŠA
U PRELIVNI PREMA PENTANA P-9A/B BUTANA
GR-1/GR-102
OD E-25
P-120A/B P-1A/B/C P-11 P-7A/B P-8A/B
ŠAHT P-2A/B P-4A/B/C P-5A/B
LAH LAL LIC
D-300 301 301 301 P- 30
F-301
SIROVI GAZOLIN IZ
PROIZVODNIH
REZERVOARA
Legenda:
24.08. 2006
Propan U PRELIVNI
N-butan D-27A
ŠAHT Jašin/Subotin
Izobutan
Gazolin
Prirodni gas
S.Josipovic
Preradeni gas
A.Ilic
Apsorpciono ulje Projektni zadatak za izr. URP
Kondezat ugljovodonika
Toplo ulje rekonstr. sist. za prikupljanje i spaljivanje
Rashladni propan
Bogato ulje
fluida u pogonu za proizv. NTG El.
Rashladna voda
NIS Naftagas
TEHNOLOŠKA ŠEMA POGONA TNG
TEG
Loživi gas 1
Pogon za proizv. NTG ELEMIR
page 140
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 141
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 142
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 143
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 144
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 145
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 146
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Oznaka NIS-
Drawing Title Design Drawing designation
RNP
complex
page 147
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Oznaka NIS-
Drawing Title Design Drawing designation
RNP
Condensate collection and
FW 2231-0-50-2512.F LO 03A18A
blowdown systems. FCC complex
Steam distribution. HP steam. MP
FW 2231-0-50-2513.E LO 03A18A
steam. FCC complex
FCC Process. LP steam system. FCC
FW 2231-0-50-2514.D LO 03A18A
complex
FCC Process. Cooling water supply.
FW 2231-0-50-2515.D LO 03A18A
FCC complex
Plant air. Instrument air. Flashed
condensate. Boiler feed water. FCC FW 2231-0-50-2516.E LO 03A18A
complex
page 148
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Oznaka NIS-
Drawing Title Design Drawing designation
RNP
water wash. FCC complex
page 149
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Columns in FCC
Sirovi benzin
DA-2301 Vrh
V=600 Lako ciklično plinsko ulje; 350oC 3,2/ 89,5
Fractionation column G/F
H=42 Međuciklično plinsko ulje; Dno 3,5 m3/h
D= 4,5 560oC
Produkt dna kolone
DA-2302 Vrh
V=60m3 Striper ICGO Međuciklično plinsko ulje 390oC 61
F 3,5
H=10 Međuciklično plinsko ulje ICGO Dno m3/h
D=2,2m 430oC P
Vrh
DA-2303
Striper LCGO LCGO (lako ciklično plinsko 270oC 123,8
V=35m3, F 3,5
(lako ciklično plinsko ulje) ulje) Dno m3/h
H/D=8m/1,5m
300oC
DC-2301 138,8
Reaktor - striper Vakuum plinsko ulje F 512 2,52
V=350m3, m3/h
DC-2302 Reaktor – regenerator 590-
Katalizator, koks, CO,CO2 S/G 1,7 -
V=700m3, katalizatora 730
FE-2301,
Ciklon posude regeneratora i
FE-2302 Katalizator vazduh 400 4 -
reaktora za katalizator
V=250m3,
page 150
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Heat exchangers
EA- plinsko ulje Plašt izmenjivača Vakuum EA- plinsko ulje 300/240
300/240 20/24
2301A/B Cevni snop izmenjivača LCGO (Lako cik. plin. ulje) 20/24
Vakuum
EA- Plašt izmenjivača 340/290
plinsko ulje 340/290 12/24 138,8
2302A/B F 12/24 P
Cevni snop izmenjivača Refluks m3/h
page 151
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
LCGO (Lako
GA–2308/S LCGO refluks pumpa ciklično plinsko F 210 10 320
ulje)
GA–2309/S Uljna pumpa apsorbera Benzin F 45 20 70
Pumpa za LCGO gotov LSGO (Lako
GA-2310/S F 250 13 80
proizvod ciklično plinsko ulje)
Pumpa za refluks
GA–2311/S benzin F 140 8 165
frakcionatora DA-2301
Pumpa za vršne produkte F
GA–2312/S frakcionatora (iz posude FA- benzin 50 20 150
2304)
Rezervoar za smešu
FA – 2305 Loživi gas G 72 7,03 8
gasovaloživi
page 152
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
gas
FA - 2308 Posuda za dekoksovano VPO vakuum pl. ulje F T 345 8,5 4
FA - 2310 Posuda za TNG TNG G 72 8,8 50
Furnaces
Vakuum plinsko 138
BA– 2301 Peć postrojenja S-2300 F 420 20
ulje m3/h
BA-2302 Rebojler ICGO Loživi gas, ICGO f 420 24 340 -
BF-2301 CO bojler CO, CO2 G 450 14 -
BC-2301 Peć za grejanje vazduha Lož ulje G/F 420 420 10 -
page 153
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 154
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 155
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Annex I, Part 1
1
Ammonium nitrate 2500 / / /
/ / /
2
Ammonium nitrate 5000 / / /
/ / /
Arsenic pentoxide, arsenic (V)
2 / / /
acid and/or salts
/ / /
Arsenic trioxide, arsenious (III)
0,1 / / /
acid and/or salts
/ / /
Bromine 100
Chlorine 25
Ethyleneimine 20
Fluorine 20
Formaldehyde (concentration
50
90 %)
1
1 This applies to ammonium nitrate and ammonium nitrate compounds in which the nitrogen content
as a result of the ammonium nitrate is more than 28 % by weight (compounds other than those
referred to in Note 2) and to aqueous ammonium nitrate solutions in which the concentration of
ammonium nitrate is more than 90 % by weight.
2
This applies to simple ammonium-nitrate based fertilizers which comply with Directive 80/876/EEC
and to composite fertilizers in which the nitrogen content as a result of the ammonium nitrate is
more than 28% in weight (a composite fertilizer contains ammonium nitrate with phosphate and/or
potash).
page 156
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Hydrogen 50 5.72
All units 33.3
Hydrogen chloride (liquefied
250
gas)
Lead alkyls 50
Acetylene 50
Ethylene oxide 50
Propylene oxide 50
Methanol 5000
4, 4-Methylenebis (2-
chloraniline) and/or salts, in 0.01
powder form
Methylisocyanate 0.15
Oxygen 2000 /
Gaseous oxygen /
Toluene diisocyanate 100 64.8
Toluen 64.8
Carbonyl dichloride (phosgene) 0.75
Phosphorus trihydride
1
(phosphine)
Sulphur dichloride 1
Sulphur trioxide 75
page 157
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Polychlorodibenzofurans and
polychlorodibenzodioxins
0.001
(including TCDD), calculated in
TCDD equivalent
Gazoline 99.6
Other gasoline 9597.31
Annex I Part 2
1. Very toxic 20
0.62
2. Toxic 200
422.2
3. Oxidizing 200
page 158
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
7121.41
9b.- DANGEROUS FOR THE
2000
ENVIRONMENT (R51/53)
1.08
10. OTHER CATEGORIES not
covered by those given above in
500
combination with risk phrases:
(i) R14/15)
page 159
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 160
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 161
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 162
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Annex 22 Damage estimates based on overpressure for process equipment (adjusted from
CPS 2000)
Overpressure
Equipment psi 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 12 14 16 18 20
0.0 0.0 0.1 0.1 0.1 0.2 0.2 0.2 0.3 0.3 0.3 0.4 0.4 0.4 0.5 0.5 0.5 0.6 0.6 0.6 0.8 0.9 1.1 1.2 1.3
bar
34 69 03 38 72 07 41 76 10 45 79 14 48 83 17 52 86 21 55 90 28 66 03 41 79
Instrument Cubicle A LM T
Fire heater G I T
Reactor: chemical A I P T
Filter – Filter H F V T
Regenerator I IP T
Reactor: cracking I I
Pine supports P SO
page 163
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Overpressure
Equipment psi 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 7.5 8 8.5 9 9.5 10 12 14 16 18 20
0.0 0.0 0.1 0.1 0.1 0.2 0.2 0.2 0.3 0.3 0.3 0.4 0.4 0.4 0.5 0.5 0.5 0.6 0.6 0.6 0.8 0.9 1.1 1.2 1.3
bar
34 69 03 38 72 07 41 76 10 45 79 14 48 83 17 52 86 21 55 90 28 66 03 41 79
Utilities: electronic
H I
transformer
Electric motor H I V
Blower – Duvaljke Q T
Fractionation colum R T
Pressure vessel:
PI T
horizontal
Utilities: gas regulato I MQ
Extraction column I V T
Steam Turbine I M S V
Heat exchanger I T
Tank sphere I I T
Pressure vessel:
I T
vertical
Pump I V
Legend:
A - Windows and gauges broken G - Brick cracks M - Controls are damaged S - Piping breaks
B - Louvers fall at 0.2 - 0.5 psi H - Debris-missile damage occurs N - Block walls fall T - Unit overturns or is destroyed
C - switch gear is damaged from roof collapse I - Unit moves and pipes breaks O - Frame collapses U - Unit uplifts (0.9 tilted)
D - Roof collapses J - Bracing falls P - Frame deforms V - Unit moves on foundation
E - Instruments are damaged K - Unit uplifts (half tilted) R - Frame cracks
F - Inner parts are damaged L - Power lines are severed Q - Case is damaged
page 164
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 165
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Consequences
Frequency Damage distance
Occurrence Explosion Dispersion Toxic/
Nr. Event of the Data Accident Scenario (m)
frequency overpressure Flammable
event Fire heat radiation
(bar) threshold
(kW/m2)
37.5 - LC50 -
Mass in flammable
5. VCE 12.5 - condition IDLH -
-
(delayed ignition) 7 - < 1000 kg. LFL -
VCE is not credible.
5 - 1/2 LFL -
37.5 - 0.3 - LC50 -
page 166
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Consequences
Frequency Damage distance
Occurrence Explosion Dispersion Toxic/
Nr. Event of the Data Accident Scenario (m)
frequency overpressure Flammable
event Fire heat radiation
(bar) threshold
(kW/m2)
7 - 0.07 - LFL 85
5 - 0.03 - 1/2 LFL 112
37.5 7 0.3 - LC50 -
Substance: 1100
37.5 - 0.3 - LC50
H2S + CO2 + (1.5F)
Leak of toxic gas from SO2 360
TOP7 combustion chamber 1E-5 Ø leak: 100 17. Toxic dispersion 1E-5 12.5 - 0.14 - IDLH
(1.5F)
FA-2455 mm
Release 7 - 0.07 - LFL -
height: 1 m 5 - 0.03 - 1/2 LFL -
page 167
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 168
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 169
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Error in material /
design
Fire detection
discovering
Shielding
corrosion
defects Thermal
Fire jet
effects
Disturbances
in the process
Shutdown system
monitoring
Vibration
Gas detection
Disturbances Corrosion
in the process fatigue Discharge
Jet fire
2-phase
Blast design
Disturbances
in the process
Maintenance
Jet Environment
VCE
Fatigue, dispersion effects
thermal Material /
Error in material / fatigue
SMS
Structural
design Pressurized
related
leak
problems
design
Overloadin Pool
Flash Thermal
g explosion
Disturbances in effects
Shutdown system
the process
Inspection
Environment
SMS
structural Leakage from VCE
damage DA-2509 effects
Repair / errors
mechanism
Acces control
Emergency planning
Fire fighting system
Fire detection
Sabotage
Shielding
Thermal
Pool fire
effects
Mistake in
process Man made
Procedures
Acces control
disturbance
Mistake in s
maintenance
PPE Person hit by
jet flow
protection system
Acces control
Functional /
Mistake in
SMS
Functional Other
Proactive
transport / Fire,
related incident
explosion
loading problems
and similar
Shield-ing
page 170
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Error in material /
design
Fire detection
discovering
Shielding
corrosion
defects Thermal
Fire jet
effects
Disturbances
in the process
Shutdown system
monitoring
Vibration
Gas detection
Disturbances Corrosion
in the process fatigue Discharge
Jet fire
2-phase
Blast design
Disturbances
in the process
Maintenance
Jet Environment
VCE
Fatigue, dispersion effects
thermal Material /
Error in material / fatigue
SMS
Structural
design Pressurized
related
leak
problems
design
Overloadin Pool
Flash Thermal
g explosion
Disturbances in effects
Shutdown system
the process
Inspection
Environment
SMS
structural Leakage from VCE
damage DA2503 effects
Repair / errors
mechanism
Acces control
Emergency planning
Fire fighting system
Fire detection
Sabotage
Shielding
Thermal
Pool fire
effects
Mistake in
process Man made
Procedures
Acces control
disturbance
Mistake in s
maintenance
PPE Person hit by
jet flow
protection system
Acces control
Functional /
Mistake in
SMS
Functional Other
Proactive
transport / Fire,
related incident
explosion
loading problems
and similar
Shield-ing
page 171
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 172
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 173
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 174
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 175
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
page 176
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Pressure
D-102 trofazni separator 1969 2009 High 2 0.5 1 1 1
vessel
kolona za sušenje
T-101 Column 1988 2009 High 2 0.5 1 1 1
gasa
prečistač posnog
T-5 Column 1962 2009 High 2 0.5 1 1 1
ulja
Pressure
D-101 separator 1962 2009 Medium High 4 1 1 1 1
vessel
Pressure
D-1 prihvatni sud 1962 2009 Medium High 5 1 1 1 1
vessel
Pressure
D-300 trofazni separator 2000 2009 Medium High 5 1 1 1 1
vessel
page 177
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Recommended Recommended
Component Service Start Evaluation Inspection Interval Inspection
Name Description Risk 2009 2010 2011
Type Date Date (Class A inspection Interval (Class D
type) inspection type)
Pressure
D-103 međusakupljač 1962 2009 Medium 7 2 1
vessel
Pressure
D-104 trofazni separator 1962 2009 Medium 7 2 1
vessel
Pressure
D-11 posuda 1962 2009 Medium 7 2 1
vessel
Pressure
D-111 posuda 1962 2009 Medium 7 2 1
vessel
Pressure
D-112 posuda 1962 2009 Medium 7 2 1
vessel
Pressure
D-12 posuda 1962 2009 Medium 7 2 1
vessel
Pressure
D-120 separator 1962 2009 Medium 7 2 1
vessel
Pressure
D-121 separator 1962 2009 Medium 7 2 1
vessel
Pressure
D-122 separator 1962 2009 Medium 7 2 1
vessel
Pressure
D-16 trofazni separator 1962 2009 Medium 7 2 1
vessel
Pressure
D-2 sakupljač refluksa 1962 2009 Medium 7 2 1
vessel
page 178
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Recommended Recommended
Component Service Start Evaluation Inspection Interval Inspection
Name Description Risk 2009 2010 2011
Type Date Date (Class A inspection Interval (Class D
type) inspection type)
Pressure
D-27A rezervoar 1963 2009 Medium 7 2 1
vessel
Pressure
D-27D rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-27F rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-28A rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-28B rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-28C rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-28D rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-28E rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-28F rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-28G rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-29A rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-29B rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-29C rezervoar 1962 2009 Medium 7 2 1
vessel
Pressure
D-4 prihvatni sud 1962 2009 Medium 7 2 1
vessel
Pressure
D-5 isparivač 1962 2009 Medium 7 2 1
vessel
page 179
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Recommended Recommended
Component Service Start Evaluation Inspection Interval Inspection
Name Description Risk 2009 2010 2011
Type Date Date (Class A inspection Interval (Class D
type) inspection type)
vessel
Pressure
D-7 sakupljač refluksa 1962 2009 Medium 7 2 1
vessel
Pressure
D-8 sakupljač refluksa 1962 2009 Medium 7 2 1
vessel
Pressure
D-9 prihvatni sud 1962 2009 Medium 7 2 1
vessel
Pressure
D-27B rezervoar 1962 2009 Medium 8 2 1
vessel
Pressure
D-27C rezervoar 1962 2009 Medium 8 2 1
vessel
Pressure
D-27E rezervoar 1962 2009 Medium 8 2 1
vessel
Boiler -
Furnace Tubes
E-10 rebojler 1962 2009 Medium 8 2 1
for Fired
Heater
Heat
E-104 izmenjivač lote 1962 2009 Medium 8 1 1 1 1
Exchanger
Boiler -
Furnace Tubes
E-11 predgrejač 1962 2009 Medium 8 2 1
for Fired
Heater
Heat
E-110 izmenjivač 1962 2009 Medium 8 1 1 1 1
Exchanger
Heat
E-113 izmenjivač 1962 2009 Medium 8 1 1 1 1
Exchanger
page 180
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Recommended Recommended
Component Service Start Evaluation Inspection Interval Inspection
Name Description Risk 2009 2010 2011
Type Date Date (Class A inspection Interval (Class D
type) inspection type)
Exchanger
Heat
E-120 1962 2009 Medium 8 1 1 1 1
Exchanger
Heat
E-14 izmenjivač lote 1962 2009 Medium 8 1 1 1 1
Exchanger
kondenzator
E-15 Condenser 1962 2009 Medium 8 1 1 1 1
propana
Heat
E-16 predgrejač 1962 2009 Medium 8 1 1 1 1
Exchanger
Boiler -
Furnace Tubes
E-17 rebojler 1962 2009 Medium 8 2 1
for Fired
Heater
Boiler -
Furnace Tubes
E-19 rebojler 1962 2009 Medium 8 2 1
for Fired
Heater
Boiler -
Furnace Tubes
E-21 rebojler 1962 2009 Medium 8 2 1
for Fired
Heater
page 181
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Recommended Recommended
Component Service Start Evaluation Inspection Interval Inspection
Name Description Risk 2009 2010 2011
Type Date Date (Class A inspection Interval (Class D
type) inspection type)
Heat
E-25 izmenjivač lote 1962 2009 Medium 8 1 1 1 1
Exchanger
Heat
E-5 izmenjivač lote 1962 2009 Medium 8 1 1 1 1
Exchanger
Heat
E-6A/B izmenjivač lote 1962 2009 Medium 8 1 1 1 1
Exchanger
Boiler -
Furnace Tubes
E-9 međubojler 1962 2009 Medium 8 2 1
for Fired
Heater
Heat
E-101/A izmenjivač lote 1963 2009 Low 10 1 1 1 1
Exchanger
Heat
E-101/B izmenjivač lote 1963 2009 Low 10 1 1 1 1
Exchanger
Heat
E-1A/B izmenjivač lote 1962 2009 Low 10 1 1 1 1
Exchanger
Filter sa aktivnim
FT-104 Filter 1962 2009 Low 10 1 1 1 1
ugljem
Other
HP-1 Hidroforska posuda 1962 2009 Low 10 3 1
Equipment
page 182
STEINBEIS ADVANCED RISK TECHNOLOGIES GmbH
Recommended Recommended
Component Service Start Evaluation Inspection Interval Inspection
Name Description Risk 2009 2010 2011
Type Date Date (Class A inspection Interval (Class D
type) inspection type)
Equipment
Other
JI-1 Jono izmenjivač 1962 2009 Low 10 3 1
Equipment
Other
JI-2 Jono izmenjivač 1962 2009 Low 10 3 1
Equipment
Peščani filter-bočna
PF-2 Filter 1962 2009 Low 10 1 1 1 1
filtrac.
Other
SP-1 Posuda za so 1962 2009 Low 10 3 1
Equipment
Total to be inspected: 51 94 56
page 183