Consider the network given, complete the analysis table shown below and indicate the
critical path. (15 marks)
Determine the total float (in days) of activities Q, T and U. (10 marks)
3. QUESTION THREE
The table below lists the lead times (in weeks) for each operation in a typical housing unit. The
operations may be assumed to be in series as shown below. (10 marks)
Operation Lead times (weeks)
1 Substructure 14
2 Brick work 12
3 Roof Carpenter 9
4 Roof Tiler 7
5 Joinery 6
6 Electrician 5
7 Plumber 3
8 Decorator 2
If 50 such units are to be constructed having a handover rate of 5 houses per week. Determine
the number of units that are planned to have brickwork and joinery completed at week 10
respectively.
SECTION B
4. QUESTION FOUR
The main disadvantage of line organization is; (2 marks)
A) Rigid structures
B) Top level execution over work
C) Extra ordinary delay in communication
D) All the above
5. QUESTION FIVE
The main advantage of line organization is: (2 marks)
A) Rigid discipline in the organization
B) Ability of quick decisions at all levels
C) Clearly defined responsibilities at all levels
D) All the above
6. QUESTION SIX
Consider the following statements in bar chart planning (2 marks)
1. Interdependence of the activities cannot be portrayed
2. Progress of work can be measured
3. Spare time of the activities can be determined
of these statements
A) 1, 2 and 3 are correct
B) 1 is correct
C) 2 and 3 are correct
D) 1 and 2 are correct
7. QUESTION SEVEN
If the total float and duration of an activity are 6 and 12 days respectively., the particular activity
can be. (2 marks)
A) Started 6 days later
B) Completed 6 days later
C) Performed at a slower rate in 18 days
D) All the above.
8. QUESTION EIGHT
Choose the correct statement below (2 marks)
A) The critical path consumes the maximum time
B) The activities connecting the events having zero slack lie on the critical path.
C) The difference of the latest occurrence time and earliest expected time is called slack.
D) All above
9. QUESTION NINE
If the optimistic time, most likely time and pessimistic time for an activity A are 40,60 and
80 hours respectively and for activity B are 50,55 and 90 hours respectively, then.
A) Expected time of activity A is greater than expected time for activity B
B) Expected time of activity B is greater than the expected time of activity A
C) Expected time of both activities A and B are the same
D) None of the above. (2 marks)