June 03 - August 16, 2022
June 03 - August 16, 2022
June 03 - August 16, 2022
Division of Work Finish Work Percentage (%) Division of Work Finish Work Percentage (%)
STRUCTURAL 57% STRUCTURAL 79%
Ground Floor 88% Ground Floor 100%
Foundation 100% Foundation 100%
Flooring 100% Flooring 100%
Walling 100% Walling 100%
Service Area and Comfort Room 50% Service Area and Comfort Room 100%
Carport and Septic tank 0% Carport and Septic tank 0%
2nd Floor 94% 2nd Floor 100%
Steel Deck 100% Steel Deck 100%
Slab 100% Slab 100%
Shear Wall 100% Shear Wall 100%
Comfort Room 75% Comfort Room 100%
Plumbing 75% Plumbing 75%
Ground (Plumbing ang Fixtures) 75% Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75% 2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 25% Plastering and Clearing 100%
Roof 60% Roof 100%
Roof Framing 100% Roof Framing 100%
Roofing 20% Roofing 100%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 42%
Wiring and Provision 0%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 17%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 50%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 16%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 20%
2nd Floor Partition 20%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 15%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 25%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 48%
Wiring and Provision 20%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 12%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 47%
Wiring and Provision 20%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 20%
Block 3 Unit 2 62%
Division of Work Finish Work Percentage (%)
STRUCTURAL 79%
Ground Floor 100%
Foundation 100%
Flooring 100%
Walling 100%
Service Area and Comfort Room 100%
Carport and Septic tank 0%
2nd Floor 100%
Steel Deck 100%
Slab 100%
Shear Wall 100%
Comfort Room 100%
Plumbing 75%
Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100%
Roof 100%
Roof Framing 100%
Roofing 100%
ARCHITECTURAL 24%
Doors 25%
Windows 25%
Staircase (Contractor) 50%
Tile Works (Contractor) 0%
Celing 50%
2nd Floor Partition 20%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 83%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 50%
ARCHITECTURAL 22%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 70%
2nd Floor Partition 25%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 12%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 50%
Wiring and Provision 25%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 12%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 47%
Wiring and Provision 20%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 20%
Block 3 Unit 3 63%
Division of Work Finish Work Percentage (%)
STRUCTURAL 79%
Ground Floor 100%
Foundation 100%
Flooring 100%
Walling 100%
Service Area and Comfort Room 100%
Carport and Septic tank 0%
2nd Floor 100%
Steel Deck 100%
Slab 100%
Shear Wall 100%
Comfort Room 100%
Plumbing 75%
Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100%
Roof 100%
Roof Framing 100%
Roofing 100%
ARCHITECTURAL 34%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 90%
Celing 100%
2nd Floor Partition 20%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 16%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 25%
2nd Floor Partition 20%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 14%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 20%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 72%
Wiring and Provision 90%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 12%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 47%
Wiring and Provision 20%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 20%
Block 3 Unit 4 58%
Division of Work Finish Work Percentage (%)
STRUCTURAL 79%
Ground Floor 100%
Foundation 100%
Flooring 100%
Walling 100%
Service Area and Comfort Room 100%
Carport and Septic tank 0%
2nd Floor 100%
Steel Deck 100%
Slab 100%
Shear Wall 100%
Comfort Room 100%
Plumbing 75%
Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 100%
Roof 100%
Roof Framing 100%
Roofing 100%
ARCHITECTURAL 21%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 70%
2nd Floor Partition 20%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 14%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 25%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 75%
Wiring and Provision 100%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 12%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 55%
Wiring and Provision 40%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 25%
ARCHITECTURAL 12%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 10%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 47%
Wiring and Provision 20%
Box setting and Piping 100%
Fixtures (Outlet and Switch) 20%
Block 4 Unit 19 37%
Division of Work Finish Work Percentage (%)
STRUCTURAL 59%
Ground Floor 88%
Foundation 100%
Flooring 100%
Walling 100%
Service Area and Comfort Room 50%
Carport and Septic tank 20%
2nd Floor 100%
Steel Deck 100%
Slab 100%
Shear Wall 100%
Comfort Room 100%
Plumbing 75%
Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10%
Roof 63%
Roof Framing 100%
Roofing 25%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
Block 4 Unit 20 35%
Division of Work Finish Work Percentage (%)
STRUCTURAL 53%
Ground Floor 88%
Foundation 100%
Flooring 100%
Walling 100%
Service Area and Comfort Room 50%
Carport and Septic tank 20%
2nd Floor 88%
Steel Deck 100%
Slab 100%
Shear Wall 100%
Comfort Room 50%
Plumbing 75%
Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10%
Roof 38%
Roof Framing 50%
Roofing 25%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
Block 4 Unit 40 0%
Division of Work Finish Work Percentage (%)
STRUCTURAL 0%
Ground Floor 0%
Foundation 0%
Flooring 0%
Walling 0%
Service Area and Comfort Room 0%
Carport and Septic tank 0%
2nd Floor 0%
Steel Deck 0%
Slab 0%
Shear Wall 0%
Comfort Room 0%
Plumbing 0%
Ground (Plumbing ang Fixtures) 0%
2nd Floor (Plumbing and Fixtures) 0%
Plastering and Clearing 0%
Roof 0%
Roof Framing 0%
Roofing 0%
ARCHITECTURAL 0%
Doors 0%
Windows 0%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 0%
Stone laying 0%
Painting 0%
ELECTRICAL 0%
Wiring and Provision 0%
Box setting and Piping 0%
Fixtures (Outlet and Switch) 0%
Block 4 Unit 21 35%
Division of Work Finish Work Percentage (%)
STRUCTURAL 53%
Ground Floor 88%
Foundation 100%
Flooring 100%
Walling 100%
Service Area and Comfort Room 50%
Carport and Septic tank 20%
2nd Floor 88%
Steel Deck 100%
Slab 100%
Shear Wall 100%
Comfort Room 50%
Plumbing 75%
Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10%
Roof 38%
Roof Framing 50%
Roofing 25%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
Block 4 Unit 22 35%
Division of Work Finish Work Percentage (%)
STRUCTURAL 53%
Ground Floor 88%
Foundation 100%
Flooring 100%
Walling 100%
Service Area and Comfort Room 50%
Carport and Septic tank 20%
2nd Floor 88%
Steel Deck 100%
Slab 100%
Shear Wall 100%
Comfort Room 50%
Plumbing 75%
Ground (Plumbing ang Fixtures) 75%
2nd Floor (Plumbing and Fixtures) 75%
Plastering and Clearing 10%
Roof 38%
Roof Framing 50%
Roofing 25%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 40%
Wiring and Provision 20%
Box setting and Piping 80%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
ARCHITECTURAL 11%
Doors 25%
Windows 25%
Staircase (Contractor) 0%
Tile Works (Contractor) 0%
Celing 0%
2nd Floor Partition 0%
Terrace 50%
Stone laying 0%
Painting 0%
ELECTRICAL 13%
Wiring and Provision 0%
Box setting and Piping 20%
Fixtures (Outlet and Switch) 20%
2 Storey Residential Row House
As of:
General Progress of the Project AUGUST 17, 2022
BLOCK 3 Finish Work (Per Week) Note:
Lot No. Structural Architectural Electrical Current Previous Progress Projecting the general progress of the
whole project. This includes delays (lack
49 57% 11% 42% 37.00% of human resources and Weather
50 79% 24% 83.00% 62.00% condition, etc...)
51 79% 34% 75.00% 63.00%
Green Represents (Finished)
52 79% 21% 75.00% 58.00% Red represents (Unfinished)
53 79% 17% 75.00% 57.00%
54 79% 22% 75.00% 57.00%
55 79% 16% 75.00% 57.00%
56 79% 14% 75.00% 56.00%
57 79% 16% 75.00% 57.00%
58 78% 13% 75.00% 55.00%
59 71% 14% 72.00% 52.00%
60 63% 12% 55.00% 43.00%
61 58% 15% 48.00% 40.00% Sector percentage of the project
62 56% 12% 50.00% 39.00% Structural Architectural Electrical
63 54% 12% 47.00% 38.00% 54.00% 13.00% 37.00%
64 56% 12% 47.00% 38.00%
65 56% 12% 47.00% 38.00%
66 56% 12% 47.00% 38.00%