REKAPITULASI

RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

NO. URAIAN BAGIAN PEKERJAAN JUMLAH

A PEKERJAAN PERSIAPAN Rp 1,038,991,497.79


B PEKERJAAN BANGUNAN PELABUHAN
- PEKERJAAN STRUKTUR Rp 16,226,019,018.72
- PEKERJAAN ARSITEKTUR Rp 14,342,395,065.92
- PEKERJAAN MEKANIKAL DAN ELEKTRIKAL Rp 12,523,997,545.93
C PEKERJAAN INFRASTRUKTUR
1 PEKERJAAN POWER HOUSE
- PEKERJAAN STRUKTUR Rp 1,165,669,345.27
- PEKERJAAN ARSITEKTUR Rp 225,290,285.24
- PEKERJAAN MEKANIKAL DAN ELEKTRIKAL Rp 6,805,933,222.98
2 PEKERJAAN GATE HOUSE Rp 936,839,514.05
3 PEKERJAAN AREA PARKIR Rp 3,120,144,846.43
4 DRAINASE Rp 590,004,792.54
5 PEKERJAAN LAIN LAIN Rp 197,820,000.00

TOTAL Rp 57,173,105,134.87
DIBULATKAN Rp 57,173,105,000.00

Err:511

Batam, September 2015


Diperiksa
Karo, Perencanaan Dan Pembangunan Kepala Kantor Pelabuhan Laut

IMAM BACHRONI CAPT. GAJAH ROOSENO M. Mar


NIP. 19620820 199603 1001 NIP. 19571002 197910 1001
Mengetahui,
Kuasa Pengguna Anggaran

I WAYAN SUBAWA
NIP. 19551203 198203 1001
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6

A PEKERJAAN PERSIAPAN

1 Papan Nama Proyek 1.00 unit 1,200,000.00 1,200,000.00


2 Penjilidan Dokumen Kontrak 5.00 set 250,000.00 1,250,000.00
3 Laporan & Dokumentasi 13.00 Bln 360,000.00 4,680,000.00
4 Mobilisasi & Demobilisasi Alat Berat 1.00 Ls 28,800,000.00 28,800,000.00
5 Pagar Sementara, Seng Tinggi 2,4 m 243.54 m' 461,600.00 112,418,064.00
6 Listrik & Air Kerja 13.00 Bln 5,000,000.00 65,000,000.00
7 Direksi Keet Lengkap Furniture 108.00 m2 1,303,548.28 140,783,213.79
8 Shop Drawing & As Built Drawing 5.00 set 3,000,000.00 15,000,000.00
9 Pengukuran dan Pemasangan Bouwplank 272.35 m' 45,200.00 12,310,220.00
10 Selasar Sementara 240.00 m2 1,650,000.00 396,000,000.00
11 Bongkaran Bangunan Lama 5,231.00 m2 50,000.00 261,550,000.00

PEKERJAAN PERSIAPAN 1,038,991,497.79


TOTAL A. PEKERJAAN PERSIAPAN 1,038,991,497.79
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6

B PEKERJAAN BANGUNAN PELABUHAN


PEKERJAAN STRUKTUR
PEKERJAAN STRUKTUR BAWAH
I Pekerjaan Tiang Pancang
1 Pengadaan tiang pancang 40 x 40 cm 2,682.00 m' 443,900.00 1,190,539,800.00
2 Pemancangan tiang pancang 2,384.00 m' 142,800.00 340,435,200.00
3 Penyambungan tiang pancang 149.00 titik 345,000.00 51,405,000.00
4 Pemotongan tiang pancang 149.00 titik 150,000.00 22,350,000.00
5 Pekerjaan Loading Test -
- PDA Loading Test 5.00 titik 12,075,000.00 60,375,000.00
-
II Pekerjaan Tanah
1 Timbunan Tanah Biasa (Fill) Jarak Angkut QRY > 2 km 18,368.95 m3 48,200.00 885,383,404.46

III Pekerjaan Pile Cap P1 uk. 850 x 850 mm -


1 Galian Tanah 45.99 m3 40,600.00 1,867,077.28
2 Pasir urug tebal 10 cm 4.84 m3 281,200.00 1,361,218.90
3 Lantai kerja K-175 tebal 5 cm 2.42 m3 1,048,400.00 2,537,521.15
4 Pembesian 8,833.15 kg 14,690.00 129,758,914.74
5 Bekisting 182.24 m2 201,400.00 36,703,136.00
6 Beton K-300 38.73 m3 1,291,000.00 49,995,266.00

IV Pekerjaan Pile Cap P2 uk. 2200 x 900 mm


1 Galian Tanah 75.24 m3 40,600.00 3,054,744.00
2 Pasir urug tebal 10 cm 7.92 m3 281,200.00 2,227,104.00
3 Lantai kerja K-175 tebal 5 cm 3.96 m3 1,048,400.00 4,151,664.00
4 Pembesian 527.01 kg 14,690.00 7,741,812.16
5 Bekisting 198.40 m2 201,400.00 39,957,760.00
6 Beton K-300 63.36 m3 1,291,000.00 81,797,760.00

V Pekerjaan Stump K1 uk. 600 x 600 mm


1 Pembesian 4,719.12 kg 14,690.00 69,323,872.80

VI Pekerjaan Stump K1A uk. 600 x 600 mm


1 Pembesian 1,691.76 kg 14,690.00 24,851,954.40

VII Pekerjaan Stump K2 300 x 300 mm


1 Pembesian 269.95 kg 14,690.00 3,965,594.88

VIII Pekerjaan Pit Lift


1 Galian Tanah 21.25 m3 40,600.00 862,750.00
2 Pasir urug tebal 10 cm 1.25 m3 281,200.00 351,500.00
3 Lantai kerja K-175 tebal 5 cm 0.63 m3 1,048,400.00 655,250.00
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
4 Pembesian 630.02 kg 14,690.00 9,255,051.09
5 Bekisting 232.48 m2 201,400.00 46,821,472.00
6 Beton K-300 33.92 m3 1,291,000.00 43,790,720.00
-
IX Pekerjaan Pit Escalator -
1 Galian Tanah 19.87 m3 40,600.00 806,803.20
2 Pasir urug tebal 10 cm 1.66 m3 281,200.00 465,667.20
3 Lantai kerja K-175 tebal 5 cm 0.83 m3 1,048,400.00 868,075.20
4 Pembesian 566.65 kg 14,690.00 8,324,129.63
5 Bekisting 4.75 m2 201,400.00 957,052.80
6 Beton K-300 34.08 m3 1,291,000.00 43,997,280.00

SUB TOTAL . ELV. - 0.00 3,166,939,555.88

PEKERJAAN STRUKTUR (ELV. ± 0.00)


I Pekerjaan Sloof TB1 uk. 350 x 700 mm
1 Galian Tanah 121.38 m3 40,600.00 4,928,028.00
2 Pasir urug tebal 10 cm 14.28 m3 281,300.00 4,016,964.00
3 Lantai kerja K-175 tebal 5 cm 7.14 m3 1,048,400.00 7,485,576.00
4 Pembesian 22,750.97 kg 14,690.00 334,211,749.30
5 Bekisting 571.20 m2 90,000.00 51,408,000.00
6 Beton K-300 99.96 m3 1,291,000.00 129,048,360.00
-
II Pekerjaan Sloof TB2 uk. 350 x 700 mm -
1 Galian Tanah 160.95 m3 40,600.00 6,534,468.50
2 Pasir urug tebal 10 cm 18.94 m3 281,300.00 5,326,415.50
3 Lantai kerja K-175 tebal 5 cm 9.47 m3 1,048,400.00 9,925,727.00
4 Pembesian 21,444.89 kg 14,690.00 315,025,390.03
5 Bekisting 91.20 m2 90,000.00 8,208,000.00
6 Beton K-300 13.68 m3 1,291,000.00 17,660,880.00
-
III Pekerjaan Sloof TB3 uk. 300 x 600 mm -
1 Galian Tanah 17.10 m3 40,600.00 694,260.00
2 Pasir urug tebal 10 cm 2.28 m3 281,300.00 641,364.00
3 Lantai kerja K-175 tebal 5 cm 1.14 m3 1,048,400.00 1,195,176.00
4 Pembesian 2,791.00 kg 14,690.00 40,999,737.12
5 Bekisting 91.20 m2 90,000.00 8,208,000.00
6 Beton K-300 13.68 m3 1,291,000.00 17,660,880.00
-
IV Pekerjaan Sloof TB4 uk. 300 x 600 mm -
1 Galian Tanah 77.40 m3 40,600.00 3,142,440.00
2 Pasir urug tebal 10 cm 10.32 m3 281,300.00 2,903,016.00
3 Lantai kerja K-175 tebal 5 cm 5.16 m3 1,048,400.00 5,409,744.00
4 Pembesian 10,908.72 kg 14,690.00 160,249,118.84
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
5 Bekisting 412.80 m2 90,000.00 37,152,000.00
6 Beton K-300 61.92 m3 1,291,000.00 79,938,720.00
- -
IV Pekerjaan Sloof TB5 uk. 300 x 500 mm -
1 Galian Tanah 1.95 m3 40,600.00 79,170.00
2 Pasir urug tebal 10 cm 0.30 m3 281,300.00 84,390.00
3 Lantai kerja K-175 tebal 5 cm 0.15 m3 1,048,400.00 157,260.00
4 Pembesian 844.95 kg 14,690.00 12,412,286.12
5 Bekisting 10.00 m2 90,000.00 900,000.00
6 Beton K-300 1.50 m3 1,291,000.00 1,936,500.00

V Pekerjaan Sloof TB6 uk. 200 x 400 mm - -


1 Galian Tanah 21.70 m3 40,600.00 881,141.80
2 Pasir urug tebal 10 cm 3.95 m3 281,300.00 1,110,009.80
3 Lantai kerja K-175 tebal 5 cm 1.97 m3 1,048,400.00 2,068,493.20
4 Pembesian 4,877.07 kg 14,690.00 71,644,186.70
5 Bekisting 144.80 m2 90,000.00 13,032,000.00
6 Beton K-300 14.48 m3 1,291,000.00 18,693,680.00
-
VI Pekerjaan Sloof CTB2 uk. 300 x 600 mm -
1 Galian Tanah 0.45 m3 40,600.00 18,270.00
2 Pasir urug tebal 10 cm 0.06 m3 281,300.00 16,878.00
3 Lantai kerja K-175 tebal 5 cm 0.03 m3 1,048,400.00 31,452.00
4 Pembesian 123.99 kg 14,690.00 1,821,428.38
5 Bekisting 2.40 m2 90,000.00 216,000.00
6 Beton K-300 0.36 m3 1,291,000.00 464,760.00

VII Pekerjaan Plat lantai tebal 12 cm Elv.0,00 -


1 Pembesian 19,575.53 kg 14,690.00 287,564,561.85
2 Beton K-300 431.58 m3 1,291,000.00 557,163,583.20
-
VIII Pekerjaan Kolom K1 uk. 600 x 600 mm -
1 Pembesian 18,128.75 kg 14,690.00 266,311,396.26
2 Bekisting 596.16 m2 168,700.00 100,572,192.00
3 Beton K-300 89.42 m3 1,291,000.00 115,446,384.00
-
IX Pekerjaan Kolom K1A uk. 600 x 600 mm -
1 Pembesian 6,042.92 kg 14,690.00 88,770,465.42
2 Bekisting 198.72 m2 168,700.00 33,524,064.00
3 Beton K-300 29.81 m3 1,291,000.00 38,482,128.00
-
X Pekerjaan Kolom K2 uk. 300 x 300 mm -
1 Pembesian 744.51 kg 14,690.00 10,936,787.26
2 Bekisting 74.40 m2 168,700.00 12,551,280.00
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
3 Beton K-300 5.58 m3 1,291,000.00 7,203,780.00
-
XI Pekerjaan Kolom KT uk. 130 x 500 mm -
1 Pembesian 230.73 kg 14,690.00 3,389,441.33
2 Bekisting 17.39 m2 168,700.00 2,933,355.60
3 Beton K-300 0.90 m3 1,291,000.00 1,158,027.00

XII Pekerjaan Kolom KL


1 Pembesian 1,326.41 kg 14,690.00 19,484,933.52
2 Bekisting 110.40 m2 168,700.00 18,624,480.00
3 Beton K-300 8.83 m3 1,291,000.00 11,402,112.00

XIII Pekerjaan Kolom Praktis uk. 13 x 13 cm


1 Pembesian 1,137.27 kg 14,690.00 16,706,437.54
2 Bekisting 40.66 m2 168,700.00 6,860,016.80
3 Beton bertulang 1Pc : 2Ps : 3Kr 5.29 m3 1,291,000.00 6,824,639.12

XIV Pekerjaan Tangga Beton tipe 1


1 Pembesian 741.75 kg 14,690.00 10,896,355.68
2 Bekisting 37.48 m2 187,600.00 7,032,148.48
3 Beton K-300 5.62 m3 1,291,000.00 7,258,931.52

XV Pekerjaan Tangga Beton Tipe 2,3,4


1 Pembesian 2,563.70 kg 14,690.00 37,660,681.31
2 Bekisting 82.86 m2 187,600.00 15,543,860.64
3 Beton K-300 12.43 m3 1,291,000.00 16,045,141.86

XVI Pekerjaan Meja Wastafel


1 Pekerjaan Meja Beton panjang 1,35 x 0,6 m 2.00 unit 3,083,700.00 6,167,400.00

SUB TOTAL . ELV. ± 0.00 3,084,056,504.68

PEKERJAAN STRUKTUR (ELV. + 4.80)


I Pekerjaan Balok G1 uk. 350 x 700 mm
1 Pembesian 19,990.16 kg 14,690.00 293,655,451.58
2 Bekisting 438.20 m2 171,400.00 75,107,480.00
3 Beton K-300 76.69 m3 1,291,000.00 99,000,335.00
-
II Pekerjaan Balok G2 uk. 350 x 700 mm -
1 Pembesian 21,932.76 kg 14,690.00 322,192,254.98
2 Bekisting 555.24 m2 171,400.00 95,168,136.00
3 Beton K-300 97.17 m3 1,291,000.00 125,442,597.00
-
III Pekerjaan Balok G3 uk. 300 x 600 mm -
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
1 Pembesian 5,677.57 kg 14,690.00 83,403,459.82
2 Bekisting 150.24 m2 171,400.00 25,751,136.00
3 Beton K-300 22.54 m3 1,291,000.00 29,093,976.00
-
IV Pekerjaan Balok B1 uk. 300 x 600 mm -
1 Pembesian 17,151.58 kg 14,690.00 251,956,766.61
2 Bekisting 371.04 m2 171,400.00 63,596,256.00
3 Beton K-300 55.66 m3 1,291,000.00 71,851,896.00
-
V Pekerjaan Balok B2 uk. 300 x 500 mm -
1 Pembesian 1,278.32 kg 14,690.00 18,778,451.02
2 Bekisting 48.60 m2 171,400.00 8,330,040.00
3 Beton K-300 7.29 m3 1,291,000.00 9,411,390.00
-
VI Pekerjaan Balok B3 uk. 200 x 400 mm -
1 Pembesian 140.98 kg 14,690.00 2,071,047.62
2 Bekisting 2.40 m2 171,400.00 411,360.00
3 Beton K-300 0.24 m3 1,291,000.00 309,840.00
-
VII Pekerjaan Balok CG2 uk. 300 x 600 mm -
1 Pembesian 514.86 kg 14,690.00 7,563,352.16
2 Bekisting 7.20 m2 171,400.00 1,234,080.00
3 Beton K-300 1.08 m3 1,291,000.00 1,394,280.00
-
VIII Pekerjaan balok TB5 uk. 200 x 300 mm -
1 Pembesian 1,629.40 kg 14,690.00 23,935,821.36
2 Bekisting 101.60 m2 171,400.00 17,414,240.00
3 Beton K-300 7.62 m3 1,291,000.00 9,837,420.00
-
IX Pekerjaan Plat S1 tebal 15 cm -
1 Pembesian 24,443.12 kg 14,690.00 359,069,452.78
2 Bekisting 2,444.12 m2 187,600.00 458,516,912.00
3 Beton K-300 366.62 m3 1,291,000.00 473,303,838.00
-
X Pekerjaan Kolom K1 uk. 600 x 600 mm -
1 Pembesian 11,463.71 kg 14,690.00 168,401,879.33
2 Bekisting 453.60 m2 168,700.00 76,522,320.00
3 Beton K-300 56.70 m3 1,291,000.00 73,199,700.00
-
XI Pekerjaan Kolom KL -
1 Pembesian 2,124.72 kg 14,690.00 31,212,136.80
2 Bekisting 105.60 m2 168,700.00 17,814,720.00
3 Beton K-300 8.45 m3 1,291,000.00 10,906,368.00
-
XII Pekerjaan Kolom Praktis uk. 13 x 13 cm -
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
1 Pembesian 1,718.81 kg 14,690.00 25,249,325.36
2 Bekisting 58.72 m2 168,700.00 9,905,245.81
3 Beton bertulang 1Pc : 2Ps : 3Kr 7.63 m3 1,048,500.00 8,003,168.52
-
XIII Pekerjaan Meja Wastafel
1 Pekerjaan Meja Beton panjang 1,35 x 0,6 m 2.00 unit 3,083,700.00 6,167,400.00
2 Pekerjaan Meja Beton panjang 1,5 x 0,6 m 3.00 unit 3,429,900.00 10,289,700.00
3 Pekerjaan Meja Beton panjang 1,06 x 0,6 m 1.00 unit 2,407,500.00 2,407,500.00

XIV Pekerjaan Atap Pipa besi -


Rangka Atap utama -
1 Rangka Pipa Galvanish dia 190.5, t=5mm ( 8") 754.40 m' 497,290.00 375,155,576.00
2 Rangka Pipa Galvanish dia 165.2 , t=5mm (6") 1,815.00 m' 369,280.00 670,243,200.00
3 Rangka Pipa Galvanish dia 89.1, t=2.8mm (4") 3,635.12 m' 217,010.00 788,857,391.20
4 Gording Baja C. 200.75.20.3.2 29,163.42 kg 29,800.00 869,069,916.00
5 Plat joint, endplate, gusset, stiffener 12,641.64 kg 29,800.00 376,720,872.00
6 baut Dia 19 2,660.93 kg 29,800.00 79,295,654.40
7 ikatan angin dia 16 2,165.02 kg 29,800.00 64,517,476.80
8 Trexstang 1 ( dia 12 ) 426.24 kg 29,800.00 12,701,952.00
9 Pengecatan Besi 4,907.20 m2 50,830.00 249,432,926.39
Kolom Lt 2 -
1 Rangka Pipa Galvanish dia 190.5, t=5mm ( 8") 288.00 m' 497,290.00 143,219,520.00
2 Plat joint, endplate, gusset, stiffener 5,887.44 kg 29,800.00 175,445,712.00
3 baut Dia 16 110.59 kg 29,800.00 3,295,641.60
4 Angkur 12 dia 32 2,131.20 kg 29,800.00 63,509,760.00
5 Pengecatan Besi 255.49 m2 50,830.00 12,986,780.35
Selasar Belakang -
1 Pipa dia 5" 78.62 m' 292,280.00 22,977,592.20
2 Pipa dia 4" 583.04 m' 217,010.00 126,525,293.39
3 Pipa 2,5 " 109.80 m' 138,280.00 15,183,144.00
4 Plat Besi 1,225.95 kg 29,800.00 36,533,432.93
5 Baut 6.91 kg 29,800.00 205,977.60
6 Streaktank baja 72.00 m' 45,000.00 3,240,000.00
7 Anchur 4dia 19 80.14 kg 29,800.00 2,388,052.80
8 Pengecatan Besi 406.84 m2 50,830.00 20,679,807.01

SUB TOTAL . ELV. ± 4.80 7,480,066,412.41

PEKERJAAN STRUKTUR (ELV. + 9.60)


I Pekerjaan Ring Balok RB1 uk. 350 x 700
1 Pembesian 7,579.77 kg 14,690.00 111,346,825.71
2 Bekisting 319.20 m2 171,400.00 54,710,880.00
3 Beton K-300 55.86 m3 1,291,000.00 72,115,260.00
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
II Pekerjaan Ring Balok RB2 uk. 300 x 600
1 Pembesian 4,293.15 kg 14,690.00 63,066,369.83
2 Bekisting 190.00 m2 171,400.00 32,566,000.00
3 Beton K-300 28.50 m3 1,291,000.00 36,793,500.00

III Pekerjaan Ring Balok RB3 uk. 300 x 500


1 Pembesian 4,293.15 kg 14,690.00 63,066,369.83
2 Bekisting 190.00 m2 171,400.00 32,566,000.00
3 Beton K-300 28.50 m3 1,291,000.00 36,793,500.00

IV Pekerjaan Ring Balok RB4 uk. 200 x 450


1 Pembesian 361.36 kg 14,690.00 5,308,338.74
2 Bekisting 17.01 m2 171,400.00 2,915,514.00
3 Beton K-300 1.70 m3 1,291,000.00 2,195,991.00

V Pekerjaan Kolom KL
1 Pembesian 1,859.62 kg 14,690.00 27,317,759.04
2 Bekisting 72.00 m2 168,700.00 12,146,400.00
3 Beton K-300 5.76 m3 1,291,000.00 7,436,160.00

VI Kolom Praktis
1 Pembesian 142.57 kg 14,690.00 2,094,279.85
2 Bekisting 3.90 m2 168,700.00 657,930.00
3 Beton bertulang 1Pc : 2Ps : 3Kr 0.51 m3 1,048,500.00 531,589.50

VII Pekerjaan Plat S2 tebal 15 cm


1 Pembesian 8,756.94 kg 14,690.00 128,639,517.94
2 Bekisting 532.24 m2 187,600.00 99,848,224.00
3 Beton K-300 79.84 m3 1,291,000.00 103,068,276.00

SUB TOTAL . ELV. ± 9.60 895,184,685.43

PEKERJAAN STRUKTUR ELV. + 12.60


I Pekerjaan Ring Balok RB1 uk. 350 x 700
1 Pembesian 1,055.27 kg 14,690.00 15,501,900.14
2 Bekisting 52.36 m2 171,400.00 8,974,504.00
3 Beton K-300 9.16 m3 1,291,000.00 11,829,433.00

II Pekerjaan Ring Balok RB2 uk. 300 x 600


1 Pembesian 558.35 kg 14,690.00 8,202,161.50
2 Bekisting 19.20 m2 168,700.00 3,239,040.00
3 Beton k-300 2.88 m3 1,291,000.00 3,718,080.00

III Pekerjaan Ring Balok RB3 uk. 300 x 500


1 Pembesian 411.98 kg 14,690.00 6,052,042.02
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
2 Bekisting 18.00 m2 168,700.00 3,036,600.00
3 Beton k-300 2.70 m3 1,048,500.00 2,830,950.00

IV Pekerjaan Ring Balok RB4 uk. 200 x 450


1 Pembesian 250.57 kg 14,690.00 3,680,905.62
2 Bekisting 17.82 m2 168,700.00 3,006,234.00
3 Beton k-300 1.78 m3 1,048,500.00 1,868,427.00

V Plat Beton T. 15 cm ( elv.12,60 )


1 Pembesian 3,035.28 kg 14,690.00 44,588,297.66
2 Bekisting 184.48 m2 187,600.00 34,608,823.20
3 Beton k-300 27.67 m3 1,291,000.00 35,724,939.30

VI Lisplank T. 10 cm panjang 70 cm
1 Pembesian 984.42 kg 14,690.00 14,461,181.22
2 Bekisting 159.48 m2 187,600.00 29,918,448.00
3 Beton k-300 7.44 m3 1,291,000.00 9,608,138.40

SUB TOTAL . ELV. ± 12.60 240,850,105.06

STRUKTUR SELASAR PENGHUBUNG


I Pekerjaan pondasi P1 (1200 x 1200 x 250 mm)
1 Galian Tanah 8.64 m3 40,600.00 350,784.00
2 Pasir urug tebal 10 cm 0.72 m3 281,200.00 202,464.00
3 Lantai kerja tebal 5 cm 0.36 m3 1,048,400.00 377,424.00
4 Pembesian 223.78 kg 14,690.00 3,287,269.44
5 Bekisting 7.20 m2 201,400.00 1,450,080.00
6 Beton k-300 1.80 m3 1,291,000.00 2,323,800.00

II Pekerjaan Sloof TB6 uk. 400 x 200 mm


1 Galian Tanah 14.85 m3 40,600.00 602,910.00
2 Pasir urug tebal 10 cm 2.70 m3 281,200.00 759,240.00
3 Lantai kerja tebal 5 cm 1.35 m3 1,048,400.00 1,415,340.00
4 Pembesian 2,182.06 kg 14,690.00 32,054,423.21
5 Bekisting 86.40 m2 201,400.00 17,400,960.00
6 Beton k-300 4.32 m3 1,291,000.00 5,577,120.00

V Pekerjaan Stump K2 300 x 300 mm


1 Pembesian 128.88 kg 14,690.00 1,893,302.29
2 Bekisting 12.00 m2 168,700.00 2,024,400.00
3 Beton k-300 0.90 m3 1,291,000.00 1,161,900.00

VI Pekerjaan Kolom K2 uk. 300 x 300 mm


RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
1 Pembesian 380.19 kg 14,690.00 5,585,049.86
2 Bekisting 39.00 m2 168,700.00 6,579,300.00
3 Beton k-300 2.93 m3 1,291,000.00 3,776,175.00

VII Plat Beton T. 10 cm


1 Pembesian 707.59 kg 14,690.00 10,394,497.10
2 Bekisting 5.20 m2 187,600.00 975,520.00
3 Beton k-300 13.00 m3 1,291,000.00 16,783,000.00

VIII Pekerjaan Pipa


Pekerjaan pipa 4 " 91.00 m' 217,010.00 19,747,910.00
Gording Baja C. 200.75.20.3.2 1,928.16 kg 29,800.00 57,459,168.00
Pengecatan besi 152.42 m2 50,830.00 7,747,508.60
Anchur 66.74 kg 29,800.00 1,988,768.56
Base Plat 94.20 kg 29,800.00 2,807,160.00

SUB TOTAL . PEKERJAAN SELASAR KIRI 204,725,474.05

STRUKTUR SELASAR DEPAN BANGUNAN


I Pekerjaan pondasi P1 (1200 x 1200 x 250 mm)
1 Galian Tanah 24.19 m3 40,600.00 982,195.20
2 Pasir urug tebal 10 cm 2.02 m3 281,200.00 566,899.20
3 Lantai kerja tebal 5 cm 1.01 m3 1,048,400.00 1,056,787.20
4 Pembesian 626.57 kg 14,690.00 9,204,354.43
5 Bekisting 20.16 m2 201,400.00 4,060,224.00
6 Beton k-300 5.04 m3 1,291,000.00 6,506,640.00

II Pekerjaan Sloof TB6 uk. 400 x 200 mm


1 Galian Tanah 58.03 m3 40,600.00 2,355,815.00
2 Pasir urug tebal 10 cm 10.55 m3 281,200.00 2,966,660.00
3 Lantai kerja tebal 5 cm 5.28 m3 1,048,400.00 5,530,310.00
4 Pembesian 8,522.24 kg 14,690.00 125,191,716.37
5 Bekisting 337.60 m2 201,400.00 67,992,640.00
6 Beton k-300 16.88 m3 1,291,000.00 21,792,080.00

III Pekerjaan Stump K2 uk. 300 x 300 mm


1 Pembesian 341.44 kg 14,690.00 5,015,738.91
2 Bekisting 25.20 m2 168,700.00 4,251,240.00
3 Beton k-300 2.52 m3 1,291,000.00 3,253,320.00

IV Pekerjaan Kolom K2 uk. 300 x 300 mm


1 Pembesian 1,064.54 kg 14,690.00 15,638,139.61
2 Bekisting 109.20 m2 168,700.00 18,422,040.00
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
3 Beton k-300 8.19 m3 1,291,000.00 10,573,290.00

V Plat Beton T. 10 cm
1 Pembesian 3,119.93 kg 14,690.00 45,831,736.44
2 Bekisting 22.93 m2 187,600.00 4,301,292.80
3 Beton k-300 57.32 m3 1,291,000.00 74,000,120.00

VI Pekerjaan Pipa
Pekerjaan pipa 4 " 616.00 m' 217,010.00 133,678,160.00
Gording Baja C. 200.75.20.3.2 17,003.40 kg 29,800.00 506,701,463.04
Pengecatan besi 1,285.19 m2 50,830.00 65,326,267.07
Anchur 373.73 kg 29,800.00 11,137,103.94
Base Plat 263.76 kg 29,800.00 7,860,048.00

-
SUB TOTAL . PEKERJAAN SELASAR DEPAN 1,154,196,281.21
TOTAL PEKERJAAN STRUKTUR BANGUNAN 16,226,019,018.72
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6

PEKERJAAN ARSITEKTUR
Pekerjaan Arsitektur Elv. +0,00
I Pekerjaan Dinding
1 Pasangan dinding Cilcon 1,971.15 m2 166,500.00 328,195,975.50
2 Pasangan dinding partisi 198.63 m2 139,100.00 27,628,737.50
3 Plester aci 3,942.29 m2 64,798.00 255,452,766.61
4 Pekerjaan Railling tangga 73.00 m' 1,500,000.00 109,500,000.00
5 Pekerjaan Alumunium Louver 97.75 m2 1,100,000.00 107,525,000.00

II Pekerjaan Pintu dan Jendela


1 Pintu PT1 2.00 bh 3,700,000.00 7,400,000.00
Kusen Allumunium
Daun pintu Rangka kayu + Penutup double multiplek lapis HPL
Kaca mati 6mm buram -Es
Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

2 Pintu PT1' 1.00 bh 3,700,000.00 3,700,000.00


Kusen Allumunium
Daun pintu Rangka kayu + Penutup double multiplek lapis HPL
Kaca mati 6mm buram -Es
Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

3 Pintu PT2 3.00 bh 3,700,000.00 11,100,000.00


Kusen Allumunium
Daun pintu Rangka kayu + Penutup double multiplek lapis HPL + Jalusi
Accecories Handle jungkit, engsel kupu kupu, lockset

4 Pintu PT2' 4.00 bh 3,700,000.00 14,800,000.00


Kusen Allumunium
Daun pintu Rangka kayu + Penutup double multiplek lapis HPL + Jalusi
Accecories Handle jungkit, engsel kupu kupu, lockset

5 Pintu PB1 2.00 bh 12,500,000.00 25,000,000.00


Kusen Metal sheet 2mm
Daun pintu metal sheet 2mm fin. Cat duco
Kaca mati 6mm buram -Es + Jalusi
Accecories Handle tanam st steel , Engsel Bubut , lockset

6 Pintu PB2 4.00 bh 7,500,000.00 30,000,000.00


Kusen Metal sheet 2mm
Daun pintu metal sheet 2mm fin. Cat duco
Accecories Handle tanam st steel , Engsel Bubut , lockset

7 Pintu P1' 1.00 bh 7,500,000.00 7,500,000.00


Kusen Allumunium
Daun pintu Kaca t=8mm
Acc. Handle tarik allumunium , engsel kupu kupu, lockset, door closer
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6

8 Pintu P2 1.00 bh 4,040,050.00 4,040,050.00


Kusen Allumunium
Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL
daun jendela Kaca mati panasap CHFSL t=6mm
Handle Tarik st steel engsel floor hinge, lockset
Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer
Silicone sealent clear ex glazing

9 Pintu PJ1 4.00 bh 131,250,000.00 525,000,000.00


Uk. 7200 mm x 4150 mm
Uk. Tempered 15 mm
Uk. 1500 (tinggi)x7200mm (lebar) (1 keping di bagi 4 pcs)
Kaca mati Tempered 15 mm
Uk. 1200 x 2450 mm (4 pcs)
Pintu tempered 12 mm
Uk. 1100 x 2450 mm (2 pcs)
In cluded item : Es200 Easy mini unit drive, Glass clamping (2 pcs), Spider 2 kaki,
U guide, Safet sensor, ellipe sensor, Pulley with lock

10 Pintu PJ2 1.00 bh 115,500,000.00 115,500,000.00


Uk. 5400 mm x 4150 mm
Uk. Tempered 15 mm
Uk. 1500 (tinggi)x5400mm (lebar) (1 keping di bagi 4 pcs)
Kaca mati Tempered 15 mm
Uk. 1200 x 2450 mm (4 pcs)
Pintu tempered 12 mm
Uk. 1100 x 2450 mm (2 pcs)
In cluded item : Es200 Easy mini unit drive, Glass clamping (2 pcs), Spider 2 kaki,
U guide, Safet sensor, ellipe sensor, Pulley with lock

11 Pintu PJ3 2.00 bh 5,420,000.00 10,840,000.00


Kusen Allumunium
Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL
daun jendela Kaca mati panasap CHFSL t=6mm
Handle Tarik st steel engsel floor hinge, lockset
Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer
Silicone sealent clear ex glazing

12 Pintu PJ4 3.00 bh 5,420,000.00 16,260,000.00

13 Pintu PJ5 1.00 bh 10,100,000.00 10,100,000.00

14 Pintu PJ6 4.00 bh 29,022,400.00 116,089,600.00

15 Pintu PJ7 4.00 bh 6,600,000.00 26,400,000.00


RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
16 Jendela J1 5.00 bh 30,555,000.00 152,775,000.00

17 Jendela J2 1.00 bh 15,859,500.00 15,859,500.00

18 Jendela J3 2.00 bh 12,483,900.00 24,967,800.00

19 Jendela J7 2.00 bh 5,456,250.00 10,912,500.00

20 Jendela Bouvenlight BV
Kusen Allumunium
Kaca mati panasap CHFSL t=6mm
Silicone sealent clear glass /box frame st steel ( hire line )
- Jendela Bouvenlight BV1 1.00 bh 2,250,000.00 2,250,000.00
- Jendela Bouvenlight BV4 2.00 bh 2,250,000.00 4,500,000.00

III Pekerjaan Lantai


1 Pemasangan Keramik Homogeneus Tile - Polish ( 80 x 80 cm ) 3,322.04 m2 283,600.00 942,131,678.40
2 Pemasangan Keramik Tangga - Polish ( 30 x 60 cm ) 82.75 m2 262,200.00 21,697,600.62
3 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x 60 cm ) 91.76 m2 262,200.00 24,059,472.00
4 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x 30 cm ) 50.89 m2 239,100.00 12,167,799.00
5 Pemasangan Keramik Dinding KM Homogeneus Tile ( 30 x 60 cm ) 514.66 m2 262,200.00 134,944,900.80
6 Plint keramik 10 x 80 cm 972.26 m' 75,300.00 73,211,253.30
7 Step Nozing pada tangga lt 1 ke lt 2 159.38 m' 184,300.00 29,372,812.50

IV Pekerjaan Plafond
1 Plafond gypsum 2,359.89 m2 128,000.00 302,065,920.00
2 Plafond Semen Board 151.92 m2 138,800.00 21,086,496.00
3 Plafond Metal Expose 43.50 m2 825,000.00 35,887,500.00
4 List Plafond 1,100.50 m' 24,000.00 26,412,000.00

V Pekerjaan Cat
1 Cat dinding 4,339.54 m2 32,100.00 139,299,362.40
2 Cat Plafond 2,511.81 m2 22,600.00 56,766,906.00

VI Pekerjaan Waterproofing
1 Lantai Satu Area toilet KM/WC 142.65 m2 70,000.00 9,985,500.00

SUB TOTAL . Pekerjaan Arsitektur Elv. +0,00 3,792,386,130.63

Pekerjaan Arsitektur Elv. +4,80


I Pekerjaan Dinding
1 Pasangan dinding Cilcon 1,516.31 m2 166,500.00 252,466,281.00
2 Pasangan dinding partisi 602.31 m2 139,100.00 83,781,321.00
3 Plester 3,032.63 m2 64,798.00 196,508,229.14

II Pekerjaan Pintu dan Jendela


1 Pintu PT1' 2.00 bh 3,700,000.00 7,400,000.00
Kusen Allumunium
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
Daun pintu Rangka kayu + Penutup double multiplek lapis HPL
Kaca mati 6mm buram -Es + frame allumunium keliling
Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

2 Pintu PT2 3.00 bh 3,700,000.00 11,100,000.00


Kusen Allumunium
Daun pintu Rangka kayu + Penutup double multiplek lapis HPL + Jalusi
Accecories Handle jungkit, engsel kupu kupu, lockset

4 Pintu PB2 5.00 bh 7,500,000.00 37,500,000.00

5 Pintu P1 5.00 bh 4,122,500.00 20,612,500.00

6 Pintu P1' 5.00 bh 4,122,500.00 20,612,500.00

8 Pintu P2 6.00 bh 4,040,050.00 24,240,300.00

7 Pintu PJ4 2.00 bh 5,420,000.00 10,840,000.00


Kusen Allumunium
Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL
daun jendela Kaca mati panasap CHFSL t=6mm
Handle Tarik st steel engsel floor hinge, lockset
Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer
Silicone sealent clear ex glazing

13 Jendela Kaca
Kusen Allumunium
Kaca mati panasap CHFSL t=6mm
Silicone sealent clear glass /box frame st steel ( hire line )
- Jendela J2 1.00 bh 17,029,320.00 17,029,320.00
- Jendela J3 5.00 bh 12,483,900.00 62,419,500.00
- Jendela J4 4.00 bh 13,677,000.00 54,708,000.00
- Jendela J5 9.00 bh 41,438,400.00 372,945,600.00
- Jendela J6 1.00 bh 11,610,900.00 11,610,900.00

14 Jendela Bouvenlight BV
Kusen Allumunium
Kaca mati panasap CHFSL t=6mm
Silicone sealent clear glass /box frame st steel ( hire line )
- Jendela Bouvenlight BV2 10.00 bh 1,875,000.00 18,750,000.00
- Jendela Bouvenlight BV3 2.00 bh 1,875,000.00 3,750,000.00
- Jendela Bouvenlight BV4 1.00 bh 1,875,000.00 1,875,000.00

15 Jendela Loket ( kaca rangka allumunium ) 10.00 bh 12,483,900.00 124,839,000.00

III Pekerjaan Lantai


1 Pemasangan Keramik Homogeneus Tile - Polish ( 80 x 80 cm ) 2,504.77 m2 283,600.00 710,351,354.00
2 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x 60 cm ) 46.64 m2 262,200.00 12,229,008.00
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
3 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x 30 cm ) 15.41 m2 239,100.00 3,684,531.00
4 Pemasangan Keramik Dinding KM Homogeneus Tile ( 30 x 60 cm ) 150.96 m2 262,200.00 39,582,760.80
5 Plint keramik 10 x 80 cm 789.52 m' 75,300.00 59,450,479.50

IV Pekerjaan Plafond
1 Plafond gypsum 887.20 m2 128,000.00 113,561,600.00
2 Plafond Metal Expose 3,285.75 m2 825,000.00 2,710,743,750.00
3 Plafond toilet Fibrous plaster 83.85 m2 138,800.00 11,638,380.00
4 List Plafond 747.75 m' 24,000.00 17,946,000.00
5 Pekerjaan alumunium composite ( fasade, pelapis kolom lantai 1 dan 2 ) 940.37 m2 892,500.00 839,280,225.00

V Pekerjaan Cat
1 Cat dinding 3,634.94 m2 32,100.00 116,681,509.80
2 Cat Plafond 971.05 m2 22,600.00 21,945,730.00

VI Pekerjaan Waterproofing
1 Lantai Dua Area toilet dan tempat wudhu 62.05 m2 75,000.00 4,653,750.00

VII Pekerjaan Penutup Atap


Atap Canopy Depan dan samping kiri bangunan ( rangka galvanis,atap alumunium metal,
1 647.06 m2 550,000.00 355,883,000.00
termasuk pembuatan talang air)

2 Atap tenant ( rangka dari hollow ) 45.78 m2 650,000.00 29,757,000.00

SUB TOTAL . Pekerjaan Arsitektur Elv. +4,80 6,380,377,529.24

Pekerjaan Arsitektur Elv. +9,60


I Pekerjaan Dinding
1 Pasangan bata ringan 97.99 m2 111,600.00 10,935,684.00
2 Plester 195.98 m2 38,298.00 7,505,642.04
3 Aci halus 195.98 m2 26,500.00 5,193,470.00

II Pekerjaan Pintu dan Jendela


1 Pintu PB1 2.00 bh 12,500,000.00 25,000,000.00
Kusen Metal sheet 2mm
Daun pintu metal sheet 2mm fin. Cat duco
Accecories Handle tanam st steel , Engsel Bubut , lockset

IV Pekerjaan Waterproofing
1 Lantai Dak atap 586.20 m2 75,000.00 43,965,000.00

VI Pekerjaan Penutup Atap


1 Atap bangunan Utama ( Alumunium Curve Metal ) 3,285.75 m2 281,900.00 926,252,925.00
2 Rock wool + kawat ayam 3,285.75 m2 70,000.00 230,002,500.00
3 Pembuatan talang dan Lisplank kovering Alumunium composite 218.40 m' 650,000.00 141,960,000.00
4 Atap bangunan selasar belakang 346.15 m2 281,900.00 97,579,685.00
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
Atap Canopy Depan dan samping kiri bangunan ( rangka galvanis,atap alumunium metal,
5 1,285.00 M2 550,000.00 706,750,000.00
termasuk pembuatan talang air)

Sub Total pekerjaan arsitektur elv.9,60 2,195,144,906.04

Pekerjaan Arsitektur Selasar Samping


1 Plafond Metal Expose 145.00 m2 825,000.00 119,625,000.00
2 Pekerjaan lisplank ( rangka hollow covering alumunium Composit ) 68.00 m' 650,000.00 44,200,000.00
3 Pekerjaan Atap Alumunium Metal 145.00 m2 281,900.00 40,875,500.00
4 Pekerjaan Keramik 800 x 800 mm 130.00 m2 283,600.00 36,868,000.00
Sub Total pekerjaan arsitektur selasar Samping 241,568,500.00

Pekerjaan Arsitektur Selasar Depan


1 Plafond Metal Expose 1,140.00 m2 825,000.00 940,500,000.00
2 Pekerjaan lisplank ( rangka hollow covering alumunium Composit ) 476.00 m' 650,000.00 309,400,000.00
3 Pekerjaan Atap Alumunium Metal 1,140.00 m2 281,900.00 321,366,000.00
4 Pekerjaan Keramik 800 x 800 mm 570.00 m2 283,600.00 161,652,000.00

Sub Total pekerjaan arsitektur selasar depan 1,732,918,000.00


TOTAL PEKERJAAN ARSITEKTUR 14,342,395,065.92
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG


LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6

C PEKERJAAN POWER HOUSE


STRUKTUR
I PEKERJAAN GROUNTANK
1 Galian Tanah 79.20 m3 40,600.00 3,215,520.00
2 Pasir urug tebal 10 cm 2.40 m3 281,200.00 674,880.00
3 Lantai kerja tebal 5 cm 1.20 m3 1,048,400.00 1,258,080.00
4 Pembesian 2,873.39 kg 14,690.00 42,210,099.10
5 Bekisting 204.60 m2 187,600.00 38,382,960.00
6 Beton 25.80 m3 1,291,000.00 33,307,800.00

II Pekerjaan pondasi P1 (1200 x 1200 x 250 mm)


1 Galian Tanah 41.62 m3 40,600.00 1,689,609.60
2 Pasir urug tebal 10 cm 2.45 m3 281,200.00 688,377.60
3 Lantai kerja tebal 5 cm 1.22 m3 898,500.00 1,099,764.00
4 Pembesian 760.84 kg 14,690.00 11,176,716.10
5 Bekisting 24.48 m2 201,400.00 4,930,272.00
6 Beton K-350 6.12 m3 #REF! #REF!

III Pekerjaan pondasi P2 (800 x 800 x 250 mm)


1 Galian Tanah 5.44 m3 40,600.00 220,864.00
2 Pasir urug tebal 10 cm 0.32 m3 281,200.00 89,984.00
3 Lantai kerja tebal 5 cm 0.16 m3 898,500.00 143,760.00
4 Pembesian 174.05 kg 14,690.00 2,556,765.12
5 Bekisting 7.20 m2 201,400.00 1,450,080.00
6 Beton K-350 0.80 m3 #REF! #REF!

IV Pekerjaan Stump P1 ( 200 x 400 mm )


1 Pembesian 579.10 kg 898,500.00 520,318,205.25
2 Bekisting 9.25 m2 1,397,900.00 12,927,779.20
3 Beton K-350 2.31 m3 166,500.00 384,948.00

V Pekerjaan plat ev.-0,15


1 Pembesian 615.97 kg 14,690.00 9,048,623.78
2 Bekisting 10.20 m2 187,600.00 1,913,520.00
3 Beton K-350 10.20 m3 #REF! #REF!

VI Pekerjaan plat elv. +0,00


1 Pembesian 547.90 kg 14,690.00 8,048,592.24
2 Bekisting 3.60 m2 187,600.00 675,360.00
3 Beton K-350 4.80 m3 #REF! #REF!

VII Pekerjaan Sloof S1 (200 x 400 mm)


1 Galian Tanah 14.59 m3 40,600.00 592,191.60
2 Pasir urug tebal 10 cm 2.65 m3 281,200.00 745,742.40
3 Lantai kerja tebal 5 cm 1.33 m3 898,500.00 1,191,411.00
4 Pembesian 1,540.30 kg 14,690.00 22,626,951.18
5 Bekisting 106.08 m2 90,000.00 9,547,200.00
6 Beton K-350 10.61 m3 #REF! #REF!
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG


LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
VIII Pekerjaan plat elv. + 1,00
1 Pembesian 3,476.00 kg 14,690.00 51,062,440.00
2 Bekisting 19.00 m2 187,600.00 3,564,400.00
3 Beton K-350 19.05 m3 #REF! #REF!
-
IX Pekerjaan Kolom K1 ( 400 X 200 mm ) -
1 Pembesian 913.10 kg 14,690.00 13,413,365.55
2 Bekisting 23.04 m2 168,700.00 3,886,848.00
3 Beton K-350 5.76 m3 #REF! #REF!

X Pekerjaan balok B1.Elv.1,00 (200 x 400 mm)


1 Pembesian 93.48 kg 14,690.00 1,373,250.58
2 Bekisting 6.40 m2 171,400.00 1,096,960.00
3 Beton K-350 0.64 m3 #REF! #REF!

XI Pekerjaan balok B2 Elv. 1,00 (200 x 400 mm)


1 Pembesian 1,165.15 kg 14,690.00 17,116,074.07
2 Bekisting 86.88 m2 171,400.00 14,891,232.00
3 Beton K-350 8.69 m3 #REF! #REF!

XII Pekerjaan balok B2 Elv. 5,00 (200 x 400 mm)


1 Pembesian 1,072.92 kg 14,690.00 15,761,162.97
2 Bekisting 80.00 m2 171,400.00 13,712,000.00
3 Beton K-350 8.00 m3 #REF! #REF!

XIII Pekerjaan plat elv. + 5,00


1 Pembesian 3,465.33 kg 14,690.00 50,905,746.67
2 Bekisting 177.00 m2 187,600.00 33,205,200.00
3 Beton K-350 26.55 m3 #REF! #REF!

XIV Lisplank
1 Pembesian 509.46 kg 14,690.00 7,483,921.86
2 Bekisting 82.50 m2 168,700.00 13,917,750.00
3 Beton K-350 3.85 m3 #REF! #REF!
4 Finising lisplank Acian 77.00 m2

SUB PEKERJAAN STRUKTUR #REF!

ARSITEKTUR
I Pekerjaan pasangan
1 Pasangan Dinding Cilcon 340.98 m2 166,500.00 56,773,170.00
2 Plester 643.38 m2 38,298.00 24,640,167.24
3 Acian 643.38 m2 26,500.00 17,049,570.00
-
II Pekerjaan Pintu dan Jendela -
1 Pekerjaan Pintu plat besi ( Dauble ) 5.00 unit 15,000,000.00 75,000,000.00
2 Pekerjaan Louvre 5.00 unit 1,800,000.00 9,000,000.00
-
III Pekerjaan Pengecatan -
1 Cat Dinding 720.38 m2 32,100.00 23,124,198.00
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG


LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6
-
IV Pekerjaan Keramik ( 300 x 300 mm ) -
1 Pasangan keramik selasar 20.00 m2 145,270.00 2,905,400.00

V PEKERJAAN WATERPROOFING
Waterproofing coating, termasuk primer coating, pada
sambungan dan lain-lain diatas lantai beton
1 Area Groundtank m2 75,000.00
2 Lantai Dak atap m2 75,000.00
-

SUB PEKERJAAN ARSITEKTUR 208,492,505.24


TOTAL PEKERJAAN POWER HOUSE #REF!
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

No Uraian pekerjaan Volume Sat. Harga satuan Jumlah


( Rp ) ( Rp )

1 2 3 4 5 6

PEKERJAAN INFRASTRUKTUR
PEKERJAAN POWER HOUSE
STRUKTUR
I PEKERJAAN GROUNTANK
1 Galian Tanah 79.59 m3 40,600.00 3,231,360.00
2 Pasir urug tebal 10 cm 1.57 m3 281,200.00 440,400.00
3 Lantai kerja K-175 tebal 5 cm 0.87 m3 1,191,700.00 1,032,000.00
4 Pembesian 3,207.87 kg 14,690.00 47,123,596.00
5 Bekisting 191.57 m2 201,400.00 38,601,882.00
6 Beton K-300 28.56 m3 1,291,000.00 36,868,200.00

II Pekerjaan pondasi P1 (1200 x 1200 x 250 mm)


1 Galian Tanah 41.82 m3 40,600.00 1,697,932.80
2 Pasir urug tebal 10 cm 1.60 m3 281,200.00 449,208.00
3 Lantai kerja K-175 tebal 5 cm 0.88 m3 1,191,700.00 1,052,640.00
4 Pembesian 849.40 kg 14,690.00 12,477,749.76
5 Bekisting 9.96 m2 201,400.00 2,007,360.00
6 Beton K-300 6.77 m3 1,291,000.00 8,745,480.00

II Pekerjaan pondasi P2 (800 x 800 x 250 mm)


1 Galian Tanah 5.44 m3 40,600.00 220,864.00
2 Pasir urug tebal 10 cm 0.32 m3 281,200.00 89,984.00
3 Lantai kerja K-175 tebal 5 cm 0.16 m3 1,191,700.00 190,672.00
4 Pembesian 174.05 kg 14,690.00 2,556,765.12
5 Bekisting 7.20 m2 201,400.00 1,450,080.00
6 Beton K-300 0.80 m3 1,291,000.00 1,032,800.00

III Pekerjaan Stump P1 ( 200 x 400 mm )


1 Pembesian 579.10 kg 898,500.00 520,318,205.25
2 Bekisting 9.25 m2 1,397,900.00 12,927,779.20
3 Beton K-300 2.31 m3 166,500.00 384,948.00

IV Pekerjaan plat ev.-0,15


1 Pembesian 615.97 kg 14,690.00 9,048,623.78
2 Bekisting 10.20 m2 181,400.00 1,850,280.00
3 Beton K-300 10.20 m3 1,291,000.00 13,168,200.00

V Pekerjaan plat elv. +0,00


1 Pembesian 547.90 kg 14,690.00 8,048,592.24
2 Bekisting 3.60 m2 181,400.00 653,040.00
3 Beton K-300 4.80 m3 1,291,000.00 6,196,800.00

VI Pekerjaan Sloof S1 (200 x 400 mm)


1 Galian Tanah 14.59 m3 40,600.00 592,191.60
2 Pasir urug tebal 10 cm 2.65 m3 281,300.00 746,007.60
3 Lantai kerja K-175 tebal 5 cm 1.33 m3 1,191,700.00 1,580,194.20
4 Pembesian 1,540.30 kg 14,690.00 22,626,951.18
No Uraian pekerjaan Volume Sat. Harga satuan Jumlah
( Rp ) ( Rp )

1 2 3 4 5 6
5 Bekisting 106.08 m2 90,000.00 9,547,200.00
6 Beton K-300 10.61 m3 1,291,000.00 13,694,928.00

VII Pekerjaan plat elv. + 1,00


1 Pembesian 3,476.00 kg 14,690.00 51,062,440.00
2 Bekisting 19.00 m2 181,400.00 3,446,600.00
3 Beton K-300 19.05 m3 1,291,000.00 24,593,550.00
-
VIII Pekerjaan Kolom K1 ( 400 X 200 mm ) -
1 Pembesian 913.10 kg 14,690.00 13,413,365.55
2 Bekisting 23.04 m2 162,500.00 3,744,000.00
3 Beton K-300 5.76 m3 1,291,000.00 7,436,160.00

IX Pekerjaan balok B1.Elv.1,00 (200 x 400 mm)


1 Pembesian 93.48 kg 14,690.00 1,373,250.58
2 Bekisting 6.40 m2 165,200.00 1,057,280.00
3 Beton K-300 0.64 m3 1,291,000.00 826,240.00

X Pekerjaan balok B2 Elv. 1,00 (200 x 400 mm)


1 Pembesian 1,165.15 kg 14,690.00 17,116,074.07
2 Bekisting 86.88 m2 165,200.00 14,352,576.00
3 Beton K-300 8.69 m3 1,291,000.00 11,216,208.00

XI Pekerjaan balok B2 Elv. 5,00 (200 x 400 mm)


1 Pembesian 1,072.92 kg 14,690.00 15,761,162.97
2 Bekisting 80.00 m2 165,200.00 13,216,000.00
3 Beton K-300 8.00 m3 1,291,000.00 10,328,000.00

XII Pekerjaan plat elv. + 5,00


1 Pembesian 3,465.33 kg 14,690.00 50,905,746.67
2 Bekisting 177.00 m2 181,400.00 32,107,800.00
3 Beton K-300 26.55 m3 1,291,000.00 34,276,050.00

XIII Lisplank
1 Pembesian 509.46 kg 14,690.00 7,483,921.86
2 Bekisting 82.50 m2 162,500.00 13,406,250.00
3 Beton K-300 3.85 m3 1,291,000.00 4,970,350.00
4 Finising lisplank Acian 77.00 m2 150,000.00 11,550,000.00

XIV Pekerjaan Chamber uk. 100 x 100 x 100 cm


1 Galian tanah 1.15 m3 40,600.00 46,690.00
2 Pasir urug tebal 10 cm 0.10 m3 281,200.00 28,120.00
3 Lantai kerja K-175 tebal 5 cm 0.05 m3 1,191,700.00 59,585.00
4 Pembesian 144.48 kg 14,690.00 2,122,411.20
5 Bekisting 11.00 m2 162,500.00 1,787,500.00
6 Beton K-300 0.90 m3 1,291,000.00 1,161,900.00

XV Pekerjaan Dinding Biotech


- Pek. Plat Lantai tebal 15 cm
1 Galian tanah 15.00 m3 40,600.00 609,000.00
2 Pasir urug tebal 10 cm 0.60 m3 281,200.00 168,720.00
3 Lantai kerja K-175 tebal 5 cm 0.30 m3 1,191,700.00 357,510.00
4 Pembesian 107.36 kg 14,690.00 1,577,089.02
5 Bekisting 1.50 m2 162,500.00 243,750.00
6 Beton K-300 0.90 m3 1,291,000.00 1,161,900.00
No Uraian pekerjaan Volume Sat. Harga satuan Jumlah
( Rp ) ( Rp )

1 2 3 4 5 6
- Pek. Kolom uk. 15 x 15 cm
1 Pembesian 55.51 kg 14,690.00 815,453.65
2 Bekisting 40.00 m2 162,500.00 6,500,000.00
3 Beton K-300 0.23 m3 1,291,000.00 290,475.00

XVI Pekerjaan Sumur Resapan Ø 100 CM


1 Galian tanah 1.15 m3 40,600.00 46,690.00
2 Pasir urug tebal 10 cm 0.10 m3 281,200.00 28,120.00
3 Lantai kerja K-175 tebal 5 cm 0.05 m3 1,191,700.00 59,585.00
4 Pembesian 144.48 kg 14,690.00 2,122,411.20
5 Bekisting 11.00 m2 162,500.00 1,787,500.00
6 Beton K-300 0.90 m3 1,291,000.00 1,161,900.00

XIV Pekerjaan Sumpit uk. 150 x 150 x 200 cm


1 Galian tanah 4.84 m3 40,600.00 196,402.50
2 Pasir urug tebal 10 cm 0.23 m3 281,200.00 63,270.00
3 Lantai kerja K-175 tebal 5 cm 0.11 m3 1,191,700.00 134,066.25
4 Pembesian 150.55 kg 14,690.00 2,211,550.12
5 Bekisting 30.30 m2 162,500.00 4,923,750.00
6 Beton K-300 2.48 m3 1,291,000.00 3,195,225.00

XV Pekerjaann tank solar


- Pek. Plat Lantai tebal 12 cm
1 Galian tanah 22.00 m3 40,600.00 893,200.00
2 Pasir urug tebal 10 cm 2.00 m3 281,200.00 562,400.00
3 Lantai kerja K-175 tebal 5 cm 1.00 m3 1,191,700.00 1,191,700.00
4 Pembesian 203.61 kg 14,690.00 2,991,030.90
5 Bekisting 1.80 m2 162,500.00 292,500.00
6 Beton K-300 2.00 m3 1,291,000.00 2,582,000.00

SUB PEKERJAAN STRUKTUR POWER HOUSE 1,165,669,345.27

ARSITEKTUR
I Pekerjaan pasangan
1 Pasangan Dinding Cilcon 340.98 m2 166,500.00 56,773,170.00
2 Plester 628.38 m2 38,298.00 24,065,697.24
3 Acian 628.38 m2 26,500.00 16,652,070.00
4 Pasangan bata dinding Biotech 25.00 m2 111,600.00 2,790,000.00
-
II Pekerjaan Pintu dan Jendela -
1 Pekerjaan Pintu plat besi ( Dauble ) 5.00 unit 15,000,000.00 75,000,000.00
2 Pekerjaan Louvre 5.00 unit 1,800,000.00 9,000,000.00
-
III Pekerjaan Pengecatan -
1 Cat Dinding 705.38 m2 32,100.00 22,642,698.00
-
IV Pekerjaan Keramik ( 300 x 300 mm ) -
1 Pasangan keramik selasar 20.00 m2 145,270.00 2,905,400.00
-
V PEKERJAAN WATERPROOFING -
Waterproofing coating, termasuk primer coating, pada -
sambungan dan lain-lain diatas lantai beton -
1 Area Groundtank 25.60 m2 75,000.00 1,920,000.00
No Uraian pekerjaan Volume Sat. Harga satuan Jumlah
( Rp ) ( Rp )

1 2 3 4 5 6
2 Lantai Dak atap 180.55 m2 75,000.00 13,541,250.00
-

SUB PEKERJAAN ARSITEKTUR POWER HOUSE 225,290,285.24


TOTAL POWER HOUSE 1,390,959,630.51

PEKERJAAN GATE HOUSE


I Pekerjaan pondasi P1 uk. 150 x 150 x 30 cm
1 Galian Tanah 63.00 m3 40,600.00 2,557,800.00
2 Pasir urug tebal 10 cm 4.50 m3 281,200.00 1,265,400.00
3 Lantai kerja K-175 tebal 5 cm 2.25 m3 1,191,700.00 2,681,325.00
4 Pembesian 2,430.12 kg 14,690.00 35,698,462.80
5 Bekisting 34.56 m2 201,400.00 6,960,384.00
6 Beton K-300 13.50 m3 1,291,000.00 17,428,500.00
7 Urugan tanah kembali 44.10 m3 19,400.00 855,540.00

II Pekerjaan Stump uk. 40 x 40 cm


1 Pembesian 751.18 kg 201,400.00 151,288,054.80
2 Bekisting 24.00 m2 162,500.00 3,900,000.00
3 Beton K-300 2.40 m3 1,291,000.00 3,098,400.00

III Pekerjaan Sloof S1 uk. 30 x 40 cm


1 Galian Tanah 3.96 m3 40,600.00 160,776.00
2 Pasir urug tebal 10 cm 0.72 m3 281,200.00 202,464.00
3 Lantai kerja K-175 tebal 5 cm 0.36 m3 1,191,700.00 429,012.00
4 Pembesian 358.77 kg 14,690.00 5,270,338.65
5 Bekisting 19.20 m2 89,900.00 1,726,080.00
6 Beton K-300 2.88 m3 1,291,000.00 3,718,080.00

IV Pekerjaan Sloof S2 uk. 20 x 30 cm


1 Galian Tanah 7.47 m3 40,600.00 303,282.00
2 Pasir urug tebal 10 cm 1.66 m3 281,200.00 466,792.00
3 Lantai kerja K-175 tebal 5 cm 0.83 m3 1,191,700.00 989,111.00
4 Pembesian 1,041.25 kg 14,690.00 15,295,979.39
5 Bekisting 66.40 m2 89,900.00 5,969,360.00
6 Beton K-300 9.96 m3 1,291,000.00 12,858,360.00

V Pekerjaan Kolom K1 uk. Ø 40 cm


1 Pembesian 1,167.45 kg 14,690.00 17,149,786.64
2 Bekisting 115.55 m2 162,500.00 18,777,200.00
3 Beton K-300 9.93 m3 1,291,000.00 12,819,952.75

VI Pekerjaan Praktis uk. 15 x 15 cm


1 Pembesian 132.16 kg 14,690.00 1,941,477.41
2 Bekisting 16.56 m2 898,500.00 14,879,160.00
3 Beton bertulang 1Pc : 2Ps : 3Kr 0.62 m3 1,291,000.00 801,711.00

VII Pekerjaan Ring Balok uk. 20 x 30 cm


1 Pembesian 1,390.68 kg 14,690.00 20,429,089.20
2 Bekisting 85.60 m2 165,200.00 14,141,120.00
3 Beton K-300 6.42 m3 1,291,000.00 8,288,220.00

VIII Pekerjaan Atap


1 Atap ( Rangka Baja atap alumunium metal ) 174.65 m2 950,000.00 165,914,141.41
2 Pekerjaan Talang air 21.00 m' 150,000.00 3,150,000.00
No Uraian pekerjaan Volume Sat. Harga satuan Jumlah
( Rp ) ( Rp )

1 2 3 4 5 6
IX Pekerjaan Dinding
1 Dinding Alumunium Compisit termasuk rangka pemasangan 101.57 m2 892,500.00 90,650,154.00
2 Pekerjaan kaca dinding 4 mm 46.80 m2 1,250,000.00 58,500,000.00

X Pekerjaan Plafon
1 Plafond Metal Expose 199.42 m2 825,000.00 164,521,500.00
2 Listplank (bahan dari alumunium composit) 98.85 m' 650,000.00 64,252,500.00

X Pekerjaan Pintu
1 Pemasangan pintu + aceccoris 3.00 bh 2,500,000.00 7,500,000.00

TOTAL PEKERJAAN PINTU MASUK 936,839,514.05

PEKERJAAN AREA PARKIR


1 Plat Beton Tebal 15 Cm
Pembesian 54,821.46 kg 14,690.00 805,327,255.63
Beton K-350 1,510.79 m3 1,369,100.00 2,068,419,850.80
2 Kansteen 728.00 m' 105,000.00 76,440,000.00
3 Taman 788.00 m2 53,230.00 41,945,240.00
4 Penanaman Pohon palem 64.00 btg 1,750,000.00 112,000,000.00
5 Pekerjaan Atap ( Rangka Besi hollow galvanis atap alumunium Metal ) 12.81 m2 1,250,000.00 16,012,500.00

SUB PEKERJAAN PAGAR 3,120,144,846.43

PEKERJAAN DRAINASE
1 Galian Tanah Saluran 403.50 m3 2,390.00 964,365.00
2 Lantai kerja K-175 tebal 5 cm 26.90 m3 201,400.00 5,417,660.00
3 Pekerjaan Saluran U.60 551.00 m' 502,308.75 276,772,120.62
4 Pekerjaan Saluran U.40 506.00 m' 401,878.75 203,350,646.92
5 Grill Penutup Saluran 138.00 m' 750,000.00 103,500,000.00

SUB PEKERJAAN PARKIR 590,004,792.54

PEKERJAAN LAIN LAIN


1 Meja Counter Tiket lantai 2 ( Bahan multiplek 15 mm dan 12 mm lapis HPL ) 33.00 m2 3,500,000.00 115,500,000.00
2 Meja Counter Tiket lantai 1 ( Bahan multiplek 15 mm dan 12 mm lapis HPL ) 11.88 m2 3,500,000.00 41,580,000.00
3 Meja Reception dan Informasi 10.56 m2 3,500,000.00 36,960,000.00
3 Box Charger 1.08 m2 3,500,000.00 3,780,000.00

SUB PEKERJAAN PARKIR 197,820,000.00


TOTAL PEKERJAAN INFRASTRUKTUR 6,235,768,783.52
BACK UP DATA

NO URAIAN PEKERJAAN PANJANG LEBAR TINGGI JUMLAH JUMLAH 2 JUMLAH 3 LUAS (M2) SATUAN BERAT VOLUME VOLUME TOTAL KETERANGAN

27

PEKERJAAN PERSIAPAN
1 Mobilisasi Dan Demobilisasi 1 1.00

2 Ditreksi keet a Kantor Kontraktor 9 4 36 108.00

b Kantor Direksi 5 4 20

c Kantor Konsultan 6 4 24

d Ruang Rapat 7 4 28

Ac ( 2 PK) Kantor Kontraktor 2 2 5.00

Kantor Direksi 1 1

Kantor Konsultan 1 1

Ruang Rapat 1 1

Kursi Kantor Kontraktor 8 8 31.00

Kantor Direksi 5 5

Kantor Konsultan 6 6

Ruang Rapat 12 12

Meja Kantor Kontraktor 8 8 20.00

Kantor Direksi 5 5

Kantor Konsultan 6 6

Ruang Rapat 1 1

Whiteboard Kantor Kontraktor 1 1 4.00

Kantor Direksi 1 1

Kantor Konsultan 1 1

Ruang Rapat 1 1
3 Barak 9 10 90.00

5 Papan Nama Proyek 1.00 1.00

6 Laboratorium 1.00 1.00

7 Shop Drawing 5.00 5.00

8 As Buil Drawing 5.00 5.00

9 Foto dokumentasi proyek 5.00 5.00

10 Pagar proyek sementara 243.54

Pemborong wajib untuk membuat pagar sementara

pada keliling areal proyek serta berkewajiban untuk


menyingkirkan/membersihkan kembali pada waktu

penyelesaian atau jika diperintahkan. Juga memperbaiki segala

kerusakan.
11 Penyediaan air kerja 1.00

Pemborong harus menyediakan air bersih untuk keperluan kerja,


termasuk penyediaan air untuk testing kebocoran pada atap, lantai
toilet Dll.

12 Penyediaan listrik kerja 1.00

Penyedia jasa harus menyediakan pembangkit tenaga listrik


sementara, untuk keperluan kerja dan penerangan yang
dipergunakan untuk keperluannya. Semua biaya pemakaian & izin izin
menjadi tanggung jawab penyedia jasa

13 Pembersihan Lapangan ringan 19,372.04

14 Pengukuran dan Pemasangan Bouwplank 272.35

15 Bongkaran bangunan lama 5,231.00


16 Jaring Pengaman untuk Bangunan ( Safety Net ) 1,740.00

17 Selasar Sementara
237.16

A Pondasi 500x 500 x 200

1 Galian Tanah 0.5 0.5 0.5 82 m3 10.25

2 Pasir urug tebal 10 cm 0.5 0.5 0.1 82 m3 2.05

3 Lantai kerja tebal 5 cm 0.5 0.5 0.05 82 m3 1.03

4 Pembesian a x 0.6 82 2 kg 0.888 87.3792 87.38

5 Bekisting 0.5 0.2 82 4 m2 32.80

6 Beton 0.5 0.2 82 m3 8.20


B Stump 200 x 200 mm
4 Pembesian lajur 1 82 4 kg 0.888 291.264 294.72

sengkang 0.7 8 0.617 3.4552

5 Bekisting 1 0.2 82 4 m2 65.60

6 Beton 1 0.2 0.2 82 m3 3.28

C Anchur 82 4 328.00

D Pipa 4 " 2.5 82 205 205.00

F Pipa 2,5" 4 82 328 1,168.00

G Gording 120 7 840

H Base Plat tebal 150 mm 82 4.71 386.22

i Anchur 82 8 1.66 1088.96

PEKERJAAN STRUKTUR
ELV. - 0.00
I Pekerjaan Tiang Pancang

1 Pengadaan tiang mini pile 40 x 40 cm 18 149 m' 2,682.00

2 Pemancangan tiang mini pile 16 149 m' 2,384.00

3 Penyambungan tiang mini pile 149 titik 149.00

4 Pemotongan tiang mini pile 149 titik 149.00

6 Pekerjaan Loading Test


- PDA Loading Test bh 5.00

PEKERJAAN URUGAN TANAH

1 Urugan Tanah ( Urugan tanah mendatangkan Dan di padatkan Untuk leveling pada Bangunan ) 18,368.95

II Pekerjaan Pile Cap P1 uk. 850 x 850 mm

1 Galian Tanah 0.85 0.85 0.95 67 m3 45.99

2 Pasir urug tebal 10 cm 0.85 0.85 0.1 67 m3 4.84

3 Lantai kerja tebal 5 cm 0.85 0.85 0.05 67 m3 2.42

4 Pembesian x 2.6 67 2 7 kg 2.226 5428.7688 8,833.15

y 2.6 67 2 5 kg 1.578 2748.876

tambahan 3.1 67 2 kg 1.578 655.5012

5 Bekisting 0.85 0.8 67 4 m2 182.24

6 Beton 0.85 0.85 0.8 67 m3 38.73


III Pekerjaan Pile Cap P2 uk. 2200 x 900 mm

1 Galian Tanah 2.2 0.9 0.95 40 m3 75.24

2 Pasir urug tebal 10 cm 2.2 0.9 0.1 40 m3 7.92

3 Lantai kerja tebal 5 cm 2.2 0.9 0.05 40 m3 3.96

4 Pembesian a x 3.5 40 6 kg 2.226 46.746 527.01

y 2.2 40 15 kg 2.226 73.458

b x 2.2 40 5 kg 1.578 17.358

y 0.9 40 12 kg 1.578 17.0424

tambahan 5.9 40 kg 1.578 372.408

5 Bekisting 6.2 0.8 40 m2 198.40

6 Beton 2.2 0.9 0.8 40 m3 63.36

IV Pekerjaan Stump K1 uk. 600 x 600 mm

1 Pembesian 2 53 20 kg 2.226 4,719.12

IV Pekerjaan Stump K1A uk. 600 x 600 mm

1 Pembesian 2 19 20 kg 2.226 1,691.76

V Pekerjaan Stump K2 300 x 300 mm

1 Pembesian 2 19 8 kg 0.888 269.95

VI Pekerjaan Pit Lift

1 Galian tanah 2.5 2.5 1.7 2 m3 21.25

2 Pasir urug tebal 10 cm 2.5 2.5 0.1 2 m3 1.25

3 Lantai kerja tebal 5 cm 2.5 2.5 0.05 2 m3 0.63

4 Pembesian x 5.8 2 13 2 kg 1.042 302.18 630.02

y 5 2 11 2 kg 1.042 218.82

samping lapis 1 luar 9.3 2 10 kg 0.617 109.0239

dalam 7.7 2 9 kg 0.617

lapis 2 luar 2 2 kg 0.617

dalam 1.5 2 kg 0.617

5 Bekisting a 5.8 0.2 2 4 m2 9.28 232.48

b 9.3 1.5 2 4 2 m2 223.2

6 Beton a 5.8 5 0.2 2 m3 11.6 33.92

b 9.3 1.5 0.2 2 4 m3 22.32

VII Pekerjaan Pit Escalator


1 Galian tanah 4.6 1.8 1.2 2 m3 19.87

2 Pasir urug tebal 10 cm 4.6 1.8 0.1 2 m3 1.66

3 Lantai kerja tebal 5 cm 4.6 1.8 0.05 2 m3 0.83

4 Pembesian a x 4.6 13 2 2 kg 0.617 147.5864 566.65

y 1.8 32 2 2 kg 0.617 142.1568

b x 1.8 8 2 2 4 kg 0.617 142.1568

y 1.05 13 2 2 4 kg 0.617 134.7528

5 Bekisting a 4.6 1.8 0.15 2 m3 2.484 4.75

b 1.8 1.05 0.15 2 4 m3 2.268

6 Beton a 12.8 0.15 2 m2 3.84 34.08

b 1.8 1.05 2 2 4 m2 30.24

VIII Pekerjaan Ground Water Tank

1 Galian tanah 8 3 3.3 m3 79.20

2 Pasir urug tebal 10 cm 8 3 0.1 m3 2.40

3 Lantai kerja tebal 5 cm 8 3 0.05 m3 1.20

4 Pembesian sisi a & b x 3 2 2 16 kg 1.578 302.976 2,636.65

y 3 2 2 16 kg 0.888 170.496

sisi c & d x 8 2 2 16 kg 0.888 454.656

y 3 2 2 41 kg 1.578 776.376

sisi bawah x 8 2 16 kg 1.578 403.968

y 3 2 41 kg 0.888 218.448

sisi atas x 8 2 16 kg 0.617 157.952

y 3 2 41 kg 0.617 151.782

5 Bekisting sisi a & b 3 3 2 2 m2 36 186.60

sisi c & d 8 3 2 2 m2 96

sisi bawah 22 0.3 m2 6.6

sisi atas 8 3 2 m2 48

6 Beton sisi a & b 3 3 0.2 2 m3 3.6 24.00

sisi c & d 8 3 0.2 2 m3 9.6

sisi bawah 8 3 0.3 m3 7.2

sisi atas 8 3 0.15 m3 3.6

PEKERJAAN STRUKTUR (ELV. ± 0.00)


I Pekerjaan Sloof TB1 uk. 350 x 700 mm

1 Galian tanah 408 0.35 0.85 m3 121.38

2 Pasir urug tebal 10 cm 408 0.35 0.1 m3 14.28

3 Lantai kerja tebal 5 cm 408 0.35 0.05 m3 7.14


4 Pembesian
a Besi Lajur 408 18 kg 2.226 16347.744 22,750.97

c lajur Samping 408 2 kg 0.617 503.472

d Sengkang
- panjang 8 m tumpuan 2 40 35 kg 0.617 1727.6

lapangan 2 27 35 0.617 1166.13

- panjang 6 m tumpuan 2 30 12 kg 0.617 444.24

lapangan 2 20 12 0.617 296.16

Penambahan sengkang 0.9 4080 408 0.617 2265.624

5 Bekisting 408 0.7 2 m2 571.20

6 Beton 408 0.35 0.7 m3 99.96

II Pekerjaan Sloof TB2 uk. 350 x 700 mm

1 Galian tanah 541 0.35 0.85 m3 160.95

2 Pasir urug tebal 10 cm 541 0.35 0.1 m3 18.94

3 Lantai kerja tebal 5 cm 541 0.35 0.05 m3 9.47

4 Pembesian
a Lajur 541 12 kg 2.226 14451.192 21,444.89

b lajur samping 541 2 kg 0.617 667.594

d sengkang tumpuan jarak 100 mm

- panjang 8 m 2 40 24 kg 0.617 1,185

- panjang 6 m 2 30 15 kg 0.617 555.3

- panjang 5 m 2 25 2 kg 0.617 61.7

- panjang 3 m 2 15 10 kg 0.617 185.1

e sengkang lapangan jarak 150 mm


- panjang 8 m 2 27 24 kg 0.617 799.632

- panjang 6 m 2 20 15 kg 0.617 370.2

- panjang 5 m 2 17 2 kg 0.617 41.956

- panjang 3 m 2 10 10 kg 0.617 123.4

Penambahan sengkang 0.9 5410 541 kg 0.617 3004.173

5 Bekisting 541 0.7 2 m2 757.40

6 Beton 541 0.35 0.7 m3 132.55

III Pekerjaan Sloof TB3 uk. 300 x 600 mm

1 Galian tanah 76 0.3 0.75 m3 17.10

2 Pasir urug tebal 10 cm 76 0.3 0.1 m3 2.28

3 Lantai kerja tebal 5 cm 76 0.3 0.05 m3 1.14


4 Pembesian
a Lajur 76 12 kg 2.226 2030.112 2,791.00

c tulangan samping 76 2 kg 0.617 93.784

d sengkang tumpuan jarak 100 mm


- panjang 8 m 1.7 40 8 kg 0.617 335.648

- panjang 6 m 1.7 30 2 kg 0.617 62.934

e sengkang lapangan jarak 150 mm

- panjang 8 m 1.7 27 8 kg 0.617 226.5624

- panjang 6 m 1.7 20 2 kg 0.617 41.956

5 Bekisting 76 0.6 2 m2 91.20

6 Beton 76 0.3 0.6 m3 13.68

IV Pekerjaan Sloof TB4 uk. 300 x 600 mm

1 Galian tanah 344 0.3 0.75 m3 77.40

2 Pasir urug tebal 10 cm 344 0.3 0.1 m3 10.32

3 Lantai kerja tebal 5 cm 344 0.3 0.05 m3 5.16

4 Pembesian

a tulangan tumpuan 344 10 kg 2.226 7657.44 10,908.72

c tulangan samping 344 2 kg 0.617 424.496

d sengkang tumpuan jarak 100 mm


- panjang 8 m 1.7 40 25 kg 0.617 1048.9

- panjang 6 m 1.7 30 17 kg 0.617 534.939

e sengkang lapangan jarak 150 mm


- panjang 8 m 1.7 27 25 kg 0.617 708.0075

- panjang 6 m 1.7 30 17 kg 0.617 534.939

5 Bekisting 344 0.6 2 m2 412.80

6 Beton 344 0.3 0.6 m3 61.92

V Pekerjaan Sloof TB5 uk. 300 x 500 mm

1 Galian tanah 10 0.3 0.65 m3 1.95

2 Pasir urug tebal 10 cm 10 0.3 0.1 m3 0.30

3 Lantai kerja tebal 5 cm 10 0.3 0.05 m3 0.15

4 Pembesian kg

a tulangan tumpuan 10 12 kg 2.226 267.12 844.95

b tulangan lapangan 10 12 kg 2.226 267.12

c tulangan samping 10 2 kg 0.617 12.34

d sengkang tumpuan jarak 100 mm 1.45 92 kg 0.888 118.4592


e sengkang lapangan jarak 150 mm 1.45 68 kg 0.888 87.5568

f sengkang tulangan ganda jarak 100 mm 0.65 92 kg 0.888 53.1024

g sengkang tulangan ganda jarak 150 mm 0.65 68 kg 0.888 39.2496

5 Bekisting 10 0.5 2 m2 10.00

6 Beton 10 0.3 0.5 m3 1.50

VI Pekerjaan Sloof TB6 uk. 200 x 400 mm

1 Galian tanah 144.8 0.2 0.55 m3 15.93 21.70

2 Pasir urug tebal 10 cm 144.8 0.2 0.1 m3 2.90 3.95

3 Lantai kerja tebal 5 cm 144.8 0.2 0.05 m3 1.45 1.97

4 Pembesian

a tulangan tumpuan 474 kg 2.226 1055.124 3,734.27 4,877.07

b tulangan lapangan 474 kg 2.226 1055.124

c sengkang tumpuan jarak 100 mm

- panjang 8 m 1.06 39 21 kg 0.888 770.90832

- panjang 6 m 1.06 29 7 kg 0.888 191.07984

- panjang 4 m 1.06 19 1 kg 0.888 17.88432

d sengkang lapangan jarak 150 mm


- panjang 8 m 1.06 25.666666667 21 kg 0.888 507.34992

- panjang 6 m 1.06 19 7 kg 0.888 125.19024

- panjang 4 m 1.06 12.333333333 1 kg 0.888 11.60912

5 Bekisting 144.8 0.5 2 m2 144.80 144.80

6 Beton 144.8 0.2 0.5 m3 14.48 14.48

VI Pekerjaan Sloof TB6 uk. 200 x 400 mm

1 Galian tanah 52.5 0.2 0.55 m3 5.78

2 Pasir urug tebal 10 cm 52.5 0.2 0.1 m3 1.05

3 Lantai kerja tebal 5 cm 52.5 0.2 0.05 m3 0.53

4 Pembesian
a tulangan tumpuan 420 kg 0.888 372.96 1,142.80

b tulangan lapangan 345 kg 0.888 306.36

c sengkang tumpuan jarak 100 mm


- panjang 4 m 1.06 19 9 kg 0.617 111.83742

- panjang 3 m 1.06 14 12 kg 0.617 109.87536

- panjang 2.5 m 1.06 12 8 kg 0.617 60.16984

d sengkang lapangan jarak 150 mm

- panjang 4 m 1.06 12.333333333 9 kg 0.617 72.59622


- panjang 3 m 1.06 9 12 kg 0.617 70.63416

- panjang 2.5 m 1.06 7.3333333333 8 kg 0.617 38.369173333

5 Bekisting 52.5 0.4 2 m2 42.00

6 Beton 52.5 0.2 0.4 m3 4.20

VI Pekerjaan Sloof CTB2 uk. 300 x 600 mm

1 Galian tanah 2 0.3 0.75 m3 0.45

2 Pasir urug tebal 10 cm 2 0.3 0.1 m3 0.06

3 Lantai kerja tebal 5 cm 2 0.3 0.05 m3 0.03

4 Pembesian
a tulangan tumpuan 20 kg 2.226 44.52 123.99

b tulangan lapangan 20 kg 2.226 44.52

c tulangan samping 2 2 kg 0.617 2.468

d sengkang tumpuan jarak 100 mm


- panjang 2.5 m 1.5 12 1 kg 0.888 15.984

e sengkang lapangan jarak 150 mm


- panjang 2.5 m 1.5 7.6666666667 1 kg 0.888 10.212

f sengkang tulangan ganda jarak 100 mm

- sengkang tulangan ganda panjang 2.5 0.36 12 1 kg 0.888 3.83616

g sengkang tulangan ganda jarak 150 mm

- sengkang tulangan ganda panjang 2.5 0.36 7.6666666667 1 kg 0.888 2.45088

5 Bekisting 2 0.6 2 m2 2.40

6 Beton 2 0.3 0.6 m3 0.36

VIII Pekerjaan Plat lantai tebal 12 cm Elv.0,00

1 Perkerasan tebal 12 cm 3596.46 m2 3,596.46

Beton 0.12 3596.46 m3 431.58

Pembesian x 3596.46 5.443 19,575.53

IX Pekerjaan Kolom K1 uk. 600 x 600 mm

1 Pembesian lajur 5.6 54 20 kg 2.226 13462.848 18,128.75

sengkang 2.1 54 31.666666667 kg 0.888 3188.808

extra 1.4 54 31.666666667 kg 0.617 1477.098

2 Bekisting 4.6 0.6 54 4 m2 596.16

3 Beton 4.6 0.6 0.6 54 m3 89.42


X Pekerjaan Kolom K1A uk. 600 x 600 mm

1 Pembesian lajur 5.6 18 20 kg 2.226 4487.616 6,042.92

sengkang 2.1 18 31.666666667 kg 0.888 1062.936

extra 1.4 18 31.666666667 kg 0.617 492.366

2 Bekisting 4.6 0.6 18 4 m2 198.72

3 Beton 4.6 0.6 0.6 18 m3 29.81

XI Pekerjaan Kolom K2 uk. 300 x 300 mm

1 Pembesian lajur 4 12 8 kg 0.888 340.992 744.51

sengkang 1.1 12 28 kg 0.617 228.0432

2 Bekisting 4 0.3 12 4 m2 57.6 74.40

3 Beton 4 0.3 0.3 12 m3 4.32 5.58

1 Pembesian lajur 1 14 8 kg 0.888 99.456

sengkang 1.1 14 8 kg 0.617 76.0144

2 Bekisting 1 0.3 14 4 m2 16.8

3 Beton 1 0.3 0.3 14 m3 1.26

XII Pekerjaan Kolom KT uk. 130 x 500 mm

1 Pembesian lajur 5 3 6 kg 1.578 142.02 230.73

sengkang 1.11 3 30 kg 0.888 88.7112

2 Bekisting 4.6 0.315 3 4 m2 17.39

3 Beton 4.6 0.13 0.5 3 m3 0.90

XIII Pekerjaan Kolom KL

1 Pembesian lajur 5 12 14 kg 1.578 1325.52 1,326.41

sengkang 2.5 12 30 kg 0.617 0.888

2 Bekisting 4.6 2 12 m2 110.40

3 Beton 4.6 0.8 0.2 12 m3 8.83

XIV Pekerjaan Kolom Praktis uk. 13 x 13 cm

1 Pembesian lajur 5 70 4 kg 0.617 863.8 1,170.72

sengkang 0.37 70 30 kg 0.395 306.915

2 Bekisting 4.6 0.13 70 m2 41.86

3 Beton 4.6 0.13 0.13 70 m3 5.44


XVI Pekerjaan Tangga Beton tipe 1

1 Pembesian plat bawah x 9.46 17 2 kg 1.042 335.14888 741.75

y 2.32 65 2 kg 0.617 186.0872

anak tangga x 2.32 26 kg 0.395 23.8264

y 1 26 13 kg 0.395 133.51

bordes x 2.6 10 2 kg 0.617 32.084

y 1.8 14 2 kg 0.617 31.0968

2 Bekisting plat bawah 9.46 2.32 m2 21.9472 37.48

anak tangga 2.32 0.18 26 m2 10.8576

bordes 2.6 1.8 m2 4.68

3 Beton plat bawah 9.46 2.32 0.15 m3 3.29208 5.62

anak tangga 2.32 0.3 0.18 26 0.5 m3 1.62864

bordes 2.6 1.8 0.15 m3 0.702

XVII Pekerjaan Tangga Beton Tipe 2,3,4

1 Pembesian plat bawah x 9.1 11 3 2 kg 1.042 625.8 2,563.7

y 1.46 63 3 2 kg 1.042 575.1

anak tangga x 1.46 3 26 kg 1.042 118.7

y 1 3 26 9 kg 1.042 731.484

bordes x 3 3 14 2 kg 1.042 262.584

y 2.5 3 16 2 kg 1.042 250.08

2 Bekisting plat bawah 9.1 1.46 3 m2 39.858 82.86

anak tangga 1.46 0.18 3 26 m2 20.4984

bordes 3 2.5 3 m2 22.5

3 Beton plat bawah 9.1 1.46 0.15 3 m3 5.9787 12.43

anak tangga 1.46 0.18 0.3 3 26 0.5 m3 3.07476

bordes 3 2.5 0.15 3 m3 3.375

PEKERJAAN MEJA WASTAFEL

1 Pekerjaan Meja Beton panjang 1,35 x 0,6 m 2.00

PEKERJAAN STRUKTUR (ELV. + 4.80)


I Pekerjaan Balok G1 uk. 350 x 700 mm

1 Pembesian
a tulangan tumpuan 3132 kg 2.226 6971.832 19,990.16

b tulangan lapangan 3132 kg 2.226 6971.832


c tulangan samping 313 2 kg 0.617 386.242

d sengkang tumpuan jarak 100 mm


- panjang 8 m 1.8 39 36 kg 0.888 2244.1536

- panjang 6 m 1.8 29 10 kg 0.888 463.536

e sengkang lapangan jarak 150 mm


- panjang 8 m 1.8 25.666666667 36 kg 0.888 1476.9216

- panjang 6 m 1.8 19 10 kg 0.888 303.696

f sengkang tulangan ganda jarak 100 mm


- sengkang tulangan ganda panjang 8 0.47 39 36 kg 0.888 585.97344

- sengkang tulangan ganda panjang 6 0.47 29 10 kg 0.888 121.0344

g sengkang tulangan ganda jarak 150 mm

- sengkang tulangan ganda panjang 8 0.47 25.666666667 36 kg 0.888 385.64064

- sengkang tulangan ganda panjang 6 0.47 19 10 kg 0.888 79.2984

2 Bekisting 313 0.7 2 m2 438.20

3 Beton 313 0.35 0.7 m3 76.69

II Pekerjaan Balok G2 uk. 350 x 700 mm

1 Pembesian
a tulangan tumpuan 3240 kg 2.226 7212.24 21,932.76

b tulangan lapangan 3240 kg 2.226 7212.24

c tulangan samping 396.6 2 kg 0.617 489.4044

d sengkang tumpuan jarak 100 mm

- panjang 8 m 1.8 39 39 kg 0.888 2431.1664

- panjang 6 m 1.8 29 20 kg 0.888 927.072

e sengkang lapangan jarak 150 mm


- panjang 8 m 1.8 25.666666667 39 kg 0.888 1599.9984

- panjang 6 m 1.8 19 20 kg 0.888 607.392

f sengkang tulangan ganda jarak 100 mm


- sengkang tulangan ganda panjang 8 0.47 39 39 kg 0.888 634.80456

- sengkang tulangan ganda panjang 6 0.47 29 20 kg 0.888 242.0688

g sengkang tulangan ganda jarak 150 mm

- sengkang tulangan ganda panjang 8 0.47 25.666666667 39 kg 0.888 417.77736

- sengkang tulangan ganda panjang 6 0.47 19 20 kg 0.888 158.5968

2 Bekisting 396.6 0.7 2 m2 555.24

3 Beton 396.6 0.35 0.7 m3 97.17


III Pekerjaan Balok G3 uk. 300 x 600 mm

1 Pembesian
a tulangan tumpuan 816 kg 2.226 1816.416 5,677.57

b tulangan lapangan 816 kg 2.226 1816.416

c tulangan samping 125.2 2 kg 0.617 154.4968

d sengkang tumpuan jarak 100 mm


- panjang 8 m 1.5 39 14 kg 0.888 727.272

- panjang 6 m 1.5 29 4 kg 0.888 154.512

e sengkang lapangan jarak 150 mm


- panjang 8 m 1.5 25.666666667 14 kg 0.888 478.632

- panjang 6 m 1.5 19 4 kg 0.888 101.232

f sengkang tulangan ganda jarak 100 mm


- sengkang tulangan ganda panjang 8 0.42 39 14 kg 0.888 203.63616

- sengkang tulangan ganda panjang 6 0.42 29 4 kg 0.888 43.26336

g sengkang tulangan ganda jarak 150 mm


- sengkang tulangan ganda panjang 8 0.47 25.666666667 14 kg 0.888 149.97136

- sengkang tulangan ganda panjang 6 0.47 19 4 kg 0.888 31.71936

2 Bekisting 125.2 0.6 2 m2 150.24

3 Beton 125.2 0.3 0.6 m3 22.54

IV Pekerjaan Balok B1 uk. 300 x 600 mm

1 Pembesian
a tulangan tumpuan 2535 kg 2.226 5642.91 17,151.58

b tulangan lapangan 2535 kg 2.226 5642.91

c tulangan samping 309.2 2 kg 0.617 381.5528

d sengkang tumpuan jarak 100 mm


- panjang 8 m 1.8 39 25 kg 0.888 1558.44

- panjang 6 m 1.8 29 23 kg 0.888 1066.1328

e sengkang lapangan jarak 150 mm


- panjang 8 m 1.8 25.666666667 25 kg 0.888 1025.64

- panjang 6 m 1.8 19 23 kg 0.888 698.5008

f sengkang tulangan ganda jarak 100 mm

- sengkang tulangan ganda panjang 8 0.47 39 25 kg 0.888 406.926

- sengkang tulangan ganda panjang 6 0.47 29 23 kg 0.888 278.37912

g sengkang tulangan ganda jarak 150 mm

- sengkang tulangan ganda panjang 8 0.47 25.666666667 25 kg 0.888 267.806

- sengkang tulangan ganda panjang 6 0.47 19 23 kg 0.888 182.38632


2 Bekisting 309.2 0.6 2 m2 371.04

3 Beton 309.2 0.3 0.6 m3 55.66

V Pekerjaan Balok B2 uk. 300 x 500 mm

1 Pembesian
a lajur 48.6 8 kg 2.226 865.4688 1,278.32

b sengkang tumpuan jarak 100 mm

- panjang 4 m 1.45 21 5 kg 0.617 93.93825

- panjang 6 m 1.45 31 1 kg 0.617 27.73415

- panjang 2,8 m 1.45 15 7 kg 0.617 93.93825

c sengkang lapangan jarak 150 mm

- panjang 4 m 1.45 14 5 kg 0.617 62.6255

- panjang 6 m 1.45 20 1 kg 0.617 17.893

- panjang 2,8 m 1.45 10 7 kg 0.617 62.6255

d tulangan extra 12.15 2 kg 2.226 54.0918

2 Bekisting 48.6 0.5 2 m2 48.60

3 Beton 48.6 0.3 0.5 m3 7.29

VI Pekerjaan Balok B3 uk. 200 x 400 mm

1 Pembesian
a lajur 3 8 kg 2.226 53.424 140.98

b sengkang tumpuan jarak 100 mm


- panjang 3 m 1.05 16 5 kg 0.617 51.828

c sengkang lapangan jarak 150 mm

- panjang 3 m 1.05 10 5 kg 0.617 32.3925

d tulangan extra 0.75 2 kg 2.226 3.339

2 Bekisting 3 0.4 2 m2 2.40

3 Beton 3 0.2 0.4 m3 0.24

VII Pekerjaan Balok CG2 uk. 300 x 600 mm

1 Pembesian
a lajur 6 18 kg 2.226 240.408 514.86

b sengkang tumpuan jarak 100 mm

- panjang 4 m 1.65 21 2 kg 0.617 42.7581

c sengkang lapangan jarak 150 mm

- panjang 4 m 1.65 14 2 kg 0.617 28.5054

d sengkang tulangan pokok 0.7 455 kg 0.617 196.5145

e tulangan extra 1.5 2 kg 2.226 6.678


2 Bekisting 6 0.6 2 m2 7.20

3 Beton 6 0.3 0.6 m3 1.08

VIII Pekerjaan Plat S1 tebal 15 cm

1 Pembesian x 1 7 2829.72 kg 0.617 12221.56068 24,443.12

y 1 7 2829.72 kg 0.617 12221.56068

2 2444.12 m2 2,444.12

3 Beton 1 1 0.15 2444.12 m3 366.62

IX Pekerjaan Kolom K1 uk. 600 x 600 mm

1 Pembesian lajur 5.6 54 16 kg 1.578 7634.9952 11,463.71

sengkang 1.85 54 29 kg 0.888 2572.6248

extra 1.3 54 29 kg 0.617 1256.0886

2 Bekisting 4.2 0.5 54 4 m2 453.60

3 Beton 4.2 0.5 0.5 54 m3 56.70

X Pekerjaan Kolom KL

1 Pembesian lajur 5 12 14 kg 1.578 1325.52 2,124.72

sengkang 2.5 12 30 kg 0.888 799.2

2 Bekisting 4.4 2 12 m2 105.60

3 Beton 4.4 0.8 0.2 12 m3 8.45

XIV Pekerjaan Kolom Praktis uk. 13 x 13 cm

1 Pembesian lajur 4.985 105 4 kg 0.617 1291.8129 1,752.19

sengkang 0.37 105 30 kg 0.395 460.3725

2 Bekisting 4.385 0.13 105 m2 59.86

3 Beton 4.385 0.13 0.13 105 m3 7.78

XV Pekerjaan Rangka Atap

Rangka atap baja ( as 3 dan 10)

Rangka Pipa Galvanish dia 190.7, t=5mm ( 8") 48.7 2 6 m' 584 754.40
Rangka Pipa Galvanish dia 89.1, t=2.8mm ( 4") -

sisi miring 2.2 25.35 6 m' 335 3,635.12

tegak 1 25.35 6 m' 152

Plat penyambung ( base plat tebal 25 mm ) 10 6 2 kg 8.635 1036.2 12,641.64

Plat penyambung ( base plat tebal 10 mm ) pengaku 10 6 2 kg 8.635 1036.2

baut plat penyambung 8 dia 19 8 10 6 2 bh 0.226 216.96 2,660.93


Rangka atap baja ( as 4-9 )

Rangka Pipa Galvanish dia 190.7, t=5mm ( 8") 42.5 2 2 m' 170
Rangka Pipa Galvanish dia 89.1, t=2.8mm ( 4")

sisi miring 2.2 22.25 2 m' 98

tegak 1 22.25 2 m' 45

Plat penyambung ( base plat tebal 25 mm ) 9 2 2 kg 8.635 310.86

Plat penyambung ( base plat tebal 10 mm ) pengaku 9 2 2 8.635 310.86

baut plat penyambung 8 dia 19 8 9 2 2 bh 0.226 65.088

FR1 PANJANG 60,5

Rangka Pipa Galvanish dia 165.2 , t=5mm (7") 60.5 2 15 1,815


Rangka Pipa Galvanish dia 89.1, t=2.8mm ( 4")

MIRING 2 42 15 1,260

TEGAK 1 42 15 630

Plat penyambung ( base plat tebal 25 mm ) 12 15 2 kg 8.635 3108.6

Plat penyambung ( base plat tebal 10 mm ) pengaku 12 15 2 8.635 3108.6

baut plat penyambung 8 dia 19 8 12 15 2 bh 0.226 650.88


FR1 PANJANG 45

Rangka Pipa Galvanish dia 165.2 , t=5mm (7") 45 2 12 1080


Rangka Pipa Galvanish dia 89.1, t=2.8mm ( 4")

MIRING 2 31 12 744

TEGAK 1 31 12 372

Plat penyambung ( base plat tebal 25 mm ) 9 12 2 kg 8.635 1865.16

Plat penyambung ( base plat tebal 25 mm ) 9 12 2 8.635 1865.16

baut plat penyambung 8 dia 19 8 9 12 2 bh 0.226 1728


Gording Baja C. 200.75.20.3.2 60.5 52 9.27 29163.42
ikatan angin dia 16 49 28 1.58 2165.016
Trexstang 1 ( dia 12 ) 10 48 0.888 426.24
Pengecatan Besi 754.40 0.7288 549.81 4,907.20

1,815 0.4788 869.02

3,635.12 0.3192 1160.33

3146 0.74 2328.04

Atap spandek 60.5 48.7


Lisplank alumunium composit termasuk rangka 218.4 218.4
KOLOM ATAS

Rangka Pipa Galvanish dia 190.7, t=5mm ( 8") 12 24 m' 288


Base Plat 25 mm kolom 24 kg 70.65 1695.6 5,887.44
Base Plat 25 mm pengikat 24 kg 135.41 3249.84
Base Plat 25 mm pengaku 24 kg 39.25 942
BAUT 6 DIA 19 24 24 bh 0.192 110.592
Angkur 12 dia 32 24 12 bh 7.4 2131.2

Pengecatan Besi 288.00 0.7288 209.89

SELASAR BELAKANG

Pipa dia 5" 8.735 9 m' 4.5 78.615


Pipa dia 4" 583.039 m' 3.46 583.039
Pipa 2,5 " 12.2 9 m' 1.76 109.8
Plat Besi 15.775 9 kg 8.635 1225.954125
L. Atap 346.145 346.145
Baut 36 0.192 6.912
Streaktank baja 8 9 0.888 63.936
Anchur 4dia 19 4 9 2.226 80.136

Pengecatan Besi 78.62 0.399 31.37 406.84

583.04 0.3192 186.11

109.80 0.1994 21.89

141.975

25.5

PEKERJAAN MEJA WASTAFEL

1 Pekerjaan Meja Beton panjang 1,35 x 0,6 m 2.00

2 Pekerjaan Meja Beton panjang 1,5 x 0,6 m 3.00

3 Pekerjaan Meja Beton panjang 1,06 x 0,6 m 1.00

PEKERJAAN STRUKTUR (ELV. + 9.60)


I Pekerjaan Ring Balok RB1 uk. 350 x 700

1 Pembesian

a lajur 228 12 kg 1.578 4317.408 7,579.77

b sengkang tumpuan jarak 100 mm


- panjang 8 m 1.95 41 24 kg 0.617 1183.8996

- panjang 6 m 1.95 31 6 kg 0.617 223.7859


c sengkang lapangan jarak 150 mm
- panjang 8 m 1.95 27 24 kg 0.617 779.6412

- panjang 6 m 1.95 20 6 kg 0.617 144.378

d sengkang tulangan pokok 0.8 1521 kg 0.617 750.7656

e tulangan extra 57 2 kg 1.578 179.892

2 Bekisting 228 0.7 2 m2 319.20

3 Beton 228 0.35 0.7 m3 55.86

II Pekerjaan Ring Balok RB2 uk. 300 x 600

1 Pembesian

a lajur 16 9 kg 1.578 227.232 1,035.23

b sengkang tumpuan jarak 100 mm

- panjang 8 m 1.65 41 2 kg 0.617 83.4801

c sengkang lapangan jarak 150 mm


- panjang 8 m 1.65 27 2 kg 0.617 54.9747

d sengkang tulangan pokok 0.7 1521 kg 0.617 656.9199

e tulangan extra 4 2 kg 1.578 12.624

2 Bekisting 16 0.6 2 m2 19.20

3 Beton 16 0.3 0.6 m3 2.88

III Pekerjaan Ring Balok RB3 uk. 300 x 500

1 Pembesian
a lajur 190 9 kg 1.578 2698.38 4,293.15

b sengkang tumpuan jarak 100 mm


- panjang 8 m 1.45 41 8 kg 0.617 293.4452

- panjang 6 m 1.45 31 21 kg 0.617 582.41715

c sengkang lapangan jarak 150 mm


- panjang 8 m 1.45 27 8 kg 0.617 193.2444

- panjang 6 m 1.45 20 21 kg 0.617 375.753

d tulangan extra 47.5 2 kg 1.578 149.91

2 Bekisting 190 0.5 2 m2 190.00

3 Beton 190 0.3 0.5 m3 28.50

IV Pekerjaan Ring Balok RB4 uk. 200 x 450

1 Pembesian

a lajur 18.9 8 kg 1.578 238.5936 361.36

b sengkang tumpuan jarak 100 mm


- panjang 6 m 1.15 31 1 kg 0.617 21.99605
- panjang 2,5 m 1.15 14 2 kg 0.617 19.8674

- panjang 2 m 1.15 11 4 kg 0.617 31.2202

c sengkang lapangan jarak 150 mm

- panjang 6 m 1.15 15 1 kg 0.617 10.64325

- panjang 3,95 m 1.15 7 2 kg 0.617 9.9337

- panjang 2 m 1.15 5 4 kg 0.617 14.191

d tulangan extra 4.725 2 kg 1.578 14.9121

2 Bekisting 18.9 0.45 2 m2 17.01

3 Beton 18.9 0.2 0.45 m3 1.70

V kolom KL

1 Pembesian lajur 4 12 14 kg 1.578 1060.416 1,859.62

sengkang 2.5 12 30 kg 0.888 799.2

2 Bekisting 3 2 12 m2 72.00

3 Beton 3 0.8 0.2 12 m3 5.76

XIV Pekerjaan Kolom Praktis uk. 13 x 13 cm

1 Pembesian lajur 4 10 4 kg 0.617 98.72 142.57

sengkang 0.37 10 30 kg 0.395 43.845

2 Bekisting 3 0.13 10 m2 3.90

3 Beton 3 0.13 0.13 10 m3 0.51

VI Pekerjaan Plat S2 tebal 15 cm

1 Pembesian 1 m2 pembesian 16.453

pembesian 532.24 16.453 8,756.94

2 Bekisting 532.24 m2 532.24

3 Beton 0.15 532.24 m3 79.84

PEKERJAAN STRUKTUR (ELV. + 12.60)


I Pekerjaan Ring Balok RB1 uk. 350 x 700

1 Pembesian
a lajur 37.4 12 kg 1.578 708.2064 1,055.27

37.4 2 kg 0.617

d sengkang tulangan pokok 0.8 375 kg 0.617 185.1

e Sengkang tulangan exstra 0.7 375 kg 0.617 161.9625


2 Bekisting 37.4 0.7 2 m2 52.36

3 Beton 37.4 0.35 0.7 m3 9.16

I Pekerjaan Ring Balok RB4 uk. 200 x 450

1 Pembesian

a lajur 19.8 8 kg 1.578 249.9552 250.57

d sengkang tulangan pokok 1 1 kg 0.617 0.617

2 Bekisting 19.8 0.45 2 m2 17.82

3 Beton 19.8 0.2 0.45 m3 1.78

I Pekerjaan Ring Balok RB2 uk. 300 x 600

1 Pembesian
a lajur 16 9 kg 1.578 227.232 558.35

exstra 16 2 kg 0.617 19.744

d sengkang tulangan pokok 1.6 161 kg 0.617 158.9392

exstra 0.6 161 1.578 152.4348

2 Bekisting 16 0.6 2 m2 19.20

3 Beton 16 0.3 0.6 m3 2.88

I Pekerjaan Ring Balok RB3 uk. 300 x 500

1 Pembesian
a lajur 18 9 kg 1.578 255.636 411.98

d sengkang tulangan pokok 1.4 181 kg 0.617 156.3478

2 Bekisting 18 0.5 2 m2 18.00

3 Beton 18 0.3 0.5 m3 2.70

Plat beton elv 12,60


Beton 0.15 184.482 27.6723

Pembesian 184.482 16.453 3035.282346

begesting 184.482 184.482

Lisplank

beton 106.32 0.1 0.7 7.4424 7.44

pembesian 106.32 8 0.617 524.79552 984.42

0.7 1064.2 0.617 459.628

begesting 106.32 0.7 2 148.848 159.48

106.32 0.1 10.632

SELASAR KIRI

I Pekerjaan pondasi P1 (1200 x 1200 x 250 mm)

1 Galian Tanah 1.2 1.2 1.2 5 m3 8.64

2 Pasir urug tebal 10 cm 1.2 1.2 0.1 5 m3 0.72

3 Lantai kerja tebal 5 cm 1.2 1.2 0.05 5 m3 0.36

4 Pembesian x 2.8 5 9 kg 0.888 111.888 223.78

y 2.8 5 9 kg 0.888 111.888

5 Bekisting 1.2 1.2 0.25 5 4 m2 7.20

6 Beton 1.2 1.2 0.25 5 m3 1.80

II Pekerjaan Sloof TB6 uk. 400 x 200 mm

1 Galian tanah 108 0.25 0.55 m3 14.85

2 Pasir urug tebal 10 cm 108 0.25 0.1 m3 2.70

3 Lantai kerja tebal 5 cm 108 0.25 0.05 m3 1.35

4 Pembesian

a tulangan tumpuan 108 5 kg 0.888 479.52 2,182.06

b tulangan lapangan 108 5 kg 0.888 479.52

d sengkang tumpuan jarak 100 mm 1.1 1081 kg 0.617 733.6747

e sengkang lapangan jarak 150 mm 1.1 721 kg 0.617 489.3427


5 Bekisting 108 0.4 2 m2 86.40

6 Beton 108 0.2 0.2 m3 4.32

XI Pekerjaan Stump K2 300 x 300 mm

1 Pembesian lajur 2 5 8 kg 0.888 71.04 128.88

sengkang 1.25 5 15 kg 0.617 57.84375

2 Bekisting 2 0.3 5 4 m2 12.00

3 Beton 2 0.3 0.3 5 m3 0.90

XI Pekerjaan Kolom K2 uk. 300 x 300 mm

1 Pembesian lajur 6.5 5 8 kg 0.888 230.88 380.19

sengkang 1.1 5 44 kg 0.617 149.314

2 Bekisting 6.5 0.3 5 4 m2 39 39.00

3 Beton 6.5 0.3 0.3 5 m3 2.925 2.93


Plat Beton T. 10 cm

Beton 26 5 0.1 13

Pembesian 130 5.443 707.59


begesting 26 0.1 2 5.2

Pekerjaan Atap

pekerjaan pipa 4 " panjang 5 m 5 7 35 91.00

pekerjaan pipa 4 " panjang 12 m 12 4 48

pekerjaan pipa 4 " panjang 4 m 4 2 8


Gording Baja C. 200.75.20.3.2 26 8 9.27 1928.16

Plat tebal 150 mm 5 2 2 4.71 94.2

Anchur 5 8 1.66843 66.7372

SELASAR DEPAN

I Pekerjaan pondasi P1 (1200 x 1200 x 250 mm)

1 Galian Tanah 1.2 1.2 1.2 14 m3 24.19

2 Pasir urug tebal 10 cm 1.2 1.2 0.1 14 m3 2.02

3 Lantai kerja tebal 5 cm 1.2 1.2 0.05 14 m3 1.01

4 Pembesian x 2.8 14 9 kg 0.888 313.2864 626.57

y 2.8 14 9 kg 0.888 313.2864

5 Bekisting 1.2 1.2 0.25 14 4 m2 20.16

6 Beton 1.2 1.2 0.25 14 m3 5.04

III Pekerjaan Sloof TB6 uk. 400 x 200 mm

1 Galian tanah 422 0.25 0.55 m3 58.03

2 Pasir urug tebal 10 cm 422 0.25 0.1 m3 10.55

3 Lantai kerja tebal 5 cm 422 0.25 0.05 m3 5.28

4 Pembesian
a tulangan tumpuan 422 5 kg 0.888 1873.68 8,522.24

b tulangan lapangan 422 5 kg 0.888 1873.68

d sengkang tumpuan jarak 100 mm 1.1 4221 kg 0.617 2864.7927

e sengkang lapangan jarak 150 mm 1.1 2814.3333333 kg 0.617 1910.0880333

5 Bekisting 422 0.4 2 m2 337.60

6 Beton 422 0.2 0.2 m3 16.88

IV Pekerjaan Stump K2 uk. 300 x 300 mm

1 Pembesian lajur 2 14 8 kg 0.888 198.912 341.44

sengkang 1.1 14 15 kg 0.617 142.527


2 Bekisting 1.5 0.3 14 4 m2 25.20

3 Beton 2 0.3 0.3 14 m3 2.52

V Pekerjaan Kolom K2 uk. 300 x 300 mm

1 Pembesian lajur 6.5 14 8 kg 0.888 646.464 1,064.54

sengkang 1.1 14 44 kg 0.617 418.0792

2 Bekisting 6.5 0.3 14 4 m2 109.20

3 Beton 6.5 0.3 0.3 14 m3 8.19

VI Plat Beton T. 10 cm

Beton 114.64 5 0.1 57.32

Pembesian 573.2 5.443 3,120

begesting 114.64 0.1 2 22.928

Pekerjaan Atap
pekerjaan pipa 4 " panjang 5 m 5 16 2 160.000 616.00

pekerjaan pipa 4 " panjang 16 m 16 13 2 416.000

pekerjaan pipa 4 " panjang 10 m 10 2 2 40.000


Gording Baja C. 200.75.20.3.2 114.64 8 2 9.27 17003.405

Plat tebal 150 mm 14 2 2 4.71 263.760

Anchur 14 8 2 1.66843 373.728


BACK UP DATA

VOLUME
NO URAIAN PEKERJAAN PANJANG LEBAR TINGGI JUMLAH JUMLAH 2 JUMLAH 3 LUAS (M2) SATUAN BERAT VOLUME KETERANGAN
TOTAL

ELV. ± 0.00
I Pekerjaan Dinding

1 Pasangan Bata ringan 510.75 4.4 m2 2247.3 1,971.15

16.25 2.4 m2 39

PT1 6 2.16 m2 12.96

PT2 16 1.95 m2 31.2

PB1 2 4.68 m2 9.36

PB2 4 0.66 m2 2.64

PJ1 4 17.568 m2 70.272

PJ2 1 13.176 m2 13.176

PJ3 2 4.043 m2 8.086

PJ4 2 3.92 m2 7.84

PJ7 2 9.042 m2 18.084

PJ8 4 20.16 m2 80.64

PJ10 3 4.665 m2 13.995

J1 5 21.016 m2 105.08

J2 1 10.934 m2 10.934

J3 2 8.586 m2 17.172

J9 2 3.7761 m2 7.5522

BV2 1 2.194 m2 2.194

BV5 2 1.94 m2 3.88

P1 1 2.5075 m2 2.5075

PG1 1 2.4 m2 2.4

2 diding partisi 47.65 4.4 m2 209.66 198.63

PJ4 1 3.92 m2 3.92

P2 1 2.45 m2 2.45

PJ10 1 4.665 m2 4.665

2 Plesteran m2 3,942.29
3 Aci halus m2 3,942.29

4 kolom praktis dan lintel beam 4.4 108 m' 475.20

II Pekerjaan Pintu dan Jendela

1 Pintu PT1 bh 3.00

Kusen Allumunium

Daun pintu Rangka kayu + Penutup double multiplek lapis HPL

Kaca mati 6mm buram -Es + frame allumunium keliling

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

1 Pintu PT1' bh 3.00

Kusen Allumunium

Daun pintu Rangka kayu + Penutup double multiplek lapis HPL

Kaca mati 6mm buram -Es + frame allumunium keliling

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

2 Pintu PT2 bh 8.00

Kusen Allumunium

Daun pintu Rangka kayu + Penutup double multiplek lapis HPL + Jalusi

Accecories Handle jungkit, engsel kupu kupu, lockset

2 Pintu PT2' bh 8.00

Kusen Allumunium
Daun pintu Rangka kayu + Penutup double multiplek lapis HPL + Jalusi

Accecories Handle jungkit, engsel kupu kupu, lockset

3 Pintu PB1 bh 2.00

Kusen Metal sheet 2mm

Daun pintu metal sheet 2mm fin. Cat duco

Kaca mati 6mm buram -Es + Jalusi

Accecories Handle tanam st steel , Engsel Bubut , lockset

4 Pintu PB2 bh 4.00

Kusen Metal sheet 2mm

Daun pintu metal sheet 2mm fin. Cat duco


Accecories Handle tanam st steel , Engsel Bubut , lockset

5 Pintu P1' bh 1.00

Kusen Allumunium

Daun pintu Kaca t=8mm

Acc. Handle tarik allumunium , engsel kupu kupu, lockset, door closer

6 Pintu P2 bh 1.00

Kusen Allumunium

Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL

Handle Tarik st steel engsel floor hinge, lockset

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

Silicone sealent clear ex glazing

5 Pintu PJ1 bh 4.00

Kusen Allumunium

Daun pintu pintu otomatis( kaca tempered 12mm frameless t=12mm

Pintu double swing Pintu kaca t=8mm frame allumunium


Handle Tarik untuk Kaca frameless handle tarik st steel untuk pintu kaca

frame allumunium, Floor hinges , Lockset

Silicone sealent clear glass /box frame st steel ( hire line )

6 Pintu PJ2 bh 1.00

Kusen Allumunium
Daun pintu kaca t8mm frame allumunium keliling

Handle Tarik st steel engsel floor hinge, lockset

frame allumunium, Floor hinges , Lockset

Silicone sealent clear glass /box frame st steel ( hire line )

7 Pintu PJ3 bh 2.00

Kusen Allumunium

Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL

Handle Tarik st steel engsel floor hinge, lockset

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

Silicone sealent clear ex glazing


8 Pintu PJ4 bh 3.00

Kusen Allumunium

Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL

Handle Tarik st steel engsel floor hinge, lockset

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

Silicone sealent clear ex glazing

10 Pintu PJ7 bh 1.00

Kusen Allumunium

Daun pintu kaca t8mm frame allumunium keliling

Handle Tarik st steel engsel floor hinge, lockset

frame allumunium, Floor hinges , Lockset

Silicone sealent clear glass /box frame st steel ( hire line )

Silicone sealent clear glass /box frame st steel ( hire line )

11 Pintu PJ8 bh 4.00

Kusen Allumunium

Daun pintu kaca t8mm frame allumunium keliling

Handle Tarik st steel engsel floor hinge, lockset


frame allumunium, Floor hinges , Lockset

Silicone sealent clear glass /box frame st steel ( hire line )

Silicone sealent clear glass /box frame st steel ( hire line )

12 Pintu PJ10 bh 4.00

Kusen Allumunium

Gawangan

Daun pintu kaca t8mm frame allumunium keliling

Handle Tarik st steel engsel floor hinge, lockset

frame allumunium, Floor hinges , Lockset

Silicone sealent clear glass /box frame st steel ( hire line )

13 Jendela J1 bh 5.00

Kusen Allumunium

Silicone sealent clear glass /box frame st steel ( hire line )


14 Jendela J2 bh 1.00

Kusen Allumunium

Silicone sealent clear glass /box frame st steel ( hire line )

15 Jendela J3 bh 2.00

Kusen Allumunium
Silicone sealent clear glass /box frame st steel ( hire line )

16 Jendela J9 bh 2.00

Kusen Allumunium

Silicone sealent clear glass /box frame st steel ( hire line )

17 Jendela Bouvenlight BV

Kusen Allumunium

Kaca mati panasap CHFSL t=6mm

Silicone sealent clear glass /box frame st steel ( hire line )

Jendela Bouvenlight BV2 bh 1.00

Jendela Bouvenlight BV5 bh 2.00

III Pekerjaan Lantai

1 Pemasangan Keramik Homogeneus Tile - Polish ( 80 x 80 cm ) F1 m2 980.54 3,322.04

Pemasangan Keramik Homogeneus Tile - UnPolish (80 x80 cm ) F2 m2 2,341.50

2 Pemasangan Keramik Tangga - Polish ( 30 x 60 cm )

tipe 1 anak tangga 2.475 0.3 26 m2 19.305 82.75

2.475 0.178 26 m2 11.4543

bordes 2.6 1.8 m2 4.68

tipe 2,3,4 ank tangga 1.3 0.3 2 26 m2 20.28

1.3 0.178 2 26 m2 12.0328

bordes 3 2.5 2 m2 15

3 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x 60 cm ) m2 91.76

4 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x30 cm ) m2 50.89

5 Pemasangan Keramik Dinding KM Homogeneus Tile ( 30 x 60 cm ) 119.2 3 m2 357.6 514.664

98.46 2.4 m2 236.304

lubang 1 12.96 m2 12.96


2 31.2 m2 62.4

1 3.88 m2 3.88
IV Pekerjaan Plafond

1 Plafond gypsum m2 2,359.89

2 Plafond Semen Board m2 151.92

3 Plafond Metal Expose m2 43.50

4 List Plafond m' 1,100.50

V Pekerjaan Cat

1 Cat dinding cilcon m2 3,942.29 4,339.54

1 Cat dinding partisi m2 397.25

2 Cat Plafond m2 2,511.81

VI Pekerjaan Waterproofing

1 Lantai Satu Area toilet m2 142.65

ELV. ± 4.80
I Pekerjaan Dinding

1 Pasangan Bata ringan 426 4.4 m2 1874.4 1,516.31

lubang PT1' 3 2.16 m2 6.48

PT2 7 1.95 m2 13.65

PB2 5 0.66 m2 3.3

P2 2 2.45 m2 4.9

J2 1 11.704 m2 11.704

J3 5 8.586 m2 42.93

J4 4 7.069 m2 28.276

J5 9 26.721 m2 240.489

J8 1 7.985 m2 7.985

J10 2 3.15 m2 6.3

BV3 10 1.18 m2 11.8

BV4 2 1.588 m2 3.176

BV5 1 1.94 m2 1.94

1 Pasangan dinding partisi 144.15 4.4 m2 634.26 602.31


PJ4 2 3.435 m2 6.87

P1 10 2.508 m2 25.08

P2 4 2.45 m2 9.8

2 Plesteran m2 3,032.63

3 Aci halus m2 3,032.63

4 kolom praktis dan lintel beam 4.4 120 m' 528.00

II Pekerjaan Pintu dan Jendela

1 Pintu PT1 bh 2.00

Kusen Allumunium

Daun pintu Rangka kayu + Penutup double multiplek lapis HPL

Kaca mati 6mm buram -Es + frame allumunium keliling

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

2 Pintu PT1' bh 1.00

Kusen Allumunium

Daun pintu Rangka kayu + Penutup double multiplek lapis HPL


Kaca mati 6mm buram -Es + frame allumunium keliling

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

3 Pintu PT2 bh 3.00

Kusen Allumunium

Daun pintu Rangka kayu + Penutup double multiplek lapis HPL + Jalusi

Accecories Handle jungkit, engsel kupu kupu, lockset

4 Pintu PT2' bh 4.00

Kusen Allumunium

Daun pintu Rangka kayu + Penutup double multiplek lapis HPL + Jalusi

Accecories Handle jungkit, engsel kupu kupu, lockset

6 Pintu PB2 bh 5.00

Kusen Metal sheet 2mm


Daun pintu metal sheet 2mm fin. Cat duco

Accecories Handle tanam st steel , Engsel Bubut , lockset

7 Pintu P1 bh 5.00

Kusen Allumunium

Daun pintu Kaca t=8mm


Acc. Handle tarik allumunium , engsel kupu kupu, lockset, door closer

8 Pintu P1' bh 5.00

Kusen Allumunium

Daun pintu Kaca t=8mm

Acc. Handle tarik allumunium , engsel kupu kupu, lockset, door closer

9 Pintu P2 bh 6.00

Kusen Allumunium

Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL

Handle Tarik st steel engsel floor hinge, lockset

Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer
Silicone sealent clear ex glazing

6 Pintu PJ4 bh 2.00

Kusen Allumunium

Daun pintu rangka kayu solid multiplek double luar dlm lapis HPL

Handle Tarik st steel engsel floor hinge, lockset


Accecories Handle biasa ( jungkit), engsel kupu kupu, lockset, door closer

Silicone sealent clear ex glazing


7 Jendela Kaca

Kusen Allumunium

Silicone sealent clear glass /box frame st steel ( hire line )

Jendela J2 bh 1.00

Jendela J3 bh 5.00

Jendela J4 bh 4.00

Jendela J5 bh 9.00

Jendela J6 bh 1.00

8 Jendela Bouvenlight BV

Kusen Allumunium

Silicone sealent clear glass /box frame st steel ( hire line )

Jendela Bouvenlight BV2 bh 10.00

Jendela Bouvenlight BV3 bh 2.00

Jendela Bouvenlight BV4 bh 1.00

9 Jendela Loket ( kaca rangka allumunium ) bh 10.00

15 Roling Door bh 10.00

III Pekerjaan Lantai

1 Pemasangan Keramik Homogeneus Tile - Polish ( 80X80 cm ) F1 m2 2,287.00 2,504.77

Pemasangan Keramik - Polish (80 x80 cm ) F3 m2 217.77

2 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x 60 cm ) m2 46.64

3 Pemasangan Keramik Kamar Mandi Homogeneus Tile - UnPolish ( 30 x30 cm ) m2 15.41

4 Pemasangan Keramik Dinding KM Homogeneus Tile ( 30 x 60 cm ) 31.7 3 m2 95.10 150.96

38.16 2.4 m2 91.58

LUBANG 6.48 m2 6.48

2 13.65 m2 27.30

1.94 m2 1.94

5 Pemasangan Keramik Dinding tempat wudhu ( 30x60 cm )

IV Pekerjaan Plafond

1 Plafond gypsum m2 887.20


2 Plafond Alumunium Curve m2 3,285.75

3 Plafond Semen Board m2 83.85

4 List Plafond m' 747.75

5 Pekerjaan alumunium composite ( fasade, pelapis kolom lantai 1 dan 2 ) m2 852.83

V Pekerjaan Cat

1 Cat dinding m2 3,634.94

2 Cat Plafond m2 971.05

VI Pekerjaan Waterproofing

1 Lantai Dua Area toilet dan tempat wudhu m2 62.05

VII Pekerjaan Penutup Atap


1 m2 647.06
Atap Canopy Depan dan samping kiri bangunan ( rangka galvanis,atap alumunium metal,
termasuk pembuatan talang air)

2 m2 346.15

Atap bangunan selasar belakang ( Alumunium Curve Metal, termasuk pembuatan talang air)

3 Atap Tenant ( rangka dari hollow ) m2 72.575

ELV. ± 9.60
I Pekerjaan Dinding

1 Pasangan Bata 53.675 2 m2 107.35 97.99

lubang PB1 2 4.68 m2 9.36

2 Plesteran m2 195.98

3 Aci halus m2 195.98

II Pekerjaan Pintu dan Jendela

1 PB1 bh 2.00

Kusen Metal sheet 2mm

Daun pintu metal sheet 2mm fin. Cat duco

Accecories Handle tanam st steel , Engsel Bubut , lockset

III Pekerjaan Lantai


1 Pekerjaan Floor Hardener 3 kg/m2 m2 32.91

IV Pekerjaan Plafond

1 Plafond Expose m2 49.38

V Pekerjaan Waterproofing

1 Lantai Dak atap m2 586.20

VI Pekerjaan Penutup Atap

1 Atap Spandek Utama m2 3,285.75

2 Rock wool + kawat ayam m2 3,285.75

Pekerjaan Arsitektur Selasar Samping

1 Pekerjaaan Plafon alumunium Metal 145.00

2 Pekerjaan lisplank ( rangka hollow covering alumunium Composit ) 68.00

3 145.00
Pekerjaan Atap ( Rangka Besi hollow galvanis, pipa 4' atap alumunium Metal termasuk
pembuatan talang air )

4 Pekerjaan Keramik 800 x 800 mm 130.00

Pekerjaan Arsitektur Selasar Depan

1 Pekerjaaan Plafon alumunium Metal 1,140.00

2 Pekerjaan lisplank ( rangka hollow covering alumunium Composit ) 476.00

3 1,140.00
Pekerjaan Atap ( Rangka Besi hollow galvanis pipa 4' atap alumunium Metal termasuk
pembuatan talang air)

4 Pekerjaan Keramik 800 x 800 mm 570.00


BACK UP DATA

VOLUME
NO URAIAN PEKERJAAN PANJANG LEBAR TINGGI JUMLAH JUMLAH 2 JUMLAH 3 LUAS (M2) SATUAN BERAT VOLUME KETERANGAN
TOTAL

VIII Pekerjaan Ground Water Tank

1 Galian tanah 8 3 3.3 m3 79.20

2 Pasir urug tebal 10 cm 8 3 0.1 m3 2.40

3 Lantai kerja tebal 5 cm 8 3 0.05 m3 1.20

4 Pembesian sisi a & b x 3 2 2 16 kg 1.578 302.976 2,873.39

y 3 2 2 16 kg 0.888 170.496

sisi c & d x 8 2 2 16 kg 0.888 454.656

y 3 2 2 41 kg 1.578 776.376

sisi bawah x 8 2 16 kg 1.578 403.968

y 3 2 41 kg 0.888 218.448

sisi atas x 8 2 16 kg 0.617 157.952

y 3 2 41 kg 0.617 151.782

sisi tengah x 3 1 2 16 kg 1.578 151.488

y 3 1 2 16 kg 0.888 85.248

5 Bekisting sisi a & b 3 3 2 2 m2 36 204.60

sisi c & d 8 3 2 2 m2 96

sisi bawah 22 0.3 m2 6.6

sisi atas 8 3 2 m2 48

tengah 3 3 2 18

6 Beton sisi a & b 3 3 0.2 2 m3 3.6 25.80

sisi c & d 8 3 0.2 2 m3 9.6

sisi bawah 8 3 0.3 m3 7.2

sisi atas 8 3 0.15 m3 3.6

8 3

tengah 3 0.2 3 1.8


III Pekerjaan pondasi P1 (1200 x 1200 x 250 mm)

1 Galian Tanah 1.2 1.2 1.7 17 m3 41.62

2 Pasir urug tebal 10 cm 1.2 1.2 0.1 17 m3 2.45

3 Lantai kerja tebal 5 cm 1.2 1.2 0.05 17 m3 1.22

4 Pembesian x 2.8 17 9 kg 0.888 380.4192 760.84

y 2.8 17 9 kg 0.888 380.4192

5 Bekisting 1.2 1.2 0.25 17 4 m2 24.48

6 Beton 1.2 1.2 0.25 17 m3 6.12

III Pekerjaan pondasi P2 (800 x 800 x 250 mm)

1 Galian Tanah 0.8 0.8 1.7 5 m3 5.44

2 Pasir urug tebal 10 cm 0.8 0.8 0.1 5 m3 0.32

3 Lantai kerja tebal 5 cm 0.8 0.8 0.05 5 m3 0.16

4 Pembesian x 2.8 5 7 kg 0.888 87.024 174.05

y 2.8 5 7 kg 0.888 87.024

5 Bekisting 1.2 1.2 0.25 5 4 m2 7.20

6 Beton 0.8 0.8 0.25 5 m3 0.80

Pekerjaan Stump P1 ( 200 x 400 mm )

Pembesian

Lajur 3.2 10 17 0.888 483.072 579.10

Sengkang 1.1 13 17 0.395 96.0245

Beton 1.7 0.4 0.2 17 2.312

begesting 1.7 0.4 0.2 4 17 9.248

Pekerjaan Stump P2 ( 200 x 400 mm )

Pembesian

Lajur 3.2 10 5 0.888 142.08 170.32

Sengkang 1.1 13 5 0.395 28.2425

Beton 1.7 0.4 0.2 5 0.68

begesting 1.7 0.4 0.2 4 5 2.72


Pekerjaan plat ev.-0,15

1 Perkerasan tebal 15 cm

Beton 68 1 0.15 10.20

Pembesian 68 8 0.617 335.6 615.97

1 454.3333333 0.617 280.3236667

Begesting 68 0.15 10.2

Pekerjaan plat elv. +0,00

1 Perkerasan tebal 15 cm

Beton 8 4 0.15 4.80

Pembesian 8 28 2 0.617 276.4 547.90

4 55 2 0.617 271.5

Begesting 8 0.15 2 2.4 3.60

4 0.15 2 1.2
Pekerjaan Sloof S1 (200 x 400 mm)

1 Galian tanah 132.6 0.2 0.55 m3 14.59

2 Pasir urug tebal 10 cm 132.6 0.2 0.1 m3 2.65

3 Lantai kerja tebal 5 cm 132.6 0.2 0.05 m3 1.33

4 Pembesian

Lajur 132.6 9 kg 0.888 1059.7392 1,540.30

Sengkang 1.1 1106 0.395 480.557

5 Bekisting 132.6 0.4 2 m2 106.08

6 Beton 132.6 0.2 0.4 m3 10.61

Pekerjaan plat elv. + 1,00

1 Perkerasan tebal 15 cm

Beton 1 11 9 0.15 14.85 19.05

2 6 4 0.15 3.6

RAMP 4 1 0.15 0.6

Begesting 47.5 0.4 19

Pembesian

1 11 61 2 0.617 1342 3,476.00

9 75 2 0.617 1350

2 6 28 2 0.617 336

4 41 2 0.617 328
RAMP 4 8 2 0.617 64

1 28 2 0.617 56

Pekerjaan Kolom K1 ( 400 X 200 mm )

1 Pekerjaan Kolom

Beton 4 0.4 0.2 18 5.76

Pembesian

Lajur 4 10 18 0.888 639.36 913.10

Sengkang 1.1 35 18 0.395 273.74

Begesting 4 0.4 0.2 4 18 23.04 23.04

Pekerjaan balok B1.Elv.1,00 (200 x 400 mm)

4 Pembesian
Lajur 8 9 kg 0.888 63.936 93.48

Sengkang 1.1 68 0.395 29.546

5 Bekisting 8 0.4 2 m2 6.40

6 Beton 8 0.2 0.4 m3 0.64

Pekerjaan balok B2 Elv. 1,00 (200 x 400 mm)

4 Pembesian

Lajur 108.6 8 kg 0.888 771.4944 1,165.15

Sengkang 1.1 906 0.395 393.657

5 Bekisting 108.6 0.4 2 m2 86.88

6 Beton 108.6 0.2 0.4 m3 8.69

Pekerjaan balok B2 Elv. 5,00 (200 x 400 mm)

4 Pembesian
Lajur 100 8 kg 0.888 710.4 1,072.92

Sengkang 1.1 834.3333333 0.395 362.5178333

5 Bekisting 100 0.4 2 m2 80.00

6 Beton 100 0.2 0.4 m3 8.00

Pekerjaan plat elv. + 5,00

1 Perkerasan tebal 15 cm
Beton 1 14.5 10 0.15 21.75 26.55
2 8 4 0.15 4.8

Begesting 14.5 10 145 177.00

8 4 32

Pembesian

1 8 67.66666667 2 0.617 1082.666667 3,465.33

10 75 2 0.617 1500

2 8 28 2 0.617 448

4 54.33333333 2 0.617 434.6666667

Lisplank

beton 55 0.1 0.7 3.85 3.85

pembesian 55 8 0.617 271.48 509.46

0.7 551 0.617 237.977

begesting 55 0.7 2 77 82.50

55 0.1 5.5

Pekerjaan Chamber uk. 100 x 100 x 100 cm

1 Galian tanah

2 Pasir urug tebal 10 cm 1.15

3 Lantai kerja tebal 5 cm 0.10

4 Pembesian 0.05

5 Bekisting 144.48

6 Beton K-350 11.00

0.90

Pekerjaan Dinding Biotech

- Pek. Plat Lantai tebal 15 cm

1 Galian tanah 15.00

2 Pasir urug tebal 10 cm 0.60

3 Lantai kerja tebal 5 cm 0.30

4 Pembesian 107.36

5 Bekisting 1.50

6 Beton K-350 0.90


- Pek. Kolom uk. 15 x 15 cm

1 Pembesian 55.51

2 Bekisting 40.00

3 Beton K-300 0.23

Pekerjaan Sumur Resapan Ø 100 CM

1 Galian tanah 1.15

2 Pasir urug tebal 10 cm 0.10

3 Lantai kerja tebal 5 cm 0.05

4 Pembesian 144.48

5 Bekisting 11.00

6 Beton K-300 0.90

Pekerjaan Sumpit uk. 150 x 150 x 200 cm

1 Galian tanah 4.84

2 Pasir urug tebal 10 cm 0.23

3 Lantai kerja tebal 5 cm 0.11

4 Pembesian 150.55

5 Bekisting a 12.00 30.30

b 12.90

c 4.50

d 0.90

6 Beton K-300 a 0.68 2.48

b 1.80

Pekerjaan tangki solar

- Pek. Plat Lantai tebal 10 cm

1 Galian tanah 22.00

2 Pasir urug tebal 10 cm 2.00

3 Lantai kerja tebal 5 cm 1.00

4 Pembesian 203.61

5 Bekisting 1.80

6 Beton K-350 2.00


PEKERJAAN ARSITEKTUR
Pasangan Bata

1 selasar 19.5 0.6 11.7 340.98

Bawah beam 54.8 0.6 32.88

Tembok utama 84 3.6 302.400

Lubang pintu 2.4 1.9 4.56

Louvre 2.4 0.6 1.44

2 Plester 628.38

3 Acian 628.38

4 Pasangan bata dinding Biotech 15.00

Pekerjaan Pintu dan Jendela

1 Pekerjaan Pintu plat besi ( Dauble ) 5.00

2 Pekerjaan Louvre 5.00

Pekerjaan Pengecatan

1 Cat Dinding 705.38

Pekerjaan Keramik ( 300 x 300 mm )

1 Pasangan keramik selasar 20.00

PEKERJAAN WATERPROOFING

Waterproofing coating, termasuk primer coating, pada

sambungan dan lain-lain diatas lantai beton

1 Area Groundtank 25.60

2 Lantai Dak atap 180.55

INFRASTRUKTUR PINTU MASUK

I Pekerjaan pondasi P1 uk. 150 x 150 x 30 cm


1 Galian Tanah 1.5 1.5 1.4 20 m3 63.00

2 Pasir urug tebal 10 cm 1.5 1.5 0.1 20 m3 4.50

3 Lantai kerja tebal 5 cm 1.5 1.5 0.05 20 m3 2.25

4 Pembesian x 3.5 20 11 kg 1.578 1215.06 2,430.12

y 3.5 20 11 kg 1.578 1215.06

5 Bekisting 1.2 1.2 0.3 20 4 m2 34.56

6 Beton 1.5 1.5 0.3 20 m3 13.50

7 Urugan tanah kembali m3 44.10

II Pekerjaan Stump uk. 40 x 40 cm

1 Pembesian lajur 1.7 20 12 kg 1.578 643.824 751.18

sengkang 1.45 20 6 kg 0.617 107.358

2 Bekisting 0.75 0.4 20 4 m2 24.00

3 Beton 0.75 0.4 0.4 20 m3 2.40

III Pekerjaan Sloof S1 uk. 30 x 40 cm

1 Galian tanah 24 0.3 0.55 m3 3.96

2 Pasir urug tebal 10 cm 24 0.3 0.1 m3 0.72

3 Lantai kerja tebal 5 cm 24 0.3 0.05 m3 0.36

4 Pembesian lajur 24 6 kg 1.578 227.232 358.77

sengkang lapangan 1.25 86 kg 0.617 66.3275

tumpuan 1.25 60 kg 0.617 46.275

extra 6 2 kg 1.578 18.936

5 Bekisting 24 0.4 2 m2 19.20

6 Beton 24 0.3 0.4 m3 2.88

IV Pekerjaan Sloof S2 uk. 20 x 30 cm

1 Galian tanah 83 0.2 0.45 m3 7.47

2 Pasir urug tebal 10 cm 83 0.2 0.1 m3 1.66

3 Lantai kerja tebal 5 cm 83 0.2 0.05 m3 0.83

4 Pembesian lajur 83 41.5 6 kg 1.578 785.844 1,041.25

sengkang lapangan 0.85 278 kg 0.617 145.7971

tumpuan 0.85 209 kg 0.617 109.61005

5 Bekisting 83 0.4 2 m2 66.40

6 Beton 83 0.3 0.4 m3 9.96


V Pekerjaan Kolom K1 uk. Ø 40 cm

1 Pembesian tinngi 5,1 m lajur 5.1 10 5 kg 1.578 402.39 1,167.45

sengkang 1.13 10 35.00 kg 0.617 244.0235

tinggi 4,1 m lajur 4.1 10 5 kg 1.578 323.49

sengkang 1.13 10 28.33 kg 0.617 197.5428333

2 Berkisting tinggi 5,1 m 5.1 1.256 10 m2 64.056 115.55

tinggi 4,1 m 4.1 1.256 10 m2 51.496

3 Beton tinggi 5,1 m 5.1 10 0.1256 m3 6.4056 9.93

tinggi 4,1 m 4.1 10 0.1256 m3 5.1496

lubang 5.1 10 0.0176625 m3 0.9007875

4.1 10 0.0176625 m3 0.7241625

VI Pekerjaan Praktis uk. 15 x 15 cm

1 Pembesian lajur 4.6 6 4 kg 0.888 98.0352 132.16

sengkang 0.45 6 32 kg 0.395 34.128

2 Bekisting 4.6 0.15 6 4 m3 16.56

3 Beton 4.6 0.15 0.15 6 m3 0.62

VII Pekerjaan Ring Balok uk. 20 x 30 cm

1 Pembesian lajur 107 6 kg 1.578 1013.076 1,390.68

sengkang 0.85 720 kg 0.617 377.604

2 Bekisting samping 107 0.3 2 m2 64.2 85.60

bawah 107 0.2 m2 21.4

3 Beton 107 0.2 0.3 m3 6.42

VIII Pekerjaan Atap

1 Pekerjaan Besi 2L 45 cm atas a 19.2 13 m' 249.6 576.96

b 13.86 13 m' 180.18

samping kiri a 5.6 6 m' 33.6

b 7.9 6 m' 47.4

samping kana a 4.95 6 m' 29.7

b 6.08 6 m' 36.48

2 Pekerjaan Besi 2L 35 cm atas 15.74 13 m' 204.62 312.56

samping kiri 10.68 6 m' 64.08


samping kanan 7.31 6 m' 43.86

3 Pemasangan Atap Spandek 174.646 m2 174.65

4 Pekerjaan Alucobond m2 174.65

5 Pekerjaan Talang air 21 m' 21.00

IX Pekerjaan Dinding

1 Alucobond dinding 9 1.2 3 m2 32.4 101.57

kolom 4.6 1.256 13 m2 75.1088

lubang 3 1.98 m2 5.94

4 Pekerjaan kaca dinding 4 mm 3 15.6 m2 46.80

5 Finishing Sloof m' 103.00

IX Pekerjaan Plafon

1 Plafon metal expose 199.42 199.42

2 Listplank 98.85 98.85

X Pekerjaan Pintu

1 Pemasangan pintu + aceccoris bh 3.00

V Pekerjaan agar

1 Pasangan Bata 18.29 1.9 m2 34.8

2 Plesteran m2 70

3 Aci halus m2 69.50

4 Pagar teralis 16 1.9 m2 30.40

PEKERJAAN AREA PARKIR


1 Plat Beton Tebal 15 Cm

Pembesian 54821.46056

Beton K-350 1510.788

2 Kansteen 728

3 Pekerjaan Atap ( Rangka Besi hollow galvanis atap alumunium Metal ) 12.81

PEKERJAAN Drainase

1 Galian Tanah Saluran 403.50

2 Lantai Kerja beton camp. 1:3:5 26.90

3 Pekerjaan Saluran U.60 475.00

4 Pekerjaan Saluran U.40 506.00

5 Grill Penutup Saluran 138.00


REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN
KEGIATAN KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

NO JENIS PEKERJAAN SATUAN PEK. HARGA SATUAN PEK.

PERSIAPAN
1 Pengukuran dan Pemasangan Bouwplank m' Rp 45,200.00
2 Pembersihan Lapangan Ringan m² Rp 4,800.00
3 Pengukuran m' Rp 2,390.00
4 Pagar Sementara Dari Seng Gelombang tinggi 2 m m' Rp 461,600.00
5 Pembuatan kantor sementara, dengan lantai plesteran m² Rp 612,600.00

PEKERJAAN TANAH DAN PONDASI


1 Timbunan Tanah Biasa m³ Rp 19,100.00
2 Urugan tanah (bahan dari luar) Leveling Lantai m³ Rp 56,800.00
3 Galian Tanah Biasa m³ Rp 40,600.00
4 Urugan Tanah Kembali ( Secara Manual ) m³ Rp 19,400.00
5 Urugan Pasir m³ Rp 281,200.00
6 Pemancangan m' Rp 142,800.00
7 Pekerjaan Pas. Batu Belah m3 Rp 676,400.00
8 Pas. Cerucuk dolken sedalam 3 m jarak 25 cm pcs Rp 34,400.00
9 Timbunan Tanah Biasa (Fill) Jarak Angkut QRY > 2 km m3 Rp 48,200.00

PEKERJAAN PEMBESIAN
1 Pembesian kg Rp 14,690.00
2 Pemasangan railling besi hollow 50x50x2.3 mm m' Rp 60,250.00
3 Pekerjaan besi baja profil kg Rp 29,700.00
4 Pekerjaan besi baja C < 100 - 150 mm kg Rp 36,900.00

PEKERJAAN BEKESTING
1 Pasang bekesting pondasi m² Rp 201,400.00
2 Pasang bekesting sloof m² Rp 89,900.00
3 Pasang bekesting kolom m² Rp 162,500.00
4 Pasang bekesting balok m² Rp 165,200.00
5 Pasang bekesting pelat lantai m² Rp 181,400.00

PEKERJAAN BETON
1 Beton Tumbuk 1 : 3 : 5 (Lantai Kerja) dengan Batu Koral m³ Rp 898,500.00
2 Beton bertulang 1Pc : 2Ps : 3Kr m³ Rp 1,048,400.00
3 Beton Ready Mix K-175 m³ Rp 1,191,700.00
4 Beton Ready Mix K-250 m³ Rp 1,269,300.00
5 Beton Ready Mix K-300 m³ Rp 1,291,000.00
6 Beton Ready Mix K-350 m³ Rp 1,369,100.00
7 Cor Beton dengan tebal 15 cm mutu beton K-350 m² Rp 1,397,900.00
8 Pekerjaan Meja Beton panjang 1,35 x 0,6 m unit Rp 3,078,700.00
9 Pekerjaan Meja Beton panjang 1,5 x 0,6 m unit Rp 3,424,200.00
10 Pekerjaan Meja Beton panjang 1,06 x 0,6 m unit Rp 2,403,800.00

PEKERJAAN PASANGAN DAN PLESTERAN


1 Pasangan Batu Bata Merah Tebal 1/2 Bata, 1PC : 4 PS m² Rp 111,600.00
2 Pasangan batu alam susun sirih m² Rp 387,600.00
3 Pasangan Rollag Bata, 1PC : 4 PS m' Rp 24,500.00
4 Plesteran halus 1Pc : 4 Ps (T=1,5 Cm) m² Rp 38,298.00
5 Aci Halus m² Rp 26,500.00
REKAPITULASI ANALISA HARGA SATUAN PEKERJAAN
KEGIATAN KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

NO JENIS PEKERJAAN SATUAN PEK. HARGA SATUAN PEK.

6 Pemasangan partisi double GRC t=6 mm rangka eka furing m² Rp 158,200.00


7 Pemasangan partisi double gypsum 9 mm rangka eka furing m² Rp 139,100.00
8 Pekerjaan Pas. Cilcon m² Rp 166,500.00

PEKERJAAN ATAP
1 Atap alumunium metal m² Rp 281,900.00
2 Pemasangan talang seng BJLS 30 (lebar 40 cm) m² Rp 108,600.00
3 Atap Baja Ringan m² Rp 140,000.00
4 Pasang Listplank tekstur kayu tebal 8mm, lebar 20 cm m' Rp 77,200.00

PEKERJAAN PLAFOND
1 Pasang plafond grc tebal 3,5 mm m² Rp 138,800.00
2 Pemasangan plafond gypsum 9 mm m² Rp 128,000.00
3 Pasang list plafon m' Rp 24,000.00

PEKERJAAN KERAMIK
1 Pemasangan keramik lantai tekstur, ukuran 80 x 80 cm m² Rp 283,600.00
2 Pemasangan plint keramik 10 x 80 cm m' Rp 75,300.00
3 Pemasangan keramik dinding, ukuran 30 x 60 cm m² Rp 235,500.00
4 Pemasangan plint keramik 10 x 80 cm m' Rp 75,300.00
5 Pemasangan plint keramik 10 x 60 cm m' Rp 184,300.00
6 Pemasangan keramik lantai tekstur, ukuran 30 x 60 cm m2 Rp 262,200.00
7 Pemasangan keramik lantai tekstur, ukuran 30 x 30 cm m2 Rp 239,100.00

PEKERJAAN PENGECATAN
1 Pengecatan tembok baru m² Rp 32,100.00
2 Pengecatan Plafond m² Rp 22,600.00
3 Pengecatan listplank m' Rp 22,700.00
4 Pengecatan besi m² Rp 50,800.00

PEKERJAAN DRAINASE
1 Pemasangan saluran U-40 m' Rp 401,878.75
2 Pekerjaan Saluran U.60 m' Rp 502,308.75

PEKERJAAN LANDSCAPE
1 Pekerjaan Penanaman Rumput Gajah Mini m² Rp 53,230.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Instalasi Titik Lampu


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 258,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0250 115,000.00 2,875.00
2 Tukang Listrik OH 0.0500 105,000.00 5,250.00
3 Pekerja OH 0.8500 90,000.00 76,500.00

JUMLAH HARGA TENAGA 84,625.00

B. BAHAN
Pipa PVC 5/8' (6m) ljr 7.5000 7,150.00 53,625.00
Isolator m 15.0000 704.00 10,560.00
Kabel NYA 1X 1.5 mm m 30.0000 3,000.00 90,000.00
Fiting Plafon bh 1.0000 10,450.00 10,450.00
Las doof bh 6.0000 715.00 4,290.00
T dos PVC bh 2.0000 2,530.00 5,060.00

JUMLAH HARGA BAHAN 173,985.00

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 258,610.00


E. DIBULATKAN 258,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Saklar Tunggal


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 31,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0167 115,000.00 1,916.67
2 Tukang Listrik OH 0.0500 105,000.00 5,250.00
3 Pekerja OH 0.1000 90,000.00 9,000.00

JUMLAH HARGA TENAGA 16,166.67

B. BAHAN
1 Saklar tunggal bh 1.0000 15,400.00 15,400.00

JUMLAH HARGA BAHAN 15,400.00

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 31,566.67


E. DIBULATKAN 31,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Saklar 2 Gang


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 37,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0167 115,000.00 1,916.67
2 Tukang Listrik OH 0.0500 105,000.00 5,250.00
3 Pekerja OH 0.1000 90,000.00 9,000.00

JUMLAH HARGA TENAGA 16,166.67

B. BAHAN
1 Saklar 2 Gang bh 1.0000 21,450.00 21,450.00

JUMLAH HARGA BAHAN 21,450.00

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 37,616.67


E. DIBULATKAN 37,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan Saklar 3 Gang
SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 44,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0167 115,000.00 1,916.67
2 Tukang Listrik OH 0.0500 105,000.00 5,250.00
3 Pekerja OH 0.1000 90,000.00 9,000.00

JUMLAH HARGA TENAGA 16,166.67

B. BAHAN
1 Saklar 3 Gang bh 1.0000 28,600.00 28,600.00

JUMLAH HARGA BAHAN 28,600.00

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 44,766.67


E. DIBULATKAN 44,800.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Saklar 4 Gang


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 50,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0167 115,000.00 1,916.67
2 Tukang Listrik OH 0.0500 105,000.00 5,250.00
3 Pekerja OH 0.1000 90,000.00 9,000.00

JUMLAH HARGA TENAGA 16,166.67

B. BAHAN
1 Saklar 4 Gang bh 1.0000 34,650.00 34,650.00

JUMLAH HARGA BAHAN 34,650.00

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 50,816.67


E. DIBULATKAN 50,800.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Instalasi Titik Stop Kontak Double


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 273,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0250 115,000.00 2,875.00
2 Tukang Listrik OH 0.0500 105,000.00 5,250.00
3 Pekerja OH 1.0000 90,000.00 90,000.00

JUMLAH HARGA TENAGA 98,125.00

B. BAHAN
Pipa PVC 5/8' ljr 7.5000 7,150.00 53,625.00
Kabel NYA 2X1.5 mm m 30.0000 4,000.00 120,000.00
T dos PVC bh 0.7500 2,530.00 1,897.50

JUMLAH HARGA BAHAN 175,522.50

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 273,647.50


E. DIBULATKAN 273,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan instalasi Titik Stop Kontak AC


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 273,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0250 115,000.00 2,875.00
2 Tukang Listrik OH 0.0500 105,000.00 5,250.00
3 Pekerja OH 1.0000 90,000.00 90,000.00

JUMLAH HARGA TENAGA 98,125.00

B. BAHAN
Pipa PVC 5/8' (6m) ljr 7.5000 7,150.00 53,625.00
Kabel NYA 2X1.5 mm m 30.0000 4,000.00 120,000.00
T dos PVC bh 0.7500 2,530.00 1,897.50

JUMLAH HARGA BAHAN 175,522.50

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 273,647.50


E. DIBULATKAN 273,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Lampu Down Light 13 Watt 4"


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 150,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0500 115,000.00 5,750.00
2 Tukang Listrik OH 0.2000 105,000.00 21,000.00
3 Pekerja OH 0.0010 90,000.00 90.00

JUMLAH HARGA TENAGA 26,840.00

B. BAHAN
1 Bola Lampu Down Light 13 Watt 4" bh 1.0000 19,800.00 19,800.00
Casing Lampu bh 1.0000 97,900.00 97,900.00
Perlengkapan bh 1.0000 5,885.00 5,885.00

JUMLAH HARGA BAHAN 123,585.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 150,425.00


E. DIBULATKAN 150,400.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan Lampu Down Light 18 Watt 4"
SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 152,700.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0500 115,000.00 5,750.00
2 Tukang Listrik OH 0.2000 105,000.00 21,000.00
3 Pekerja OH 0.0010 90,000.00 90.00

JUMLAH HARGA TENAGA 26,840.00

B. BAHAN
1 Bola Lampu Down Light 18 Watt 4" bh 1.0000 22,000.00 22,000.00
Casing Lampu bh 1.0000 97,900.00 97,900.00
Perlengkapan bh 1.0000 5,995.00 5,995.00

JUMLAH HARGA BAHAN 125,895.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 152,735.00


E. DIBULATKAN 152,700.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Lampu Hias 50 Watt


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 1,017,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0500 115,000.00 5,750.00
2 Tukang Listrik OH 0.2000 95,000.00 19,000.00
3 Pekerja OH 0.0010 85,000.00 85.00

JUMLAH HARGA TENAGA 24,835.00

B. BAHAN
1 Bola Lampu Hias 50 Watt bh 1.0000 935,000.00 935,000.00
Fiting Flafond bh 1.0000 10,450.00 10,450.00
Perlengkapan bh 1.0000 47,272.50 47,272.50

JUMLAH HARGA BAHAN 992,722.50

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,017,557.50


E. DIBULATKAN 1,017,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan Exhaust Fan 8"
SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 364,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah Pekerja ls 1.0000 60,800.00 60,800.00

JUMLAH HARGA TENAGA 60,800.00

B. BAHAN
1 Exhaust Fan bh 1.0000 300,000.00 300,000.00
Kabel NYA 2X1.5 mm m 1.0000 4,000.00 4,000.00

JUMLAH HARGA BAHAN 304,000.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 364,800.00


E. DIBULATKAN 364,800.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Lampu Taman 25 Watt


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 1,672,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah Pekerja ls 1.0000 278,795.00 278,795.00

JUMLAH HARGA TENAGA 278,795.00

B. BAHAN
1 Bola Lampu Taman 25 Watt bh 1.0000 550,000.00 550,000.00
Pipa GIV 2' bh 1.0000 132,000.00 132,000.00
Kabel NYFGbY 4X2.5 mm m 1.0000 33,000.00 33,000.00
Timer Switch bh 2.0000 220,000.00 440,000.00
Contactor bh 1.0000 238,975.00 238,975.00

JUMLAH HARGA BAHAN 1,393,975.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,672,770.00


E. DIBULATKAN 1,672,800.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Stop Kontak Double 250 Watt


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 53,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0500 115,000.00 5,750.00
2 Tukang Listrik OH 0.2000 95,000.00 19,000.00
3 Pekerja OH 0.0010 85,000.00 85.00

JUMLAH HARGA TENAGA 24,835.00

B. BAHAN
1 Stop Kontak bh 1.0000 23,320.00 23,320.00
T dos PVC bh 2.0000 2,530.00 5,060.00

JUMLAH HARGA BAHAN 28,380.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 53,215.00


E. DIBULATKAN 53,200.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan Stop Kontak AC
SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 65,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0500 115,000.00 5,750.00
2 Tukang Listrik OH 0.2000 95,000.00 19,000.00
3 Pekerja OH 0.0010 85,000.00 85.00
,
JUMLAH HARGA TENAGA 24,835.00

B. BAHAN
1 Stop Kontak bh 1.0000 35,200.00 35,200.00
T dos PVC bh 2.0000 2,530.00 5,060.00

JUMLAH HARGA BAHAN 40,260.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 65,095.00


E. DIBULATKAN 65,100.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan MCB BOX
SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 2,285,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah Pasang ls 1.0000 380,872.80 380,872.80

JUMLAH HARGA TENAGA 380,872.80

B. BAHAN
1 BOX MCB 6 WAYS bh 1.0000 44,000.00 44,000.00
ELCB 10A/1P/250mA pcs 1.0000 640,200.00 640,200.00
MCB 6A/1P/6KA pcs 6.0000 118,580.00 711,480.00
Busbar MCB pcs 1.0000 253,000.00 253,000.00
Cu Tin Bar set 1.0000 165,000.00 165,000.00
accessories set 1.0000 90,684.00 90,684.00

JUMLAH HARGA BAHAN 1,904,364.00

C ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 2,285,236.80


E. DIBULATKAN 2,285,200.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan Kabel NYY 2CX4 mm
SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 114,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
3 Tukang Listrik OH 0.2500 95,000.00 23,750.00
4 Pekerja OH 0.5000 85,000.00 42,500.00

JUMLAH HARGA TENAGA 66,250.00

B. BAHAN
1 Kabel NYY 2X4 mm m' 1.0000 18,480.00 18,480.00
2 Batu pelindung kabel bh 5.0000 2,750.00 13,750.00
3 Pasir Urug m3 0.1000 105,600.00 10,560.00
4 BCC 2,5 m' 1.0000 5,500.00 5,500.00

JUMLAH HARGA BAHAN 48,290.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 114,540.00


E. DIBULATKAN 114,500.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Kabel NYFGbY 4X6 mm


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 134,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
3 Tukang Listrik OH 0.2500 95,000.00 23,750.00
4 Pekerja OH 0.5000 85,000.00 42,500.00

JUMLAH HARGA TENAGA 66,250.00

B. BAHAN
1 Kabel NYFGbY 4X6 mm m' 1.0000 38,500.00 38,500.00
2 Batu pelindung kabel bh 5.0000 2,750.00 13,750.00
3 Pasir Urug m3 0.1000 105,600.00 10,560.00
4 BCC 2,5 m' 1.0000 5,500.00 5,500.00

JUMLAH HARGA BAHAN 68,310.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 134,560.00


E. DIBULATKAN 134,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Kabel NYFGbY 4X2,5 mm


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 129,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.2500 95,000.00 23,750.00
1 Tukang Listrik OH 0.2500 95,000.00 23,750.00
2 Pekerja OH 0.5000 85,000.00 42,500.00

JUMLAH HARGA TENAGA 66,250.00

B. BAHAN
1 Kabel NYFGbY 4X2,5 mm m' 1.0000 33,000.00 33,000.00
2 Batu pelindung kabel bh 5.0000 2,750.00 13,750.00
3 Pasir Urug m3 0.1000 105,600.00 10,560.00
4 BCC 2,5 m' 1.0000 5,500.00 5,500.00

JUMLAH HARGA BAHAN 62,810.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 129,060.00


E. DIBULATKAN 129,100.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Kabel NYFGbY 4X185 mm


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 742,700.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0625 115,000.00 7,187.50
2 Tukang Listrik OH 0.0625 95,000.00 5,937.50
3 Pekerja OH 0.1250 85,000.00 10,625.00

JUMLAH HARGA TENAGA 16,562.50

B. BAHAN
1 Kabel NYFGbYY 4X185 mm m' 1.1000 638,000.00 701,800.00
2 Batu pelindung kabel bh 5.0000 2,750.00 13,750.00
3 Pasir Urug m3 0.1000 105,600.00 10,560.00

JUMLAH HARGA BAHAN 726,110.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 742,672.50


E. DIBULATKAN 742,700.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Grounding Listrik


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 5,128,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah pasang 20% ls 1.0000 854,700.00 854,700.00

JUMLAH HARGA TENAGA 854,700.00

B. BAHAN
1 Copper Massive lot 1.0000 1,430,000.00 1,430,000.00
2 Pipa GIP batang 1.0000 990,000.00 990,000.00
3 BCC lot 1.0000 330,000.00 330,000.00
4 Bak Kontrol lot 1.0000 1,320,000.00 1,320,000.00
5 Accessories lot 1.0000 203,500.00 203,500.00

JUMLAH HARGA BAHAN 4,273,500.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 5,128,200.00


E. DIBULATKAN 5,128,200.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan Panel Umum LT-1
SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 4,955,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah pasang 20% ls 1.0000 825,940.50 825,940.50

JUMLAH HARGA TENAGA 825,940.50

B. BAHAN
1 P. Panel BOX 50X40X20cm m' 1.0000 660,000.00 660,000.00
2 ELCB 10A/3P/250mA pcs 1.0000 1,007,930.00 1,007,930.00
3 MCB 6A/3P/6KA pcs 1.0000 470,085.00 470,085.00
4 MCB 6A/1P/6KA pcs 7.0000 118,580.00 830,060.00
5 Busbar MCB pcs 1.0000 253,000.00 253,000.00
6 Combar set 1.0000 165,000.00 165,000.00
7 Timer Switch bh 1.0000 220,000.00 220,000.00
8 Contactor bh 1.0000 238,975.00 238,975.00
9 Fuse pcs 1.0000 88,000.00 88,000.00
10 Accessories set 1.0000 196,652.50 196,652.50

JUMLAH HARGA BAHAN 4,129,702.50

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 4,955,643.00


E. DIBULATKAN 4,955,600.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pemasangan Panel Umum LT-2


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 3,321,700.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah pasang 20% ls 1.0000 553,614.60 553,614.60

JUMLAH HARGA TENAGA 553,614.60

B. BAHAN
1 P. Panel BOX 50X40X20cm m' 1.0000 660,000.00 660,000.00
3 ELCB 10A/3P/250mA pcs 1.0000 640,200.00 640,200.00
55 MCB 6A/1P/6KA pcs 7.0000 118,580.00 830,060.00
6 Busbar MCB pcs 1.0000 253,000.00 253,000.00
7 Cu Tin Bar set 1.0000 165,000.00 165,000.00
8 Fuse pcs 1.0000 88,000.00 88,000.00
9 Accessories set 1.0000 131,813.00 131,813.00

JUMLAH HARGA BAHAN 2,768,073.00

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 3,321,687.60


E. DIBULATKAN 3,321,700.00
ANALISA HARGA SATUAN PEKERJAAN
MEKANIKAL DAN ELEKTRIKAL BAHAN LISTRIK

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
JENIS PEKERJAAN : Pemasangan Penangkal Petir
SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 10,005,900.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah pasang 20% ls 1.0000 1,667,650.18 1,667,650.18

JUMLAH HARGA TENAGA 1,667,650.18

B. BAHAN
1 Split Tembaga dia.1 bh 1.0000 70,620.00 70,620.00
2 Timah kg 0.5000 31,484.75 15,742.38
3 Pipa Arde m 1.0000 100,045.00 100,045.00
4 Pipa Galvanis Dia.1" ljr 0.2500 136,061.20 34,015.30
5 Pipa PVC tipe AW 1/2" ljr 10.0000 13,000.00 130,000.00
6 Kawat BC m 40.0000 41,195.00 1,647,800.00
7 Air Curtain unit 1.0000 6,340,028.20 6,340,028.20

JUMLAH HARGA BAHAN 8,338,250.88

C ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 10,005,901.05


E. DIBULATKAN 10,005,900.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Pekerjaan pemasangan elbow 2"


SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 15,000.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 2,500.00 2,500.00

JUMLAH HARGA TENAGA 2,500.00

B. BAHAN
1 Elbow 2" bh 1.0000 12,500.00 12,500.00

JUMLAH HARGA BAHAN 12,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 15,000.00


E. DIBULATKAN 15,000.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan elbow 1"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 4,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 690.00 690.00

JUMLAH HARGA TENAGA 690.00

B. BAHAN
1 Ebow 1" bh 1.0000 3,450.00 3,450.00

JUMLAH HARGA BAHAN 3,450.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 4,140.00


E. DIBULATKAN 4,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan elbow 4"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 73,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 12,190.00 12,190.00

JUMLAH HARGA TENAGA 12,190.00

B. BAHAN
1 Ebow 4" bh 1.0000 60,950.00 60,950.00

JUMLAH HARGA BAHAN 60,950.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 73,140.00


E. DIBULATKAN 73,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan elbow 45,4"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 82,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 13,800.00 13,800.00

JUMLAH HARGA TENAGA 13,800.00

B. BAHAN
1 Ebow 45,4" bh 1.0000 69,000.00 69,000.00

JUMLAH HARGA BAHAN 69,000.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 82,800.00


E. DIBULATKAN 82,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Tee 2"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 5,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 920.00 920.00

JUMLAH HARGA TENAGA 920.00

B. BAHAN
1 Tee 2" bh 1.0000 4,600.00 4,600.00

JUMLAH HARGA BAHAN 4,600.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 5,520.00


E. DIBULATKAN 5,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Tee 1"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 19,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 3,220.00 3,220.00

JUMLAH HARGA TENAGA 3,220.00

B. BAHAN
1 Tee 1" bh 1.0000 16,100.00 16,100.00

JUMLAH HARGA BAHAN 16,100.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 19,320.00


E. DIBULATKAN 19,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Tee 3"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 44,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 7,360.00 7,360.00

JUMLAH HARGA TENAGA 7,360.00

B. BAHAN
1 Tee 3" bh 1.0000 36,800.00 36,800.00

JUMLAH HARGA BAHAN 36,800.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 44,160.00


E. DIBULATKAN 44,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Tee 4"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 88,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 14,720.00 14,720.00

JUMLAH HARGA TENAGA 14,720.00

B. BAHAN
1 Tee 4" bh 1.0000 73,600.00 73,600.00

JUMLAH HARGA BAHAN 73,600.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 88,320.00


E. DIBULATKAN 88,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Tee 1"-3/4"-1"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 5,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 920.00 920.00

JUMLAH HARGA TENAGA 920.00

B. BAHAN
1 Tee 1"-3/4"-1" bh 1.0000 4,600.00 4,600.00

JUMLAH HARGA BAHAN 4,600.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 5,520.00


E. DIBULATKAN 5,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Tee 3"-2"-3"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 44,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 7,360.00 7,360.00

JUMLAH HARGA TENAGA 7,360.00

B. BAHAN
1 Tee 3"-2"-3" bh 1.0000 36,800.00 36,800.00

JUMLAH HARGA BAHAN 36,800.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 44,160.00


E. DIBULATKAN 44,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Socket 2"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 12,000.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 2,000.00 2,000.00

JUMLAH HARGA TENAGA 2,000.00

B. BAHAN
1 Socket 2" bh 1.0000 10,000.00 10,000.00

JUMLAH HARGA BAHAN 10,000.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 12,000.00


E. DIBULATKAN 12,000.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Socket 1"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 4,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 700.00 700.00

JUMLAH HARGA TENAGA 700.00

B. BAHAN
1 Socket 1" bh 1.0000 3,500.00 3,500.00

JUMLAH HARGA BAHAN 3,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 4,200.00


E. DIBULATKAN 4,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Socket 3"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 27,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 4,600.00 4,600.00

JUMLAH HARGA TENAGA 4,600.00

B. BAHAN
1 Socket 3" bh 1.0000 23,000.00 23,000.00

JUMLAH HARGA BAHAN 23,000.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 27,600.00


E. DIBULATKAN 27,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Socket 4"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 52,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 8,740.00 8,740.00

JUMLAH HARGA TENAGA 8,740.00

B. BAHAN
1 Socket 4" bh 1.0000 43,700.00 43,700.00

JUMLAH HARGA BAHAN 43,700.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 52,440.00


E. DIBULATKAN 52,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Socket 1"-3/4"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 4,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 700.00 700.00

JUMLAH HARGA TENAGA 700.00

B. BAHAN
1 Socket 1"-3/4" bh 1.0000 3,500.00 3,500.00

JUMLAH HARGA BAHAN 3,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 4,200.00


E. DIBULATKAN 4,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
JENIS PEKERJAAN : Pekerjaan pemasangan Elbow 45, 3"
SATUAN PEKERJAAN : Ls
HARGA SATUAN : Rp 41,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. UPAH
1 Upah pemasangan Ls 1.0000 6,900.00 6,900.00

JUMLAH HARGA TENAGA 6,900.00

B. BAHAN
1 Elbow 45, 3" bh 1.0000 34,500.00 34,500.00

JUMLAH HARGA BAHAN 34,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 41,400.00


E. DIBULATKAN 41,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Mobilisasi Dan Demobilisasi


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 28,800,000.00

lembar :
JENIS PEKERJAAN : MOBILISASI DAN DEMOBILISASI

Lembar 1.2-2
KODE HARGA JUMLAH
No. JENIS ALAT ALAT SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)

A PERALATAN

1 EXCAVATOR 80-140 HP E10 Unit 2.00 5,000,000.00 10,000,000.00


2 TANDEM ROLLER 6-8 T. E17 Unit 1.00 5,000,000.00 5,000,000.00
3 PILE DRIVER + HAMMER+CRANE ON TRACK 3,5 TON E30 Unit 1.00 13,800,000.00 13,800,000.00

Total untuk Item B pada Lembar 1 28,800,000.00


ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pengukuran dan Pemasangan Bouwplank


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 45,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0050 115,000.00 575.00
2 Kepala tukang OH 0.0100 110,000.00 1,100.00
3 Tukang kayu OH 0.1000 105,000.00 10,500.00
4 Pekerja OH 0.1000 90,000.00 9,000.00

JUMLAH HARGA TENAGA 21,175.00

B. BAHAN
1 Kayu papan 2/20 (campur) m3 0.0042 2,860,000.00 12,012.00
2 Kayu usuk 5/7 m3 0.0039 2,860,000.00 11,154.00
3 Paku kayu kg 0.0200 22,000.00 440.00
4 Benang lot m' 1.2000 275.00 330.00

JUMLAH HARGA BAHAN 23,936.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 45,111.00


E. DIBULATKAN 45,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pembersihan Lapangan Ringan


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 4,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0025 115,000.00 287.50
2 Pekerja Tak Terampil OH 0.0500 90,000.00 4,500.00

JUMLAH HARGA TENAGA 4,787.50

B. BAHAN

JUMLAH HARGA BAHAN

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 4,787.50


E. DIBULATKAN 4,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pengukuran


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 2,390.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0013 115,000.00 143.75
2 Pekerja OH 0.0250 90,000.00 2,250.00

JUMLAH HARGA TENAGA 2,393.75

B. BAHAN

JUMLAH HARGA BAHAN -

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 2,393.75


E. DIBULATKAN 2,390.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pagar Pengaman proyek t.2,4 m


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 461,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang kayu OH 0.5000 105,000.00 52,500.00
2 Pekerja OH 1.0000 90,000.00 90,000.00
4 Mandor OH 0.1000 115,000.00 11,500.00

JUMLAH HARGA TENAGA 154,000.00

B. BAHAN
1 Beton 1:2:3 m3 0.0133 1,048,400.00 13,978.67
2 Seng gelombang BJLS 20 lbr 1.5000 62,000.00 93,000.00
3 Kayu 5/7 m3 0.0490 2,860,000.00 140,140.00
4 Paku kayu biasa 2"-5" kg 0.2000 22,000.00 4,400.00
5 Pasir m3 0.0350 247,500.00 8,662.50
6 Semen zak 0.3720 66,000.00 24,552.00
7 batu Split m3 0.0600 380,160.00 22,809.60

JUMLAH HARGA BAHAN 307,542.77

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 461,542.77


E. DIBULATKAN 461,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pembuatan kantor sementara, dengan lantai plesteran


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 612,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang kayu OH 2.0000 105,000.00 210,000.00
2 Pekerja OH 1.5000 90,000.00 135,000.00
4 Mandor OH 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 350,750.00

B. BAHAN
1 Kayu campur m3 0.0180 2,860,000.00 51,480.00
2 Paku usuk kg 0.8500 22,000.00 18,700.00
3 Besi Beton ulir kg 1.1000 10,080.00 11,088.00
4 Semen PC ( Portland Cement ) kg 35.0000 1,320.00 46,200.00
5 Pasir pasang m3 0.2500 247,500.00 61,875.00
6 Koral Beton m3 0.1500 380,160.00 57,024.00
7 Seng BJLS 0,20 lembaran L = 90 cm lbr 0.2500 62,000.00 15,500.00

JUMLAH HARGA BAHAN 261,867.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 612,617.00


E. DIBULATKAN 612,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN 2015-2016

JENIS PEKERJAAN : Galian Tanah Biasa


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 40,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0400 115,000.00 4,600.00
2 Pekerja Tak Terampil OH 0.4000 90,000.00 36,000.00

JUMLAH HARGA TENAGA 40,600.00

B. BAHAN

JUMLAH HARGA BAHAN -

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 40,600.00


E. DIBULATKAN 40,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN 2015-2016

JENIS PEKERJAAN : Urugan Tanah Kembali ( Secara Manual )


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 19,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tak Terampil OH 0.1920 90,000.00 17,280.00
2 Mandor OH 0.0190 115,000.00 2,185.00

JUMLAH HARGA TENAGA 19,465.00

B. BAHAN

JUMLAH HARGA BAHAN -

C. ALAT

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 19,465.00


E. DIBULATKAN 19,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN 2015-2016

JENIS PEKERJAAN : Timbunan Tanah Biasa


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 19,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0100 115,000.00 1,150.00
2 Pekerja OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 19,150.00

B. BAHAN

JUMLAH HARGA BAHAN -

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 19,150.00


E. DIBULATKAN 19,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN 2015-2016

JENIS PEKERJAAN : Urugan tanah (bahan dari luar) Leveling Lantai


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 56,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0100 115,000.00 1,150.00
2 Pekerja OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 19,150.00

B. BAHAN
1 Tanah timbunan biasa m3 1.1000 27,500.00 30,250.00

JUMLAH HARGA BAHAN 30,250.00

C. ALAT
1 Excavator jam 0.0120 350,000.00 4,200.00
2 Dump truck 6 ton jam 0.0128 230,000.00 2,944.00
3 Stamper jam 0.0070 25,000.00 175.00

JUMLAH HARGA ALAT 7,319.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 56,719.00


ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN 2015-2016

JENIS PEKERJAAN : Pas. Cerucuk dolken sedalam 3 m jarak 25 cm


SATUAN PEKERJAAN : titik
HARGA SATUAN : Rp 34,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja OH 0.1000 90,000.00 9,000.00
2 Mandor OH 0.0250 115,000.00 2,875.00

JUMLAH HARGA TENAGA 11,875.00

B. BAHAN
1 Dolken Ø 10 cm x 425 cm btg 1.0000 22,550.00 22,550.00

JUMLAH HARGA BAHAN 22,550.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 34,425.00


E. DIBULATKAN 34,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN 2015-2016

JENIS PEKERJAAN : Timbunan Tanah Biasa (Fill) Jarak Angkut QRY > 2 km
SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 48,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja OH 0.1600 90,000.00 14,400.00
2 Mandor OH 0.0402 115,000.00 4,623.00

JUMLAH HARGA TENAGA 19,023.00

B. BAHAN

JUMLAH HARGA BAHAN -

C. ALAT

Dump Truck jam 0.0415 230,000.00 9,545.00


VIBRATORY ROLLER 5 - 8 T jam 0.0100 300,000.00 3,000.00
WATER TANKER 3000 - 4500 L jam 0.0070 130,000.00 910.00
Wheel Loader Cat 950 jam 0.0400 300,000.00 12,000.00
Motor Greder Cat 950 jam 0.0117 325,000.00 3,802.50

JUMLAH HARGA ALAT 29,257.50

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 48,280.50


E. DIBULATKAN 48,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Urugan Pasir


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 281,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tak Terampil OH 0.3000 90,000.00 27,000.00
2 Mandor OH 0.0100 115,000.00 1,150.00

JUMLAH HARGA TENAGA 28,150.00

B. BAHAN
1 Pasir urug m³ 1.2000 210,900.00 253,080.00

JUMLAH HARGA BAHAN 253,080.00

C. ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 281,230.00


E. DIBULATKAN 281,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemancangan


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 142,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja jam 1.2909 11,250.00 14,522.63


2 Operator jam 0.5820 13,125.00 7,638.75
3 Mandor jam 0.1291 14,375.00 1,855.81
- -

JUMLAH HARGA TENAGA 24,017.19

B. BAHAN

JUMLAH HARGA BAHAN -

C. ALAT

1 Crane On Track 75 - 100Ton jam 0.1757 450,000.00 79,065.00


2 Pile Driver + Hammer jam 0.1088 300,000.00 32,640.00
3 Genset jam 0.0144 150,000.00 2,160.00
4 Alat bantu jam 1.0000 5,000.00 5,000.00

JUMLAH HARGA ALAT 118,865.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 142,882.19


E. DIBULATKAN 142,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan Pas. Batu Belah


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 676,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Pekerja OH 0.7800 90,000.00 70,200.00


2 Tukang Batu OH 0.3900 105,000.00 40,950.00
3 Kepala Tukang OH 0.0390 110,000.00 4,290.00
4 Mandor OH 0.0390 115,000.00 4,485.00

JUMLAH HARGA TENAGA 119,925.00

B. BAHAN
Batu Belah m3 1.1000 242,000.00 266,200.00
Pasir m3 0.4100 247,500.00 101,475.00
Semen zak 2.8612 66,000.00 188,839.20

JUMLAH HARGA BAHAN 556,514.20

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 676,439.20


E. DIBULATKAN 676,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pembesian


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 14,690.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang besi OH 0.01 105,000.00 872.81
2 Pekerja OH 0.02 90,000.00 2,244.38
3 Mandor OH 0.01 115,000.00 934.38

JUMLAH HARGA TENAGA 4,051.56

B. BAHAN
1 Besi beton/tulangan kg 1.0500 10,080.00 10,584.00
2 Kawat ikat beton kg 0.0025 22,000.00 55.00

JUMLAH HARGA BAHAN 10,639.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 14,690.56


E. DIBULATKAN 14,690.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan besi baja profil


SATUAN PEKERJAAN : kg
HARGA SATUAN : Rp 29,700.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang besi OH 0.006 105,000.00 630.00
2 Pekerja OH 0.050 90,000.00 4,500.00
3 Mandor OH 0.003 115,000.00 345.00

JUMLAH HARGA TENAGA 5,475.00

B. BAHAN
1 Besi baja kg 1.1000 14,300.00 15,730.00
2 Elektroda baja kg 0.2000 42,900.00 8,580.00

JUMLAH HARGA BAHAN 24,310.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 29,785.00


E. DIBULATKAN 29,700.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang bekesting pondasi


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 201,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0260 115,000.00 2,990.00
2 Kepala Tukang OH 0.0260 110,000.00 2,860.00
3 Tukang Kayu OH 0.2600 105,000.00 27,300.00
4 Pekerja ( pasang & bongkar ) OH 0.5200 90,000.00 46,800.00

JUMLAH HARGA TENAGA 79,950.00

B. BAHAN
1 Kayu campur m3 0.0400 2,860,000.00 114,400.00
2 Paku kayu Kg 0.3000 22,000.00 6,600.00
3 Minyak bekisting Ltr 0.1000 5,170.00 517.00

JUMLAH HARGA BAHAN 121,517.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 201,467.00


E. DIBULATKAN 201,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang bekesting sloof


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 89,900.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0100 115,000.00 1,150.00
2 Kepala Tukang OH 0.0100 110,000.00 1,100.00
3 Tukang Kayu OH 0.0250 105,000.00 2,625.00
4 Pekerja ( pasang & bongkar ) OH 0.1250 90,000.00 11,250.00

JUMLAH HARGA TENAGA 16,125.00

B. BAHAN
1 Kayu campur m3 0.0233 2,860,000.00 66,733.33
2 Paku kayu Kg 0.3000 22,000.00 6,600.00
3 Minyak bekisting Ltr 0.1000 5,170.00 517.00

JUMLAH HARGA BAHAN 73,850.33

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 89,975.33


E. DIBULATKAN 89,900.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang bekesting kolom


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 162,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0150 115,000.00 1,725.00
2 Kepala Tukang OH 0.0150 110,000.00 1,650.00
3 Tukang Kayu OH 0.0400 105,000.00 4,200.00
4 Pekerja ( pasang & bongkar ) OH 0.1700 90,000.00 15,300.00

JUMLAH HARGA TENAGA 22,875.00

B. BAHAN
1 Multipleks tebal 9 mm lbr 0.3500 132,000.00 46,200.00
2 Kayu campur m3 0.0300 2,860,000.00 85,800.00
3 Paku kayu Kg 0.3000 22,000.00 6,600.00
3 Minyak bekisting Ltr 0.2000 5,170.00 1,034.00

139,634.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 162,509.00


E. DIBULATKAN 162,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang bekesting balok


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 165,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0150 115,000.00 1,725.00
2 Kepala Tukang OH 0.0150 110,000.00 1,650.00
3 Tukang Kayu OH 0.0400 105,000.00 4,200.00
4 Pekerja ( pasang & bongkar ) OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 25,575.00

B. BAHAN
1 Multipleks tebal 9 mm lbr 0.3500 132,000.00 46,200.00
2 Kayu campur m3 0.0300 2,860,000.00 85,800.00
3 Paku kayu Kg 0.3000 22,000.00 6,600.00
4 Minyak bekisting Ltr 0.2000 5,170.00 1,034.00

JUMLAH HARGA BAHAN 139,634.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 165,209.00


E. DIBULATKAN 165,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang bekesting pelat lantai


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 181,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0150 115,000.00 1,725.00
2 Kepala Tukang OH 0.0150 110,000.00 1,650.00
3 Tukang Kayu OH 0.0400 105,000.00 4,200.00
4 Pekerja ( pasang & bongkar ) OH 0.2500 90,000.00 22,500.00

JUMLAH HARGA TENAGA 30,075.00

B. BAHAN
1 Multipleks tebal 9 mm lbr 0.3500 132,000.00 46,200.00
2 Kayu campur m3 0.0333 2,860,000.00 95,333.33
3 Paku kayu Kg 0.4000 22,000.00 8,800.00
4 Minyak bekisting Ltr 0.2000 5,170.00 1,034.00

JUMLAH HARGA BAHAN 151,367.33


###

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 181,442.33


E. DIBULATKAN 181,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Beton Tumbuk 1 : 3 : 5 (Lantai Kerja) dengan Batu Koral


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 898,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang Batu OH 0.2500 105,000.00 26,250.00
2 Pekerja Tak Trampil OH 1.5000 90,000.00 135,000.00
3 Kepala Tukang Batu OH 0.0250 110,000.00 2,750.00
4 Mandor OH 0.0800 115,000.00 9,200.00

JUMLAH HARGA TENAGA 173,200.00

B. BAHAN
1 Portland Cement 50 kg zak 4.0000 66,000.00 264,000.00
2 Pasir Beton/cor m3 0.5000 261,250.00 130,625.00
3 Koral m3 0.8700 380,160.00 330,739.20

JUMLAH HARGA BAHAN 725,364.20

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 898,564.20


E. DIBULATKAN 898,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Beton bertulang 1Pc : 2Ps : 3Kr


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 1,048,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.2500 105,000.00 26,250.00
2 Pekerjan tak terampil OH 1.5000 90,000.00 135,000.00
3 Kepala tukang OH 0.0250 110,000.00 2,750.00
4 Mandor OH 0.0800 115,000.00 9,200.00

JUMLAH HARGA TENAGA 173,200.00

B. BAHAN
1 Portland Cement Zak 6.4000 66,000.00 422,400.00
2 Pasir Beton m3 0.5400 261,250.00 141,075.00
3 Koral m3 0.8200 380,160.00 311,731.20

JUMLAH HARGA BAHAN 875,206.20

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,048,406.20


E. DIBULATKAN 1,048,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Beton Ready Mix K-250


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 1,269,300.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.2000 105,000.00 21,000.00
2 Pekerjan tak terampil OH 0.6000 90,000.00 54,000.00
3 Kepala tukang OH 0.1000 110,000.00 11,000.00
4 Mandor OH 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 91,750.00

B. BAHAN
1 Beton Ready Mix K 250 M3 1.0500 1,119,360.00 1,175,328.00

1,175,328.00

C. ALAT
1 alat bantu jam 1.0000 2,293.75 2,293.75

JUMLAH HARGA ALAT 2,293.75

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,269,371.75


E. DIBULATKAN 1,269,300.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Beton Ready Mix K-175


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 1,191,700.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.2000 105,000.00 21,000.00
2 Pekerjan tak terampil OH 0.6000 90,000.00 54,000.00
3 Kepala tukang OH 0.1000 110,000.00 11,000.00
4 Mandor OH 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 91,750.00

B. BAHAN
1 Portland Cement kg 1.0500 1,045,440.00 1,097,712.00

1,097,712.00

C. ALAT
1 alat bantu jam 1.0000 2,293.75 2,293.75

JUMLAH HARGA ALAT 2,293.75

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,191,755.75


E. DIBULATKAN 1,191,700.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Cor Beton dengan tebal 15 cm mutu beton K-350


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 1,397,900.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 2.3427 15,000.00 35,140.50
2 Pekerjan tak terampil OH 4.6854 12,857.14 60,240.86
3 Mandor OH 0.5020 16,428.57 8,247.14

JUMLAH HARGA TENAGA 103,628.50

B. BAHAN
1 Beton Ready Mix K 350 m3 1.1000 1,119,360.00 1,231,296.00
2 kayu perancah m3 0.0063 2,860,000.00 17,875.00
3 plastik Cor m2 6.6667 3,300.00 22,000.00
4 Multiplek 9 mmm m2 0.3400 60,500.00 20,570.00

1,291,741.00

C. ALAT
2 Alat bantu ls 1.0000 2,590.71 2,590.71

JUMLAH HARGA ALAT 2,590.71

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,397,960.21


E. DIBULATKAN 1,397,900.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Beton Ready Mix K-300


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 1,291,000.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.2000 105,000.00 21,000.00
2 Pekerjan tak terampil OH 0.6000 90,000.00 54,000.00
3 Kepala tukang OH 0.1000 110,000.00 11,000.00
4 Mandor OH 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 91,750.00

B. BAHAN
1 Beton Ready Mix K 300 M3 1.0500 1,140,000.00 1,197,000.00

1,197,000.00

C. ALAT
1 alat bantu jam 1.0000 2,293.75 2,293.75

JUMLAH HARGA ALAT 2,293.75

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,291,043.75


E. DIBULATKAN 1,291,000.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Beton Ready Mix K-350


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 1,369,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.2000 105,000.00 21,000.00
2 Pekerjan tak terampil OH 0.6000 90,000.00 54,000.00
3 Kepala tukang OH 0.1000 110,000.00 11,000.00
4 Mandor OH 0.0500 115,000.00 5,750.00

JUMLAH HARGA TENAGA 91,750.00

B. BAHAN
1 Beton Ready Mix K 350 M3 1.0500 1,214,400.00 1,275,120.00

1,275,120.00

C. ALAT
1 alat bantu jam 1.0000 2,293.75 2,293.75

JUMLAH HARGA ALAT 2,293.75

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,369,163.75


E. DIBULATKAN 1,369,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan Meja Beton panjang 1,35 x 0,6 m


SATUAN PEKERJAAN : unit
HARGA SATUAN : Rp 3,078,700.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

JUMLAH HARGA TENAGA -

B. BAHAN
1 Beton bertulang 1Pc : 2Ps : 3Kr m3 0.0472 1,048,400.00 49,484.48
2 Pembesian kg 4.0290 14,690.00 59,186.01
3 Bekisting m2 0.7925 181,400.00 143,759.50
4 Granit m' 1.3500 2,093,570.00 2,826,319.50

3,078,749.49

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 3,078,749.49


E. DIBULATKAN 3,078,700.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan Meja Beton panjang 1,5 x 0,6 m


SATUAN PEKERJAAN : unit
HARGA SATUAN : Rp 3,424,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

JUMLAH HARGA TENAGA -

B. BAHAN
1 Beton bertulang 1Pc : 2Ps : 3Kr m3 0.0544 1,048,400.00 57,032.96
2 Pembesian kg 4.2660 14,690.00 62,667.54
3 Bekisting m2 0.9050 181,400.00 164,167.00
4 Granit m' 1.5000 2,093,570.00 3,140,355.00

3,424,222.50

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 3,424,222.50


E. DIBULATKAN 3,424,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan Meja Beton panjang 1,06 x 0,6 m


SATUAN PEKERJAAN : unit
HARGA SATUAN : Rp 2,403,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

JUMLAH HARGA TENAGA -

B. BAHAN
1 Beton bertulang 1Pc : 2Ps : 3Kr m3 0.0333 1,048,400.00 34,890.75
2 Pembesian kg 3.0968 14,690.00 45,491.99
3 Bekisting m2 0.5750 181,400.00 104,305.00
4 Granit m' 1.0600 2,093,570.00 2,219,184.20

2,403,871.94

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 2,403,871.94


E. DIBULATKAN 2,403,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan grouting


SATUAN PEKERJAAN : m3
HARGA SATUAN : Rp 75,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.0750 105,000.00 7,875.00
2 Pekerjan tak terampil OH 0.0500 90,000.00 4,500.00
3 Kepala tukang OH 0.0075 110,000.00 825.00
4 Mandor OH 0.0250 115,000.00 2,875.00
-
JUMLAH HARGA TENAGA 16,075.00

B. BAHAN
1 - semen grouting M3 0.1667 352,000.00 58,666.67

58,666.67

C. ALAT
1 alat bantu jam 1.0000 401.88 401.88

JUMLAH HARGA ALAT 401.88

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 75,143.54


E. DIBULATKAN 75,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasangan Batu Bata Merah Tebal 1/2 Bata, 1PC : 4 PS
SATUAN PEKERJAAN : m²
HARGA SATUAN : Rp 111,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.1000 105,000.00 10,500.00
2 Pekerja tak terampil OH 0.2500 90,000.00 22,500.00
3 Kepala tukang baru OH 0.0100 110,000.00 1,100.00
4 Mandor OH 0.0150 115,000.00 1,725.00

JUMLAH HARGA TENAGA 35,825.00

B. BAHAN
1 Bata merah bh 70.0000 715.00 50,050.00
2 Portland Cement zak 0.2300 66,000.00 15,180.00
3 Pasir Pasang m³ 0.0430 247,500.00 10,642.50

JUMLAH HARGA BAHAN 75,872.50

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 111,697.50


E. DIBULATKAN 111,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasangan Rollag Bata, 1PC : 4 PS


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 24,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.0220 105,000.00 2,310.00
2 Pekerja tak terampil OH 0.0550 90,000.00 4,950.00
3 Kepala tukang baru OH 0.0022 110,000.00 242.00
4 Mandor OH 0.0033 115,000.00 379.50

JUMLAH HARGA TENAGA 7,881.50

B. BAHAN
1 Bata merah bh 15.4000 715.00 11,011.00
2 Portland Cement zak 0.0506 66,000.00 3,339.60
3 Pasir Pasang m³ 0.0095 247,500.00 2,341.35

JUMLAH HARGA BAHAN 16,691.95

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 24,573.45


E. DIBULATKAN 24,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan partisi double gypsum 9 mm rangka eka furing


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 139,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0750 115,000.00 8,625.00
2 Kepala Tukang OH 0.0450 110,000.00 4,950.00
3 Tukang OH 0.4500 105,000.00 47,250.00
4 Pekerja OH 0.1500 90,000.00 13,500.00

JUMLAH HARGA TENAGA 74,325.00

B. BAHAN
1 Gypsum 9 mm lbr 0.6944 60,500.00 42,013.62
2 Rangka plafond eka furing m2 1.0000 14,300.00 14,300.00
3 Paku skrup 1" kotak 0.0500 58,300.00 2,915.00
4 Stopping zak 0.0250 99,000.00 2,475.00
5 Joint tape roll 0.0250 17,600.00 440.00
6 Paku ramset set 0.0200 132,000.00 2,640.00

JUMLAH HARGA BAHAN 64,783.62

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 139,108.62


E. DIBULATKAN 139,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan dinding Cilcon


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 166,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Tukang batu OH 0.1000 105,000.00 10,500.00
2 Pekerja tak terampil OH 0.2500 90,000.00 22,500.00
3 Kepala tukang baru OH 0.0100 110,000.00 1,100.00
4 Mandor OH 0.0150 115,000.00 1,725.00

JUMLAH HARGA TENAGA 35,825.00

B. BAHAN
1 bata Cilcon lbr 9.0000 13,500.00 121,500.00
2 PC zak 0.0720 66,000.00 4,752.00
3 Pasir pasang m3 0.0180 247,500.00 4,455.00

JUMLAH HARGA BAHAN 130,707.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 166,532.00


E. DIBULATKAN 166,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Plesteran halus 1Pc : 4 Ps (T=1,5 Cm)


SATUAN PEKERJAAN : m²
HARGA SATUAN : Rp 38,298.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0100 115,000.00 1,150.00
2 Kepala tukang OH 0.0150 110,000.00 1,650.00
3 Tukang batu OH 0.1500 105,000.00 15,750.00
4 Pekerja tak trampil OH 0.1000 90,000.00 9,000.00

JUMLAH HARGA TENAGA 27,550.00

B. BAHAN
1 Semen 50 kg Zak 0.0916 66,000.00 6,045.60
2 Pasir pasang m³ 0.0190 247,500.00 4,702.50

JUMLAH HARGA BAHAN 10,748.10

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 38,298.10


E. PEMBULATAN 38,298.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Aci Halus


SATUAN PEKERJAAN : m²
HARGA SATUAN : Rp 26,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0030 115,000.00 345.00
2 Kepala tukang OH 0.0030 110,000.00 330.00
3 Tukang batu OH 0.0600 105,000.00 6,300.00
4 Pekerja tak trampil OH 0.0600 90,000.00 5,400.00

JUMLAH HARGA TENAGA 12,375.00

B. BAHAN
1 Semen 50 kg Zak 0.2150 66,000.00 14,190.00

JUMLAH HARGA BAHAN 14,190.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 26,565.00


E. PEMBULATAN 26,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Pemasangan partisi double GRC t=6 mm rangka eka furing
SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 158,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0750 115,000.00 8,625.00
2 Kepala Tukang OH 0.0450 110,000.00 4,950.00
3 Tukang OH 0.4500 105,000.00 47,250.00
4 Pekerja OH 0.1500 90,000.00 13,500.00

JUMLAH HARGA TENAGA 74,325.00

B. BAHAN
1 GRC t = 6 mm lbr 0.6944 88,000.00 61,110.72
2 Rangka plafond eka furing m2 1.0000 14,300.00 14,300.00
3 Paku skrup 1" kotak 0.0500 58,300.00 2,915.00
4 Stopping zak 0.0250 99,000.00 2,475.00
5 Joint tape roll 0.0250 17,600.00 440.00
6 Paku ramset set 0.0200 132,000.00 2,640.00

JUMLAH HARGA BAHAN 83,880.72

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 158,205.72


E. DIBULATKAN 158,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!

#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang Listplank tekstur kayu tebal 8mm, lebar 20 cm


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 77,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0100 115,000.00 1,150.00
2 Kepala Tukang OH 0.0200 110,000.00 2,200.00
3 Tukang Kayu OH 0.0600 105,000.00 6,300.00
4 Pekerja OH 0.0400 90,000.00 3,600.00

JUMLAH HARGA TENAGA 13,250.00

B. BAHAN
1 Listplank tekstur kayu tebal 8mm m' 1.1000 55,000.00 60,500.00
2 Sekrup 1" kotak 0.0500 58,300.00 2,915.00
3 Stopping zak 0.0050 99,000.00 495.00

JUMLAH HARGA BAHAN 63,910.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 77,160.00


E. DIBULATKAN 77,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang plafond grc tebal 3,5 mm


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 138,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0750 115,000.00 8,625.00
2 Kepala Tukang OH 0.0771 110,000.00 8,485.71
3 Tukang OH 0.0900 105,000.00 9,450.00
4 Pekerja OH 0.0800 90,000.00 7,200.00

JUMLAH HARGA TENAGA 33,760.71

B. BAHAN
1 Papan fiber cement tebal 6 mm lbr 0.4514 88,000.00 39,722.22
2 Rangka plafond eka furing btg 3.5000 14,300.00 50,050.00
3 Paku skrup 1" kotak 0.0500 58,300.00 2,915.00
4 Stopping zak 0.0250 99,000.00 2,475.00
5 Joint tape roll 0.0250 17,600.00 440.00
6 Paku ramset set 4.0000 2,200.00 8,800.00

JUMLAH HARGA BAHAN 104,402.22

C. ALAT
1 Scafolding (1 set) bulan 0.0200 35,000.00 700.00

JUMLAH HARGA ALAT 700.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 138,862.94


E. DIBULATKAN 138,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan plafond gypsum 9 mm

SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 128,000.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0750 115,000.00 8,625.00
2 Kepala Tukang OH 0.0771 110,000.00 8,485.71
3 Tukang OH 0.0900 105,000.00 9,450.00
4 Pekerja OH 0.0800 90,000.00 7,200.00

JUMLAH HARGA TENAGA 33,760.71

1 Gypsum 9 mm lbr 0.4514 60,500.00 27,309.03


2 Rangka plafond eka furing btg 3.5000 14,300.00 50,050.00
3 Paku skrup 1" kotak 0.0500 58,300.00 2,915.00
4 Stopping zak 0.0250 99,000.00 2,475.00
5 Joint tape roll 0.0250 17,600.00 440.00
6 Ramset bh 4.0000 2,200.00 8,800.00

JUMLAH HARGA BAHAN 91,989.03

C. ALAT
1 Alat bantu ls 1.0000 2,299.73 2,299.73

JUMLAH HARGA ALAT 2,299.73

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 128,049.47


E. DIBULATKAN 128,000.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan keramik lantai tekstur, ukuran 80 x 80 cm


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 283,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0125 115,000.00 1,437.50
2 Kepala tukang OH 0.0120 110,000.00 1,320.00
3 Tukang Batu OH 0.1200 105,000.00 12,600.00
4 Pekerja OH 0.2500 90,000.00 22,500.00

JUMLAH HARGA TENAGA 37,857.50

B. BAHAN
1 keramik 80 x 80 cm m2 1.0500 220,000.00 231,000.00
2 Semen portland zak 0.0160 66,000.00 1,056.00
3 Semen warna kg 0.2000 13,200.00 2,640.00
4 Pasir m3 0.0450 247,500.00 11,137.50

245,833.50

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 283,691.00


E. DIBULATKAN 283,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan plint keramik 10 x 80 cm


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 75,300.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0125 115,000.00 1,437.50
2 Kepala tukang OH 0.0120 110,000.00 1,320.00
3 Tukang Batu OH 0.1200 105,000.00 12,600.00
4 Pekerja OH 0.2500 90,000.00 22,500.00

JUMLAH HARGA TENAGA 37,857.50

B. BAHAN
1 Plint lantai 10 x 60 cm bh 1.2500 27,500.00 34,375.00
2 Semen portland zak 0.0160 66,000.00 1,056.00
3 Pasir pasang m3 0.0030 247,500.00 742.50
4 Semen warna kg 0.1000 13,200.00 1,320.00

JUMLAH HARGA BAHAN 37,493.50

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 75,351.00


E. DIBULATKAN 75,300.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan plint keramik 10 x 60 cm


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 184,300.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0125 115,000.00 1,437.50
2 Kepala tukang OH 0.0120 110,000.00 1,320.00
3 Tukang Batu OH 0.1200 105,000.00 12,600.00
4 Pekerja OH 0.2500 90,000.00 22,500.00

JUMLAH HARGA TENAGA 37,857.50

B. BAHAN
1 Plint lantai 10 x 60 cm bh 1.6600 72,500.00 120,350.00
2 Semen portland zak 0.0160 66,000.00 1,056.00
3 Pasir pasang m3 0.0030 99,000.00 297.00
4 Semen warna kg 0.1000 247,500.00 24,750.00

JUMLAH HARGA BAHAN 146,453.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 184,310.50


E. DIBULATKAN 184,300.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan keramik dinding, ukuran 30 x 60 cm


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 235,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0125 115,000.00 1,437.50
2 Kepala tukang OH 0.0120 110,000.00 1,320.00
3 Tukang Batu OH 0.1200 105,000.00 12,600.00
4 Pekerja OH 0.2500 90,000.00 22,500.00

JUMLAH HARGA TENAGA 37,857.50

B. BAHAN
1 Ubin keramik 30 x 60 cm, warna std m2 1.0500 165,000.00 173,250.00
2 Semen 50 kg zak 0.1424 66,000.00 9,398.40
3 Pasir pasang / plester m3 0.0500 247,500.00 12,375.00
4 Semen warna kg 0.2000 13,200.00 2,640.00

JUMLAH HARGA BAHAN 197,663.40

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 235,520.90


E. DIBULATKAN 235,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan keramik lantai tekstur, ukuran 30 x 60 cm


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 262,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0125 115,000.00 1,437.50
2 Kepala tukang OH 0.0120 110,000.00 1,320.00
3 Tukang Batu OH 0.1200 105,000.00 12,600.00
4 Pekerja OH 0.2500 90,000.00 22,500.00

JUMLAH HARGA TENAGA 37,857.50

B. BAHAN
1 keramik 30 x 60 cm m2 1.0500 165,000.00 173,250.00
2 Semen portland zak 0.0160 66,000.00 1,056.00
3 Semen warna kg 0.2000 247,500.00 49,500.00
4 Pasir m3 0.0450 13,200.00 594.00

224,400.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 262,257.50


E. DIBULATKAN 262,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan keramik lantai tekstur, ukuran 30 x 30 cm


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 239,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0125 115,000.00 1,437.50
2 Kepala tukang OH 0.0120 110,000.00 1,320.00
3 Tukang Batu OH 0.1200 105,000.00 12,600.00
4 Pekerja OH 0.2500 90,000.00 22,500.00

JUMLAH HARGA TENAGA 37,857.50

B. BAHAN
1 keramik 60 x 60 cm m2 1.0500 143,000.00 150,150.00
2 Semen portland zak 0.0160 66,000.00 1,056.00
3 Semen warna kg 0.2000 247,500.00 49,500.00
4 Pasir m3 0.0450 13,200.00 594.00

201,300.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 239,157.50


E. DIBULATKAN 239,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pengecatan tembok baru


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 32,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0025 115,000.00 287.50
2 Kepala tukang OH 0.0063 110,000.00 693.00
3 Tukang cat OH 0.0630 105,000.00 6,615.00
4 Pekerja OH 0.0200 90,000.00 1,800.00

JUMLAH HARGA TENAGA 9,395.50

B. BAHAN
1 Cat dasar (sealer minyak) Kg 0.1000 45,833.33 4,583.33
2 Cat tembok penutup 2 kali Kg 0.2381 76,388.89 18,187.83

JUMLAH HARGA BAHAN 22,771.16

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 32,166.66


E. DIBULATKAN 32,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pengecatan Plafond


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 22,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0025 115,000.00 287.50
2 Kepala tukang OH 0.0063 110,000.00 693.00
3 Tukang cat OH 0.0630 105,000.00 6,615.00
4 Pekerja OH 0.0200 90,000.00 1,800.00

JUMLAH HARGA TENAGA 9,395.50

B. BAHAN
1 Cat dasar (sealer minyak) Kg 0.1700 45,833.33 7,791.67
2 Cat plafond penutup 2 kali Kg 0.2000 27,500.00 5,500.00

JUMLAH HARGA BAHAN 13,291.67

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 22,687.17


E. DIBULATKAN 22,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pengecatan besi


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 50,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0120 115,000.00 1,380.00
2 Kepala tukang OH 0.0230 110,000.00 2,530.00
3 Tukang cat OH 0.1250 105,000.00 13,125.00

JUMLAH HARGA TENAGA 17,035.00

B. BAHAN
1 Cat dasar meni Ltr 0.1000 25,000.00 2,500.00
2 Cat warna/cat minyak Kg 0.2000 70,000.00 14,000.00
3 Amplas lbr 0.5000 6,600.00 3,300.00
4 Minyak cat ltr 0.2000 70,000.00 14,000.00

JUMLAH HARGA BAHAN 33,800.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 50,835.00


E. DIBULATKAN 50,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Atap alumunium metal


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 281,900.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja OH 0.1400 90,000.00 12,600.00
2 Tenaga Skill OH 0.0670 105,000.00 7,035.00
3 Mandor OH 0.0070 115,000.00 805.00
4 Kepala Tukang OH 0.0070 110,000.00 770.00

JUMLAH HARGA TENAGA 21,210.00

B. BAHAN
1 Atap alumunium metal m2 1.0200 245,000.00 249,900.00
2 Paku bh 9.0000 1,200.00 10,800.00

JUMLAH HARGA BAHAN 260,700.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 281,910.00


E. DIBULATKAN 281,900.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan talang seng BJLS 30 (lebar 40 cm)


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 108,600.00

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0250 115,000.00 2,875.00
2 Kepala Tukang OH 0.0800 110,000.00 8,800.00
3 Tukang OH 0.5000 105,000.00 52,500.00
4 Pekerja OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 82,175.00

B. BAHAN
1 Seng talang BJLS 30 lebar 40 m' 1.0000 24,200.00 24,200.00
2 Paku sumbat bh 5.0000 452.00 2,260.00

JUMLAH HARGA BAHAN 26,460.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 108,635.00


E. DIBULATKAN 108,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Atap Solid Polycarbonate Sheet


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 559,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja OH 0.1500 90,000.00 13,500.00
2 Tenaga Skill OH 0.3000 105,000.00 31,500.00
3 Mandor OH 0.0150 115,000.00 1,725.00

JUMLAH HARGA TENAGA 46,725.00

B. BAHAN
1 Atap Solid Polycarbonate Sheet m2 1.0200 495,000.00 504,900.00
2 Baut kotak 0.1200 - -
3 Joint / sambungan m' 0.1300 57,500.00 7,475.00

JUMLAH HARGA BAHAN 512,375.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 559,100.00


E. DIBULATKAN 559,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Memasang 1 bh floor drain


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 103,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0050 115,000.00 575.00
2 Kepala Tukang OH 0.0100 110,000.00 1,100.00
3 Tukang batu OH 0.1000 105,000.00 10,500.00
4 Pekerja OH 0.0100 90,000.00 900.00

JUMLAH HARGA TENAGA 13,075.00

B. BAHAN
1 Floor drain bh 1.0000 90,000.00 90,000.00

JUMLAH HARGA BAHAN 90,000.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 103,075.00


E. DIBULATKAN 103,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Memasang Kran air


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 81,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Kepala Tukang OH 0.0300 110,000.00 3,300.00
2 Tukang batu OH 0.1500 105,000.00 15,750.00

JUMLAH HARGA TENAGA 19,050.00

B. BAHAN
1 Kran air bh 1.0000 60,000.00 60,000.00
2 Sealtipe roll 1.0000 2,500.00 2,500.00

JUMLAH HARGA BAHAN 62,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 81,550.00


E. DIBULATKAN 81,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Memasang 1 buah wastafel


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 1,672,890.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.1000 115,000.00 11,500.00
2 Kepala Tukang OH 0.1500 110,000.00 16,500.00
3 Tukang batu OH 1.4500 105,000.00 152,250.00
4 Pekerja OH 1.2000 90,000.00 108,000.00

JUMLAH HARGA TENAGA 288,250.00

B. BAHAN
1 Wastafel bh 1.0000 1,195,000.00 1,195,000.00
2 Perlengkapan set 1.0000 179,250.00 179,250.00
3 Semen abu-abu kg 6.0000 1,320.00 7,920.00
4 Pasir pasang m3 0.0100 247,500.00 2,475.00

JUMLAH HARGA BAHAN 1,384,645.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,672,895.00


E. DIBULATKAN 1,672,890.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Memasang 1 buah kloset jongkok


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 372,070.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0050 115,000.00 575.00
2 Kepala Tukang OH 0.0100 110,000.00 1,100.00
3 Tukang batu OH 0.4000 105,000.00 42,000.00
4 Pekerja OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 61,675.00

B. BAHAN
1 Semen portland 50 kg zak 0.1200 66,000.00 7,920.00
2 Kloset jongkok bh 1.0000 300,000.00 300,000.00
3 Pasir pasang m3 0.0100 247,500.00 2,475.00

JUMLAH HARGA BAHAN 310,395.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 372,070.00


E. DIBULATKAN 372,070.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Memasang 1 buah kloset duduk


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 3,036,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Kepala Tukang OH 0.1500 110,000.00 16,500.00


2 Tukang batu OH 1.5000 105,000.00 157,500.00

JUMLAH HARGA TENAGA 174,000.00

B. BAHAN
1 Bahan Perekat Ls 1.0000 60,000.00 60,000.00
2 Kloset duduk bh 1.0000 2,640,000.00 2,640,000.00
3 Jet shower bh 1.0000 162,500.00 162,500.00

JUMLAH HARGA BAHAN 2,862,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 3,036,500.00


E. DIBULATKAN 3,036,500.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Memasang 1 buah zink dapur


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 1,761,540.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1 Kepala Tukang OH 0.1500 110,000.00 16,500.00


2 Tukang batu OH 0.3030 105,000.00 31,815.00
3 Mandor OH 0.0150 115,000.00 1,725.00

JUMLAH HARGA TENAGA 50,040.00

B. BAHAN
1 kitchen zink bh 1.0000 1,380,000.00 1,380,000.00
2 Kran zink bh 1.0000 250,000.00 250,000.00
3 asesories bh 1.0000 81,500.00 81,500.00

JUMLAH HARGA BAHAN 1,711,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,761,540.00


E. DIBULATKAN 1,761,540.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Mengerjakan inst. air bekas pipa uPVC dia. 3"
SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 149,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0041 115,000.00 471.50
2 Pembantu Tukang OH 0.0810 90,000.00 7,290.00
3 Tukang OH 0.1350 105,000.00 14,175.00
4 Kepala tukang OH 0.1350 110,000.00 14,850.00

JUMLAH HARGA TENAGA 36,786.50

B. BAHAN
1 Pipa PVC Class AW dia 3" m' 1.1000 97,500.00 107,250.00
2 Accessories ls 1.0000 5,362.50 5,362.50

JUMLAH HARGA BAHAN 112,612.50

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 149,399.00


E. DIBULATKAN 149,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Mengerjakan inst. air bersih uPVC dia. 1/2"


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 24,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0018 115,000.00 207.00
2 Tukang OH 0.0600 105,000.00 6,300.00
3 Pembantu Tukang OH 0.0360 90,000.00 3,240.00
4 Kepala Tukang OH 0.0060 110,000.00 660.00

JUMLAH HARGA TENAGA 10,407.00

B. BAHAN
1 Pipa PVC AW 1/2" m' 1.0000 13,000.00 13,000.00
2 Assesories ls 1.0000 650.00 650.00

13,650.00

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 24,057.00


E. DIBULATKAN 24,100.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Mengerjakan inst. air bersih uPVC dia. 3/4"


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 29,400.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0018 115,000.00 207.00
2 Tukang OH 0.0600 105,000.00 6,300.00
3 Pembantu Tukang OH 0.0360 90,000.00 3,240.00
4 Kepala Tukang OH 0.0060 110,000.00 660.00

JUMLAH HARGA TENAGA 10,407.00

B. BAHAN
1 Pipa PVC AW 3/4" m' 1.0000 18,000.00 18,000.00
2 Assesories ls 1.0000 900.00 900.00

18,900.00

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 29,307.00


E. DIBULATKAN 29,400.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Mengerjakan inst. air bekas pipa uPVC dia. 4"
SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 208,000.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0041 115,000.00 471.50
2 Pembantu Tukang OH 0.0810 90,000.00 7,290.00
3 Tukang OH 0.1350 105,000.00 14,175.00
4 Kepala tukang OH 0.1350 110,000.00 14,850.00

JUMLAH HARGA TENAGA 36,786.50

B. BAHAN
1 Pipa PVC Class AW dia 4" m' 1.0000 163,000.00 163,000.00
2 Accessories ls 1.0000 8,150.00 8,150.00

JUMLAH HARGA BAHAN 171,150.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 207,936.50


E. DIBULATKAN 208,000.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Mengerjakan inst. air bersih uPVC dia. 1"


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 36,700.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0018 115,000.00 207.00
2 Tukang OH 0.0600 105,000.00 6,300.00
3 Pembantu Tukang OH 0.0360 90,000.00 3,240.00
4 Kepala Tukang OH 0.0060 110,000.00 660.00

JUMLAH HARGA TENAGA 10,407.00

B. BAHAN
1 Pipa PVC Class AW dia 1" m' 1.0000 25,000.00 25,000.00
2 Accessories ls 1.0000 1,250.00 1,250.00

JUMLAH HARGA BAHAN 26,250.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 36,657.00


E. DIBULATKAN 36,700.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Mengerjakan inst. air kotor pipa uPVC dia. 2"
SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 68,200.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0027 115,000.00 310.50
2 Pembantu Tukang OH 0.0900 105,000.00 9,450.00
3 Tukang OH 0.0540 90,000.00 4,860.00
4 kepala tukang OH 0.0090 110,000.00 990.00

JUMLAH HARGA TENAGA 15,610.50

B. BAHAN
1 Pipa PVC Class AW dia 2" m' 1.0000 50,000.00 50,000.00
2 Accessories ls 1.0000 2,500.00 2,500.00

JUMLAH HARGA BAHAN 52,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 68,110.50


E. DIBULATKAN 68,200.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016
JENIS PEKERJAAN : Pekerjaan Saluran U.40
SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 401,878.75

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0182 115,000.00 2,091.36
2 Tukang OH 0.0545 105,000.00 5,727.00
3 Pekerja OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 25,818.36

B. BAHAN
1 Parit pracetak type U-40 bh 1.6600 195,000.00 323,700.00
2 Pasir pasang m3 0.0036 247,500.00 891.00
3 Semen zak 0.0346 66,000.00 2,280.96
4 Pasir urug m3 0.0600 210,900.00 12,654.00

JUMLAH HARGA BAHAN 339,525.96

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 365,344.32


E. OVERHEAD & PROFIT 10.0 % x D 36,534.43
F. HARGA SATUAN PEKERJAAN ( D + E ) 401,878.75
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan Saluran U.60


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 502,308.75

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0182 115,000.00 2,091.36
2 Tukang OH 0.0545 105,000.00 5,727.00
3 Pekerja OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 25,818.36

B. BAHAN
1 Parit pracetak type U-60 bh 1.6600 250,000.00 415,000.00
2 Pasir pasang m3 0.0036 247,500.00 891.00
3 Semen zak 0.0346 66,000.00 2,280.96
4 Pasir urug m3 0.0600 210,900.00 12,654.00

JUMLAH HARGA BAHAN 430,825.96

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 456,644.32


E. OVERHEAD & PROFIT 10.0 % x D 45,664.43
F. HARGA SATUAN PEKERJAAN ( D + E ) 502,308.75
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : #REF!
TAHUN ANGGARAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG

JENIS PEKERJAAN : Pasangan batu belah 1 : 4


SATUAN PEKERJAAN : m³
HARGA SATUAN : Rp 797,830.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0700 115,000.00 8,050.00
2 Kepala tukang OH 0.0600 110,000.00 6,600.00
3 Tukang batu OH 0.6000 105,000.00 63,000.00
4 Pekerja OH 1.5000 90,000.00 135,000.00

JUMLAH HARGA TENAGA 212,650.00

B. BAHAN
1 Batu belah m3 1.1000 242,000.00 266,200.00
2 PC ( 50 kg ) zak 2.7924 66,000.00 184,298.40
3 Pasir pasang m3 0.5442 247,500.00 134,689.50

JUMLAH HARGA BAHAN 585,187.90

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 797,837.90


E. DIBULATKAN 797,830.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pasang kanstin / kerb type K 8 dan K 8L


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 121,130.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0100 115,000.00 1,150.00
2 Kepala tukang batu OH 0.0100 110,000.00 1,100.00
3 Tukang batu OH 0.1000 105,000.00 10,500.00
4 Pekerja OH 0.1000 90,000.00 9,000.00

JUMLAH HARGA TENAGA 21,750.00

B. BAHAN
1 Kanstin / kerb type K 8 dan K 8L Bh 1.2000 52,000.00 62,400.00
2 Pasir pasang m3 0.0800 247,500.00 19,800.00
3 PC Zak 0.2236 66,000.00 14,758.18

JUMLAH HARGA BAHAN 96,958.18

C. ALAT
1 Alat bantu Ls 1.0000 2,423.95 2,423.95

JUMLAH HARGA ALAT 2,423.95

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 121,132.14


E. DIBULATKAN 121,130.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! ###
#REF!
#REF! ### #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan railling besi hollow 50x50x2.3 mm


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 60,250.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0760 115,000.00 8,739.01
2 Tukang OH 0.0760 105,000.00 7,978.86
3 Pekerja OH 0.1520 90,000.00 13,680.98

JUMLAH HARGA TENAGA 30,398.85

B. BAHAN
1 Besi hollow 50x50x2.3 mm m' 1.0000 27,500.00 27,500.00
2 Elektroda baja kg 0.0060 42,900.00 257.40

JUMLAH HARGA BAHAN 27,757.40

C. ALAT
1 Welding set jam 0.0210 100,000.00 2,100.00

JUMLAH HARGA ALAT 2,100.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 60,256.25


E. DIBULATKAN 60,250.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : #REF!
PEKERJAAN : #REF!
LOKASI : BATAM
TAHUN ANGGARAN : 2014

JENIS PEKERJAAN : Memasang Shower


SATUAN PEKERJAAN : bh
HARGA SATUAN : Rp 519,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Upah Pekerja ls 1.0000 86,625.00 86,625.00

JUMLAH HARGA TENAGA 86,625.00

B. BAHAN
1 Shower bh 1.0000 350,000.00 350,000.00
2 Kran Air bh 1.0000 60,000.00 60,000.00
3 Sealtipe roll 1.0000 2,500.00 2,500.00
4 Perlengkapan set 1.0000 20,625.00 20,625.00

JUMLAH HARGA BAHAN 433,125.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 519,750.00


E. DIBULATKAN 519,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!

#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Pemasangan saluran U-40


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 184,810.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0182 115,000.00 2,091.36
2 Tukang OH 0.0545 105,000.00 5,727.00
3 Pekerja OH 0.2000 90,000.00 18,000.00

JUMLAH HARGA TENAGA 25,818.36

B. BAHAN
1 Parit pracetak type U-40 bh 1.6600 86,250.00 143,175.00
2 Pasir pasang m3 0.0036 247,500.00 891.00
3 Semen zak 0.0346 66,000.00 2,280.96
4 Pasir urug m3 0.0600 210,900.00 12,654.00

JUMLAH HARGA BAHAN 159,000.96

C JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B ) 184,819.32


D DIBULATKAN 184,810.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!

#REF! : #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Pemasangan gril penutup saluran


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 242,950.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.1800 115,000.00 20,700.00
2 Tukang OH 0.4000 105,000.00 42,000.00
3 Pekerja OH 0.4000 90,000.00 36,000.00
4 Kepala Tukang OH 0.1500 110,000.00 16,500.00

JUMLAH HARGA TENAGA 115,200.00

B. BAHAN
1 Pembesian kg 6.3200 10,080.00 63,705.60
2 Besi siku 50 x 50 x 5 mm kg 3.2000 10,080.00 32,256.00
3 elektroda zak 0.5000 42,900.00 21,450.00
4 Pengecatan besi m2 0.4000 25,850.00 10,340.00

JUMLAH HARGA BAHAN 127,751.60

C JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B ) 242,951.60


D DIBULATKAN 242,950.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

#REF! : #REF!
#REF! ### #REF!
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM

JENIS PEKERJAAN : Pemasangan Pintu P2


SATUAN PEKERJAAN : unit
HARGA SATUAN : Rp 1,896,100.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tak Terampil OH 0.6000 90,000.00 54,000.00
2 Mandor OH 0.0300 115,000.00 3,450.00
3 Tukang Kayu OH 2.0000 105,000.00 210,000.00
4 Kepala Tukang OH 0.2000 110,000.00 22,000.00

JUMLAH HARGA TENAGA 289,450.00

B. BAHAN
1 Pintu Panel Multiplek 4 mm double bh 1.0000 1,600,000.00 1,600,000.00
2 Paku kg 0.3000 22,000.00 6,600.00

JUMLAH HARGA BAHAN 1,606,600.00

C. ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 1,896,050.00


E. DIBULATKAN 1,896,100.00
JENIS PEKERJAAN : Pemasangan Pintu P3
SATUAN PEKERJAAN : unit
HARGA SATUAN : Rp 789,500.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tak Terampil OH 0.6000 90,000.00 54,000.00
2 Mandor OH 0.0300 115,000.00 3,450.00
3 Tukang Kayu OH 2.0000 105,000.00 210,000.00
4 Kepala Tukang OH 0.2000 110,000.00 22,000.00

JUMLAH HARGA TENAGA 289,450.00

B. BAHAN
1 Pintu PVC bh 1.0000 500,000.00 500,000.00

JUMLAH HARGA BAHAN 500,000.00

C. ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 789,450.00


E. DIBULATKAN 789,500.00
JENIS PEKERJAAN : Pemasangan Pintu P1
SATUAN PEKERJAAN : unit
HARGA SATUAN : Rp 17,308,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tak Terampil OH 0.8000 90,000.00 72,000.00
2 Mandor OH 0.0400 115,000.00 4,600.00
3 Tukang Kayu OH 2.0000 105,000.00 210,000.00
4 Kepala Tukang OH 0.2000 110,000.00 22,000.00

JUMLAH HARGA TENAGA 308,600.00

B. BAHAN
1 Pintu kaca sandblast 9 mm bh 1.0000 17,000,000.00 17,000,000.00

JUMLAH HARGA BAHAN 17,000,000.00

C. ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 17,308,600.00


E. DIBULATKAN 17,308,600.00
JENIS PEKERJAAN : Pemasangan Pintu PJ1
SATUAN PEKERJAAN : unit
HARGA SATUAN : Rp 9,508,600.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja Tak Terampil OH 0.8000 90,000.00 72,000.00
2 Mandor OH 0.0400 115,000.00 4,600.00
3 Tukang Kayu OH 2.0000 105,000.00 210,000.00
4 Kepala Tukang OH 0.2000 110,000.00 22,000.00

JUMLAH HARGA TENAGA 308,600.00

B. BAHAN
1 Pintu kaca sandblast 9 mm bh 1.0000 9,200,000.00 9,200,000.00

JUMLAH HARGA BAHAN 9,200,000.00

C. ALAT
-

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 9,508,600.00


E. DIBULATKAN 9,508,600.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan Paving Blok


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 261,800.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.00 120,000.00 300.00
2 Pekerja Tak Terampil OH 0.75 90,000.00 67,500.00
3 Tukang Batu OH 0.25 100,000.00 25,000.00
4 Kepala Tukang Batu OH 0.03 110,000.00 2,750.00

JUMLAH HARGA TENAGA 95,550.00

B. BAHAN
1 Paving blok m2 33.0000 4,400.00 145,200.00
2 Pasir Urug m3 0.1000 210,900.00 21,090.00
-

JUMLAH HARGA BAHAN 166,290.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 261,840.00


E. DIBULATKAN 261,800.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) T= 5 cm


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 238,350.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja OH 0.1118 90,000.00 10,062.72
2 Mandor OH 0.0112 115,000.00 1,285.70

JUMLAH HARGA TENAGA 11,348.42

B. BAHAN
1 Laston lapis Aus ( AC-WC) T. 5 cm ton 0.1160 1,890,000.00 219,240.00

JUMLAH HARGA BAHAN 219,240.00

C. ALAT
1 Dump Truck Jam 0.0262 230,000.00 6,030.83
2 Asphalt Finisher Jam 0.0014 500,000.00 698.75
3 Tandem Roller Jam 0.0020 390,000.00 762.06
4 P. Tyre Roller Jam 0.0009 320,000.00 279.04

JUMLAH HARGA ALAT 7,770.68

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 238,359.10


E. DIBULATKAN 238,350.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Lapis Resap Pengikat


SATUAN PEKERJAAN : liter
HARGA SATUAN : Rp 15,900.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Pekerja OH 0.0167 90,000.00 1,500.00
2 Mandor OH 0.0033 115,000.00 383.33

JUMLAH HARGA TENAGA 1,883.33

B. BAHAN
1 Aspal Kg 0.6790 15,000.00 10,184.64
2 Kerosene liter 0.3708 10,000.00 3,708.00

JUMLAH HARGA BAHAN 13,892.64

C. ALAT
1 Asp. Distributor Jam 0.0002 450,000.00 93.75
2 Compressor Jam 0.0002 150,000.00 31.25

JUMLAH HARGA ALAT 125.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 15,900.97


E. DIBULATKAN 15,900.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan Pipa Galvanish 2,5" termasuk Elektrode


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 138,280.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0759 115,000.00 8,723.57
2 Tukang Besi OH 0.0759 105,000.00 7,965.00
3 Pekerja OH 0.1520 90,000.00 13,680.00

JUMLAH HARGA TENAGA 30,368.57

B. BAHAN
1 Elektroda Baja kg 0.0060 42,900.00 257.40
2 Pipa Galvanish 2,5" m' 1.0500 100,833.33 105,875.00

JUMLAH HARGA BAHAN 106,132.40

C. ALAT
1 Welding Set jam 0.0210 85,000.00 1,785.00

JUMLAH HARGA ALAT 1,785.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 138,285.97


E. DIBULATKAN 138,280.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan Pipa Galvanish 4" termasuk Elektrode


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 217,010.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0759 115,000.00 8,723.57
2 Tukang Besi OH 0.0759 105,000.00 7,965.00
3 Pekerja OH 0.1520 90,000.00 13,680.00

JUMLAH HARGA TENAGA 30,368.57

B. BAHAN
1 Elektroda Baja kg 0.0060 42,900.00 257.40
2 Pipa Galvanish 4" m' 1.0500 175,816.67 184,607.50

JUMLAH HARGA BAHAN 184,864.90

C. ALAT
1 Welding Set jam 0.0210 85,000.00 1,785.00

JUMLAH HARGA ALAT 1,785.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 217,018.47


E. DIBULATKAN 217,010.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan Pipa Galvanish 5" termasuk Elektrode


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 292,280.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0759 115,000.00 8,723.57
2 Tukang Besi OH 0.0759 105,000.00 7,965.00
3 Pekerja OH 0.1520 90,000.00 13,680.00

JUMLAH HARGA TENAGA 30,368.57

B. BAHAN
1 Elektroda Baja kg 0.0060 42,900.00 257.40
2 Pipa Galvanish 5" m' 1.0500 247,500.00 259,875.00

JUMLAH HARGA BAHAN 260,132.40

C. ALAT
1 Welding Set jam 0.0210 85,000.00 1,785.00

JUMLAH HARGA ALAT 1,785.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 292,285.97


E. DIBULATKAN 292,280.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan Pipa Galvanish 6" termasuk Elektrode


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 369,280.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0759 115,000.00 8,723.57
2 Tukang Besi OH 0.0759 105,000.00 7,965.00
3 Pekerja OH 0.1520 90,000.00 13,680.00

JUMLAH HARGA TENAGA 30,368.57

B. BAHAN
1 Elektroda Baja kg 0.0060 42,900.00 257.40
2 Pipa Galvanish 6" m' 1.0500 320,833.33 336,875.00

JUMLAH HARGA BAHAN 337,132.40

C. ALAT
1 Welding Set jam 0.0210 85,000.00 1,785.00

JUMLAH HARGA ALAT 1,785.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 369,285.97


E. DIBULATKAN 369,280.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pemasangan Pipa Galvanish 8" termasuk Elektrode


SATUAN PEKERJAAN : m'
HARGA SATUAN : Rp 497,290.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0759 115,000.00 8,723.57
2 Tukang Besi OH 0.0759 105,000.00 7,965.00
3 Pekerja OH 0.1520 90,000.00 13,680.00

JUMLAH HARGA TENAGA 30,368.57

B. BAHAN
1 Elektroda Baja kg 0.0060 42,900.00 257.40
2 Pipa Galvanish 8" m' 1.0500 442,750.00 464,887.50

JUMLAH HARGA BAHAN 465,144.90

C. ALAT
1 Welding Set jam 0.0210 85,000.00 1,785.00

JUMLAH HARGA ALAT 1,785.00

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 497,298.47


E. DIBULATKAN 497,290.00
ANALISA HARGA SATUAN PEKERJAAN
KONSTRUKSI BANGUNAN DAN REKAYASA SIPIL

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

JENIS PEKERJAAN : Pekerjaan Penanaman Rumput Gajah Mini


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 53,230.00

HARGA JUMLAH
NO. KOMPONEN SATUAN INDEKS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 Mandor OH 0.0020 115,000.00 230.00
2 Pekerja OH 0.0500 90,000.00 4,500.00

JUMLAH HARGA TENAGA 4,730.00

B. BAHAN
1 Rumput Gajah Mini m2 1.0000 35,000.00 35,000.00
2 Tanah Hitam m3 0.1200 112,500.00 13,500.00

JUMLAH HARGA BAHAN 48,500.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 53,230.00


E. DIBULATKAN 53,230.00
HARGA SATUAN UPAH TENAGA KERJA

KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT


PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

A. UPAH TENAGA KERJA

No. Uraian Satuan Harga Satuan


(Rp.)

1 Kepala Tukang Batu Hari - Orang 110,000.00


2 Kepala Tukang Besi Hari - Orang 110,000.00
3 Kepala Tukang Cat Hari - Orang 110,000.00
4 Kepala Tukang Kayu Hari - Orang 110,000.00
5 Kepala Tukang listrik Hari - Orang 110,000.00
6 Kepala Tukang Pipa Hari - Orang 110,000.00
7 Mandor Hari - Orang 115,000.00
8 Pekerja / Knek / Pembantu tuk Hari - Orang 90,000.00
9 Tukang Batu Hari - Orang 105,000.00
10 Tukang Besi Hari - Orang 105,000.00
11 Tukang Cat Hari - Orang 105,000.00
12 Tukang Kayu Hari - Orang 105,000.00
13 Tukang listrik Hari - Orang 105,000.00
14 Tukang listrik Hari - Orang 105,000.00
HARGA SATUAN ALAT
KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

C. HARGA SEWA ALAT

No. Alat Satuan Harga Satuan


(Rp)

1 DUMP TRUCK 6 ton Jam 230,000.00


2 EXCAVATOR Jam 350,000.00
3 STAMPER Jam 25,000.00
4 BULLDOZER Jam 360,000.00
5 TANDEM ROLLER Jam 390,000.00
6 CONCRETE PUMP jam 240,000.00
7 MOTOR GRADER > 100 HP jam 325,000.00
8 VIBRATORY ROLLER 5 - 8 T jam 300,000.00
9 WATER TANKER 3000 - 4500 L jam 130,000.00
10 TIRE ROLLER 8 - 10 T jam 300,000.00
11 WHELL LOADER 1,0 - 1,6 m3 jam 300,000.00
12 Pile Driver + Hammer jam 300,000.00
13 Genset jam 150,000.00
14 Crane On Track 75 - 100Ton Jam 450,000.00
15 Asphalt Finisher jam 500,000.00
16 P. Tyre Roller Jam 320,000.00
17 Asp. Distributor Jam 450,000.00
18 Compressor Jam 150,000.00
19 Welding Set Jam 85,000.00
HARGA SATUAN BAHAN BANGUNAN
KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

B. HARGA BAHAN

No. Bahan/Material Satuan Harga Satuan

A Bahan Pasir, Batu, Semen dan Beton


1 Pasir dan tanah
- Pasir pasang m3 247,500.00
- Pasir beton / cor m3 261,250.00
- Pasir urug m3 210,900.00
- Tanah timbunan biasa m3 27,500.00
- Tanah bauksit m3 99,000.00
- Tanah hitam m3 112,500.00
2 Batu -
- Batu bata merah biasa bh 715.00
- Kerikil / koral beton m3 380,160.00
- Batu alam susun sirih m2 275,000.00
- Batu belah m3 242,000.00
- Cilcon bh 13,500.00
- kansteen K8 bh 52,000.00
- Paving bh 4,400.00
- Laston lapis Aus ( AC-WC) T. 5 cm ton 1,890,000.00
- Aspal kg 15,000.00
- Kerosene liter 10,000.00
-
3 Semen -
- Semen PC 50 kg zak 66,000.00
- Semen warna kg 13,200.00
- Ready mix K-175 m3 1,045,440.00
- Ready mix K-250 m3 1,119,360.00
- Ready mix K-300 m3 1,140,000.00
- Ready mix K-350 m3 1,214,400.00
- semen grouting zak 352,000.00
- Parit pracetak type U-40 bh 195,000.00
- Parit pracetak type U-60 bh 250,000.00
-
B Bahan Langit-langit -
1 Multipleks tebal 9 mm lbr 132,000.00
2 Gypsum 9 mm lbr 60,500.00
3 GRC tebal 3,5 mm Lembar 88,000.00
4 Rangka eka puring btg 14,300.00
5 Stoping 20 kg zak 99,000.00
6 Cornice gypsum uk. 10 cm m' 7,700.00
7 Papan fiber cement (1.2x2.4 m) tebal 6 mm lbr 88,000.00
8 Listplank tekstur kayu tebal 8mm m' 55,000.00
9 Joint tape roll 17,600.00
10 Ramset bh 2,200.00
-
C Bahan Besi, hollow, besi stainless, dan Baja -
1 Besi beton Kg 10,080.00
2 Besi
Besi baja
Profil, Pipa alvanis Kg 14,300.00
3 Kawat ikat beton Kg 22,000.00
4 Besi hollow 50x50x2.3 mm m' 27,500.00
5 Elektroda baja kg 42,900.00
6 Amplas lbr 6,600.00
7 Wiremesh m8-200 m2 53,350.00
8 Gorong - gorong dia. 30 bh 192,500.00
9 Baja WF 200.100.18.20 kg/m kg 16,500.00
10 Kanal C 150.65.20.2,3 Kg 13,200.00
11 Pipa Galvanish 2,5" m' 100,833.33
12 Pipa Galvanish 4" m' 175,816.67
13 Pipa Galvanish 5" m' 247,500.00
HARGA SATUAN BAHAN BANGUNAN
KEGIATAN : PENGELOLAAN DAN PENYELENGGARAAN PELABUHAN LAUT
PEKERJAAN : PEMBANGUNAN TERMINAL DOMESTIK SEKUPANG
LOKASI : SEKUPANG, BATAM
TAHUN ANGGARAN : 2015-2016

B. HARGA BAHAN

No. Bahan/Material Satuan Harga Satuan

14 Pipa Galvanish 6" m' 320,833.33


15 Pipa Galvanish 8" m' 442,750.00
-
D Bahan Paku -
1 Paku Kayu 2" - 5" kg 22,000.00
2 Sekrup 1" kotak 58,300.00
3 Paku ramset hilti set 132,000.00
-
E Bahan Kayu -
1 Kayu campur m3 2,860,000.00
2 Dolken btg 22,550.00
3 Benang lot m' 275.00
4 Baut kotak -
-
F Bahan Finishing -
1 Cat dasar (sealer minyak) Kg 45,833.33
2 Cat tembok kg 76,388.89
3 Cat plafond kg 27,500.00
4 Minyak Bekisting Ltr 5,170.00
5 Cat meni Kg 25,000.00
6 Minyak
Thiner cat Kg 18,000.00
7 Cat minyak Kg 70,000.00
-
H Bahan Penutup Lantai -
1 Keramik 80 x 80 cm homogeneus m2 220,000.00
2 Keramik lantai 30 x 60 cm m2 165,000.00
3 Keramik lantai 30 x 30 cm m2 143,000.00
4 Keramik dinding 30 x 60 cm m2 165,000.00
5 Plastik Cor m2 3,300.00
6 Granit m' 1,900,000.00
7 Plint keramik 10 x 80 cm bh 27,500.00
8 Step nozing bh 72,500.00
-
I Bahan Penutup Atap -
1 Seng talang BJLS 30 lebar 60 m' 24,200.00
2 Seng gelombang BJLS 20 m' 62,000.00
3 Atap Solid Polycarbonate Sheet m2 495,000.00
4 Atap Alumunium Metal m2 245,000.00