Timeline Gaskeun

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

TIMELINE PEKERJAAN PEMBANGUNAN SET

GOOD NET SHOW / GASKEUN


TIMELINE SET UP GASKEUN / GOOD NET SHOW
KAMIS JUMAT SABTU MINGGU SENIN SELASA RABU KAMIS Jumat
NO NAMA PEKERJAAN
27 28 29 30 31 1 2 3 4
1 FOH Loading pagi finishing
2 Tribun Loading pagi finishing
3 Floor Main Stage Loading pagi finisshing finisshing
4 RIGGING LENGKUNG Installasi
5 RIGGING HBEAM Installasi
6 RANGKA LED SCREEN Installasi
7 BACKDROP TALKSHOW Loading sore
8 BACKDROP BOCORAN TALKSHOW CITYLIGHT 1
9 BACKDROP IN/OUT start area kiri done area kiri start area kanan done area kanan
10 BACKDROP TENGAH 5
11 BACKDROP LED SCREEN
12 PEMASANGAN LED SCREEN
13 BACKDROP TENGAH CITYLIGHT 2
14 BACKDROP 8
15 BACKDROP HOMEBAND
16 REHERSAL & TAPPING
17 ONCAM

Note :
Vendor Sudah Melakukan Produksi Set Di workshop 3-5 hari sebelum loading di tanggal 27 agustus