Method Statement (Hael)

1. Storage.

Store the received (uPVC) pipes and fittings at a safe and secure area to protect it from damage from
heat and other ongoing activities.

2. Ensuring availability of proper team and tools.

Confirm with Foreman that proper team of technicians and labors is available with proper tools and
equipment.

3. Start marking.

Identify & Mark the outline of the precise locations where the drainage pipes will be installed. To
ensures accurate alignment and placement of the pipes according to the drainage design.

Also Mark the Finished Floor Level confirming it with the Architectural department.

4. Install Pipes and fittings.

Once the marking is done install the pipes and fittings by properly securing both the horizontal and
vertical pipes with clamps.

A thread level should be used for achieving proper slopes and alignments.

5. Inspect for flow and leakage.

After installing the pipes and fittings, inspect the system to ensure proper flow and check for any
potential leakage and checking of flow and the alignment of the fittings, it can be done by the following
ways:

 Visual Inspection- to check for alignments and positions of the pipe fittings.
 Flow Direction inspection- It can be done by introducing water or other liquid and manually
tracing the bath of the flow.
 Leakage test- For the (uPVC) pipes, Smoke test or pressure test can be done to check for any
sort of leakages.

6. Protection

Wherever required pipes should be insulated

Pipes going to the area with special fire protection should be sealed with appropriate fire proof
material
7. Raise a request for inspection by consultant/client.

Request an official inspection to verify that the installation complies with regulations and standards
before proceeding further.

8. Site clean-up.

Remove excess material from site & ensuring clean and safe work areas.

9. Precautionary measures during the concreting process.

During the laying of aggregate materials, compacting and concreting process it is to be made sure that
none of the fittings dislocate or mis-align.