Professional Documents
Culture Documents
Hyprep September Monthly Report 2022
Hyprep September Monthly Report 2022
HYDROCARBON POLLUTION
REMEDIATION PROJECT [HYPREP]
HYPREP ACTIVITIES
REPORT
SEPTEMBER 2022
TABLE OF CONTENTS
TABLE OF CONTENT
The Federal Government of Nigeria (FGN) commissioned the United Nations Environmental Program
(UNEP) to conduct an independent environmental assessment of Ogoniland in 2006. The UNEP report
'Environmental Assessment of Ogoniland', was submitted to the FGN in August 2011. The report had
recommendations for the Nigerian Government, Oil companies (with operational interest in Ogoniland)
and the Ogoni community. One of the key recommendations is for the Government to establish a body
with the mandate to oversee the implementation of the UNEP report. The Hydrocarbon Pollution
Remediation Project (HYPREP) was therefore established in July 2012 under the Ministry of Petroleum
as the vehicle for implementing the UNEP report recommendations, but the initial efforts by HYPREP
were less than successful thus the organization soon became moribund.
In June 2016, the FGN flagged off the Ogoniland Clean-up Campaign at Patrick Waterside, Bodo. A
restructured HYPREP was established under the Federal Ministry of Environment (FMEnv) with a
governance structure comprising of the Governing Council (GC), Board of Trustees (BOT), and Project
Coordination Office (PCO) as stipulated in the Gazette.
As recommended in the UNEP report, the initial scope of projects and programs to be implemented by
HYPREP are to cover the following key areas:
· Potable Water Supply: Provision of safe and alternative drinking water for communities whose
water sources were contaminated by hydrocarbon pollution and the rehabilitation of selected
existing water supply schemes amongst the eight (8) Emergency Measures that warranted
immediate action.
· Alternative Livelihoods: Sustainable alternative livelihood programs for the Ogonis particularly
those engaged in artisanal refining and oil bunkering, as well as other initiatives to address the
socioeconomic impacts of oil pollution.
· Public Health Assessments: Investigations and evaluations of the nature, scope, and scale of
impacts of hydrocarbon pollution on the health of the Ogoni people, and programs to monitor,
mitigate and remedy the impact.
2
2.0 REMEDIATION WORKS
2.1 STATUS OF ON-GOING REMEDIATION WORKS AT PHASE 1 BATCH 1 SITES
Nineteen (19) of the 21 Lots in Phase 1 Batch 1 Remediation works have been completed successfully
including the securing of regulatory close-out by the National Oil Spill Detection and Response Agency
(NOSDRA). The remaining two (2) Lots have completed site works and are at different stages of
completion of close-out processes. These include Lot 011 (undergoing a six-month regulatory
monitoring) and 016 (awaiting results from regulatory close-out sampling).
Detailed information of remediation work performance status of the outstanding Two (2) Lots in Batch
1 is summarized in Table 1.1 below:
Table 2.1: Performance Status of outstanding Sites in Phase 1 Batch 1 Remediation Works
PERFORM AN CE
LOT
REM EDI AT I ON SI T E N AM E/ PERCEN TAGE
S/N N R. L.G.A.
CON T RACTOR COM M U N I T Y (% )
1. 0 11 Mosvinny Nig. Lt d De b o n , B o d o / M o g h o Go k a n a 98
B u e m e n e We l l 0 0 5 ,
2. 016 New line West Afric a Lt d Ta i 98
K orok oro
Detailed information of remediation work performance status of the twenty-one (21) Lots in Phase 1
Batch 1 is summarized in Table 1.2 below:
Table 2.2: Details of Status of Lots in Phase 1 Batch 1 HYPREP Remediation Works
PERFOR-
S/ LOT REM EDI AT I ON SI T E L.G.A. STAT U S M AN CE
N N R. CON T RACTOR (SI T E N AM E, PERCEN-
COM M U N I T Y ) TAGE (% )
Com plet ed rem ediat ion
1 001 Naut ilus Nigeria Ok e n t a , El e m e
Alode N OSDRA Cl o s e
En g i n e e r i n g
o u t /Ce r t i c a t i o n
Const ruc t ion Lt d
Proc esses suc c essfully. 100
Com plet ed rem ediat ion
2 002 Basic Nigeria Ob o o l o , El e m e NOSDRA Close 100
Te c h n o l o g y L t d Eb u b u o u t /Ce r t i c a t i o n
Processes successfully.
El e m e Com plet ed rem ediat ion
3 003 Pa c r i m Nk eleok en, N OSDRA Cl o s-e
En g i n e e r i n g L t d A l o d e o u t /Ce r t i c a t i o n
Proc esses suc c essfully. 100
3
PERFOR-
S/ LOT REM EDI AT I ON SI T E L.G.A. STAT U S M AN CE
N N R. CON T RACTOR (SI T E N AM E, PERCEN-
COM M U N I T Y ) TAGE (% )
Co m p l e t e d r e m e d i a t i o n
4 004 RDK Nk eleok en, El e m e
N OSDRA Cl o s e 100
En v i r o n m e n t a l Alode
o u t /Ce r t i c a t i o n
Ec o So l u t i o n s L t d
Pr o c e s s e s s u c c e s s f u l l y.
Nk eleok en, El e m e Co m p l e t e d r e m e d i a t i o n
5 005 Ea r t h p r o U n i q u e
Alode N OSDRA Cl o s e 100
Int egrat ed
o u t /Ce r t i c a t i o n
Se r v i c e s L t d
Pr o c e s s e s s u c c e s s f u l l y.
Co m p l e t e d r e m e d i a t i o n
6 006 En v i r o n m e n t a l Nk eleok en, El e m e
N OSDRA Cl o s-e
Re s o u r c e s Alode
o u t /Ce r t i c a t i o n
Managers Lt d
Pr o c e s s e s s u c c e s s f u l l y. 100
Co m p l e t e d r e m e d i a t i o n
7 007 Av o n d a l e Nk eleok en, El e m e
N OSDRA Cl o s-e
Se r v i c e s a n d Alode
o u t /Ce r t i c a t i o n
Su p p l i e s L t d
Pr o c e s s e s s u c c e s s f u l l y. 100
Nk eleok en, El e m e Co m p l e t e d r e m e d i a t i o n
8 008 Gi o l e e Gl o b a l Alode N OSDRA Cl o s-e
Re s o u r c e s L t d o u t /Ce r t i c a t i o n
Pr o c e s s e s s u c c e s s f u l l y. 1 0 0
Go k a n a Co m p l e t e d r e m e d i a t i o n
9 009 Od u n Sa a n a k o ,
N OSDRA Cl o s-e
En v i r o n m e n t a l L t d Mogho
o u t /Ce r t i c a t i o n 100
Seven (7) lots in this Batch have completed the NOSDRA Close-out / Certification processes
successfully. They are Lots 026 (B.Dere/Gio, Gokana/Tai L.G.A), Lot 028 (Bara Alue, Tai LGA), Lot
042 (Korokoro Well 4, Korokoro Tai LGA), Lot 044 (Ngofa –Aleto, Eleme L.G.A), Lot 046 (Nsioken
Akpajo, Eleme LGA), Lots 056 and 057 (New Elelenwo, Akpajo, Eleme LGA).
Fifteen (15) Lots have pending corrections following exceedances from the Closeout results recently
released by NOSDRA. These are Lots 023, 024, 031, 033 &034 -B.Dere/Gio, Gokana/Tai L.G.A; Lot
027 -Bara Alue, Tai LGA; Lots 029 & 030 - Aabue Korokoro Flow Station, Tai L.G.A.; Lots 043 & 045 -
Ngofa –Aleto, Eleme L.G.A; Lots 047, 048, 050, 053 and 054 at Okuluebu 2, Ogale, Eleme L.G.A.
One (1) lot (Lot 022) is currently undergoing a six-month regulatory monitoring
Three (3) lots (Lot 025 at B. Dere/Gio, Gokana/Tai L.G.A) as well as Lots 049 and 051 in Okuluebu 2,
Ogale, Eleme L.G.A.), are awaiting results from regulatory (NOSDRA/NUPRC) Closeout/certification
sampling.
One (1) other Lot (Lot 055 Okuluebu 2, Ogale, Eleme L.G.A.) have completed active remediation works
and is awaiting NOSDRA Close-out/Certification sampling.
4
Remediation works are still on-going at different stages at the remaining Two (2) Lots which are Lots
052 (Okuluebu 2, Ogale Eleme LGA) and Lot 032 (B-Dere/Gio, Gokana/Tai LGA).
Details of Status of Lots in Batch 2 are presented in Table 2.3 below:
29 9 Sites
Lots
Details on Excavation/Earthwork Status at Lots in Batch 2 are presented in Table 1.4 below:
Table 2.4: Details of Status of Excavation Works at Lots in Phase 1 Batch 2 HYPREP Remediation
Status of
Excavation and Lot Numbers Number Site(s)
Treatment of Lots
Works
022, 023, 024, 025,
B.Dere/Gio in Gokana/Tai L.G.A.
026, 031, 033, 034
2 9 Lot s
Plate 2.1: Mechanical transferring of excavated impacted soil for treatment in progress at Lot 052
Okuluebu Ajeokpori Well 3, Ogale Eleme L.G.A.
(Remediation Contractor -MONTEGO UPSTREAM SERVICES LTD)
Plate 2.2: Backfilling of a section of the Excavated Area at Lot 032 B-Dere/Gio Gokana/Tai LGA
(Remediation Contractor -Mosito Environmental Ltd)
Detailed information of remediation work performance status of Phase 1 Batch 2 sites is summarized in
Table 1.5 below:
Table 2.5: Remediation Works Performance Status of Phase 1 Batch 2 Sites.
PERFOR-
LO M AN CE
S/ REM EDI AT I ON SI T E
T L.G.A. STAT U S PERCEN-
N CON T RACTOR N AM E
N R. TAGE
Com plet ed Ac t ive Rem ediat ion
1 022 Vit ruvian Global B . De r e / Go k a n a / Wo r k s .Aw a i t i n g N OSDRA
Re s o u r c e s L t d Gi o Ta i . Closeout Sam pling Analyt ic al
Re s u l t s 98
6
PERFOR-
LO M AN CE
S/ REM EDI AT I ON SI T E
T L.G.A. STAT U S PERCEN-
N CON T RACTOR N AM E
N R. TAGE
2 0 2 3 Ca s c a d e Having pending c orrec t ions from
B . De r e / Go k a n a /
En g i n e e r i n g t he rec ent ly released NOSDRA
Gi o Ta i .
Sy s t e m s L t d Cl o s e-o u t Re s u l t s 98
Having pending c orrec t ions from
3 0 2 4 L e v e n e En e r g y B . De r e / Go k a n a/
t he rec ent ly released NOSDRA
De v L t d Gi o Ta i .
Cl o s e-o u t Re s u l t s 98
Com plet ed Ac t ive Rem ediat ion
4 0 2 5 Su b a d o m
B . De r e / Go k a n a / Wo r k s . Aw a i t i n g N OSDRA
Gl o b a l
Gi o Ta i . Closeout Sam pling Analyt ic al
Re s o u r c e s L t d
Re s u l t s 98
Ea r t h q u e s t I n t 'l B . De r e / Go k a n a / Co m p l e t e d a n d Ce r t i e d b y
5
026 Lt d Gi o Ta i . N OSDRA 100
6 027 Marm Having Pending c orrec t ions from
Co n s u l t i n g B a r a A l u e Ta i r e c e n t l y r e l e a s e d N OSDRA
Se r v i c e s L t d Cl o s e-o u t Re s u l t s 98
7 0 2 8 Em a m e d N i g Co m p l e t e d a n d Ce r t i e d b y
B a r a A l u e Ta i
Lt d N OSDRA 100
AABUE
K orok oro Having pending c orrec t ions from
8 0 2 9 We a f r i We l l
Fl o w Ta i r e c e n t l y r e l e a s e d N OSDRA
Se r v i c e s L t d
St a t i o n Cl o s e-o u t Re s u l t s
(FS) 98
AABUE
K orok oro Having pending c orrec t ions from
9 0 3 0 Elizax Bleet Nig t he rec ent ly released NOSDRA
Fl o w Ta i Cl o s e -o u t Re s u l t s
Lt d
St a t i o n
(FS) 98
Com plet ed Ac t ive Rem ediat ion
B . De r e / Go k a n a /
10 0 3 1 Oi l s e r v L t d Wo r k s . Aw a i t i n g N OSDRA
Gi o Ta i .
Cl o s e o u t Sa m p l i n g 98
11 032 Mosit o B . De r e / Go k a n a/ A c t i v e Re m e d i a t i o n Wo r k s 78
7
PERFOR-
LO M AN CE
S/ REM EDI AT I ON SI T E
T L.G.A. STAT U S PERCEN-
N CON T RACTOR N AM E TAGE
N R.
Having pending c orrec t ions from
12 0 3 3 Ch r i s t o h o u s t o n B . De r e / Go k a n a /
r e c e n t l y r e l e a s e d N OSDRA
En e r g y L t d Gi o Ta i .
Cl o s e-o u t Re s u l t s 98
Having pending c orrec t ions from
13 0 3 4 DL K Oi l & Ga s B . De r e / Go k a n a /
t h e r e c e n t l y r e l e a s e d N OSDRA
Lt d Gi o Ta i .
Cl o s e-o u t Re s u l t s 98
K orok oro Co m p l e t e d a n d Ce r t i e d b y
14 042 K anny K oy Lt d Ta i .
W-4 N OSDRA 100
Having pending c orrec t ions from
15 0 4 3 Ot a o i l f Se r v i c e sA l e t o
El e m e r e c e n t l y r e l e a s e d N OSDRA
Lt d (N g o f a )
Cl o s e-o u t Re s u l t s 98
16 0 4 4 M /S H a r r i s c o Alet o Co m p l e t e d a n d Ce r t i e d b y
El e m e
I n t 'l L t d (N g o f a ) N OSDRA 100
Co m p l e t e d A c t i v e Re m e d i a t i o n
Alet o Wo r k s . Aw a i t i n g N OSDRA
17 0 4 5 Ch a v y n N i g L t d El e m e
(N g o f a ) Cl o s e o u t Sa m p l i n g A n a l y t i c a l
Re s u l t s 98
Nsiok en Co m p l e t e d a n d Ce r t i e d b y
18 046 Andelst a Lt d El e m e
Ak pajo N OSDRA 100
Ajeok pori Having pending c orrec t ions from
19 047 Lapideo Mult i
W-3 El e m e t he rec ent ly released NOSDRA
Se r v i c e s L t d
Ok u l u e b u Cl o s e-o u t Re s u l t s 98
Ajeok pori Having pending c orrec t ions from
20 0 4 8 Sl o t En g N i g L t dW-3 El e m e t h e r e c e n t l y r e l e a s e d N OSDRA
Ok u l u e b u Cl o s e-o u t Re s u l t s 98
Co m p l e t e d A c t i v e Re m e d i a t i o n
21 0 4 9 En v i r o n Co n s u l tA j e o k p o r i
Wo r k s . Aw a i t i n g N OSDRA
& Re m e d i a l W-3 El e m e
Cl o s e o u t Sa m p l iAnnga l y t i c a l
Se r v i c e L t d Ok u l u e b u
Re s u l t s 98
Ajeok pori Having pending c orrec t ions from
22 0 5 0 K l a r t e k N i g L t d W-3 El e m e r e c e n t l y r e l e a s e d N OSDRA
Ok u l u e b u Cl o s e-o u t Re s u l t s 98
Com plet ed Ac t ive Rem ediat ion
Ajeok pori
Wo r k s . Aw a i t i n g N OSDRA
23 0 5 1 Er o t i n a N i g L t d W-3 El e m e
Closeout Sam pling Analyt ic al
Ok u l u e b u
Re s u l t s 98
Mont ego Ajeok pori
Ac t ive Rem ediat ion Work s st ill
24 052 Upst ream W-3 El e m e
ongoing.
Se r v i c e s L t d Ok u l u e b u 63
8
Ajeok pori Having pending c orrec t ions from
A t l a -s Ra y &
25 W-3 El e m e r e c e n t l y r e l e a s e d N OSDRA
So n s Co y L t d
053 Ok u l u e b u Cl o s e-o u t Re s u l t s 98
Brant Ajeok pori Having pending c orrec t ions from
26 Te c h n o l o g i e s W-3 El e m e r e c e n t l y r e l e a s e d N OSDRA
054 Lt d Ok u l u e b u Cl o s e-o u t Re s u l t s 98
Ajeok pori Com plet ed Ac t ive Rem ediat ion
A DG I n t 'l
27 W-3 El e m e Wo r k s . Aw a i t i n g N OSDRA
Re s o u r c e s L t d
055 Ok u l u e b u Cert i c at ion/Closeout Sam pling 95
New
Aw a
El e l e n w a Co m p l e t e d a n d Ce r t i e d b y
28 En g i n e e r i n g Co y El e m e
Manifold, N OSDRA
Lt d
056 Ak pajo 100
New
Int egrat ed
El e l e n w a Co m p l e t e d a n d Ce r t i e d b y
29 Chem ic al Work s El e m e
Manifold, N OSDRA
Lt d
057 Ak pajo 100
2 9 LOT S 2 ,7 9 8
Ave ra ge 9 6 .4 8
Pe r f o r m a n c e Ra t i n g s f r o m t h e p r e v i o u s M o n t h f o r T M PS & A M PS.
2 ,7 9 0 9 6 .2 1
Co m m e n t (s ) o n Pe r c e n t a g e Di ff e r e n c e i n M o n t h l y Pe-r f o r m a n c e
Ra t i n g s :- Appre c ia ble a nd e x pe c t e d t o inc re a se re m a rk a bly in
Oc t obe r 2 0 2 2 a s t he re m a ining 2 Cont ra c t ors a re e x pe c t e d t o
c om ple t e t he ir sit e w ork s a nd m ore re gula t ory re sult s obt a ine d
be fore t he e nd of t he m ont h.
9
2.3 SUMMARY OF STATUS OF LOTS IN PHASE 1 BATCH 1 & 2 REMEDIATION
WORKS
A summary of Status of Lots in Batch 1 and 2 of Phase 1 Remediation Works and NOSDRA Close-out
Process on Category N Sites is provided in Table 1.6 below:
Table 2.6: Summary of Status of Lots in Phase 1 Batch 1 & 2 Remediation Works and Category N Sites.
SU B-
REM EDI AT I ON CAT E-
REM EDI AT I ON TOTAL GRAN D
PH ASE 1 BAT CH GORY N
PH ASE BAT CH 1 (B1 +B2 TOTAL
2 SI T ES
SI T E STAT U S )
LOT LOT
N O. OF N O. OF
N U M BER N U M BE
LOT S LOT S
S RS*
0 0 1- 0 1 0 , 026, 028,
NOSDRA Close-out
19 0 1 2 -0 1 4 , 7 042, 044, 26 1 27
c om plet ed
0 1 5 , 0 1-7 046, 056,
suc c essfully
021 057
Undergoing-6Mont h
Po s t Re g u l a t o r y
1 0 11 1 022 2 0 2
Cl o s e- o u t Re s u l t s
Monit oring
022, 025
Aw ait ingRegulat ory
1 016 5 031, 049, 6 11 17
Cl o s e-
051
023, 024,
027, 029,
Having pending
030, 033,
c orrec t ions from
0 0 14 034, 043, 14 0 14
NOSDRA Close-out
045, 047,
Re s u l t s
048, 050,
053, 054
Undergoing
N OSDRA Cl o s e o u t
0 0 0 0 0 0 0
a n d Ce r t i c a t i o n
Sa m p l i n g
10
SU B-
REM EDI AT I ON CAT E-
REM EDI AT I ON TOTAL GRAN D
PH ASE 1 BAT CH 2 GORY N
PH ASE BAT CH 1 (B1 +B2 ) TOTAL
SI T ES
SI T E STAT U S
N O. OF LOT N O. OF LOT
LOT S NUMBERS LOT S NUMBERS
Pl a n n e d f o r
Regulat ory Close-out 0 0 1 055. 1 1 1
Sa m p l i n g
Sub-Tot a l (N um be r
of LOT S 21 27 48 13 61
Com ple t e d)
St i l l Wo r k i n g 0 0 2 032, 052. 2 0 2
Not ac t ive 0 0 0 0 0 0 0
Sub-Tot a l (N um be r
of LOT S not 0 2 2 2
Com ple t e d)
Tot a l N um be r of
Lot s 21 29 50 13 63
To t a l M o n t h l y
Perform anc e Sc ore 2,096.00 2,798.00 4,894.00
(% )
Av e r a g e M o n t h l y
Perform anc e Sc ore 9 9 .8 1
9 6 .4 8 9 8 .1 5
(% )
*Lot Numbers 035 – 041 were allocated to Tier 2 Detailed Quantitative Risk Assessment Works.
11
2 .4 QU ALI T Y ASSU RAN CE / QU ALI T Y CON T ROL (QAQC) AN D CERT I FI CAT I ON
The year started with Twenty (20) contractors from both Phase1 Batch 1 and 2 still in active remediation
works in various phases, of which some of these Lots (023, 027, 029, 033, 046, 050, 053, 054 and 057)
participated in the Batch 6 NOSDRA External Certification and Close-Out Sampling done in May/June
2022 and Results sent by NOSDRA having Lots 046 and 057 Cleared and Certified and Lots 023, 027,
029, 033, 050, 053, and 054 having values in some points exceeding RBCA values of 1000mg/kg.
Tremendous progress has been made by the outstanding Contractors (Lots 013, 011, 016, 022, 025, 031,
049, 052, 051 and 055) in their remediation works, with a total of Eight (8) Lots (011, 013, 016, 022, 025,
031, 049 and 051) out of the stated Nine (9) Lots participated in the Batch 7 NOSDRA External
Certification/Close-Out and so far, results sent by NOSDRA having Lot 013 Cleared and certified and
Lots 011,022, and 031 having values in some points exceeding RBCA values of 1000mg/kg.
th
Table 2.7: showing the Contractor's Progress Status as of 28 September 2022
S/N LOT COMMUNITY / CERT I FI CAT I ON DAT E OF REM ARK S
N O LGA STAT U S CERT I FI -
CAT I ON
SAM PLI N G
13
S/N LOT COMMUNITY / CERTIFICATION DATE OF REMARKS
NO LGA STATUS CERTIFI-
CATION
SAMPLING
14
S/N LOT COMMUNITY / CERTIFICATION DATE OF REMARKS
NO LGA STATUS CERTIFI-
CATION
SAMPLING
13. 02 B De r e / Va l u e s i n s o m e We d . Re-s a m p l i n g t o b e
3 Gi o , sam pling point s c arried out on
18/05/2022
Go k a n a & e x c e e d e d RB CA c om plet ion.
Ta i value of 1000m g/k g
in soil. Cont rac t or
w as ask ed t o
rew ork sec t ions
14. 05 Ok uluebu2, Va l u e s i n s o m e Mon. Re -s a m p l i n g t o b e
0 Og a l e , sam pling point s c arried out on
27/05/2022
El e m e e x c e e d e d RB CA c om plet ion.
value of 1000m g/k g 30/05/2022
in soil. Cont rac t or
w as ask ed t o
rew ork sec t ions
15. 05 Ok uluebu2, Va l u e s i n s o m e Tu e s . Re -s a m p l i n g t o b e
3 Og a l e , sam pling point s c arried out on
31/05/2022
El e m e e x c e e d e d RB CA c om plet ion.
value of 1000m g/k g
in soil. Cont rac t or
w as ask ed t o
rew ork sec t ions
16. 05 Ok uluebu2, Va l u e s i n s o m e Fr i . Re -s a m p l i n g t o b e
4 Og a l e , sam pling point s c arried out on
27/05/2022
El e m e e x c e e d e d RB CA c om plet ion.
value of 1000m g/k g
in soil. Cont rac t or
w as ask ed t o
rew ork sec t ions
15
S/N LOT COMMUNITY / CERTI FI CAT I ON DATE OF REMARKS
NO LGA STAT US CERT I FI -
CATI ON
SAMPLING
16
2.4.1 BATCH 7 NOSDRA EXTERNAL CERTIFICATION/CLOSE
-OUT SAMPLING.
The Batch 7 NOSDRA External Certification and Close-Out sampling commenced in August involving
both Phase 1 Batch 1 and 2 Remediation contractors and was finalized in September 2022.
The Close-Out Activity led to the end of remediation works for the Phase 1 Batch 1 Contractors with the
outstanding Contractors from Lots 011 (Mogho/Bodo, Gokana LGA), 013 (Nweekol Zorbuke, Gokana
LGA) and 016(Buemene Koro-Koro, Tai LGA) and also Phase 1 Batch 2 Contractors Lots 022, 025 and
031 (B-Dere/Gio, Gokana) and 049, 051 (Okuleubu Ogale, Eleme LGA).
Ta b l e 2 .8 : b e l o w s h o w s t h e Va r i o u s L o t s a n d I n f o r m a t i o n o f Cl o s e -Ou t Sa m p l i n g .
S/N LOT COM PAN Y COM M U N I T Y LGA DAT E OF SAM PLI N G
NO N AM E
1. 016 N e w l i n e We s t B u e m e n e K o-r o 2 2 /0 9 /2 0 2 2
Afric a K o r o We l l 0 0 5
Su b a d o m
2. 025 Gl o b a l B“ De re /Gio Go k a n a 2 0 /0 9 /2 0 2 2
Re s o u r c e s
Lim it ed
En v i r o -n 2 1 /0 9 /2 0 2 2
3. 049 Co n s u l t a n d
Re m e d i a l Ok u l e u b u , El e m e
Se r v i c e A j e k p o r i We l l 3
Lim it ed. Og a l e . (q c-0 0 5-
4. 051 Er o t i n a 001) 2 1 /0 9 /2 0 2 2
Nigeria
Lim it ed.
Plate 2.3: Water sample collection from monitoring boreholes at Lot 016 (Buemene Korokoro Well 5,
Tai L.G.A)
Plate 2.4: Cross Section of participants at Lot 025 (B. Dere/ Gio) during the NOSDRA / NUPRC
Regulatory Close-Out Sampling.
2.5 SITE CHARACTERIZATION AND DELINEATION OF IMPACTED SITES
HYPREP had in 2020 done reconnaissance survey (Preliminary Site Environmental Assessment) on
impacted sites without UNEP site specific facts sheets. As a result of the survey, over a hundred and
twenty sites were scoped and recommended for further investigation. However, fifteen (15)
Medium/Complex Risk Sites were selected by the Assessment Team for characterization and
17
delineation. Site characterisation and delineation is carried out to determine specific geologic and
hydrologic characteristics of the sites, determine the extent of contamination, potential threat to the
environment and users, as well as the possible remedial actions that may be required. This activity is
Site characterisation and delineation starts with Electrical Resistivity Tomography (ERT) modelling by
our ERT Team. Electric resistivity tomography (ERT) is a near-surface geophysical tool for ground
investigations that helps to reveal ground features and map the soil structure. It works by using electrical
current that is injected into the ground through short steel (electrodes) distributed along a straight line,
and the resistance values between the injection points measured. When processed, a two-dimensional
resistivity profile of the ground is derived and displayed graphical on the Tomogram. This gives a guide
for the distribution of auger points and borehole for soil and groundwater sampling.
Hand augers are used for drilling and profiling the soil for physical observation of soil and groundwater
where necessary. As the soil is drilled to collect samples, they are immediately probed for the soil profile
– soil type, colour, texture, structure, depth to groundwater, depth to Hydrocarbon contamination etc.
Physical observations (olfactory and sheen test) are also carried out on soil sample. All these are logged
(recorded) on the Sampling Log Sheet. Samples are collected and stored in the ice packed cooler and
IMPACTED SITES
A total of sixteen (16) site have been completed. The table below shows the details of Site
18
Table 2.9: Details of site characterization and delineation works.
Si t e s N o . 5 a n d
6 are boundary
Nork po, Nork po, Undoc um ent ed Co m p l e t e d Sit e w it hout s i t e b e t w e e n
B a r a -A l e a n d
6 Ta i L GA Si t e M e d i u m e l d w o r k s U N EP Fa c t N o r k p o
Ri s k Sh e e t Co m m u n i t y.
19
S/N Site Name Category Status SSFS
20
S/N Site Name Category Status SSFS
Sit es No. 14
and 15 are
boundary sit es
bet w een Bera
14 Boobaam uu, Undoc um ent ed Com plet ed Sit e w it hout and B-Dere
Bera, Gok ana Sit e Medium eldw ork s UNEP Fac t Com m unit y.
Risk Sheet Det ailed
LGA c om m unit y
engagem ent
advised prior t o
land ac c ess.
16 Ok ansim u, Undoc um ent ed Com plet ed Sit e w it hout Disc overed Free
phase of re ned
Ogale, Elem e Sit e Medium eldw ork s UNEP Fac t
Sheet pet roleum
Risk
produc t
21
2.6 SHORELINE CLEAN-UP AND MANGROVE RESTORATION
HYPREP, on its mandate to remediate and restore the shoreline inter-tidal areas in Ogoniland, has
completed the Pre-Shoreline Clean-up Assessment Technique (Pre-SCAT) of two communities namely
B-Dere and K-Dere, while field activities are yet to be concluded in Kpor, Goi, Mogho and Bodo
The HYPREP Pre-SCAT Team has assessed a total of 549 grids (200m X 200m) covering an area of
2,196 hectares. The assessed grids are along shorelines, channels, mud flats and degraded mangrove
platforms.
Table 2.10 below shows the breakdown of coastal Communities and the number of assessed grids respectively.
Table 2.10: Communities and Number of Grids Assessed
22
2.6.1: SHORELINE CLEANU-UP STAKEHOLDERS SENSITIZATION AND AWARENESS
WORKSHOP
th
On the 27 of September, 2022, HYPREP organized an Awareness and Sensitization Workshop for
Stakeholders of the upcoming Shoreline Clean-up and Mangrove Restoration program. The
Stakeholders included the Leadership of Ogoni Coastal Communities, Ogoni Traditional Rulers, Youth
Groups, Government Regulatory Agencies, KAGOTE, Civil Society and Non-Governmental
Organizations, Ogoni Elected Representatives and the Academia. The event was held at the
Gberesaakoo Hall, Gokana Local Government Area Council Secretariat, Kpor.
At the event, the Project Coordinator announced the plan of HYPREP to commence the remediation of
hydrocarbon impacted shoreline inter tidal areas in Ogoniland. He highlighted the benefits of the
shoreline remediation, which included job creation, training and certification of Community personnel
with internationally recognized Certificates, restoration of the aquatic livelihood sources of the coastal
Communities, amongst others.
Additionally, one of the Guests from the Academia, Professor John Onwuteaka enlightened the target
beneficiary Communities of a vast array of global opportunities in carbon and biodiversity credits as
sustainable short- and long-term benefits associated with the clean-up and restoration of the degraded
mangrove ecosystem.
23
3.0 HEALTH, SAFETY AND ENVIRONMENT (HSE) SEPTEMBER MONTHLY
REPORT
24
Fig 3.1: Summary of HSE statistics for the month.
3.2.1 HAZARD IDENTIFICATION AND REPORTING (HIR)
3.2.1.1 UA/UC CHART DISTRIBUTION CHART
The project unsafe act and unsafe conditions reported for the month of September 2022 is seventy
(68) and the distribution is represented below:
3.3 LOOK-AHEAD
In October 2022, the HSE team would review, update the HSE plan, develop and cascade the Life
Saving Rules(LSR) to HYPREP staff, create more HSE documents, issue PPEs to operational staff,
conduct HSE induction trainings, conduct health surveillance, undertake HSE inspections on all
HYPREP active sites to monitor contractors HSE compliance, upgrading and installation of more fire
alarm systems in the building, do regular testing of emergency response preparedness in-view of its
effective operation, attend contractors monthly HSE meetings and HSE campaigns as maybe required.
25
4.0 PROVISION OF POTABLE WATER
The task of providing potable water to the people of Ogoniland is progressing on a daily basis, with
effective supervision by the Potable Water Unit of HYPREP.
In further pursuant of this HYPREP mandate, rehabilitated water facilities and the freshly constructed
ones are gradually approaching completion across various communities of the four (4) Local
Government Areas (LGAs) in Ogoniland.
Officers of the Potable Water unit, Lot contractors and stakeholders within the communities have
combined efforts in overseeing these construction of water facilities to ensure timely delivery to the
people.
The status of work done on sites covering Bori/kpean; Barako/B-Dere; Terabor; Korokoro/Nonwa;
Alesa; Agbonchia, Alode, Aleto and Ebubu/Nsisioken/Ogale communities are highlighted in the report
below.
4.1 LOT 1: ALESA ELEME
Operational activities and maintenance of the newly rehabilitated Alesa Headworks are currently
ongoing. The Alesa station currently supplies drinking water to Alesa, Alode, Agbonchia, Aleto and part
of Ogale communities, on a daily basis.
26
4.2 LOT 2: EBUBU/NSISSIOKEN-OGALE, ELEME LGA
The construction of Ebubu and Ogale headworks, Eleme Local Government Area is at a general
completion rate of over 85%.
5 Co n n e c t i o n o f l t e r s a n d t a n k s On g o i n g
27
4.4 LOT 4: BARAKO/B-DERE GOKANA
The newly constructed stations, at Barako and B-Dere communities, Gokana are at a general completion
of 93%. The completed works include the installation of overhead and ground tanks, construction of
Staff quarters, treatment houses, etc.
2 Co n n e c t i o n o f Fi l t e r t a n k s On g o i n g
3 Wellhead inst allat ion at K orok oro and On g o i n g
Nonw a
28
4.6 LOT 6: BORI/KPEAN/ZAAKPON, KHANA LGA
Activities at Lot 6 are at a general completion rate of 83.7% covering the rehabilitation of the Bori Water
Station, fresh construction of Headworks at Kpean, and the construction of a new booster station at
Zaakpon.
29
5.0 LIVELIHOOD PROGRAM REPORT
5.1 INTRODUCTION
The Livelihood Unit Report for September 2022 covers the activities of the Livelihood unit within the
reporting period. This includes but is not limited to commencement of sorting for specialized training
applicants, submission of Livelihood unit exit plan for the cassava processing factory, etc.
31
S/N SCOPE AREA PROGRAM U PDAT E STAT U S REM ARK
6 Ca s s a v a Pr o c e s s i n g Developm ent of ex it plan Im plem ent at ion of
Fa c t o r y for t he c assava proc essing ex it plan in progress
fac t ory
7 Needs Assessm ent Re p o r t w r i t i n g o n t h e
needs assessm ent ac t ivit y.
Le ge nd
In Progress Completed Delayed Yet to commence
32
6.0 Centre of Excellence for Environmental Restoration (NCEER)
6.1 Introduction
The National Centre of Excellence for Environment Restoration (NCEER) is one of the
recommendations of UNEP in the Ogoni Environmental Assessment Report. This centre will serve as
the repository and depository of all experiences and knowledge gained through the Ogoni
Environmental Restoration Project.
The centre has different components, research, demonstration (ICSMC) and the entrepreneurship area.
The research will serve to train high-man-power knowledge in areas of environmental pollution
management, remediation, and restoration. The demonstration area (Integrated Contaminated Soil
Management Centre) will be used to demonstrate various environmental restoration strategies and to
showcase new knowledges in environmental management. The entrepreneurship centre as will used
for knowledge incubation and training in various sets relevant to the environment and industrial
processes.
In the period under review, the following activities were carried out.
35
Plate 6.4: Construction works at Gokana LGA Liaison Office
2 Su r v e y o f d o n a t e d l a n d Co m p l e t e d s u r v e y o f 100
donat ed land
4 De s i g n o f t h e N CEER b u i l d i n g On g o i n g 20
infrast ruc t ure
5 Co n s t r u c t i o n o f p e r i m e t e r f e n c e t o Undergoing 2
sec ure land from int ruders Pr o c u r e m e n t
Pr o c e s s e s
36
7.0 PROCUREMENT
The Procurement Unit successfully carried out the under-listed activities;
I. Finalization of Report on Financial Evaluation of documents for Remediation of Simple
Hydrocarbon Impacted Sites in Ogoniland;
II. Undertaking of Due Diligence on Contractors for Remediation of Simple Hydrocarbon
Impacted Sites in Ogoniland and submission of Report;
III. Evaluation of Prequalification bids and submission of Report on Construction of Center of
Excellence for Environmental Restoration (CoEER) along with an Integrated Contaminated
Soil Management Center (ICSMC); and
IV. Issuance of Request for Proposal (RfP) to short listed bidders for Engagement of
Consultants/Service Providers for Livelihood Sundry Trainings, opening of the bids and
commencement of the evaluation process.
37