Professional Documents
Culture Documents
Solar FAQ
Solar FAQ
Voltaic Projects in
Andhra Pradesh
If solar and BESS systems are failured due to some internal Solar and Battery will be co-located but will be
8. RFS General failures, is there any limitations for avoiding the losses separate for any practical purpose.
9. RFS 3.2 Kindly extend the last date of submissions by at least 15 days. Please refer the revised RFS.
Response to Queries for RFS of Grid connected Solar Photo Voltaic Projects in Andhra Pradesh
1
SL Clause Query Reply
There is no restriction on AC/ DC site. However, the
The CUF value is in the DC or AC site. Is there any limitation AC output in no case shall exceed project capacity
10. RFS 3.4.1 between AC and DC site ratios for maintaining? Kindly Clarify. (5 MW). The CUF is in AC site.
Response to Queries for RFS of Grid connected Solar Photo Voltaic Projects in Andhra Pradesh
2
SL Clause Query Reply
Synchronization, Commissioning and Commercial Operation
3.10.1 The Solar Power Developer shall give a written notice to
the concerned SLDC and DISCOM, at least 60 30 days in
advance to the date on which it intends to synchronize the
18. PPA 3.10.1 Project to the grid system No change is contemplated.
“Billing Date” shall mean the fifth (5th) Working day after the
19. PPA Definition Meter Reading Date. No change is contemplated.
Lower capacity solar plant has higher percentage of auxiliary
consumption; therefore kindly revise the Auxiliary consumption
20. PPA Schedule 1 from 0.1% to 1 % of capacity for Solar PV. No change is contemplated.
We understand that APSPDCL and APEPDCL is envisaging
BESS system with the same substations as common coupling
point. We request you to consider clubbing both the bids so that
solar developer will provide both solar power plant and BESS
21. General system. No change is contemplated.
We presume that point of common coupling will be the Both shall be connected to HV side of 33kV
22. General substation. Please clarify substations.
Integration shall be under scope of BESS Supplier/
Developer. Solar developer needs to provide line
Further Solar plant side requirement for integrating BESS diagram of the Solar Project integration as per
23. General should be specified in the RfS Article 6 of revised PPA
Yes. In case of any change, all bidders shall be
24. General Please clarify if reverse auction is finalized for this bid. conveyed the same.
Further please clarify that there is no shortlisting for reverse
25. RFS 4.1.3 auction. Please refer 4.1.3 of revised RFS.
Request you to postpone RfS submission date for at least two
26. RFS 3.2 weeks Please refer the revised RFS
The definition for Change in Law is limited and needs to be
27. PPA Definition elaborated as per the Standard practice and SECI bids Please refer revised PPA
Response to Queries for RFS of Grid connected Solar Photo Voltaic Projects in Andhra Pradesh
3
SL Clause Query Reply
Response to Queries for RFS of Grid connected Solar Photo Voltaic Projects in Andhra Pradesh
4
SL Clause Query Reply
Note: The Utility has modified relevant clauses in the Request for Selection document for Grid connected Solar Photo Voltaic Projects in
Andhra Pradesh dated 22nd May 2017, after considering responses from participants and earlier tender documents approved by State
Commission.
The above mentioned project specific changes are subject to the approval of State Commission.
Response to Queries for RFS of Grid connected Solar Photo Voltaic Projects in Andhra Pradesh
5