PROJECT AGENDA
CRITICAL ISSUES
20 September 2023
I. QAQC
iii. AB11s PMB (Steel & Concrete section); then for SMA
i. trials completed
d. Improvement / Arrangement to Maintain Weekly Certification / Approval of Test Reports (for IPC purposes)
e. Personnel recruitment
a. Isolation:
b. Curbstone:
i. Procurement
i. Procurement
ii. MAR
d. Span construction and post-tensioning of remaining sections (Freyssinet): 1000 ton jack to be on site on 02.10.2023
f. Guardrails & Handrails (Unipromet agreement signed, advance payment), Handrail Design (CIP)
g. Asphalt Production:
i. Mix-Designs of Binder and Wearing Courses (follow-up AGI), PMB, MAR, Price Proposal &
Procurement
KSR_Agenda_2023-09-20.Docx
1/
KUZMIN ‐ SREMSKA RAČA PROJECT
PROJECT AGENDA
CRITICAL ISSUES
20 September 2023
h. Electricity & Lighting: Tehnounion & Elsing price proposal, procurement, MAR
i. Expansion Joints: Mageba-Produkt BG / Freyssinet; Agreement is at Belgrade office, Decision on modular within 2
days
k. Removal of Remaining Temporary Pier Parts at the bottom of Sava Bridge: Proposals to be collected
l. Follow-up Design of Sava Bridge – BiH Customs connection. (Construction - VO for Taşyapı)
m. Follow-up Design of Sava Bridge – Serbia Customs connection. (Design & Construction - VO for Taşyapı)
o. As-built Design
a. Drainage: Price Proposal, Polyester Pipe DN200 SN5, might be executed while formworks and scaffolding are set
i. Pipe culverts’ construction, start from chainage near Sava Bridge and towards Kuzmin Interchange
e. Relocation of Utilities: Check electricity pole near to M7 structure. Agreement for remaining scope.
f. Provision of Embankment Material: Balkan GP, Rapid, LA, Eagle City, Vimil [Increase of Quantities; New Rates]
a. Delivery of Bearings.
KSR_Agenda_2023-09-20.Docx
2/