KUZMIN ‐ SREMSKA RAČA PROJECT

PROJECT AGENDA
CRITICAL ISSUES

20 September 2023

I. QAQC

a. Asphalt Mix Designs

i. AGI (Vladan) is expected on/before 22.09.2023

ii. CIP to refine PZI (BS)

iii. AB11s PMB (Steel & Concrete section); then for SMA

b. Concrete Statistical Data: AGI (Ceberkapa)

i. H2&M4 to be submitted on 20.09.2023

ii. H4&M1 are awaited

iii. M19 water permeability results to be communicated with CIP

c. Concrete Mix Designs (Aqualink): AGI (Ceberkapa)

i. trials completed

ii. reports are awaited

d. Improvement / Arrangement to Maintain Weekly Certification / Approval of Test Reports (for IPC purposes)

i. Additional staff of AGI is requested, response is awaited

ii. Improvement of internal process organization

e. Personnel recruitment

f. Test Equipment: 2 air content (in payment process), 1 asphalt extractor

II. SAVA BRIDGE

a. Isolation:

i. Antikor agreement at Belgrade

ii. CIP (consent for design solution) for concrete section

b. Curbstone:

i. Procurement

ii. MAR (new test report with current date)

iii. Site crew started on 19.09.2023

c. Service Pipes for Utilities

i. Procurement

ii. MAR

d. Span construction and post-tensioning of remaining sections (Freyssinet): 1000 ton jack to be on site on 02.10.2023

e. Drainage Works: Proposals collected [Pimex – Grandpipe], further communication to be followed

f. Guardrails & Handrails (Unipromet agreement signed, advance payment), Handrail Design (CIP)

g. Asphalt Production:

i. Mix-Designs of Binder and Wearing Courses (follow-up AGI), PMB, MAR, Price Proposal &
Procurement

KSR_Agenda_2023-09-20.Docx
1/
KUZMIN ‐ SREMSKA RAČA PROJECT

PROJECT AGENDA
CRITICAL ISSUES

20 September 2023

ii. Plant attachment to Asphalt Plant for fiber unit

iii. Tank for filler

h. Electricity & Lighting: Tehnounion & Elsing price proposal, procurement, MAR

i. Expansion Joints: Mageba-Produkt BG / Freyssinet; Agreement is at Belgrade office, Decision on modular within 2
days

j. Road Marking & Traffic Signs: Price proposals, MAR

k. Removal of Remaining Temporary Pier Parts at the bottom of Sava Bridge: Proposals to be collected

l. Follow-up Design of Sava Bridge – BiH Customs connection. (Construction - VO for Taşyapı)

m. Follow-up Design of Sava Bridge – Serbia Customs connection. (Design & Construction - VO for Taşyapı)

n. Landscaping & Scour Protection Design: CIP

o. As-built Design

p. Detailed Internal Work Schedule

III. KUZMIN INTERCHANGE

a. Drainage: Price Proposal, Polyester Pipe DN200 SN5, might be executed while formworks and scaffolding are set

b. Embankment Construction at Certain Structures (critical to shorten consolidation period)

c. Protection of existing utilities: fiber optic cable, payment on Monday (18.09.2023)

d. Traffic Signs & Road Marking

e. Traffic management: Further stages to be followed

f. Post-tensioning: Delivery of strands (Freyssinet)

IV. HIGHWAY ALIGNMENT

a. Remaining Structure’s Construction: 3 Box Culverts, 10 Pipe Culverts

i. Pipe culverts’ construction, start from chainage near Sava Bridge and towards Kuzmin Interchange

b. Provision of Material and Embankment Construction

c. Resource Planning & Allocation

d. Toll Plazas: Design, Schedule, Market Research, MAR

e. Relocation of Utilities: Check electricity pole near to M7 structure. Agreement for remaining scope.

f. Provision of Embankment Material: Balkan GP, Rapid, LA, Eagle City, Vimil [Increase of Quantities; New Rates]

V. M5 (BOSUT RIVER BRIDGE)

a. Delivery of Bearings.

b. Pre-cast beam production.

KSR_Agenda_2023-09-20.Docx