Professional Documents
Culture Documents
Stable Cost
Stable Cost
Unit Rate
Item Description Unit Quantity
Materials Others Total
I. PRELIMINARIES
1. Supervision mo 1.00 25,000.00 25,000.00
2. Tempoprary Facility lot 1.00 30,000.00 30,000.00
3. Water and Electrical utilization lot 1.00 20,000.00 20,000.00
SUB-TOTAL:
Steel works
a. Columns and Beams
BI Pipe 3" pcs 15.00 5,000.00 2,500.00 7,500.00
base plate pcs 30.00 400.00 200.00 600.00
anchor bolt pcs 120.00 150.00 75.00 225.00
Miscellaneous lot 1.00 7,875.00 3,937.50 11,812.50
b. Roof Frame
c purlin 2 x 3 pcs 166.00 550.00 220.00 770.00
I beam C4x5.4 kgs 1,932.22 80.00 32.00 112.00
sag rods 10mm pcs 26.00 220.00 88.00 308.00
miscelleanous lot 1.00 17,611.82 8,805.91 26,417.73
c. Roofing Sheet including accesory and insulation
Roofings Sheet sqm 540.00 450.00 350.00 800.00
Ridge Roll lm 90.00 350.00 175.00 525.00
Gutter lm 114.00 480.00 240.00 720.00
Miscellaneous lot 1.00 28,066.50 11,226.60 39,293.10
2. Architectural Works
Stables
a. 5" CHB Laying m2 762.00 800.00 250.00 1,050.00
c. Plastering Works m2 1,524.00 150.00 225.00 375.00
d. Lintel Beam and Stiffner Col lm - 400.00 300.00 700.00
e. Painting Works (Boysen/Davies) sqm 1,524.00 150.00 150.00 300.00
f. Stable Gate
2" pipe pcs 50.00 1,560.00 624.00 2,184.00
1" pipe pcs 160.00 535.00 214.00 749.00
consumables lot 1.00 21,840.00 8,736.00 30,576.00
Plumbing Works
a. 50mm PVC Pipe lm 60.00 53.33 85.98 139.32
b. 75mm PVC Pipe lm 60.00 70.00 85.98 155.98
c. 100mm PVC Pipe lm 120.00 106.67 114.54 221.20
d. Fittings lot 1.00 4,426.25 1,770.50 6,196.75
e. PPR Pipe 25mm lm 100.00 83.33 85.98 169.32
f. PPR Pipe 13mm lm 60.00 56.67 85.98 142.65
f. Hose Bibb lm 8.00 450.00 180.00 630.00
d. Fittings lot 1.00 5,098.13 2,039.25 7,137.39
Electrical Works
a. Rough Ins (Conduit, boxes & consumables) lot 1.00 15,000.00 6,000.00 21,000.00
b. Electrical Wires lot 1.00 30,000.00 12,000.00 42,000.00
Unit Rate
Item Description Unit Quantity
Materials Others Total
c. Lighting Fixtures set 30.00 350.00 120.00 470.00
d. Outlets pcs 30.00 300.00 120.00 420.00
f. electric fan set 20.00 2,300.00 920.00 3,220.00
e. miscellaneous lot 1.00 8,970.00 3,588.00 12,558.00
Unit Rate
Item Description Unit Quantity
Materials Others Total
Inner Fence
a. 5" CHB Laying m2 88.00 800.00 250.00 1,050.00
c. Plastering Works m2 176.00 150.00 225.00 375.00
d. Lintel Beam and Stiffner Col lm 77.50 400.00 300.00 700.00
e. Painting Works (Boysen/Davies) sqm 216.00 150.00 150.00 300.00
f. GI Pipe 1 1/2" pcs 22.00 1,320.00 528.00 1,848.00
g. Flat bar 1" x 1/8 pcs 22.00 450.00 180.00 630.00
h. 6mm steel matting sqm 40.00 385.00 154.00 539.00
Outer Fence
a. 5" CHB Laying m2 62.40 800.00 250.00 1,050.00
c. Plastering Works m2 124.80 150.00 225.00 375.00
d. Lintel Beam and Stiffner Col lm 51.00 400.00 300.00 700.00
e. Painting Works (Boysen/Davies) sqm 150.80 150.00 150.00 300.00
f. GI Pipe 1 1/2" pcs 13.00 1,320.00 528.00 1,848.00
g. Flat bar 1" x 1/8 pcs 13.00 450.00 180.00 630.00
h. 6mm steel matting sqm 26.00 385.00 154.00 539.00
Oval
Oval Frame
concreting m2 1.21 4,400.00 850.00 5,250.00
rebar m2 48.60 60.00 9.00 69.00
form m2 4.86 300.00 450.00 750.00
2" GI Pipe lm 22.00 1,560.00 624.00 2,184.00
SUB-TOTAL:
To Collection Php
VAT
INCOME
TOTAL
area
cost per sqm
cost per stable
Roofings
Roofings Sheet sqm 369.60 450.00 350.00 800.00
Ridge Roll lm 42.00 350.00 175.00 525.00
Gutter lm 100.00 480.00 240.00 720.00
Miscellaneous lot 1.00 19,486.50 7,794.60 27,281.10
Roof Frame
c purlin 2 x3 pcs 112.00 550.00 220.00 770.00
c channel 4 x 5.4 kgs 2,318.40 80.00 32.00 112.00
sag rods 10mm pcs 169.00 220.00 88.00 308.00
miscelleanous lot 1.00 19,897.64 9,948.82 29,846.46
To Collection Php
VAT
INCOME
Unit Rate
Item Description Unit Quantity
Materials Others Total
TOTAL
area
cost per sqm
cost per stable
25,000.00
30,000.00
20,000.00
10,000.00
-
5,000.00
90,000.00
17,292.80
8,646.40
14,300.00
278,790.75
380,935.20
247,562.90
112,500.00
18,000.00
27,000.00
11,812.50
127,820.00
216,408.44
8,008.00
26,417.73
432,000.00
47,250.00
82,080.00
39,293.10
800,100.00
571,500.00
-
457,200.00
109,200.00
119,840.00
30,576.00
8,359.00
9,359.00
26,544.50
6,196.75
16,931.67
8,559.00
5,040.00
7,137.39
21,000.00
42,000.00
14,100.00
12,600.00
64,400.00
12,558.00
92,400.00
66,000.00
54,250.00
64,800.00
40,656.00
13,860.00
21,560.00
65,520.00
46,800.00
35,700.00
45,240.00
24,024.00
8,190.00
14,014.00
6,378.75
3,353.40
3,645.00
48,048.00
5,093,758.27
5,183,758.27
259,187.91
5,442,946.19
690.00
7,888.33
272,147.31
295,680.00
22,050.00
72,000.00
27,281.10
86,240.00
259,660.80
52,052.00
29,846.46
844,810.36
42,240.52
887,050.88
690.00
1,285.58
44,352.54
Unit Rate
Item Description Unit Quantity
Materials Others Total
I. PRELIMINARIES
1. Supervision mo 3.00 25,000.00 25,000.00
2. Tempoprary Facility lot 1.00 30,000.00 30,000.00
3. Water and Electrical utilization lot 1.00 20,000.00 20,000.00
SUB-TOTAL:
Steel works
a. Columns and Beams
BI Pipe 3" pcs 15.00 5,000.00 2,500.00 7,500.00
base plate pcs 30.00 400.00 200.00 600.00
anchor bolt pcs 120.00 150.00 75.00 225.00
Miscellaneous lot 1.00 7,875.00 3,937.50 11,812.50
b. Roof Frame
c purlin 2 x 3 pcs 166.00 550.00 220.00 770.00
I beam C4x5.4 kgs 1,932.22 80.00 32.00 112.00
sag rods 10mm pcs 26.00 220.00 88.00 308.00
miscelleanous lot 1.00 17,611.82 8,805.91 26,417.73
c. Roofing Sheet including accesory and insulation
Roofings Sheet sqm 540.00 350.00 350.00
Ridge Roll lm 90.00 175.00 175.00
Gutter lm 114.00 240.00 240.00
Miscellaneous lot 1.00 28,000.00 11,200.00 39,200.00
2. Architectural Works
Stables
a. 5" CHB Laying m2 762.00 800.00 250.00 1,050.00
c. Plastering Works m2 1,524.00 150.00 225.00 375.00
d. Lintel Beam and Stiffner Col lm - 400.00 300.00 700.00
e. Painting Works (Boysen/Davies) sqm 1,524.00 150.00 150.00 300.00
Plumbing Works
a. 50mm PVC Pipe lm 60.00 53.33 85.98 139.32
b. 75mm PVC Pipe lm 60.00 70.00 85.98 155.98
c. 100mm PVC Pipe lm 120.00 106.67 114.54 221.20
d. Fittings lot 1.00 4,426.25 1,770.50 6,196.75
e. PPR Pipe 25mm lm 100.00 83.33 85.98 169.32
f. PPR Pipe 13mm lm 60.00 56.67 85.98 142.65
f. Hose Bibb lm 8.00 450.00 180.00 630.00
d. Fittings lot 1.00 5,098.13 2,039.25 7,137.39
Electrical Works
a. Rough Ins (Conduit, boxes & consumables) lot 1.00 15,000.00 6,000.00 21,000.00
b. Electrical Wires lot 1.00 30,000.00 12,000.00 42,000.00
c. Lighting Fixtures set 30.00 350.00 120.00 470.00
d. Outlets pcs 30.00 300.00 120.00 420.00
f. electric fan set 20.00 2,300.00 920.00 3,220.00
e. panel board lot 1.00 7,500.00 3,000.00 10,500.00
e. miscellaneous lot 1.00 16,460.00 6,584.00 23,044.00
Unit Rate
Item Description Unit Quantity
Materials Others Total
Inner Fence
a. 5" CHB Laying m2 88.00 800.00 250.00 1,050.00
c. Plastering Works m2 176.00 150.00 225.00 375.00
d. Lintel Beam and Stiffner Col lm 77.50 400.00 300.00 700.00
e. Painting Works (Boysen/Davies) sqm 216.00 150.00 150.00 300.00
f. GI Pipe 1 1/2" pcs 22.00 1,320.00 528.00 1,848.00
g. Flat bar 1" x 1/8 pcs 22.00 450.00 180.00 630.00
h. 6mm steel matting sqm 40.00 385.00 154.00 539.00
Outer Fence
a. 5" CHB Laying m2 62.40 800.00 250.00 1,050.00
c. Plastering Works m2 124.80 150.00 225.00 375.00
d. Lintel Beam and Stiffner Col lm 51.00 400.00 300.00 700.00
e. Painting Works (Boysen/Davies) sqm 150.80 150.00 150.00 300.00
f. GI Pipe 1 1/2" pcs 13.00 1,320.00 528.00 1,848.00
g. Flat bar 1" x 1/8 pcs 13.00 450.00 180.00 630.00
h. 6mm steel matting sqm 26.00 385.00 154.00 539.00
Oval
Oval Frame
concreting m2 1.21 4,400.00 850.00 5,250.00
rebar m2 48.60 60.00 9.00 69.00
form m2 4.86 300.00 450.00 750.00
2" GI Pipe lm 22.00 1,560.00 624.00 2,184.00
V Oval Roof and Roof Frame
Roofing
Roofings sheets m2 369.60 200.00 200.00
ridge lm 42.00 175.00 175.00
Gutter lm 100.00 240.00 240.00
miscelleanous lot 1.00 18,000.00 9,000.00 27,000.00
Roof Framing
c purlin pcs 112.00 600.00 240.00 840.00
angle bar kgs 4,300.00 80.00 32.00 112.00
sag rods 10mm pcs 169.00 220.00 88.00 308.00
miscelleanous lot 1.00 31,000.00 15,000.00 46,000.00
VI Owner Supply Materials
SUB-TOTAL:
To Collection Php
Unit Rate
Item Description Unit Quantity
Materials Others Total
VAT
INCOME
TOTAL
area
cost per sqm
cost per stable
75,000.00
30,000.00
20,000.00
10,000.00
-
5,000.00
140,000.00
17,292.80
8,646.40
28,600.00
278,790.75
380,935.20
247,562.90
112,500.00
18,000.00
27,000.00
11,812.50
127,820.00
216,408.44
8,008.00
26,417.73
189,000.00
15,750.00
27,360.00
39,200.00
800,100.00
571,500.00
-
457,200.00
8,359.00
9,359.00
26,544.50
6,196.75
16,931.67
8,559.00
5,040.00
7,137.39
21,000.00
42,000.00
14,100.00
12,600.00
64,400.00
10,500.00
23,044.00
92,400.00
66,000.00
54,250.00
64,800.00
40,656.00
13,860.00
21,560.00
65,520.00
46,800.00
35,700.00
45,240.00
24,024.00
8,190.00
14,014.00
6,378.75
3,353.40
3,645.00
48,048.00
73,920.00
7,350.00
24,000.00
27,000.00
94,080.00
481,600.00
52,052.00
46,000.00
65,520.00
22,470.00
18,345.60
270,000.00
31,500.00
54,720.00
184,800.00
14,700.00
48,000.00
6,056,172.77
6,196,172.77
309,808.64
6,505,981.41
690.00
9,428.96
325,299.07
Concreting Works
75.10 cbm gravel 3/4
477.93 bags cement
26.55 cbm sand
Rebar Works
186.00 pcs 12mm rebar
507.00 pcs 10mm rebar
70.00 kgs ties
4.00 pcs phenolilc board 3/4
40.00 pcs coco lumber
20.00 kgs CW Nails
Steel Works
15.00 pcs BI Pipe 3" sched 40
30.00 pcs Base Plate (.15x.20x12mm)
10.00 pcs 10mm roundbar for Leg Bar as per plan
60.00 kgs welding rod
10.00 pcs 10mm sagr rods
168.00 pcs C purlins 2 x 3
34.00 pcs C channel 2 x 6 x 1/4
Roofing Sheet
88.00 pcs Roofing sheet 5.5m length x 1.0m width 0.5mm thick
19.00 pcs RidgeRoll (2.44m length)
38.00 pcs Gutter
25.00 pcs Flashing
CHB Works
9,525.00 pcs 5" CHB
1,143.00 bags cement
138.55 cbm sand
762.00 pcs 10mm rebar
254.00 bags skimcoat
20.00 pail paint latex white
Plumbing Works
20.00 pcs 2" PVC Pipe
20.00 pcs 3" PVC Pipe
40.00 pcs 4" PVC Pipe
12.00 pcs 2" elbow 90 deg
16.00 pcs 3" elbow 90 deg
10.00 pcs 4" elbow 90 deg
25.00 pcs PPR pipe 1"
15.00 pcs PPR Pipe 1/2"
10.00 pcs PPR Pipe tee 1"
10.00 pcs PPR Pipe elbow 1"
10.00 pcs PPR Pipe tee 1/2"
10.00 pcs PPR Pipe elbow 1/2"
8.00 pcs hose bibb
4.00 pcs gate valve 1/2"
10.00 cans neltex solvent cement 200cc
Electrical Works
40.00 pcs orange pipe 1/2"
20.00 pcs orange pipe 1"
3.00 box 12mm thhn wire
50.00 lm 8mm thhn wire
1.00 set Panel Board (30 amp main 4 - 20 amp sub)
30.00 pcs Convenience Outlet
30.00 pcs Lighting Fixture (LED light)
20.00 pcs Electric Fan
Fencing Works
1,875.00 pcs 5" CHB
225.00 bags cement
27.27 cbm sand
150.00 pcs 10mm rebar
50.00 bags skimcoat
4.00 pail paint latex white
35.00 pcs GI Pipe 1 1/2"
35.00 pcs Flat bar 1"x1/8
20.00 sheet steel matting 4'x8'
Concreting Works
150.21 cbm gravel 3/4
955.85 bags cement
53.10 cbm sand
Rebar Works
372.00 pcs 12mm rebar
1,014.00 pcs 10mm rebar
140.00 kgs ties
8.00 pcs phenolilc board 3/4
80.00 pcs coco lumber
40.00 kgs CW Nails
Steel Works
30.00 pcs BI Pipe 3" sched 40
60.00 pcs Base Plate (.15x.20x12mm)
20.00 pcs 10mm roundbar for Leg Bar as per plan
120.00 kgs welding rod
20.00 pcs 10mm sagr rods
336.00 pcs C purlins 2 x 3
68.00 pcs C channel 2 x 6 x 1/4
Roofing Sheet
176.00 pcs Roofing sheet 5.5m length x 1.0m width 0.5mm thick
38.00 pcs RidgeRoll (2.44m length)
76.00 pcs Gutter
50.00 pcs Flashing
CHB Works
19,050.00 pcs 5" CHB
2,286.00 bags cement
277.09 cbm sand
1,524.00 pcs 10mm rebar
508.00 bags skimcoat
40.00 pail paint latex white
Plumbing Works
40.00 pcs 2" PVC Pipe
40.00 pcs 3" PVC Pipe
80.00 pcs 4" PVC Pipe
24.00 pcs 2" elbow 90 deg
32.00 pcs 3" elbow 90 deg
20.00 pcs 4" elbow 90 deg
50.00 pcs PPR pipe 1"
30.00 pcs PPR Pipe 1/2"
20.00 pcs PPR Pipe tee 1"
20.00 pcs PPR Pipe elbow 1"
20.00 pcs PPR Pipe tee 1/2"
20.00 pcs PPR Pipe elbow 1/2"
16.00 pcs hose bibb
8.00 pcs gate valve 1/2"
20.00 cans neltex solvent cement 200cc
Electrical Works
80.00 pcs orange pipe 1/2"
40.00 pcs orange pipe 1"
6.00 box 12mm thhn wire
100.00 lm 8mm thhn wire
2.00 set Panel Board (30 amp main 4 - 20 amp sub)
60.00 pcs Convenience Outlet
60.00 pcs Lighting Fixture (LED light)
40.00 pcs Electric Fan
Fencing Works
3,750.00 pcs 5" CHB
450.00 bags cement
54.55 cbm sand
300.00 pcs 10mm rebar
100.00 bags skimcoat
8.00 pail paint latex white
70.00 pcs GI Pipe 1 1/2"
70.00 pcs Flat bar 1"x1/8
40.00 sheet steel matting 4'x8'
CHB 33.75 lm
chb laying 162.00 sqm 750.00 300.00 1,050.00
plastering 324.00 sqm 120.00 150.00 270.00
Walls Stables
Footing 68.00 lm
concrete 5.44 cbm 4,000.00 1,600.00 5,600.00
rebar 326.40 kgs 50.00 20.00 70.00
form 27.20 sqm 450.00 400.00 850.00
excavation 21.76 cbm
CHB 300.00 lm
chb laying 600.00 sqm 750.00 300.00 1,050.00
plastering 1,200.00 sqm 120.00 150.00 270.00
painting 1,200.00 sqm
Roofing 540.00
Roofings sheets 540.00 sqm 400.00 160.00 560.00
ridge 90.00 lm 327.87 131.15 459.02
Gutter 114.00 lm 389.34 155.74 545.08
FENCE
Outer Wall
CHB 26.00 lm
chb laying 62.40 sqm 750.00 300.00 1,050.00
plastering 124.80 sqm 120.00 150.00 270.00
painting 150.80 sqm
lintel column 25.00 lm
lintel beam 26.00 lm
wall ftg 26.00 lm
2" GI Pipe 13.00 pcs
flat bar 13.00 pcs
mesh 26.00 sqm
Inner Wall
CHB 40.00 lm
chb laying 88.00 sqm 750.00 300.00 1,050.00
plastering 176.00 sqm 120.00 150.00 270.00
painting 216.00 sqm
lintel column 37.50 lm
lintel beam 40.00 lm
wall ftg 40.00 lm
2" GI Pipe 22.00 pcs
flat bar 22.00 pcs
mesh 40.00 sqm
OVAL
Roofing 369.60
Roofings sheets 369.60 sqm 400.00 160.00 560.00
ridge 42.00 lm 327.87 131.15 459.02
Gutter 100.00 lm 389.34 155.74 545.08
Electrical Works
a. Rough Ins (Conduit, boxe 1.00
b. Electrical Wires 1.00
c. Lighting Fixtures 30.00
d. Outlets 30.00
e. miscellaneous 1.00
148,396.02
Summary
259,616.00 12,980.80
109,200.00 24.00 4,550.00
119,840.00 24.00 4,993.33
30,576.00 24.00 1,274.00
69,888.00 24.00 2,912.00
34,944.00 24.00 1,456.00
26,520.00 24.00 1,105.00
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
343.85 412.62
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
343.85 412.62
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
chb 12.500
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
343.85 412.62
chb 12.500
10.00 12.00
558.00 465.00
0.01 0.01
0.616 0.887
cement 0.75
sand 0.10
10mm 1.00
cement 0.30
cement 0.30
sand 0.03
30.79
#DIV/0!
870.00
28.26
2"
truss 32.00
0.05
4.71
150.72
c purlin
2x3 c purlin 1,035.00
gate 22.50
22.50
c purlin
2x3 c purlin 1,035.00
gate 22.50
22.50
2"
truss 32.00
0.05
sand 0.10
10mm 1.00
cement 0.30
cement 0.30
sand 0.03
756.48
756.48
187.50
15.00 187.50
756.48
625.00
15.00 187.50
250.00 187.50
900.00 90.00
160.00 160.00
-
14.13
172.50
31.50
9.00
172.50
31.50
9.00
1"
130.00
0.03
900.00 90.00
160.00 160.00