1. Promptly issuing the Certificates of Payment and the Final Certificate of Completion is a responsibility of the Architect
to whom?
A manufacturer B public
C contractor D client
2. Which is an unethical action with respect to the Architect's responsibility to the people?
3. This shall be issued by the Owner to the Contractor following the execution of the Contract Agreement.
4. What pre-design service involves problem seeking process which will lead to the statement and identification of both
horizontal and vertical requirements?
5. Invitations issued to prospective bidders, giving information as to the nature of the proposed project, conditions for
the issuance of contract documents, date of bidding, and estimated cost or information that would give the Contractor
a general idea of the magnitude and extent of the project.
6. Information, advice or notification pertinent to the project delivered in person or sent by registered mail to the
individual. firm or corporation at the last known business address of such individual, firm or corporation.
?
7. A method of compensation frequently used where there is a continuing relationship on a series of projects.:
8. A method of compensation that is flexible, easy to apply and is related to the size and the type of the project.
9. The multiple of personnel direct expense is applicable only to what type of work?.
10. A method of selection for an Architect most often used by an individual person undertaking a relatively small project
11. Duly notarized written contract or equivalent public instrument stipulating the scope of services and guaranteeing
compensation of such services?
13. What official body formulates rules and regulations relating to signing / sealing of drawings, specifications and other
documents registered by the architect?
14. In the Architect’s Code of Ethics, to whom does the architect have responsibility to provide for arbitration as a method
for settlement of disputes?
A a. Contractor B d. Client
C c. Manufacturers/dealers D b. Public
15. One of the methods of compensation for architectural service is based on technical hours and expenses & made by
adding all costs of technical services (man-hours time rate). A multiplier is used to take care of overhead & profit. This
method, however, is applicable only to non-creative work & aspects of pre-design services & supervision work. What is
this method called?
A b. Per diem plus reimbursable expenses B a. Per diem plus reimbursable expenses
16. Under what phase of design services does the architect prepare complete construction drawings and specifications on
materials/construction methods?
17. Architect shall at no time act in a manner detrimental to the best interest of what?
18. Architect shall refrain from taking part in paid advertisement endorsing any materials of?
19. The Architect's _____ of purpose must be beyond reproach; he/she acts as professional adviser to his/her Client and
his/her advice must be unprejudiced;
C b. Integrity D c. Professional
20. Under General Provisions, The Architect is engaged in a profession which carries with it grave responsibilities to
whom?
C c. Public D b. Government
21. This shall be issued by the Owner to the Contractor following the execution of the Contract Agreement?
22. What method of compensation is most suitable for compensating the Architect's services for the pre-design phase?
24. What pre-design service involves investigating, identifying and documenting the needs of the client for use in the
design of the project?
25. Which of the following is a responsibility of the Architect in the Construction Phase of the Regular Design Services?
26. Promptly issuing the Certificates of Payment and the Final Certificate of Completion is a responsibility of the Architect
to whom?
A b. public B d. Manufacturer
C a. client D c. Contractor
27. Which is an unethical action with respect to the Architect's responsibility to his colleagues and subordinates?
c. Undertakes a commission from another Architect d. Serving as professional adviser, accepts employment
C D
duly notified as Design Architect for a competition project.
28. Which activity is included in the Contract Document Phase of the Architect's Regular Design Services?
A b. Prepares forms for contract letting and bidding B a. Prepares forms for contract documents
d. Checks samples, schedules and shop drawings c. Assists the Owner in obtaining proposals from
C D
contractors
29. What percentage of the Architect's Basic Fee is for the liability of the Architect under the Civil Code?
A b. 10% B a. 5%
C d. 20% D c. 15%
32. A method of selection for an Architect most often used by an individual person undertaking a relatively small project?
33. A method of compensation frequently used where there is a continuing relationship on a series of projects?
34. A method of compensation that represents a risk situation to the Architect since his costs may exceed the agreed
amount?
35. State-owned Architecture Schools exempted from being ______by the Government Architecture Degree?
A c. Professionally B a. Technically
C b. Legally D d. current
37. The ____regulates the practice of the Profession of Architecture in the Philippines?
A a. RA 8266 B c. RA 9246
C b. RA 8256 D d. RA 9266
38. The client can select an architect for a project through ____?
A d. Proposal B a. Bidding
C a. Bidding D b. advertisement
40. Architects are people who are registered and _____ qualified to practice architecture?
A c. Professionally B a. Technically
C b. Legally D d.Current
A d. Facebook B a. an invitation
45. The ____ entails the conduct of primary and secondary search for facts as basis for future conclusion to be use in
decision making in the Architectural Project?
46. The detailed analysis that will determine the viability of a proposed development?
47. The ____ is the formulation of site criteria to determine the most appropriate for a proposed project?
48. The ____ are studies involving the studies of secondary information as in-puts in Architectural Design?
A c. PRC B d. SEC
C b. CHED D a. UAP
54. Architect should register with the____in order to qualify to practice Architecture?
A a. PRC B c. LGU
55. For Non creative projects, the architect is compensated on the basis of?
56. The ____can order changes in the construction based on technicalities only?
A d. Contractor B c. Consultant
C a. Owner D b. Architect
A b. IAPOA B a. UAP
C d. Non-listed D c. GOD
58. In a typical owner-general contractor agreement, who is responsible for the payment of insurance for personal injury
and to property?
C d. Contractor D a. Architect
63. Under which phase of Regular design services the Architect prepares an initial statement of probable construction
cost.
65. A method of compensation that represents a risk situation to the Architect since his costs may exceed the agreed
amount.
67. Under what phase of design services does the architect prepare complete construction drawings and specifications on
materials/construction methods?
68. One of the methods of compensation for architectural service is based on technical hours and expenses & made by
adding all costs of technical services (man-hours time rate). A multiplier is used to take care of overhead & profit. This
method, however, is applicable only to non-creative work & aspects of pre-design services & supervision work. What is
this method called?
69. What official body formulates rules and regulations relating to signing / sealing of drawings, specifications and other
documents registered by the architect?
70. When were the 3 architectural organizations integrated into one association of architects called UAP?
A 1976 B 1978
C 1972 D 1975
71. What is the general basis of the Architect’s minimum basic fee?
75. This type of selection may be conducted by committees representing institutions, corporations or public agencies.
A 100km B 50km
C 200km D 150km
80. The Architect can render services in any of the following ways:
Individual Architect / Architect’s Own Staff / By Individual Architect / Architect’s Own Staff / By
A B
Association, Company or Networking Association, Consultation or Networking
Individual Architect / Owner's Own Staff / By Independent Architect / Architect’s Own Staff / By
C D
Association, Consultation or Networking Association, Consultation or Networking
81. MANNER OF PROVIDING SERVICES:
After the initial meeting / conversation / correspondence with the Client, the Architect must submit his proposal for
pre-design services, stating the following: Manner of Payment, Scope of Work, Other Conditions of Services and
___________.
82. Under Pre-design services, the Architect states the project terms of reference (ToR) including the concept, objectives
and other necessary requirements to bid out architectural services (whether public or private).
84. RA 9266:
ARTICLE I - General Provision
"Section 1"
85. RA 9266:
ARTICLE I - General Provision
"Section 2"
86. RA 9266:
ARTICLE I - General Provision
"Section 3"
87. RA 9266:
ARTICLE IV - PRACTICE OF ARCHITECTURE
"Section 38"
89. RA 9266:
ARTICLE V - Final Provisions
"Section 44
90. The Architect in this area of practice undertakes a scientific study on the built environment’s well being, which allows
the Architect to focus on the ways in which the building/structure can best maintain itself and prolong its life in a cost-
efficient manner, and finally provide recommendations to the Owner/ Client.
Answer Key
89.a 90.d