Sialkot Project SSEMP
Sialkot Project SSEMP
Site-Specific Environmental
Management Plan (SSEMP)
Loan No. 3562-Pak
Table of Contents
1 INTRODUCTION.......................................................................................................................08
1.1 Requrement of SSEMP....................................................................................................08
1.2 Aims and objectives of SSEMP...................................................................................................08
1.3 SSEMP Administration....................................................................................................09
2.0 Project Desciption............................................................................................................09
2.1 Contract Desciption.........................................................................................................10
2.2 Project Location and construction of boundries...............................................................11
2.3 Objective and scope of Work...........................................................................................14
2.4 Project layout Plan...........................................................................................................15
2.5 Camp site and Batching Plant..........................................................................................19
2.6. Objectives of SSEMP for Camp and Batching Plant........................................................19
2.7 Camp Allied all Facilities ...............................................................................................20
3.0 Senstive receptors .........................................................................................................663
3.1 Impact on Sensitive Receptors.........................................................................................66
3.2 Impact of Construction Equipments...............................................................................674
3.3 Mitigation Measures for noise reducing.........................................................................685
4.0 policies nd legal framwork of Environmental parameters ...............................................68
4.0 National Policy and legal framwork...............................................................................697
4.1 EPA Environmental regulation........................................................................................70
4.2 regulatory clearence EPA Punjab...................................................................................707
4.3 NEQS Standard 2000.....................................................................................................717
4.4 other Environmental Legislation......................................................................................71
4.5 ADBs Safeguard Policies statement(SPS) 2009.............................................................719
4.6 ADB access to information policy...................................................................................30
4.7 Implication of ADB Policy..........................................................................................................30
4.8 IFC guidelines on road construction project.....................................................................31
5.0 Environmental Management Measures..........................................................................192
6.0 Environmental work management Plan............................................................................52
6.1 conduct of work...............................................................................................................52
6.2 Types of security and safety events..................................................................................52
6.3 signage and access control...............................................................................................53
6.4 drugs and alchole usage ..................................................................................................53
6.5 fall protection....................................................................................................................54
6.6 Amber lights:...................................................................................................................54
6.7 use and storage of hazardious material.............................................................................55
6.8 Tools and Equipments(lighting,PPEs, Fire protection etc)...............................................55
6.9 fire fighting......................................................................................................................56
6.10 severe weather.................................................................................................................56
6.11 house keeping and material storage.............................................................................................56
6.12 Security Risks..................................................................................................................57
6.13 Site Inspection.................................................................................................................57
6.14 Hazard Management, traing, TBT and internal audit.......................................................58
6.18 Emergency Respons Plan (ERP)......................................................................................59
6.19 Emergency Response Team (ERT) preparedness ............................................................61
6.20 Emergency Contact..........................................................................................................62
2|Page Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
7 EMP Roles and responsibilities.......................................................................................62
7.0 Institutional arrangements for EMP during construction phase........................................62
7.1 EPD Punjab......................................................................................................................62
7.2 3rd Party M&E contractor.................................................................................................63
7.3 EA (ESMMC)PD.............................................................................................................63
7.4 Role of ADB....................................................................................................................63
7.5 Role of CIU......................................................................................................................64
7.6 Role of Municipal Corporation (MC)..............................................................................64
7.7 Role of Supervisory Consultant RE.............................................................................................64
7.8 Role of Supervisory Consultant Environmental specialist...........................................................65
7.9 Role of contractor Environmental specialist....................................................................65
7.10 Employees Obligations ...................................................................................................67
7.11 Implimentation of SSEMP during construction phase.....................................................67
7.12 Environmental awareness training ..................................................................................68
7.13 Communication and documentation.................................................................................69
7.14 Reporting Mechanism......................................................................................................70
7.15 Environmental management Cost....................................................................................71
7.16 Environmental Staffing....................................................................................................72
8. Risk Assessment..............................................................................................................72
8.1 Risk assessment and management....................................................................................73
8.2 Risk Identification and assessment process......................................................................74
8.4 Risk response ..................................................................................................................78
8.5 cumulative and residual impacts ...................................................................................120
9.0 instrumental environmental monitoring and its objects..................................................121
10 Grievance Redressal Mechanism (GRM).......................................................................124
11,11.1 Anticipated environmental impact and methodolgy for screening and mitigations........121
11.2 Degradation of ambient air quality.................................................................................130
11.3 noise and vibration.........................................................................................................133
11.4 Soil Quality Management..............................................................................................136
11.5 Soil Erosion and sedimentation .....................................................................................137
11.6 Traffic Management.......................................................................................................137
11.7 construction waste dumping ..........................................................................................138
11.8 OHS and mitigation.......................................................................................................139
11.9 Camp and batching plant effluents.................................................................................148
11.10 cummulative Impacts.....................................................................................................148
List of Tables
List of Figures
List of Annexures
List of Abbreviations
ADB Asian Development Bank
CO Carbon monoxide
CSSP Construction Safety and Security Plan
dB Decibels (A measure of audible noise)
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EPA Environmental Protection Agency
EPD Environment Protection Department
ERC Emergency Response Coordinator
ERT Emergency Response Team
ES Environment Specialist of Project Management Organization
ESMMC Environment & Social Management and Monitoring Cell
GOP Government of Pakistan
GRM Grievance Redress Mechanism
HSE Health, Safety and Environment
ICB International Competitive Bidding
K/M Kilometer
L/S Left Side
MSDS Material Safety Data Sheet
NEQS National Environmental Quality Standards
NOC No Objection Certificate
NOx Oxides of Nitrogen
PD Project Director
PEQS Punjab Environmental Quality Standards
PM Project Manager
PM2.5 Particulate Matter of 2.5 micron
PM10 Particulate Matter of 10 microns
PMO Project Management Organization
PPE Personal Protective Equipment
ROW Right of Way
RD Reduce Distance
RE Resident Engineer
R/S Right Side
RTA Road Traffic Accidents
SC Supervision Consultant
SPM Suspended Particulate Matter
SSEMP Site Specific Environmental Management Plan
6|Page Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
SOx Oxides of Sulphur
SWMP Solid Waste Management Plan
TBT Tool Box Talk
PICIIP Punjab Intermediate Cities Improvement Investment Project
LAA Land Acquisition Act (of 1984)
LARP Land Acquisition and Resettlement Plan
IEE Initial Environmental Examination
IFC International Finance Corporation
IPCC Intergovernmental Panel on Climate Change
BOQ Bill of Quantities
COVID Corona Virus Infectious Disease
The Site-Specific Environmental Management Plan (SSEMP) for the Construction of Flyover
on shahabpura road, grade separation at railway crossing of shahab pura road (from km
7+643 to km 8+417) identifies the principles, approach, procedures and methods, that will be
used to control and minimize the environmental and social impacts of all construction and
operational activities associated with this project on construction sites as well as on camp and
batching plant site. This section explains the purpose of SSEMP, the procedures and
responsibilities associated with its implementation. This contains the general overview of the
SSEMP & the details of measures, which would be included in this SSEMP. The mitigation
measures of each specific condition have also been addressed in this document.
SSEMP minimizes negative impacts of activities on local communities and the natural
environment, to reduce the induced impacts of construction activities; to prevent pollution
and ensure that construction activities are planned to create sustainability and there will be
minimum risk to the environment. This SSEMP has been compiled for the Construction of
flyover at railway crossing of shahab pura road (from km 7+643 to km 8+417)
The LG&CDD, PICIIP Departments of Government of the Punjab, Pakistan, are the
proponent of this project.
The main stakeholders, namely the Client, Consultant and the Contractor of Flyover on
shahabpura road, grade separation at railway crossing of shahab pura road (from km 7+643 to
km 8+417), this SSEMP will provide a guide on what mitigative actions need to be taken and
where and when they are needed. It will thus help to improve and mitigate adverse impacts
through which project benefits will be showcased, and environmentally beneficial standards
of best practice is provided to all the stakeholders to this project.
SSEMP is the requirement for different activities (such as construction of camp,
rehabilitation & construction of structures and excavation of borrow pits) at the construction
stage which could provide the delivery mechanism to address environmental and Social
Impacts of this project. The aim of formulating this SSEMP is to identify potential impacts
during construction stage of this project that will prevent or at least mitigate any negative
effects of the work and specify a monitoring program for implementation by the LG&CDD,
PICIIP & PMU Department. The other main objectives of this SSEMP are;
Identify the potential negative environmental impacts that can result from the
construction activities and identify measures to control or avoid these impacts.
Outline specific roles and responsibilities of project staff related to environmental
management and mitigation measures.
8|Page Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
List reporting mitigation measures,
Take actions and conduct monitoring to show the compliance with Provincial, National
and International legislative requirements.
To ensure that the impacts on the environment are kept to a minimum by ensuring the
mitigation measures described in the SSEMP are implemented and continuously
monitored.
To plan, organize and implement all the measures required for the health and safety of the
workers.
The SSEMP will perform a risk assessment & hazard identification and will propose site
specific mitigation options that would appropriate and commensurate with the actual
impact.
Copies of this Site-Specific Environmental Management Plan shall be kept at the site office
and will be distributed to all senior Project officers. All senior officers shall be required to
understand and familiarize themselves with the contents of this document
The Government of Punjab has received a Loan from Asian Development Bank (ADB). Part
of the financing will be used for Urban Mobility Design and Supervision Consultant financed
by the Loan. The Local Government and Community Development (LG&CD) Department of
Punjab is the executing agency of the project, and the city governments of Sahiwal and
Sialkot (municipal corporations) are the implementing agencies.
A Project Management Unit (PMU) has been established to support LG&CD Department,
and two City Implementation Units (CIUs)have been established to support in Sialkot. Under
the guidance of the project steering committee, LG&CD Department is responsible for the
overall execution of the project. Priority project were identified under the UMDS which
included Grade Separator at Railway Crossing at Shahabpura Road. Technical analysis of
existing condition of the railway crossing at Shahabpura road has been carried out from the
data collected at site conservatively taking the highest peak hour movement count of the
road.The transport infrastructure in Sialkot is generally inadequate for existing requirements;
there are relatively few circumferential links. This results in extended journey times for many
trips, and the misuse of minor roads through traffic. On all roads mostly motorcycle
rickshaws or auto rickshaws are being used as urban transport services which causes the
traffic congestion as well air pollution
Shahabpura road develops a link between main city of Sialkot and Wazirabad bypass Chowk.
A railway line is crossing at Shahabpura road and splits the road to east and the west. This
intersection has a complex geometry and forms a 5 legs intersection. An elevated flyover is
proposed from km 7+643 to km 8+417 to pass the railway line with two lane 12ft
carriageway on both sides of the flyover.
Sponsoring
Asian Development Bank (ADB)
Agency
20 months.
Project Duration
Date of
1st April 2023
Commencement
Sialkot City is a district head quarter of Punjab province of Pakistan. It is situated in the north
east corner of the country close to the border of Indian held territory of Kashmir. Sialkot city
is well connected with adjoining cities and towns through regional road network and rail
links. It is an industrial city having major share in export based industry. The facilities of a
dry port and recently built airport have contributed towards its economic growth. Sialkot has
witnessed more than 17 percent growth rate of vehicles during last five years.
Currently more than 250,000 vehicles are registered in the district and majority is operating
in the city. High growth of vehicles has created congestion on city streets and pressure for
investments on road infrastructure improvements.
Road network in the city is well developed and recently executed road improvements; carried
through joint efforts of Sialkot Chambers of Commerce and Industry (SCCI) and the
Government, has fairly improved the road surface conditions in most of city areas. However
problem lies in road junction layouts, traffic management, utility of road space, inadequate
facilities for pedestrians, NMT and public transport, uncontrolled road side parking and
absence of clear demonstration and display of traffic regulatory control measures A
dualcarriageway connects Sialkot to the nearby city of Wazirabad, with onward connections
throughout Pakistan via the N-5 National Highway, while another dual carriageway connects
Sialkot to Daska, and onwards to Gujranwala and Lahore. And the Shahabpura road near Pir
Syed Riyzat Ali Maroof shirne crossing the railway tract The train crosses Shahapura road 2
times in 24 hours its splits the Shahab pura Road to the east and west. And the Flyover
project is proposed to save the time and life of people.
The main objective of the study was to perform travel demand forecast for at railway crossing
at Shahab Pura road. This scope of work covers various other purpose like,
Flyover: The train passes through the Shahabpura road twice a day. The average delay at
intersection is 20 minutes when the gates are closed for train. If the flyover is proposed at
the desired location the delay on the Shahabpura road will be diminished. A 70feet span
flyover is proposed for this project.
14 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Service Road: 12 feet service road is proposed on both side of the flyover for light traffic
which connects the small link roads. Service road is provide below the flyover which
intersect with the rail track. These service roads will be used for the light traffic.
Channelization: The service road is properly channelized for the light traffic below
flyover for the smooth traffic flow.
Road Lighting Poles, RCC Walls, Gravel for Sub Base, base Course, and Asphaltic Base
Course will be used in the proposed intervention.
The construction of project roads will provide improved and efficient transportation
services and utility services to the people of the area and those travelling in Sialkot
city. The construction of road will encourage communities to move toward project
area. Migration of communities would lead to development of infrastructure like
hospital, market, educational centres and business centres. The project will add to the
overall social development of the area. The infrastructure of road related and other
business activities will get a boost thereby resulting in employment opportunities and
numerous social benefits for the people.
Thus, the proposed scope of works needs to be implemented on an urgent basis with
the population and traffic projections over different time periods.
Figure2.4.2: Layout Plan of Grade Separator at Railway Crossing (Station from 8+700 to 9+700)
KNK-SMC (JV) will acquire a temporary private land for the construction of Camp and
batching plants yard. The proposed location of camp is near Sambial Interchange private and
building is hired on rental basis for offices and residence of site staff. The total area, which
will be acquired for the camp site will be 05 Acre. This land will be acquired according to the
sub clause 7.15 and through term lease agreement between the Contractor and the land
owner. This camp will include, Residential Areas of labours, Well Equipped First Aid
Station, Material Testing Laboratory, Mechanical Workshop, Store yard, steel yard and
Batching plant yard. The contractor camp will be temporarily built and will be restored
according to the term and condition set with the land owner. In case of fertile agriculture
land, topsoil of agricultural fields will be preserved in a condition as near as possible to its
pre-project condition in order to allow successful land rehabilitation. The layout plan of the
camp, is attached in Annexure-
The mitigation measures included in SSEMP shall be strictly adhered to minimize any
negative impacts on soil, water, air and biological resources. The basic objectives of SSEMP
for the Camp Management are to:
Avoid or reduce negative impacts on the nearby community (if any) and maintain
amicable relationship between local communities and camp residents.
Maintain good standards for worker welfare and living conditions at the camp that
provide a healthy, safe and comfortable environment.
Following measures shall be taken to establish and maintain allied facilities at proposed
Camp site:
Suitable and adequate living accommodation shall be provided to all workers.
The living rooms/ dormitories shall be airy/ventilated and lighted. No congestion
inside the rooms shall be allowed.
Toilets shall have waste flush system for correct disposal and operation of sewage
system. Toilets shall be provided with facilities such as Water Closets WCs. Use of
antiseptics shall be made on daily basis to ensure proper hygiene and sanitation.
Recreational facilities shall be arranged including common TV rooms, badminton
court, volley ball ground, etc.
Heating and cooling facilities shall be provided in the living rooms.
Ample space shall be provided to the labor to maintain keep good housekeeping
inside their living areas.
Uninterrupted electricity supply shall be provided round the clock.
Water coolers shall be installed for labor.
Separate messing facility shall be arranged for labor and supervisory/managerial staff,
where free of cost good quality food shall be served as well as good hygienic
conditions shall be maintained.
Garbage cans and refusal collection container shall be placed for collection of waste.
The Contractor shall arrange tractor trolley to transfer waste from Camp to the
recommended waste dumping site.
Rain water drainage shall be established for proper disposal of water in rainy season.
Drinking water free of any contamination shall be provided at all locations of the
Camp.
Dengue/Mosquitoes/Disinfecting Chlorinated sprays shall be conducted frequently in
all living areas of the Camp.
Kitchens
HSE Staff shall ensure periodic checks of the cooking staff, particularly for symptoms
of hepatitis B, C and HIV AIDS.
All the cooking places shall be enclosed with fly’s net or covered lids
Dining Areas
Dining areas shall be spacious, airy and well lighted. All floors in the dining areas shall be
tile soled. HSE staff shall ensure that all dining areas, including those of the sub-Contractor’s
and canteens etc. will be fly proof and remain clean at all times.
For better hygiene and sanitation, temporary sewerage shall be laid down which shall culminate
in septic tank(s) and soakage pit(s). A separate sewage system shall be established for each
living/accommodation facility of Camp and shall be kept well maintained. Likewise,
wherever necessary, open drains shall be constructed in the Camp for the disposal of rain
water.
With a large number of vehicles and other similar machinery a repair workshop is essential. The KNK-
SMC (JV) will establish own workshop. The plant shall be at least five hundred meter away from the
any population dwellings, water resources and sensitive receptors. Before finalizing the asphalt plant
and batching plant sites labour camp site, the contractor will obtain the permission from PMU/CIU. A
due diligence report will also be prepared for this purpose
Given the prevailing security condition in the project area, security staff is necessary.
Adequate security will be provided by the M/S KNK –SMS (JV) at Camp, Labor
Camp, Material Store, Equipment Yards and location of the work in progress on the
work site. Coordination will be necessary with nearby law enforcing agencies.
First aid arrangements shall be ensured at Camp and Work Sites. The first aid provider (or
nominated person who has been trained in giving first aid) at sites shall perform following
duties:
Keep all necessary first aid medicines and bandages in the first aid box.
Replace the medicines before their expiry dates to avoid any health hazard.
21 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Provide first aid to the injured in the event of accident
Immediately report any accident/incident to HSE Manager for necessary action
Call ambulance in case of any serious emergency.
Ring the emergency siren to make others alert about specific emergency.
Furnished dispensary shall be established at the Camp that shall remain functional
round the clock.
Paramedic staff shall be appointed in the camp dispensary round the clock.
Ambulance shall remain available at camp round the clock.
Dispensary shall be provided with all necessary medicines, first aid items and
equipment where free of cost medical treatment shall be given to all workers.
DHQ Hospital / CMH Sialkot, all nearby medical facilities along the project alignment shall
be taken on panel for the detailed medical examination of workers in case of any major
emergency
Sensitive receptors are generally considered to include those, where noise/dust exposure
could result in health-related risks to individuals, as well as places where individuals expect
silence to be an essential element of the location. Residential dwellings are of primary
concern because of the potential for increased and prolonged exposure of individuals to both
22 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
interior and exterior noise and potential sleep disruptions. Additional areas, such as parks,
historic sites, cemeteries, and recreation areas, are also considered sensitive to exterior noise.
Schools, mosques and other places of worship, hotels, libraries, nursing homes, and other
places where low interior noise levels are essential are also considered as sensitive receptors.
The majority of sensitive receptors in the study area are hospitals, mosques, schools and
residential dwellings, etc. An assessment of potential sensitive receptors within 500 meters
from the centreline was conducted along the project corridor. . Fig 3.0.below provides
sensitive receptor assessment area.
Construction would result in intermittent construction activities near the sensitive receptors.
These construction activities could potentially expose sensitive receptors to noise levels in
excess of the applicable noise standards or result in a noticeable increase in ambient noise
levels, or both. Impacts of construction equipment, noise, dust and construction-related traffic
on exposure of sensitive receptors to temporary and short-term construction related activities
are discussed separately below.
Construction noise levels in the study area would fluctuate, depending on the particular types
of equipment, the number of equipment used and the time duration of equipment use. The
effects of construction noise depend largely on the type of construction activities.
Construction generally occurs in several discrete stages, each phase requiring a specific
balance of equipment with varying equipment type, quantity, and intensity. Construction
equipment includes bulldozers; loaders; excavation equipment, such as graders and scrapers;
and compaction equipment. Erection of large structural elements and mechanical systems
could require the use of a crane for placement and assembly tasks, which may also generate
high noise levels.
To assess noise levels associated with the various equipment types and operations,
construction equipment can be considered to operate in two modes: mobile and stationary.
Mobile equipment, such as loaders, graders, and dozers, moves around a construction site,
performing tasks in a recurring manner. Stationary equipment is used to perform continuous
or periodic operations in a given location for an extended period, such as a batching plant,
pile driver etc. Thus, determining the effective acoustical center of operations for mobile
equipment during the construction process or the location of stationary sources during
specific activities is necessary when conducting a noise analysis. Operation of heavy
construction equipment typically is characterized by short periods of full-power operation,
then by extended periods of operation at lower power, idling, or powered-off conditions
Approximate
Predicted Noise at
Sources Distance of sensitive
Activities sensitive receptor
receptors from
dB (A)
construction site (m)
- - 70 79.8
- - 100 76.7
- - 175 71.8
- - 200 70.6
- - 500 62.7
- - 650 60.4
The M/S KNK- SMC (JV) will implement the following measures during construction
activities when noise-sensitive receptors are located nearby;
This section provides an overview of the policy framework and national legislation that
applies to the proposed up gradation of roads project in Sialkot. The project will comply with
all national legislation relating to the environment in Pakistan and will obtain all the
regulatory clearances required from the financing agency, ADB.
The Pakistan National Conservation Strategy (NCS) that was approved by the federal cabinet
in March 1992 is the principal policy document on environmental issues in the country
(EUAD/IUCN, 1992). The NCS outlines the country's primary approach towards
encouraging sustainable development, conserving natural resources, and improving efficiency
in the use and management of resources. The NCS has 68 specific programs in 14 core areas
in which policy intervention is considered crucial for the preservation of Pakistan's natural
and physical environment. The core areas that are relevant in the context of the proposed Up
gradation of Roads Project are pollution prevention and abatement and increasing energy
efficiency while conserving biodiversity.
Prior to the adoption of the 18th Constitutional Amendment, the Pakistan Environmental
Protection Act (PEPA) 1997 was the governing law for environmental conservation in the
country. Under PEPA 1997, the Pakistan Environmental Protection Council (PEPC) and Pak
EPA were primarily responsible for administering PEPA 1997. Post the adoption of the 18th
Constitutional Amendment in 2011, the subject of environment was devolved, and the
provinces have been empowered for environmental protection and conservation
Under Section 12 (and subsequent amendment) of the PEPA (1997), a project falling under
any category specified in Schedule I of the IEE/EIA Regulations (SRO 339 (I0/2000),
requires the proponent of the project to file an IEE with the concerned provincial EPA.
Projects falling under any category specified in Schedule II require the proponent to file an
EIA with the provincial agency, which is responsible for its review and accordance of
approval or request any additional information deemed necessary
The National Environmental Quality Standards (NEQS), 2000, specify the following
standards:
Maximum allowable concentration of pollutants (32 parameters) in municipal and
liquid industrial effluents discharged to inland waters, sewage treatment facilities,
and the sea (three separate sets of numbers);
These standards apply to the gaseous emissions and liquid effluents discharged by
construction machinery.
The national laws and regulations are provided in Table 4.0 below
The ADB’s SPS 2009 requires that environmental considerations be incorporated into ADB
funded projects to ensure that the project will have minimal environmental impacts and be
environmentally sound. Occupational health & safety of the local population should also be
addressed as well as the project workers as stated in SPS. A Grievance Redress Mechanism
(GRM) to receive application and facilitate resolution of affected peoples’ concerns,
complaints, and grievances about the project’s environmental performance is also established.
All loans and investments are subject to categorization to determine environmental assessment
requirements. Categorization is to be undertaken using Rapid Environmental Assessment
(REA) checklists, consisting of questions relating to (i) the sensitivity and vulnerability of
environmental resources in project area, and (ii) the potential for the project to cause
significant adverse environmental impacts. Projects are classified into one of the following
environmental categories:
ADB’s new Access to Information Policy (AIP), reflects the ADB’s ongoing commitment to
transparency, accountability, and participation by stakeholders. The policy contains principles
and exceptions to information sharing with external stakeholders, led by a new overarching
principle of “clear, timely, and appropriate disclosure.”
‘Environmental issues during the construction and operation of roads are similar to those of
other large infrastructure projects involving significant earth moving and civil works and
their prevention and control recommendations are presented in the General EHS Guidelines.
These impacts include, among others, construction site waste generation; soil erosion and
sediment control from materials sourcing areas and site preparation activities; fugitive dust
and other emissions (e.g. from vehicle traffic, land clearing and movement, and materials
stockpiles); noise from heavy equipment and truck traffic; and potential hazardous materials
and oil spills associated with heavy equipment operation and fuelling activities.’’
World Bank Environmental Health and Safety (EHS) Standards-ADB advocates adherence to
environmental standards set out in the World Bank Group Environmental, Health and Safety
Guidelines (EHS Guidelines) of which the following are most applicable to these road
improvement project:
Following table gives the detail of environmental issues and their related mitigation measures
that are required to be considered during project execution. The cost for implementation EMP
will be utilized for implementation of EMP under the provision of Contract
practices will be
ensured at storage and
workshop areas.
It will ensured that
the mixing of waste in
to fresh water sources
shall not be allowed.
(averaged).
Schools /
Hospitals
Concerns.
community.
Traffic Management
plan will be prepared
and approval will be
taken from the
Engineer.
Construction material
will be covered while
transportation.
If vehicles and
equipment repairing
in the field will be
unavoidable then
impervious sheath
will be used to avoid
soil and water
contamination.
driving. PMU.
Traffic speed 15 km /
hr. will be maintained
near and within the
community.
As far as possible
clearing of area will
be avoided where soil
is highly erodible and
steeps and slops are
prone to water and
wind.
Dismantled asphalt
pavement will be
dumped to the waste
sites.
Excavation works
will be carried out
progressively and re-
vegetation done at the
earliest.
material will be
contained with best
handling practices
and strict skilled
supervision.
Appropriate water
and sanitation
facilities will be
provided inside the
camp.
Proper Sewerage
disposal arrangements
will be provided such
as septic tanks and
soakage pits at camp
site.
The construction safety plan for the project covers the safety and health policy, safety rules,
job safety training, vehicle safety, hazard communication program, etc.
The construction safety plan for the project covers the safety and health policy, safety rules,
job safety training, vehicle safety, hazard communication program, etc.
Contractor and sub-contractors shall familiarize their staff and work crews with known
hazards on jobsites, provide training, and ensure work proceeds in a safe and secure manner.
Jobsite rules must be followed and no work shall be conducted in an unsafe manner or unsafe
environment. Project and contractor staff shall not tamper with or otherwise render any
safety or security measure ineffective, which include alarms, signage, notices, guardrails,
lighting, or any other measure.
Contractor shall ensure that hazard analysis and vulnerability assessments are undertaken and
completed, and that mitigations of hazards and vulnerabilities are implemented. Any
hazards or vulnerabilities that cannot be mitigated to an acceptable risk level must be
communicated to all work crews and visitors.
The variety of safety and security events, impacts, locations, levels of severity, and
combinations with other elements or other emergencies makes it impossible to define and
plan for every scenario. However, general types of events can be identified that may be faced
by contractors, whether natural (e.g., flooding), accidental (e.g., fall), intentional (e.g., theft),
or technological (e.g., communications failure). Contractor Construction Safety and Security
Plan (CSSP) must adequately address reasonable possibilities. Listed below are safety and
security events and emergencies for which Contractor shall be prepared to respond to.
Proper signage shall be placed on the exterior of each worksite so that persons approaching
the site from any area, sidewalk or known or anticipated access point are sufficiently
informed that they are approaching a controlled area. Signage must identify the site as a
worksite, with restricted public entry, and warn of the potential dangers. A phone number
must be provided for notification of hazardous or emergency conditions or to report
suspicious or inappropriate activity.
Signage shall be placed within the site prohibiting unauthorized crewmembers from operating
machinery or equipment for which they are not qualified or trained, informing site crews and
visitors of PPEs requirements and any other safety or security requirements. Appropriate
access controls shall be implemented at all worksites. Access control shall include barriers,
fencing and gates or other methods to prevent unauthorized individuals and vehicles from
entering the worksite.
All worksites on and along public roadways shall provide physical separation through traffic
control and pedestrian control, using barrels, barriers, tape, signage, or other means as
appropriate. Work performed in close proximity to traffic must comply with all Standard
Operating Procedures (SOPs) set by the Contractor. Work zones must be adequately
protected from live traffic.
Contractor shall keep entry/exit records of all construction work zone visitors. Each visitor
shall be briefed and trained as appropriate about concerned hazards and dangers present at the
work site before they are allowed to enter. All authorized work site visitors shall be required
to wear PPEs.
No person shall be working on or otherwise present at any contractor construction site while
under the influence of alcohol or any prescription drug that was not specifically prescribed to
that person and taken in the directed amounts. No person shall operate any vehicle or
machinery, or work in hazardous areas while under any narcotic or drug that impairs
judgment or cause dizziness or drowsiness unless there is written approval by the attending
physician. Particular concern shall be applied if this individual performs a safety sensitive
role and or operates equipment or machinery at the job site. Any person found in such
condition must be immediately removed by the site foreman. Contractor shall enforce all
alcohol and drug-free workplace policies and requirements.
The use of illegal drugs and alcohol is strictly prohibited on all contractor construction
project sites. As part of their CSSP, construction contractors and all subcontractors are
required to have a Program that addresses the prohibited use of alcohol and drugs, including
pre-placement, periodic, for cause, and post-accident/incident testing.
51 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
6.5 Fall Protection
Contractors are committed to 100% continuous fall protection, whenever workers are
exposed to fall hazards of six feet (6') or greater. This policy applies to all personnel working
for or on behalf of Contractors.
Contractors will take all practical measures to eliminate, prevent, and control fall
hazards. All work will be planned with the intent to eliminate identified fall hazards.
When a fall hazard has been identified, and cannot be eliminated, then effective
means of fall protection will be implemented.
Employees who are exposed to falls of six feet (6’) or greater while working on
scaffolds, elevated decks, elevated platforms, low-slope roofing, stairways, stairwells,
reinforced steel, and any other elevated area or equipment, and excavations with a
slope greater than 40 degrees will be protected from falls. There is no set safe distance
from a leading edge or perimeter that would exempt a worker from fall protection.
Any employee who must remove a guardrail, wall or floor opening cover, or other fall
protection system in the course of their work will be responsible for providing interim
protection for themselves as well as others and immediately replacing the protective
system when their work is complete, during breaks or at the end of the work shift.
When no other practical means of fall protection can be used, employees will be tied
off at all times utilizing a personal fall arrest system.
Employees may work from ladders without personal fall protection when the
following criteria are met:
Working at height does not exceed 6 feet.
Work can be performed without reaching beyond the side rail limits of the ladder.
(Worker remains inside the area between the vertical side rails)
Ladder is properly tied off/secured or in the case of a stepladder; legs are fully
extended and spreaders are locked.
Amber warning lights shall be used on all vehicles in work zones to identify them in
protected areas from adjacent traffic and other work or construction vehicles and to improve
their visibility within traffic areas
The use of any toxic materials must be properly labeled, handled only with proper PPE and
used as directed by the manufacturer and in compliance with the MSDS. All hazardous
materials, if stored on site, must be properly stored in safe, designated locations in
appropriate containers, and shall be adequately protected from inappropriate access.
MSDS for all materials used on site must be kept at the worksite and will be available in case
of accidental or intentional release or exposure. Contractor safety and security personnel shall
be advised as to what material is on site and where within the site it is located to allow for
52 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
any PPE or ventilation requirements that must be followed when patrolling or handling such
material. All hazardous materials shall be disposed of through proper means and locations
based on the material type.
All tools and equipment shall be either securely locked up each day before leaving a worksite
or shall be removed from the site. No machinery or equipment shall be left unsecured and
unattended such that a non-authorized person may move, start, and/or operate such machinery
or equipment.
6.8.1 Lighting
All worksites shall have adequate lighting to provide a safe and secure working environment.
If natural light is insufficient for the task or to provide a safe environment and to support
police, security, or patrols of worksites, supplemental lighting will be provided
All personnel, including visitors to the work site locations associated with the project, shall
wear the following minimum PPE:
Temporary fire protection measures, such as fire extinguishers will be installed at required
places. If a fire extinguisher is discharged for any purpose, it will be reported to a supervisor
and removed from the work area.
Only authorized person will be allowed to deal the machinery while refuelling
Immediate and appropriate action is the key to preventing major losses due to fires. If a fire
occurs, call HSE Staff immediately and assist with evacuation of the area if necessary. If
possible, remove or shut off the fuel source such as removing debris or material or shutting
off the fuel supply. Evacuation routes shall be kept clear. After the fire has been extinguished,
a thorough investigation shall be conducted and documented.
The project activities shall include procedures to address severe weather that affects
construction sites, including the protection of machines/equipment and the crew working on
location. Protection and hydration will be provided for workers in extreme heat. Rain must
not be permitted to enter electrical equipment, which may cause electrocution to the user.
All equipment, tools and materials will be stored, stacked, located, placed, temporarily
spotted, or set up for manipulation in such a manner as to render it highly improbable that an
accident/incident or injury could occur in the work area. The following measures regarding
housekeeping will be taken;
All material, spoils, debris, etc. is to be cleaned-up as it accumulates and at the end of
each work shift.
Accumulation of trash and debris will not be tolerated.
Access walkways, roadways, and fire lanes will not be blocked with material, tools,
ladders, scaffolds, welding leads, air hoses or electrical cords.
In view of the present security situation, the Contractor will have to make necessary security
measures to avoid the risk of security. Due to the uncertainty of the attacker the measures for
security will be with the orientation of precaution. The following precaution measures will be
taken strictly.
All camps will be fenced with temporary arrangement and at the entry of fenced the
camp, security guards will be deployed for the security checking. All persons who
The Contractor shall develop a health, safety and security training program and provide
instructional health, safety, and security training for all staff working at construction sites.
Training shall advise all employees at construction sites of the potential hazards on the site;
the knowledge and procedures to identify, mitigate, and/or avoid such hazards; and actions to
be taken in the event of a health, safety, or security incident.
All trainings shall be conducted by a qualified competent person familiar with the work and
hazards at the job sites, and deemed competent in terms of education, relevant experience,
and instructional capability.
Contractor shall do internal audit & review to ensure compliance with this Plan and the
Contractor’s CSSP, to ensure a safe, healthy, and secure environment, both physically and
behaviorally, for workers, equipment, property, visitors and the general public at and near
work sites. Internal audit maybe (i) At least once every year; (ii) after a major safety or
security incident.
A Tool Box Talks (TBT) is another term for a safety meeting. The term “TBT” was
originally used as a way to encourage building workers to have a regular documented safety
meeting. The best time to do this was considered to be when they stood around the tool box
in the morning before starting work, so the term TBTs was born.
Today the TBT is widely accepted as a common way of ensuring consultation occurs between
workers, and is a practical way to raise workers’ awareness of specific problems on site. It
also helps to remind workers that health and safety are an important part of the working day.
TBT should be scheduled as needed, depending on the level of risks faced on the job, or the
levels of experience of the workers. Management should assess how often and for how long
TBT should be held in your company.
The TBT should generally, but not necessarily, be conducted by an employee of supervisory
level or with basic Occupational Health & Safety (OHS) awareness. Any issues raised that
cannot be resolved should be addressed by senior management.
The following information should be included when completing a TBT Form, TBT form is
attached in Fig 6-1
Names and signatures of all persons present – this is important to show who has
participated in the meeting,
Topics discussed - this shows what topics were covered during the meeting,
any job specific training or instructions that have been given in the meeting, and
Who raised the issue or added to the discussion, to show that there has been active
consultation with all persons attending the meeting, and that all parties have had a
chance to raise issues rather than the TBT just being a lecture conducted by the
supervisor
56 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Figure 6-3 - Toolbox Talks Form
The objective of this ERP is to develop a plan and corresponding response procedures and
mechanism which will ensure emergency preparedness and provide means for mitigating the
consequences of emergencies, including very low probability events, in order to protect the
health and safety of the general public and working personnel.
Following is a list of the hazards and emergency situations, which need planning and proper
handling to minimize their risks.
Fire,
Road Traffic Accidents,
COVID-19 Pandemic
Materials/ effluents spills i.e. chemical, POL, etc.,
57 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Natural disasters i.e. torrential rains, floods, earthquakes,
Occupational accidents i.e. fall from heights, electrocutions, cave-ins,
Arsons, vandals,
Terrorist attacks, etc.
Put in place effective arrangements for the planning, organization, control, monitoring
and review of health and safety measures in the workplace. Such arrangements should
be recorded if there are more than four employees. Employ (to be preferred) or
contract competent persons to help them Comply with health and safety duties.
Develop suitable emergency procedures, which ensure that employees and others are
aware of these procedures and can apply them.
Provide health and safety information to employees and others, such as other
employers, the self-employed and their employees who are sharing the same
workplace and parents of child employees or those on work experience.
Co-operate in health and safety matters with other employers who share the same
workplace.
Provide employees with adequate and relevant health and safety training.
Provide temporary workers and their contract agency with appropriate health and
safety information.
Provide safe plant and equipment.
Provide safe means of access/egress.
Provide safe work environment.
Provide adequate welfare facilities.
Provide written statement of Health and Safety Policy, including precautionary
measures for COVID-19
Ensure safety of workers dealing with hazardous substances (during storage,
transportation, use, disposal etc.).
Provide competent staff.
The Contractor’s on-site in-charge shall be responsible for handling emergency situations for
concerned site. He will act as Emergency Response Coordinator (ERC) and shall be
responsible for ensuring that all subcontractors, staff, on-site visitors and others adhere to the
appropriate emergency response procedures as stated in this Plan.
Tble-6.1- on site Nominated Officer for emergency
6.19 Preparedness
Emergency Response Team shall be formatted at all camps, each team comprised of 3 or 5
members including and lead by the ER Coordinator or the concerned person in-charge. All
the members of the ER Team shall be trained in basic First Aid, search & rescue and
firefighting; that will further provide search & rescue, first aid and arrange transportation in
case of accidents and emergencies, and extinguish fires, guide workers and staff to assembly
points and other safe places. The ERT shall assist the ER Coordinator in accidents
investigation. The contact details of the ERTs shall be posted at prominent places so that all
workers are aware of them. The contact details of is provided in section 8.24 “Emergency
Contact Numbers”.
There is an ongoing pandemic of Novel Coronavirus (COVID-19) in Pakistan which was first
notified on 26 February 2020. As of 14 April 2020, over 5,719 cases with 96 deaths (CFR
1.68%) had been reported. The pandemic has spread to all provinces in Pakistan with over
115 districts affected, largely in Punjab and Sindh. ERT will thouroughly review and adopt
preparedness plan in light of the COVID-19 Pakistan Preparedness and Response Plan
(PPRP) (available at https://reliefweb.int/report/pakistan/pakistan-preparedness-response-
plan-covid-19).
Table-6.2- Detail of Emergency Response Team
In case of any emergency, Safety Manager or designated person will be authorized to contact
the external public safety agencies/emergency services. Following are the contacts of
emergency services.
Fire departments 16
Police 15
Edhi Rescue 115
Rescue 1122
COVID-19 Helpline 1166
The EA (PID) will formulate an Environmental & Social Management and Monitoring cell
(ESMMC) which is comprising of senior professionals, and should preferably have
representative from various line departments including Forest, Wildlife and local
administration. The cell should also include at least one technical expert from research and
development (R & D) Institute.
The following staff will be involved in the implementation of EMP.
EPD Punjab is a regulatory authority for issuance of NOC for this Project. As part of its
mandate, protection of environment (water, air and noise) is its responsibility. Therefore, this
agency will undertake an audit (as when required) of project activities with respect to the
protocols as defined in EMP
Project Director will have responsibility for assuring implementation of EMP. This includes
the following:
The CIU will support the Municipal Corporations of Sialkot in the following aspects:
The MC will:
Approve and implement all reforms related system, organizations, plans, and
programs as required for the project including service delivery arrangements;
Transfer assets and completed civil works to WSCs/USCs, as required for the
projects and agreements;
Fill all vacancies in the MC, as per approved organogram and facilities required
for CIU and Staff.
Its contractor contractual obligation to appoint site Environmental Engineer / Manager with
relevant educational back ground and experience. Contractor Environmental Engineer /
Manager will carry out the following activities.
The HSE Manager with assistance of his HSE team shall perform following duties.
Daily inspection of all workplace areas and make sure the safe execution of the
ongoing activities.
Address the causes of any NCR issued to the Contractor taking adequate steps for
rectification.
Ensure maximum local employment at camp and site.
Ensure that hygienic food is served to the labor at an affordable and reasonable price
Ensure proper living facilities have been provided to labor and staff at site.
Ensure proper disposal of waste water and sludge.
Ensure Water Sprinkling water at all the time to suppress the dust emission.
Conduct trainings and internal audits with the Contractor staff to minimize the non-
compliances.
To take reasonable care for the health and safety of themselves and of other persons who may
be affected by their acts or omissions at work. This involves the same wide group that the
employer has to cover, not just the people on the next desk or bench.
To cooperate with employers in assisting them to fulfill their statutory duties.
Not to interfere with deliberately or misuse anything provided, in accordance with
health and safety legislation, to further health and safety at work.
The Contractor shall ensure that adequate environmental awareness training of seniors, site
personnel takes place and that all construction workers receive an induction presentation on
the importance and implications of the EMP.
The presentation shall be conducted, as far as is possible, in the English/Urdu language. The
trainings will be conducted on quarterly basis for each defined working groups. As a
minimum, training should include:
A suitable training program is proposed to train the Contractor staff who will be involved in
the Construction Phase and the professional staff from the proponent involved at the
operational stage of the Project.
Table 7.1 Detail of Environmental Awareness Training
Standard format will be developed and utilized for recording information during the
environmental and other aspects monitoring. The Project data will include information
regarding following aspects:
7.13.2 Meetings
The following environmental meetings during the Project will take place. Primary meeting
will be done for setting out the requisite end frame sounding for the regular meetings.
Scheduled meetings between Contractor and Supervising Consultants will also take place.
The purpose of the meeting will be to discuss the conduct of the operation, non –
compliances noted by the consultant’s environmental team and measures for their remedy.
The meeting will be recorded in the form of a daily/monthly environmental report.
The Contractor will maintain a complaint register at the Camp where complaints record from
local communities will be registered and measures shall be taken by the Contractor to
mitigate these concerns. Contractor’s HSE Manager shall check the register on daily basis
and deploy resources to mitigate the registered complaints on prior basis.
The Contractor’s HSE Manager shall maintain photographic records during the
implementation EMP/SSEMP that will be reflected in monthly based HSE Progress Report.
As a minimum, the photographic records will include the site photographs, all the roads,
camp sites and monitoring activities etc.
Prepare the monthly based Environmental Monitoring / HSE Progress Report that will
include detailed implementation procedures and practices regarding EMP/SSEMP/HSE
67 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
management along with sufficient supporting photographic evidences. The Contractor will
submit this report to the SC’s Environmental Engineer/Scientist and he will be responsible
for submitting monthly compliance report for the Project to the Project Director (PD), who
will submit it ultimately to regulatory body. The reporting mechanism to be followed during
construction phase is summarized in table below
Environmental Prepared by
Monitoring / HSE Monthly Contractor, PMU, PID
Progress Report Reviewed by SC
The costs associated with implementation of the EMP and the necessary mitigation
measures are provided as Table 7.3 below. Below provided table shows the ‘Capacity
development and training programme’ for project contractors for the proposed project.
Below provides cost estimates for ‘Pre-Construction phase’ monitoring while later on
tables provides cost estimates for ‘Construction phase’ and ‘Operation phase’
monitoring of key environmental parameters.
8 RISK ASSESSMENT
8.0 Summary:
Risk assessment and management techniques will be adopted so that potential hazards are
identified and evaluated prior to execution of critical job or the job which is going to be
conducted first time. In the Risk Assessment Matrix, the environmental impacts and the
control measures are explained with respect to the construction activities. Special attention
needs to be paid during construction with adequate protection, to create friendly environment.
These potential risk activities can damage the community badly if not controlled. In order to
prevent or mitigate any potential adverse impacts of the construction, it is necessary to
implement the recommendations.
On the most common failures of environmental management is that the construction teams
have no guidance as to what environmental management measures are required and so there
is a high probability that environmental damage will occur. Once the damage has taken place
it is often impossible to put right again, therefore the environmental management measures
have failed right at the point when they are most needed. It also becomes difficult to retrofit
the environmental management requirements after the construction activities have started.
Proper planning is therefore essential.
Risk assessment and management are used interchangeably to describe a sequence of analysis
and management activities focused on creating a project-specific response to the inherent
risks of developing a new capital facility. The objectives of Risk Assessment for this
construction phase SSEMP are described in Table 8-1 below.
The risk identification process identifies and categorizes risks that could affect the project.
The objective of risk identification is the early and continuous identification of events that, if
they occur, will have negative impacts on the project ability to achieve performance or
capability outcome goals. The tools and techniques outlined in this chapter will support the
risk identification process, but it will be the people involved in the exercises who are most
critical to the success of the process.
Risk is assessed as the likelihood that the activity will have an effect on the environment as
well as the consequence of the effect occurring, as described below:
Risk = Likelihood1 X Consequence2
The above model is adoptive from ADB - Environmental Management for Construction
Handbook. Any Medium to Significant risk requires an environmental management measure
to manage the potential environmental risk. Judgment will be required concerning the
application of an environmental management measure to mitigate low risk situations.
Risk identification, assessment, and analysis exercises form the basis for sound risk response
options. A series of risk response actions to avoid or mitigate the identified risks is considered
as follows:
Table 8.2 - Likelihood Scale
Will occur more than once or twice during the activity but less
B Likely 3
than weekly if preventative measures are not applied
All the risks assessed are handled by providing mitigation, management or both. Special
consideration and specific management sub plans are formulated for moderate and major
risks.
Construction Activities
Site Surveying
Earth work
Mechanical Works
will be carried
out
progressively,
so that re-
vegetation done
at the earliest.
Top soil
management,
stock piling and
removal of top
6” inches to
preserve in a
condition as
near as possible
to its pre-
project
condition in
order to allow
successful land
rehabilitation
for example
during summer
when intense
rain storm are
common.
Vehicles,
machinery
movement will
be kept on well
define haul
roads.
It will be
ensured that no
soil will remain
unconsolidated
after
completion of
work.
Deterioration of 3 3 9 Water
Air Quality due sprinkling will
to machinery be carried out
and equipment whenever
operation. required
particularly
near work sites
and local
communities to
avoid dust
pollution.
Burning of
cleared
vegetation will
be prohibited.
Proper tuned
machinery and
equipment will
be used for
Clearance of
vegetation to
meet the
requirement of
PEQS.
Vehicle’s speed
will be kept
minimum near
local
settlements and
at site.
Necessary PPE
i-e face mask
will be
provided to
workers
maintenance,
lubrication of
Machinery and
equipment will
be carried out.
In case high
noise level in
working areas,
Provision of
PPE like Ear
Plug or Ear
muffs and their
use will be
ensured by the
workers.
Noise 3 2 6 Vehicles
equipped with
exhaust muffler
(Silencers) will
be used for
construction
activities inside
the camp.
It will be
ensured that the
regular
inspection,
maintenance,
lubrication of
construction
vehicles and
equipment will
be carried out.
Provision of
PPE like ear
plug or ear
muff will be
ensured if
workers
execute the
work in noise
prone area i-e
Concrete
Batching
Operation.
Soil 5 3 15 It will be
Contamination ensured that the
due to chemical care and
spill. handling of
used oil and
80 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
chemical waste
will be carried
out in
accordance
with MSDS.
Chemical used
in construction
activities,
Mobil oil and
hydraulic oil
will be placed
on brick paved
bottom to avoid
soil
contamination.
Good
housekeeping
practices will
be ensured at
workshop areas.
Spills kits and
spill catching
trays will be
provided to the
mechanical
workshop crew.
Land 5 3 15 Disposal of
degradation due camp site waste
to Solid Waste near residential
Disposal of colonies or in
camp site. agriculture
fields will be
strictly
prohibited.
Camp Solid
waste will be
dumped at
dumping site of
TMA.
NOC will be
obtained from
TMA for
dumping of
solid waste.
Primary
collection bins
will be placed
inside the
camp.
Solid waste
management
plan (SWMP)
will be
described in
this document.
Before final
disposal of
solid waste, the
waste will be
stored in lined
secondary
storage pit.
Good
housekeeping
practices will
be promoted
inside the
camp.
Deterioration of 3 3 9 Water
air quality due sprinkling will
to machinery be carried out
and equipment inside the camp
operations. whenever
required
particularly at
grey road in
front of the
camp.
Vehicles speed
will be kept
minimum with
in the camp to
avoid
unnecessary
dust.
Necessary PPE
i-e face mask
will be
provided to
workers
Vehicles shall
be kept in good
working
condition and
properly tuned,
in order to
minimize the
exhaust
emissions.
near fuel
refueling unit.
Fuel storage
area will be
isolated and
entrance of
unauthorized
person will be
strictly
prohibited.
Only authorized
personnel will
be allowed to
deal with
machinery
refueling
process.
Firefighting
training will be
provided to the
camp staff.
First Aid
facilities will be
provided inside
the camp.
Ambulance will
be available in
side the camp
for 24 hrs.
Keeping in
view the health
of workers,
hygienic food
and safe
drinking water
will be
provided.
84 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
Safety
precaution will
be taken in to
account while
transporting,
handling and
storage of
hazardous
substance.
Insulation of
electrical wires,
switch boards
and electric
equipment will
be ensured
inside the
camp.
Contractor will
prepare HSE
Management
plan and get
approval from
the Engineer.
used for
dismantling
operations will
be well
maintained.
Provision of
PPE like Ear
Plug or Ear
muffs and their
use will be
ensured by the
workers.
Nearby local
community will
be well
informed
regarding noise
generation.
Community 3 3 9 Demarcation
safety tapes will be
installed around
the dismantling
activity to avoid
any
unauthorized
entry.
Restrict public
to enter into
dismantled site
through fixing
of various
warning
signs/banners &
temporary hard
barriers.
No machinery
will be left
unattended,
particularly in
running
condition.
Permission will
be granted to the
concerned
department
before any
dismantling
activity.
Public
consultation will
be carried out
with nearby
communities
87 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
before starting
dismantling
activity.
check and
maintained in
good condition.
Necessary
training or
toolbox talks
will be given to
the workers
regarding the
dismantling
activities.
Waste 5 3 15 Disposal of
89 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
management construction
and disposal waste will be
done at properly
designated
landfill/disposal
sites.
For disposal of
construction
waste, the site
will be
identified and
before disposal
approval will be
taken from
Resident
Engineer.
Disposal will be
not allowed in
agriculture land.
equipment will
be carried out to
minimize noise
at working site.
Provision of
PPE like Ear
Plug or Ear
muffs and their
use will be
ensured by the
workers.
Public
Consultations
will be carried
out with nearby
Community,
schools and
hospitals if any
to minimize
tress passing of
peoples in
working areas.
Local
community will
be well
informed in case
of night traffic.
avoid dust
pollution.
Well maintained
and tuned
vehicles will be
used for the
transportation
and disposal of
borrow material.
Vehicle’s speed
will be kept
minimum with
in project
vicinity.
Necessary PPE
i-e face mask
will be provided
to workers
equipment will
not hamper the
traffic at main
road near
borrow areas
and sites.
As far as
possible,
haulage route
for
transportation
of borrow
earthen material
will be selected
away from the
community.
Necessary
training,
information
will be
provided to the
workers
regarding
traffic rules.
Flag man will
be present near
borrow sites to
keep safe
smooth traffic
flow.
Engineer.
As far as
possible
material
borrowing from
agricultural field
will be avoided.
Before
extracting the
borrow material
written approval
/ permission will
be taken from
the Land owner.
As far as
possible the
waste land and
natural areas
with a high
elevation will be
used for
borrowing earth
material.
Top soil about
300 mm of
agricultural
borrow areas
will be stock
pile for
redressing.
Where deep
ditching is to be
carried out, the
top 1 m layer
will be stock
piled. The ditch
will be initially
94 | P a g e Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
Necessary
training and
toolbox talks
will be provided
to the workers
regarding work
at height.
Necessary PPE
will be provided
to the workers.
Earth work
operations will
be carried out in
supervision of
competent
person.
generators and
equipment will
be carried out.
Provision of
PPE like Ear
Plug or Ear
muffs and their
use will be
ensured by the
workers.
Necessary
training and
information will
be provided to
the drivers
regarding
unnecessary use
of pressure horn
near local
community.
Public
Consultations
will be carried
out with nearby
schools and
hospitals if any
Local
community will
be well
informed in case
of night traffic.
workers
regarding
traffic rules.
construction
vehicles and
equipment will
be carried out.
Provision of
PPE like Ear
Plug Ear muffs
and their use
will be ensured
by the workers.
Public
Consultations
will be carried
out with nearby
schools and
hospitals if any
Local
community will
be well
informed in case
of night traffic.
clothing for
workers at sites
that work in
areas with high
active traffic.
Any works at
night should be
adequately lit
and workers
worn high
visibility
clothing.
Contractor
should provide
basic training on
use of protective
clothing and
equipment.
Contractor will
ensure the
provision of first
aid boxes at
construction
site.
Necessary
training or
toolbox talks
will be given to
the workers
regarding the
work activities
and portable
electric
equipment used
in construction
works.
102 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
Work at height
will be carried
out in
supervision of
trained
supervisors and
with full
protection.
Excavation
operation will be
supervised by
competent
person, flooding
inside the
excavated areas
will be
controlled by
dewatering.
Excavation
areas will be
barricaded to
protect the
workers from
fall in hazard.
Movement of
vehicles near
excavated areas
will be strictly
prohibited to
keep the
excavation safe
from collapsing.
Contractor will
ensure
insulation of
electric wires,
103 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
switch boards
and electric
equipment used
at construction
site.
Community 5 2 10 Demarcation
safety tapes will be
installed around
the Construction
activity to avoid
any
104 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
Construction Likelihood Consequences Risk Score: Environmental
Issues to
(Consequence X Mitigation
Activity Consider
Score Score Likelihood) Measures
unauthorized
entry.
Restrict public
to enter into
construction site
through fixing
of various
warning
signs/banners &
temporary hard
barriers.
No machinery
will be left
unattended,
particularly in
running
condition.
Public
Consultation
with the nearby
community will
be carried out
before the start
of construction
activities
flood carrier
channels.
It will be
ensured that the
regular
inspection,
maintenance,
lubrication of
construction
vehicles and
equipment will
be carried out.
Provision of
PPE, like Ear
Plug, Ear muffs
and their use
will be ensured
by the workers.
Public
Consultations
will be carried
out with nearby
schools and
hospitals if any
avoid dust
pollution.
Contractor will
keep the
working
machinery and
equipment in
well-tuned
condition.
Vehicles speed
will be kept
minimum with
in project
vicinity.
Necessary PPE
i-e face mask
will be provided
to workers
traffic rules.
machine
operators and
workers.
Necessary
training or
toolbox talks
will be given to
the workers
regarding the
work activities.
provided to the
workers
regarding
traffic rules.
protective masks
to the machine
operators and
workers.
Necessary
training or
toolbox talks
will be given to
the workers
regarding the
work activities.
workers.
Public
Consultations
will be carried
out with nearby
schools and
hospitals if any.
Community 3 3 9 Demarcation
Safety tapes will be
installed around
the working area
to avoid any
unauthorized
entry.
Restrict public
to enter into
construction site
through fixing
of various
warning
signs/banners &
temporary hard
barriers. No
machinery will
be left
unattended,
particularly in
running
condition.
Public
Consultation
with the nearby
community will
be carried out
before the start
of construction
activities
regarding the
work activities.
Community 3 3 9 Demarcation
safety tapes will be
installed around
the working area
to avoid any
unauthorized
entry.
Restrict public
to enter into
working site
through fixing
of various
warning
signs/banners &
temporary hard
barriers. No
machinery will
be left
unattended,
particularly in
running
condition.
Cumulative impacts are deemed to occur when the effects of project components, other
projects, and/or other land use activities overlap with each other by affecting the same Valued
Environmental and Social Component (VESCs). That is, cumulative impacts are the
incremental impact of the project when combined with the cumulative effects of other past,
present and reasonably foreseeable future projects.
Cumulative impacts can also be due to the induced actions of projects and activities that may
occur if the action under assessment is implemented, such as growth inducing impacts and
other effects related to induced changes to the pattern of future land use or additional road
network, population density or growth rate. Induced impacts are those that arise indirectly as
a consequential effect of the project. They usually have no direct relationship with the action
under assessment and represent the growth-inducing potential of an action. For example,
roads leading from those constructed for a project, increased recreational activities, and
construction of new service facilities are examples of induced actions.
All upgrades to existing infrastructure and new works are proposed within existing
landholdings, existing structures or existing rights of way. There are accordingly no
cumulative impacts on physical, ecological or social resources in any of the areas subject to
development or redevelopment, since all of these areas have been intensively developed in
the past and are highly urbanized
Residual Impact
Provided the proposed mitigative measures are implemented, the air and climatic impacts
during operational phase will be short term and moderate. Therefore, no significant adverse
residual environmental impacts are likely to occur.
Also as and
when
required
visual
inspection;
basis for the
activities
generating
dust
pollution.
Once before -
construction
Groundwater Construction to establish
(suite of camps where PEQs baseline & Contractor
Ground Water Contaminants
ground water
given in EIA) is utilized Quarterly
for drinking during
by labour. construction
by EPA
Approved
Laboratory at
approximate
2 points.
Once before -
construction
Selected to establish
Waste Water PEQs effluent baseline &
discharge
points at: PEQs Quarterly Contractor
Construction during
camp construction
location by EPA
where Approved
wastewater Laboratory at
is collected. approximate
Construction 3 points.
site
wastewater
(Slurry
121 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
waste water)
Final
Disposal
point.
10.0 General
1. The ADB Policy (SPS 2009) requires establishment of a local grievance redress
mechanism to receive and facilitate resolution of the Displaced/Affected Persons
concerns and grievances regarding the project’s social and environment performance.
The measures have been identified to mitigate any potential environmental and social
impacts to be caused due to implementation of the roads works.
2. However, in spite of best efforts, there is every chance that the individuals /
households affected by the project or other stakeholders are dissatisfied with measures
adopted to address adverse social impacts of the project. To address, such situation an
effective Grievance Redress Mechanism (GRM) will be established to ensure timely
and successful implementation of the project. It will also provide a public forum to
the aggrieved to raise their objections and the GRM would address such issues
adequately. It will receive, evaluate and facilitate the resolution of displaced persons’
concerns, complaints and grievances about the social and environmental performance
at the level of the project.
3. The GRM will aim to investigate charges of irregularities and complaints receive
from any displaced persons and provide a time-bound early, transparent and fair
resolution to voice and resolve social and environmental concerns link to the project.
4. The PIU shall make the public aware of the GRM through public awareness
campaigns. The name of contact person(s) and his/her phone number, PMU contact
numbers will serve as a hotline for complaints and shall be publicized through the
media and placed on notice boards outside their offices, construction camps of
contractors, and at accessible and visible locations in the project area. The project
information brochure will include information on the GRM and shall be widely
122 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
disseminated throughout the project area. Grievances can be filed in writing, via web-
based provision or by phone with any member of the PIU.
5. First tier of GRM. The PIU is the first tier of GRM which offers the fastest and most
accessible mechanism for resolution of grievances. The PIU staff for environment and
social safeguards will be designated as the key officers for grievance redressal.
Resolution of complaints will be completed within seven (7) working days.
Investigation of grievances will involve site visits and consultations with relevant
parties (e.g., affected persons, contractors, traffic police, etc.). Grievances will be
documented and personal details (name, address, date of complaint, etc.) will be
included, unless anonymity is requested. A tracking number will be assigned for each
grievance, including the following elements:
Initial grievance sheet (including the description of the grievance), with an
acknowledgement of receipt handed back to the complainant when the complaint is
registered;
Grievance monitoring sheet, mentioning actions taken (investigation, corrective
measures);
Closure sheet, one copy of which will be handed to the complainant after he/she has
agreed to the resolution and signed-off.
6. The updated register of grievances and complaints will be available to the public at
the PIU office, construction sites and other key public offices in the project area.
Should the grievance remain unresolved, it will be escalated to the second tier.
7. Second Tier of GRM. The PIU will activate the second tier of GRM by referring the
unresolved issue (with written documentation) to the Sialkot Waste Management
Company (SWMC) who will pass unresolved complaints upward to the Grievance
Redress Committee (GRC). The GRC will be established by SWMC before start of
site works. The GRC will consist of the following persons: (i) Project Director; (ii)
representative District; (iii) representative of the affected person(s); (iv) representative
of the local Deputy Commissioners office (land); and (v) representative of the PEPA
(for environmental-related grievances). A hearing will be called with the GRC, if
necessary, where the affected person can present his/her concerns/issues. The process
will facilitate resolution through mediation. The local GRC will meet as necessary
This chapter identifies the potential impacts due to the implementation of the proposed project on
the physical, ecological and socio-cultural environment of the proposed roads of Sialkot city and
the proposed mitigation measures to minimize the negative impacts, if any.
Potential impacts arising from design, construction and operation phase of grade separator has
been identified and assessed on the basis of field data, secondary data, expert opinion and
examining previous similar projects in Pakistan. These include effects on physical, biological and
socio-economic environments. Impacts associated with design, construction, operation and
phases of project components such as access road, piling for bridge have been detailed in the
section. The impact assessment has been carried in accordance with the requirements of Punjab
EPA, 2012 and ADB SPS, 2009.
Impact-screening matrices during each of the project phases i.e. project design, construction and
operation are presented below.
Risk is assessed as the likelihood that the activity will have an effect on the environment as well as
the consequence of the effect occurring. It is often described like this:
Risk = Likelihood × Consequence
Likelihood Scale
Will occur more than once or twice during the activity but less
Likely 3
than weekly if preventative measures are not applied
Consequence
Certain 25 15 10 5
Likelihood
Likely 15 9 6 3
Unlikely 10 6 4 2
Rare 5 3 2 1
Vehicles carrying construction material are expected to result in increased SPM levels near
the haul roads. This can be of potential importance if the vehicles pass through the areas with
a high concentration of sensitive receptors, such as residential areas, in this particular case.
At the construction site, the dust levels are also expected to increase due to unloading of
construction materials. It shall be ensured that most of the excavated material will be used
within the project, with minimal cut and fill material to come from outside the site.
Poor air quality due to the release of contaminants into the workplace can result in possible
respiratory irritation, discomfort, or illness to workers. Employers should take appropriate
measures to maintain air quality in the work area.
The quantity of dust that will be generated on a particular day will depend on the magnitude
and nature of activity and the atmospheric conditions prevailing on the day. Due to the
uncertainty in values of these parameters, it is not possible to calculate the quantity from a
‘bottom-up’ approach, that is, from adding PM10emissions from every activity on the
construction site separately.
Mitigation Measures
The following mitigation measures will be adopted for preservation of the environment:
At the project site and the immediately adjoining areas, water will be sprinkled
every three hours and at a higher frequency if felt necessary, at all construction
sites to suppress dust emissions.
All heavy equipment and machinery shall be fitted in full compliance with the
national and local regulations.
Stockpiled soil and sand shall be slightly wetted before loading, particularly in
windy conditions.
Fuel-efficient and well-maintained haulage trucks shall be employed to minimize
129 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
exhaust emissions.
Vehicles transporting soil, sand and other construction materials shall be covered
with tarpaulin.
Limitations to speeds of such vehicles as felt necessary. Transport through densely
populated area should be avoided.
Concrete plants to be controlled in line with statutory requirements and shall not
be close to sensitive receptors.
Stack height of generators will be at least 3 meters above the ground.
Project traffic will maintain maximum speed limit of 20 km/hr. on all unsealed
roads within project area.
A minimum distance of 300 meters will be ensured between batching plant(s) and
the nearest community.
The need for large stockpiles shall be minimized by careful planning of the supply
of materials from controlled sources. Stockpiles should not be located within 50 m
of schools, hospitals or other public amenities and shall be covered with tarpaulin
when not in use and at the end of the working day to enclose dust. If large
stockpiles (>25m3) of crushed materials are necessary, they should be enclosed
with side barriers and also covered when not in use.
Dust emissions due to road travel shall be minimized through good construction
practices (such as keeping stock piles down wind and away from communities)
and sprinkling water over the access road.
Maintaining levels of contaminant dusts, vapors and gases in the work
environment at concentrations below those recommended as TWA-TLV’s
(threshold limit value)-concentrations to which most workers can be exposed
repeatedly (8 hours/day, 40 hrs./week, week-after week), without sustaining
adverse health effects.
Developing and implementing work practices to minimize release of contaminants
into the work environment including:
Direct piping of liquid and gaseous materials
Minimized handling of dry powdered materials; Enclosed operations
Local exhaust ventilation at emission/release points
Vacuum transfer of dry material rather than mechanical or pneumatic
conveyance
Indoor secure storage, and sealed containers rather than loose storage
Where ambient air contains several materials that have similar effects on the same
body organs (additive effects).
For any earth moving that is to take place in the immediate vicinity
Earth Moving from the site boundary, watering must be conducted as required to
prevent visible dust emissions
Apply dust suppressants (clear vegetation only from areas where work
Inactive
is to commence, plant or mulch areas that will not receive traffic,
Disturbed
construct artificial wind breaks or wind screens) in sufficient quantity
Surface Areas
and frequency to maintain a stabilized surface
Water all roads used for any vehicular traffic at least twice per day
Unpaved Roads
during active operations and restrict vehicle speed to 20 kmph.
Residual Impacts
The impacts of dust generation and air emission of project is not expected to be significant
with the implementation of mitigation measures outlined above. Therefore, residual impact is
expected to be not significant
The up gradation of roads will result in different construction equipment and machinery
being used which will generate high noise levels at the project site.
The assessment of the noise impacts on the sensitive receptors that have been identified at
various locations in the project area depend upon:
Characteristics of noise source (instantaneous, intermittent or continuous in nature)
Each construction phase has its unique noise characteristics due to use of different equipment
items. The potential sources of noise during the preparation, construction, and worksite
closure phases for the upgradation of roads include equipment, machinery, and transportation
used for the construction activities. The equipment used for construction will be the major
source of noise.
The construction activities will include use of generators, excavators, concrete mixing trucks
and back up alarms, which can generate significant noise.
Since various modern machines are acoustically designed to generate low noise levels, any
high noise levels that might be generated will only be for a short duration during the
construction phase.
Depending on the construction equipment used and its distance from the receptors, the
community and the workers may typically be exposed to intermittent and variable noise
levels. During the day, such noise results in general annoyance and can interfere with sleep
during the night. In general, human sound perception is such that a change in sound level of 3
dB is just noticeable, a change of 5 dB is clearly noticeable, and a change of 10 dB is
perceived as a doubling or halving of sound level.
Due to the various construction activities, there will be temporary noise impacts in the
immediate vicinity of the project site. The movement of heavy vehicles, loading,
transportation and unloading of construction materials produces significant noise during the
The Table 11.2 below represents typical noise levels from various construction equipment
items. It should be noted that the values indicated in the table may differ depending on the
brand and age of machinery provided/used by construction company.
This Table 11.2 below is only indicative since at the Site-Specific Environmental
Management Plan (SSEMP) development stage, the Contractor will clearly define the
specific equipment to be used. However, it is clear that the scope and scale of works for the
road rehabilitation works will be quite minor. In this regard, since the construction works will
only be short term in nature, thus any potential noise generation during the construction
works will also be short term in nature and are not expected to significantly impact any
sensitive receptors that may be present along the project corridors.
Lastly, the mitigation measures already provided in the EMP will be implemented in true
letter and spirit to ensure that any potential impacts from noise are minimized as far as
possible.
Mitigation Measures
Excessive noise emitting equipment will not be allowed to operate and will be
replaced.
Impacts
During the project construction, spills of fuel, lubricants and chemicals can take place while
transferring from one container to another or during refueling. Also, during maintenance of
Depending on the nature of the material, location of spill and quantity of spill, the soil can get
contaminated.
Mitigation measures
It will be ensured that spill prevention trays are provided and used during
refueling. Also, on-site maintenance of construction vehicles and equipment will
be avoided as far as possible. In case on-site maintenance is unavoidable,
tarpaulin or other impermeable material will be spread on the ground to prevent
contamination of soil.
Impacts
The majority of the works proposed for upgradation of roads may result in soil erosion and
sedimentation. Earthwork excavation involves open cutting upto 5'-0" (1.5 m depth for storm
water channels, drains, sullage drains in open areas, roads, streets, lanes, including under
pinning of walls and shoring to protect existing works, shuttering and timbering the trenches,
dressed to design level and dimensions, trimming, back filing and surplus excavated material.
Mitigation measures
Any drainage structures, culverts or pipes crossing the project site may need to be
modified or protected and the detailed designs must make provisions to protect or
re-provision all infrastructure that may be affected by the construction works. The
surplus excavated material will be disposed on designated dumping sites, yet to
be identified by the metropolitan corporation.
135 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
11.5 Traffic Management
While the proposed project will make the road safer in some respects, the increase in traffic
and the potential for higher speeds may result in more road accidents especially in urban
areas where there is a potentially dangerous mix of non-motorized, two, three and four-wheel
traffic using the same carriageway.
Mitigation Measures:
Traffic calming measures and speed limit signage will be provided to reduce the
impact of the traffic.
Crossing areas will be marked and amber flashing lights installed in areas where
some population exists when full traffic signals are not warranted.
Improved traffic signage and road markings will be used to warn motorists of
impending changes in road standards and to advise appropriate speeds.
Properly designed traffic calming measures such as speed humps, speed signs
and, possibly traffic signals will be installed where settlements are nearest.
Traffic police should be trained to more consistently enforce road rules.
Residual Impact:
Provided the proposed mitigative measures are implemented, the accidents due to high speed
during operational phase will be short term and low. Therefore, no significant
Impacts
During the construction it is anticipated to construction waste material will be generated
which will require sustainable disposal. Therefore, waste disposal site/s should be identified
before to start the construction.
Mitigation Measures
Contractor shall submit and get approval for the waste management plan as well
as the dumping site/s for construction waste disposal.
Residual Impact
The impacts of lack of Waste / construction material dumping sites are not expected to be
significant with the implementation of mitigation measures outlined above. Therefore,
residual impact is expected to be not significant.
Impacts
There is invariably a safety risk when construction works are conducted, and precautions will
be needed to ensure the safety of the workers.
The major safety hazards expected during the proposed activities are as follows:1
Accident Hazards
Slips, trips and falls, especially while carrying heavy or bulky loads;
Burns caused by hot parts of equipment, steam lines etc, by release of hot water or
steam;
Physical Hazards
1
https://www.ilo.org/wcmsp5/groups/public/---ed_protect/---protrav/---safework/documents/
publication/wcms_192256.pdf
137 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
Exposure to cold and/or heat stress, as a result of rapid movement between cold
and hot areas;
Chemical Hazards
Biological Hazards
Exposure to parasites, such as hookworm, ascaris, and various mites, chiggers and
ticks;
General ill feeling as a result of work in confined spaces and development of ‘sick
building syndrome’;
Mitigation Measures
Provide on-site Health and Safety Training for all site personnel;
The Contractor will be required to prepare and implement an effective Worker Health and
Safety Plan that is supported by trained first aid personnel and emergency response facilities.
Construction contracts will include standard Worker Health and Safety measures and
contractors will be bound to implement these fully. This will include mandatory wearing of
dust masks for any cement handling operations or at any area were cement dust is in the air.
Monitoring will be required to ensure that the health and safety plan based on contract
specifications is followed. Cement feed hopper areas will be inspected daily to ensure
compliance with the requirement of dust masks.
Injury or death can occur from being trapped, entangled, or struck by machinery parts due to
unexpected starting of equipment or unobvious movement during operations. Recommended
protective measures include:
Designing machines to eliminate trap hazards and ensuring that extremities are
kept out of harm’s way under normal operating conditions. Examples of proper
design considerations include two-hand operated machines to prevent amputations
or the availability of emergency stops dedicated to the machine and placed in
strategic locations. Where a machine or equipment has an exposed moving part or
exposed pinch point that may endanger the safety of any worker, the machine or
equipment should be equipped with, and protected by, a guard or other device that
prevents access to the moving part or pinch point. Guards should be designed and
installed in conformance with appropriate machine safety standards.
Turning off, disconnecting, isolating, and de-energizing (Locked Out and Tagged
Out) machinery with exposed or guarded moving parts, or in which energy can be
stored (e.g. compressed air, electrical components) during servicing or
maintenance.
Designing and installing equipment, where feasible, to enable routine service, such
as lubrication, without removal of the guarding devices or mechanisms.
Noise
The use of hearing protection should be enforced actively when the equivalent
sound level over 8 hours reaches 85 dB(A), the peak sound levels reach 140 dB(C),
or the average maximum sound level reaches 110dB(A). Hearing protective
devices provided should be capable of reducing sound levels at the ear to at least
85 dB(A). ·
2
https://www.ifc.org/wps/wcm/connect/1d19c1ab-3ef8-42d4-bd6b-cb79648af3fe/
2%2BOccupational%2BHealth%2Band%2BSafety.pdf?MOD=AJPERES&CVID=ls62x8l
139 | P a g e Site-Specific Environmental Management
Plan
, KNK-SMC Joint Venture
Although hearing protection is preferred for any period of noise exposure in excess
of 85 dB(A), an equivalent level of protection can be obtained, but less easily
managed, by limiting the duration of noise exposure. For every 3 dB(A) increase in
sound levels, the ‘allowed’ exposure period or duration should be reduced by 50
percent.
Prior to the issuance of hearing protective devices as the final control mechanism,
use of acoustic insulating materials, isolation of the noise source, and other
engineering controls should be investigated and implemented, where feasible.
Vibration
Exposure to hand-arm vibration from equipment such as hand and power tools, or whole-
body vibrations from surfaces on which the worker stands or sits, should be controlled
through choice of equipment, installation of vibration dampening pads or devices, and
limiting the duration of exposure. Limits for vibration and action values. Exposure levels
should be checked on the basis of daily exposure time and data provided by equipment
manufacturers.
Electrical
Exposed or faulty electrical devices, such as circuit breakers, panels, cables, cords and hand
tools, can pose a serious risk to workers. Overhead wires can be struck by metal devices, such
as poles or ladders, and by vehicles with metal booms. Vehicles or grounded metal objects
brought into close proximity with overhead wires can result in arcing between the wires and
the object, without actual contact. Recommended actions include:
Marking all energized electrical devices and lines with warning signs; ·
Locking out (de-charging and leaving open with a controlled locking device) and
tagging-out (warning sign placed on the lock) devices during service or
maintenance;
Checking all electrical cords, cables, and hand power tools for frayed or exposed
cords and following manufacturer recommendations for maximum permitted
operating voltage of the portable hand tools; ·
Rubber tired construction or other vehicles that come into direct contact with, or
arcing between, high voltage wires may need to be taken out of service for periods
of 48 hours and have the tires replaced to prevent catastrophic tire and wheel
assembly failure, potentially causing serious injury or death;
Conducting detailed identification and marking of all buried electrical wiring prior
to any excavation work.
Eye Hazards
Solid particles from a wide variety of industrial operations, and / or a liquid chemical spray
may strike a worker in the eye causing an eye injury or permanent blindness. Recommended
measures include:
Use of machine guards or splash shields and/or face and eye protection devices,
such as safety glasses with side shields, goggles, and/or a full face shield. Specific
Safe Operating Procedures (SOPs) may be required for use of sanding and grinding
tools and/or when working around liquid chemicals. Frequent checks of these types
of equipment prior to use to ensure mechanical integrity is also good practice.
Machine and equipment guarding should conform to standards published by
organizations such as CSA, ANSI and ISO. ·
Moving areas where the discharge of solid fragments, liquid, or gaseous emissions
can reasonably be predicted (e.g. discharge of sparks from a metal cutting station,
pressure relief valve discharge) away from places expected to be occupied or
transited by workers or visitors. Where machine or work fragments could present a
hazard to transient workers or passers-by, extra area guarding or proximity
restricting systems should be implemented, or PPE required for transients and
visitors.
Provisions should be made for persons who have to wear prescription glasses either
through the use overglasses or prescription hardened glasses.
Welding/Hot Work
Welding creates an extremely bright and intense light that may seriously injure a worker’s
eyesight. In extreme cases, blindness may result. Additionally, welding may produce noxious
Special hot work and fire prevention precautions and Standard Operating
Procedures (SOPs) should be implemented if welding or hot cutting is undertaken
outside established welding work stations, including ‘Hot Work Permits, stand-by
fire extinguishers, stand-by fire watch, and maintaining the fire watch for up to one
hour after welding or hot cutting has terminated. Special procedures are required
for hot work on tanks or vessels that have contained flammable materials.
Poorly trained or inexperienced industrial vehicle drivers have increased risk of accident with
other vehicles, pedestrians, and equipment. Industrial vehicles and delivery vehicles, as well
as private vehicles on-site, also represent potential collision scenarios. Industrial vehicle
driving and site traffic safety practices include:
Training and licensing industrial vehicle operators in the safe operation of
specialized vehicles such as forklifts, including safe loading/unloading, load limits.
Ensuring moving equipment with restricted rear visibility is outfitted with audible
back-up alarms. ·
Restricting the circulation of delivery and private vehicles to defined routes and
areas, giving preference to ‘one-way’ circulation, where appropriate.
Injuries due to ergonomic factors, such as repetitive motion, overexertion, and manual
handling, take prolonged and repeated exposures to develop, and typically require periods of
Selecting and designing tools that reduce force requirements and holding times,
and improve postures. ·
Incorporating rest and stretch breaks into work processes, and conducting job
rotation.
Physical Hazards
Air Quality
Poor air quality due to the release of contaminants into the workplace can result in possible
respiratory irritation, discomfort, or illness to workers. Employers should take appropriate
measures to maintain air quality in the work area. These include: ·
Maintaining levels of contaminant dusts, vapors and gases in the work environment
at concentrations below those recommended as TWA-TLV’s (threshold limit
value)—concentrations to which most workers can be exposed repeatedly (8
hours/day, 40 hrs/week, week-after week), without sustaining adverse health
effects. ·
Indoor secure storage, and sealed containers rather than loose storage
Where ambient air contains several materials that have similar effects on the same
body organs (additive effects).
Fires and or explosions resulting from ignition of flammable materials or gases can lead to
loss of property as well as possible injury or fatalities to project workers. Prevention and
control strategies include:
Storing flammables away from ignition sources and oxidizing materials. Further,
flammables storage area should be:
Have natural or passive floor and ceiling level ventilation and explosion
venting
Be equipped with fire extinguishing devices and self closing doors, and
constructed of materials made to withstand flame impingement for a moderate
period of time ·
Providing bonding and grounding of, and between, containers and additional
mechanical floor level ventilation if materials are being, or could be, dispensed in
the storage area. ·
Defining and labeling fire hazards areas to warn of special rules (e.g. prohibition in
use of smoking materials, cellular phones, or other potential spark generating
equipment).
Biological Hazards
Biological agents represent potential for illness or injury due to single acute exposure or
chronic repetitive exposure. Biological hazards can be prevented most effectively by
implementing the following measures: ·
If the nature of the activity permits, use of any harmful biological agents should be
avoided and replaced with an agent that, under normal conditions of use, is not
dangerous or less dangerous to workers. If use of harmful agents cannot be
avoided, precautions should be taken to keep the risk of exposure as low as
possible and maintained below internationally established and recognized exposure
limits.
Measures to eliminate and control hazards from known and suspected biological
agents at the place of work should be designed, implemented and maintained in
close co-operation with the local health authorities and according to recognized
international standards.
Impacts
The staff and labor camps for the construction of the proposed upgradation of roads will be a
source of wastewater generated from the toilets, washrooms and the kitchen. The wastewater
will not meet the national environmental standards and will therefore need treatment prior to
disposal.
The project sites where construction is being conducted must not be treated by the project
staff and/or labor as a public toilet or for disposal of camp effluent.
Mitigation measures
Cumulative impacts are deemed to occur when the effects of project components, other
projects, and/or other land use activities overlap with each other by affecting the same Valued
Environmental and Social Component (VESCs). That is, cumulative impacts are the
incremental impact of the project when combined with the cumulative effects of other past,
present and reasonably foreseeable future projects.
All upgrades to existing infrastructure and new works are proposed within
existing landholdings, existing structures or existing rights of way. There are
accordingly no cumulative impacts on physical, ecological or social resources in
any of the areas subject to development or redevelopment, since all of these areas
have been intensively developed in the past and are highly urbanized in the main;
ANNEXURES
Annexure-A
Occupational Health and Safety Plan
General
Occupational Health and Safety covers all personnel working under the project and will be in
line with the World Bank/IFC EHS guidelines on health and safety.
The Occupational Health and Safety program will aim to ensure that the workplace is safe
and healthy by: addressing the hazards and risks at the workplace; outlining the procedures
and responsibilities for preventing, eliminating and minimizing the effects of those hazards
and risks; identifying the emergency management plans for the workplace or workplaces;
and, specifying how consultation, training and information are to be provided to employees
at various workplaces.
Some of the risks/hazards associated with workplaces are due to working close to or at sites
associated with the various project construction activities. Other risks associated with the
project construction phase include risk of increase of vector borne and other different
diseases.
The following sections will be implemented during the construction phase to address and
ensure workers’ health and safety.
150
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
iii. Providing a safe storage site/area for large equipment such as power tools and
chains, to prevent misuse and loss.
iv. Proper Housekeeping: Ensuring that materials are all stacked, racked, blocked,
interlocked, or otherwise secured to prevent sliding, falling, or collapse. Brick stacks
will not be more than 7 feet in height and for concrete blocks they will not be more
than 6 feet high.
v. Removing all scrap timber, waste material and rubbish from the immediate work area
as the work progresses.
vi. Where scaffolds are required, ensuring that each scaffold or its components shall be
capable of supporting its own weight and at least 4 times the maximum intended load
applied or transmitted to it. The platform/scaffold plank shall be at least 15 inches
wide and 1.5 inches thick. The rope should be capable of supporting at least 6 times
the maximum intended load applied or transmitted to that rope. Pole scaffolds over
60 feet in height shall be designed by a registered professional engineer and shall be
constructed and loaded in accordance with that design. Where scaffolds are not
provided, safety belts/safety nets shall be provided;
vii. Ensure that all ramps or walkways are at least 6 feet wide, having slip resistance
threads and not inclined at more than a slope of 1 vertical and 3 horizontal.
viii. Stacking away all excavated earth at least 2 feet from the pit to avoid material such
as loose rocks from falling back into the excavated area and injuring those working
inside excavated sites.
ix. Constructing support systems, such as bracing to adjoining structures that may be
endangered by excavation works nearby.
x. Only a trained electrician to construct, install and repair all electrical equipment to
prevent risks of electrical shocks and electrocution.
xi. Install fire extinguishers and/or other fire-fighting equipment at every work site to
prepare for any accidental fire hazards.
151
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
ii. Helmet shall be provided to all workers, or visitors visiting the site, for protection of
the head against impact or penetration of falling or flying objects.
iii. Safety belt shall be provided to workers working at heights (more than 20 ft) such
as roofing, painting, and plastering.
iv. Safety boots shall be provided to all workers for protection of feet from impact or
penetration of falling objects on feet.
v. Ear protecting devices shall be provided to all workers and will be used during the
occurrence of extensive noise.
vi. Eye and face protection equipment shall be provided to all welders to protect
against sparks.
vii. Respiratory protection devices shall be provided to all workers during occurrence of
fumes, dusts, or toxic gas/vapor.
viii. Safety nets shall be provided when workplaces are more than 25 feet (7.5 m) above
the ground or other surfaces where the use of ladders, scaffolds, catch platforms,
temporary floors or safety belts is impractical.
The specific PPE requirements for each type of work are summarized below.
152
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Quarries Hard hat, eye protectors, hearing protection, safety footwear,
leather gloves and dust respirator.
d. Procedures to Deal with Emergencies such as Accidents, Sudden Illness
and Death of Workers
First aid kits will be made available at all times throughout the entire construction period by
the respective contractors. This is very important, because most work sites will be at some
distance from the nearest hospital. In addition to the first aid kits, the following measures
should be in place:
ix. Provision of dispensaries by the individual EPC contractor.
x. A vehicle shall be on standby from the Project Office so that
emergency transportation can be arranged to take severely
injured/sick workers to the nearest hospital for immediate medical
attention.
xi. A designated Health Officer/worker for the Project will be identified as
a focal person to attend to all health and safety related issues. This
employee’s contact number will be posted at all work sites for speedy
delivery of emergency services. The focal person shall be well versed
with the medical system and facilities available at the hospital.
xii. Communication arrangements, such a provision of radios or mobile
communication for all work sites, for efficient handling of emergencies,
will be made.
153
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
written reports from witnesses, report of the examining doctor and his/her recommendation
for treatment. Each individual contractor will be responsible for ensuring compensation for
the respective workers.
g. Awareness Programs
The Project management will undertake awareness programs through posters, talks, and
meetings with the contractors to undertake the following activities:
i. Dissemination sessions will clarify the rights and responsibilities of the workers regarding
interactions with local people (including communicable disease risks, such as HIV/AIDS),
work site health and safety, waste management (waste separation, recycling, and
composting), and the illegality of poaching.
ii. Make workers aware of procedures to be followed in case of emergencies such as
informing the focal health person who in turn will arrange the necessary emergency
transportation or treatment.
154
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Annexure-B
Emergency Response Plan
155
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
1 PURPOSE
The purpose of this Emergency Response Procedure is to provide measures and guidance
for the establishment and implementation of emergency preparedness plans for the project.
The aim of the Emergency Response Procedure is to:
i) Ensure all personnel and visitors to the office/job sites are given the
maximum protection from unforeseen events.
ii) Ensure all personnel are aware of the importance of this procedure to
protection of life and property.
3 RESPONSIBILITIES
The detailed roles and responsibilities of certain key members of the Emergency Response
team available to assist in emergency are provided in Table F.1 below.
156
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Table F.1 Emergency Response Team
Action Group Responsibility
Emergency Coordinator Overall control of personnel and resources.
The Emergency Coordinator will support and advise the Site Safety
Supervision as necessary.
Serves as public relations spokes persons, or delegates to some
staff member the responsibility for working with news media
regarding any disaster or emergency. Also assure proper
coordination of news release with appropriate corporate staff or
other designated people.
Site Safety Supervision Overall responsibility for activating emergency plan and for
(Emergency Commander) terminating emergency actions.
Be alternative of emergency response chairpersons.
Disseminates warnings and information as required to ensure all
people in the immediate area have been warned and evacuated
either by alarms or by word of mouth.
Supervise the actions of the Emergency Response Team to ensure
all persons are safe from the danger.
Notify outside authorities if assistance is required.
Carries the responsibility for coordinating actions including other
organizations in accordance with the needs of the situation.
Ensure maximum co-operation and assistance is provided to any
outside groups called to respond to an emergency.
Establish and appoint all emergency organization structure and
team.
Assures adequate delegation of responsibilities for all key positions
of assistants on the Project to assist with any foreseeable
emergency.
Ensure resources available to purchase needed emergency
response equipment and supplies.
Assures that all persons on the Emergency Response Team aware
and fully understand their individual responsibilities for
implementing and supporting the emergency plan.
Establish the emergency drill schedule of all identified emergency
scenarios, track the status and evaluate the emergency.
The Emergency Commander shall ensure that senior management
personnel have been reported of the emergency as soon as
practical after the event.
Security Team Ensure that the exit route is regularly tested and maintained in good
working order.
Maintain station at the security gate or most suitable location to
secure the area during any emergency such that only authorized
157
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
personnel and equipment may enter, prevent access to the site of
unauthorized personnel.
Assist with strong/activation of services during an emergency.
Ensure vehicles and obstructions are moved to give incoming
emergency vehicles access to the scene, if ambulance or
emergency services are attending the site, ensure clear access and
personnel are located to direct any incoming emergency service to
the site of emergency.
Rescue & Medical Team Protect the injured from further danger and weather.
Provide treatment to the victim(s) to the best of their ability by first
aid and then transfer to hospital.
Remain familiar with the rescue activities and rescue apparatus.
Assist outside medical services personnel when they arrive
General Administration Response to support any requested general facilities for assisting
Team Emergency Response Team in their work.
Government Relation Coordinate with local government on a matter of concerned in the
Team emergency response plan to liaise with local officers in their affair
for support Emergency Response Team.
Coordinate emergency plan with the government authorities, local
community.
Environment Team In case of emergency related to the environmental pollution such as
the chemical spill, oil spill into the ambient, the environment team
will support the technical advice to control and mitigate the pollution
until return to the normal situation.
Department Heads Call up of personnel into the safe location for protective life and
property.
Take immediate and appropriate action while Emergency Response
Team is being mobilized.
Keep in touch with the Emergency Commander
Control and supervise operators and contractors on the
implementation of this procedure, with consultation with Safety
Team as necessary.
Provide and maintain emergency equipment of their responsible
areas.
Other Staff and All other staff and employees will remain at their workstations or
Employees assembly point unless directed otherwise from Emergency
Response Team.
Each supervisor will ensure that all members of his work group are
accounted for and keep in touch with each of their Department
Head.
158
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
F.4 PROCEDURE
Emergency situation and injuries to person can occur at any time or place either on Project site or
elsewhere. The most two common types of emergencies on site are fire and serious accident.
Figure F.1 Emergency Procedure for Fire
159
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
In the event of an accident or incident, only senior staff is permitted to give factual
information to the authorities for resource of liability exposure. The press must be avoiding
politely, at all costs, with the terse comment that “the matter is under investigation and
relevant information when available will be provided by our Head Office” Do not ever give
your opinion or story.
First Aid Persons
Upon advice of medical emergency, make immediate assessment to response required and
if necessary, advise security to summon ambulance or medical assistance, the qualified first
aid attendant should also,
Provide treatment to the victim(s) to the best of his/her ability.
Ensure the safety of victims by ceasing any work activity in the area.
Protect the injured from further danger and weather.
Assist medical services personnel when they arrive.
General Administration Team
Upon advice of medical emergency, maintain contact with first aid personnel and summon
ambulance if required.
Security Team
If ambulance or emergency services are attending the site, ensure clear access and
personnel are located to direct vehicle closest to the scene.
Prevent access to the site of unauthorized personnel (press, etc.).
Emergency Coordinator
The Emergency Coordinator shall assist emergency personnel at the scene as required
through allocation of company resources.
The Emergency Coordinator shall ensure next-of-kin are properly notified as soon as
possible and give whatever company support and assistance is necessary to assist them
bundle the situation
The Emergency Coordinator shall ensure that senior management personnel are advised of
the emergency as soon as practical after the event.
160
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
161
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Annexure C
Archaeological ‘Chance Find’ procedure
162
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Background
The purpose of this document is to address the possibility of archaeological deposits
becoming exposed during ground altering activities within the project area and to provide
protocols to follow in the case of a chance archaeological find to ensure that archaeological
sites are documented and protected as required.
Archaeological sites are an important resource that is protected for their historical, cultural,
scientific and educational value to the general public and local communities. Impacts to
archaeological sites must be avoided or managed by development proponents. The
objectives of this ‘Archaeological Chance Find Procedure’ are to promote preservation of
archaeological data while minimizing disruption of construction scheduling/ It is
recommended that due to the moderate to high archaeological potential of some areas
within the project area, all on site personnel and contractors be informed of the
Archaeological Chance Find Procedure and have access to a copy while on site.
Potential Impacts to Archaeological Sites
Developments that involve excavation, movement, or disturbance of soils have the potential
to impact archaeological materials, if present. Activities such as road construction, land
clearing, and excavation are all examples of activities that may adversely affect
archaeological deposits.
163
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
vi) A precautionary approach will be adopted in the application of these procedures.
Detailed Procedural Steps
If the Director, department of Archaeology receives any information or otherwise has the
knowledge of the discovery or existence of an antiquity of which there is no owner, he shall,
after satisfying himself as to the correctness of the information or knowledge, take such
steps with the approval of the Government, as he may consider necessary for the custody,
preservation and protection of the antiquity.
Whoever discovers, or finds accidentally, any movable antiquity shall inform forth with the
Directorate within seven days of its being discovered or found.
If, within seven days of his being informed, the Director decides to take over the antiquity for
purposes of custody, preservation and protection, the person discovering or finding it shall
hand it over to the Director or a person authorized by him in writing.
Where the Director decides to take over an antiquity, he may pay to the person by whom it is
handed over to him such cash reward as may be decided in consultation with the Advisory
Committee.
The Director or any officer authorized by him with police assistance may, after giving
reasonable notice, enter into, inspect and examine any premises, place or area which or the
sub-soil of which he may have reason to believe to be, or to contain an antiquity and may
cause any site, building, object or any antiquity or the remains of any antiquity in such
premises, place or area to be photographed, copied or reproduced by any process suitable
for the purpose.
The owner or occupier of the premises, place or area shall afford all reasonable opportunity
and assistance to the Director.
No photograph, copy of reproduction taken or made shall be sold or offered for sale except
by or with the consent of the owner of the object of which the photograph, copy or the
reproduction has been taken or made.
Where substantial damage is caused to any property as a result of the inspection, the
Director shall pay to the owner thereof reasonable compensation for the damage in
consultation with the Advisory Committee.
If the Director after conducting an inquiry, has reasonable grounds to believe that any land
contains any antiquity, he may approach the Government to direct the Revenue Department
to acquire such land or any part thereof and the Revenue Department shall thereupon
acquire such land or part as for a public purpose.
164
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Annexure D
Dust Management Plan
165
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
General
The purpose of this plan is to describe the measures that the project shall take to ensure that
the risk of emissions from dust generated by site operations during construction are
minimized and that best practice measures are implemented.
Dust emissions from construction can cause ill health effects to Contractor staff along with
nuisance and annoyance to members of the local community. Dust will be controlled
through:
Elimination
Reduction/Minimization
Control
This dust management plan shall be implemented based on the measures already provided
in the Environmental Management Plan (EMP) relating to controlling dust emissions.
Methodology
The following methodology will be undertaken for each project section:
Storage of material
Stockpiles
Spillages
Storage of Waste
166
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Demolition
Training
All Contractor staff will be required to attend training seminars as already mentioned in the
EMP document. A site-specific induction will also be required before being allowed to work
167
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
on site. These will include site-specific sensitive receptors and details regarding dust control
measures to be taken.
Toolbox talks on air pollution and minimizing dust emissions will be provided on a regular
basis to Contractor staff.
168
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
Stockpiles will be placed so as to minimize
Stockpile location
double handling and facilitate the site restoration.
Stockpiles, tips and mounds will not be stored at
Building stockpiles an angle greater than an angle of repose of the
material.
Where possible, stockpiles will be placed under
sheeting.
Small and temporary stockpiles Dusty material will be damped down.
Wind barriers (protective fences) of a similar
height to the stockpile will be erected, if required.
Long-term stockpiles will be vegetated and
stabilized as soon as possible.
Stock plies will be dampened down until
Large and long term stockpiles
stabilized, where necessary.
Wind barriers (protective fences) of a similar
height to the stockpile will be erected, if required.
Waste Material from Construction
A dedicated lay-down area will be available for
waste.
Disposal method Waste will not be allowed to build up and will be
disposed off at the designated locations as per
EMP.
Site Preparation and Restoration
These activity areas will be kept damp where
Earthworks, excavation and digging required and if possible, will be avoided during
dry and windy periods.
Surfaces will be stabilized by re-vegetation as
Completed earthworks
soon as possible, where applicable.
Construction and Fabrication Process
Authorization will be obtained from PMU and
UMDS before using any mobile plant on site for
Crushing of material for reuse,
activities such as crushing and screening.
transportation and disposal
Any crushing or screening activities will be
located away from sensitive receptors.
These activities will be avoided wherever
possible.
Cutting, grinding, drilling, sawing,
Equipment and techniques that minimize dust will
trimming, planning, sanding
be implemented.
Water will be used to minimize dust.
Cutting roadways, pavements, Water sprinkling to be used.
169
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
blocks
Best practice measures will be used such as dust
Angle grinders and disk cutters
extraction.
Monitoring Arrangements
Monitoring will be conducted at sensitive receptor locations in the project area as provided in
the EMP. Furthermore, at locations where PM levels are exceeding applicable guidelines,
additional stringent measures will be implemented at the respective location(s) in the project
area to ensure dust levels are controlled as far as possible.
170
Site-Specific Environmental Management Plan
, KNK-SMC Joint Venture
ANNEXURE - E
Traffic Management Plan
171
Site-Specific Environmental Management Plan
Construction of Grade Separation at Railway
Crossing of Shahab Pura Road, Sialkot
2 The plan
The Objective of Traffic Management Plan (TMP) is to define the requirements that should
be implemented to mitigate any potential negative risks to the environment, workers or the
community resulting from construction traffic.
The TMP will advise and inform site Contractors and external suppliers of equipment and
materials of access and entry points along with other key information such tipping areas and
wash-out areas. It is intended to compliment and work alongside relevant ESMMP. The TMP
will be classed as “live” and therefore be subjected to updates as required.
Contractor, at the time of the execution of the project will prepare a comprehensive TMP in
coordination with local traffic police department, PMU, emergency services and local
administrative department. The PMU and CSC will review and approve contractors TMP.
The contractor’s TMP shall include following mitigation measures during its preparation:
Undertake a road conditions assessment prior to and following the peak construction period,
to assess any damage to road infrastructure that can be attributed to Project construction.
Repair damage as appropriate or enter into a voluntary agreement with the relevant roads
authority to reimburse the cost of any repairs required to the public road network as a result
of the Project.
Spoil dumpsites located close to Project site to minimise journey distance and limit
movements to site access roads.
Concrete mixing plant located at Project site limiting traffic movements associated with
concrete delivery to site access roads
Construction of worker accommodation on site to reduce light vehicle movements relating to
travel to/ from the site
Provision of bus/minibus services for personnel living in nearby settlements
Movements of construction workers will be planned to avoid the busiest roads and times of
day when traffic is at its greatest.
Schedule deliveries and road movements to avoid peak periods
208 | P a g e
Construction of Grade Separation at Railway
Crossing of Shahab Pura Road, Sialkot
Road maintenance fund to leave a useful asset for communities after the construction
phase.
Driver training for HGV drivers and refresher course every six months for Project drivers
Speed restrictions for project traffic travelling through communities (to be agreed with Traffic
Manangement Authority)
Run a safety campaign to improve the people’s knowledge of the traffic hazard on their
roads, public information and other activities to address the issues.
Run a pedestrian awareness programme
Temporary signage
The traffic management plan is provided below.
3 Other Recommendations
It is important to manage public access routes during construction because it can cause
delay to local traffic and create a safety hazard both on and offsite. People working and
living near the project site would be annoyed by the emissions, noise and visual intrusion of
queuing vehicles. Some important factors involved in access routes and site traffic are as
follows:
Time limits
Parking
Pedestrian conflicts
Contractor should have consultation with the local police or local authority to address these
issues and to effectively manage them before the beginning of the construction.
On leaving the site, vehicles must be directed to follow the directions given.
Assign designated personnel on site to receive deliveries and to direct the vehicles.
4 Contractor’s Obligation
The traffic management plan of the Contractor should be safe enough and widening of
access roads and construction of the detours must be completed before start of project
construction activities so that heavy vehicular transportation for construction activities do not
hinder the normal course of traffic lanes. While widening the access roads, the safe
movement of the vehicles, people, animals and wildlife must be ensured. It will be sole
responsibility of Contractor. The roads widening should be designed on the basis of the
traffic survey, summarized and estimated site traffic. Contractor must ensure that road
closures are carried out by a competent person. The Contractor obligation must include the
display of traffic signs according to the need to divert the traffic volume and to guide the road
users in advance. The traffic sign, traffic light should be placed from any diverting route or
road marking.
The Contractor should consider the environmental and social impacts of the traffic during
construction. It will be sole responsibility of the Contractor to implement a plan which
produces minimum nuisance to the local people and to the environment. Safety of the
people should be given due importance. It will be under Contractor obligation to notify the
traffic management plan and its later changes to CSC, PMU, emergency services and Traffic
Police, and also publish weekly programme in local newspapers.
210 | P a g e
Construction of Grade Separation at Railway
Crossing of Shahab Pura Road, Sialkot
ANNEXURE - F
Punjab Environmental Quality Standards
(PEQs)
211 | P a g e
Construction of Grade Separation at Railway
Crossing of Shahab Pura Road, Sialkot
ANNEXURE - G
WHO advice on Use of Masks for the
COVID-19 Virus
Annexure- H
Environmental Monitoring Results
Annexure- H
Daily Monitoring Checklist
Annexure – I
Weekly Monitoring Checklist
Annexure – J
Monthly Monitoring Checklist
Annexure – K
Incident Reporting Format
Annexure-L
Draft for Recording Air Quality Stack
Emmision Values
Annexure-M
Waste Management plan
Management Responsible
Waste Stream Description Quantity Method Person Contingency Plan
In case of landfill
closure or capacity
limitations, explore
Non- alternative disposal
hazardous, options such as
non-recyclable Landfill incineration or
General Waste waste disposal Site Manager recycling.
On-site
storage,
labeling,
and
transport by
licensed
contractor
for
treatment In case of spill or
Waste that and disposal release, follow
poses a risk to at emergency response
Hazardous health or the authorized procedures and notify
Waste environment facility HSE Officer appropriate authorities.
Waste Segregation
Construction
generated of In case of insufficient
and Demolition Site
during site recyclable space for on-site
Waste Supervisor
construction materials, storage, explore options
and transport to for off-site disposal or
Site-Specific Environmental Management Plan
KNK-SMC Joint Venture
Management Responsible
Waste Stream Description Quantity Method Person Contingency Plan
demolition recycling
activities facility recycling.
In case of insufficient
Transport to storage space, explore
Electronic authorized options for interim
waste such as e-waste storage or partnering
computers and recycling with local organizations
E-waste mobile phones facility IT Manager for e-waste collection.