Professional Documents
Culture Documents
25045-A1000-18-3GS-E-019r001 - Insuation of Central Lightning Inverter
25045-A1000-18-3GS-E-019r001 - Insuation of Central Lightning Inverter
25045-A1000-18-3GS-E-019r001 - Insuation of Central Lightning Inverter
• t
SKYORYX
JOINT VENTURE
sr s s r I1I1D
• •
@ GAUP
METHOD STATEMENT
SKY ORYX JOINT VENTURE
T A I Sf I
PURSUANT TO SPECIAL CONDITION 5. WE. SKY ORYX JOINT VENTURE . VERIFY THAT THIS SUBMITTAL SATISFIES ALL
REQUIREMENTS OF THE CONTRACT . WITH THE EXCEPTION OF THE FOLLOWING CLARIFICATIONS / PROPOSALS
ACCEPTED BY THE ENGINEER :
M.HORIKAWA
PRINT NAME
M
SIGNATURE
IQ.:.Q'l -o
DATE
s By JT Thomas at 10:29 am, Feb 20, 2008
o STATUS 2: REVISE & RESUBMIT. WORK MAY PROCEED SUBJECT TO INCORPORATIO N OF COMMENTS INDICATED.
PERMISSION TO PROCEED SHALL NOT CONSTITUTE ACCEPTANCE OR APPROVAL OF DESIGN DETAILS. CALCULATIONS,
ANALYSES. TEST METHODS. OR MATERIALS DEVELOPED OR SELECTED BY CONTRACTO R AND SHALL NOT RELIEVE
CONTRACTOR FROM FULL COMPLIANCE WITH THE CONTRACT TECHNICAL SPECIFICATIONS AND DRAWINGS .
-- -
" ./
./,~~
.-" u s/}!ta/ .-l~~
23 Jan 08 As per OBI Comment P. Nel A. ~ M :,~awa
1 { { t'<J/,WQ j
, /
M. r,
---
.,
~
II"
/ I
Page 1 of 28
Submittal Review for Method Statement for Installation of Central Lighting Inverter
Comments
Page 2 of 29
TABLE OF CONTENTS
2. SCOPE OF WORK
4. ENVIRONMENTAL ISSUES
4.1 Environmental Impact assessment.
4.2 NDIA E S & H Contractor Requirements
4.3 Contractual Requirements.
4.4 Emergency Procedures.
5. QUALITY ASSURANCE
5.1 Contractual Requirements.
5.2 Critical works.
5.3 Inspection & Testing.
5.4 Follow up & Evaluation.
6. APPENDICES
6.1 Risk Assessment Form
Page 3 of 29
1. INSTALLATION OF CENTRAL LIGHTING INVERTER
2. SCOPE OF WORK
2.1 General Description
The methodology covers the procedure to be followed for the sequence of work. The
main works involve in the installation of Central Lighting Inverter Panel in accordance
with Section 16631. The document describes the method of installation,
characteristic and general scope of work for the supply and installation of Inverter
Panel at Concourse A, B and Main Terminal and Concourse C building.
The use of the right tool and equipment is paramount in order to achieve a quality
of work and performance not mentioned the qualification of personnel working for
it.
A. Lifting/Hauling Equipment
• Fork Lift
• Pick Up Truck
• Pallet/Roller steel equipment
B. Tools
Page 4 of 29
2.3 Materials
All materials that will be used will be based on approved material submittal,
shop drawing and specifications.
• Coordination meetings with the other trade contractors will be carried out in order
to notify their interfacing works.
• SOJV will inform in advance all related internal sub-contractors and organize a
meeting to prevent future problem during the installation of Panel board.
• In case of any interface issue with other contractor on site,
Call CP18 Interface Manager Mr. George Yousef (Ph: 580-8797)
• Permit to work
Material and equipment will be laid in approved space where environment that
are controlled within manufacturer’s ambient temperature requirement and
humidity tolerances for non operating equipment. Ensure a safe distance from
any falling debris and isolate the area by using barricade tape.
2.4.6 Communication
Communication on site will be provided by radios and cellular phones (if the
Cellular phone doesn’t work in all areas, radios will be preferred).
Page 5 of 29
2.5 Work Methodology
a. Prepare Purchase Order and ensure that all approved shop drawing, material
submittal and specification are properly transmitted to the vendor/manufacturer.
b. The procurement Engineer shall follow up with the supplier for the timely delivery of
the equipments.
c. The vendor/manufacturer shall formally submit the complete test report prior to
release for shipment of the equipment.
Page 6 of 29
2.5.4 Site Survey
Site Engineer shall perform the following task.
a. Verify the access route prior to the delivery of equipment on site.
b. Check and to ensure that mounting location for panel is free from any mechanical
damage.
c. Inform in advance with a report the existence of any foreseen problem
encountered.
Page 8 of 29
- Construction Environmental Control Plan – 25045-M-4CP-G01-01105
- Safety Field Manual – 25045-M-2HP-G01-009
- Health Field Manual – 25045-M-2HP-G01-020
- Environmental Clearance for NDIA
Upon the failure of contractor to comply with any of the requirements set forth in
these documents, engineer shall have the authority to stop any operations of
contractor affected by such failure until the condition is remedied acceptable to
engineer.
3.3 Protective & Safety Equipment
All workers engaged in the job site shall wear mandatory P.P.E. in accordance
to the NDIA ES&H requirements as follows;
• Safety Helmet
• Safety Shoes / Boots
• Safety Glasses
• High Visibility Luminous Vest
Also there will be additional special PPE to be used in case of necessary as
follows;
• Dust Mask
• Protective Gloves
• Full Body Harness
• Security belt
GC-19 WATCHING and LIGHTING: The Contractor shall in connection with the
works provide and maintain at his own cost all lights, guards fencing and
watching when and where necessary or required by the engineer or by any duly
constituted authority for the protection of the works or for the safety and
convenience of the public or others.
Page 9 of 29
GC-31.1: There may be other contractors, and agents or employees of the
Employer working at or adjacent to the site during the performance of the works
by the contractor. The contractor shall, at the Engineer’s instructions and
orders, allow those other contractors who might be working for the Employer
the opportunity to enable them to execute their work. The contractor shall allow
the same opportunity to the workers of the said contractors and to the
employer’s workers and to Government workers who might be employed at the
site or adjacent to it, to execute any work not included in this contract or to
execute any contract which might be performed by the employer and which is
related to the works of this contract, annexed to, or complementary to the
works.
Page 10 of 29
SC-11 Site Work Rules:
1. The jobsite normal working hours are 7:00am to 6:00pm Sunday thru
Thursday. The Contractor shall obtain approval from the engineer prior to
conducting site activities outside normal working hours.
2. Contractor shall keep an up to the minute record of its employees working
on site.
3. Contractor shall keep a record of all employees leaving the site at other than
normal quitting or shift change time.
4. Contractor shall take disciplinary action, including discharge, against its
employees for violations including but not limited to;
a. Refusing to work as directed
b. Excessive or chronic absenteeism
c. Consumption, possession of or being under the influence of drugs or
alcohol on the site.
d. Freighting, discrimination and horseplay on site
e. Disregard for Environmental, Health, Safety Rules
f. Theft of Employer’s, Engineer’s or other Contractor’s property.
g. Gambling on site.
h. Possession of deadly weapon(s) on site
i. Damage, misuse/or unauthorized use of permanent plant or facilities
j. Unauthorized entry to site or site facilities
5. Contractor shall comply with all requirements of the contractors approved
Environmental, Safety and Health Programs.
6. Contractor shall provide and require all its employees to wear approved
heard hats, safety eye protection and safety working shoes and high
visibility vests in any site area designated as a Hard Required Area.
7. Contractor shall provide and require visitors to wear hard hats, safety work
boots, high visibility vest and safety eye protection in any site area
designated as a hard Hat Required Area.
8. Contractor’s safety representative on site shall wear green colored hard
hats. The Contractors supervisors on site shall wear yellow colored hard
hats.
Page 11 of 29
9. Contractor’s employees shall be subject to Contractor inspection of all
vehicles, tool boxes, carry boxes etc. at the site.
10. Minors (anyone under 18 years of age) will not be permitted on site.
11. No private vehicles will be used on site, outside of designated compounds.
Only Contractors vehicles bearing Contractors logo may be used on Site.
12. Delivery Vehicles
a. All contractors shall ensure that all delivery vehicles entering the site
have some form of paperwork, such as delivery note collection
note/off hire note or NDIA order, stating the purpose of the visit. It is
in the interest of the Project and or services, a correct order number,
name and or location is given at the time of ordering to ensure correct
delivery of those goods, materials etc., and all likely losses are
minimized or traced.
b. All delivery vehicle drivers must have the following Personal
Protective Equipment available for use if his delivery task requires
him to work outside:
Safety Helmet
Hi Visibility Vest
Safety Boot
Safety Glasses
c. Compliance with the above delivery requirements is the sole
responsibility of the Contractor. Failure to ensure compliance will
result in stoppage of offloading.
Page 12 of 29
In the event of an emergency, Contractor shall follow the Emergency Procedure
as instructed by OBI ( Ref: 25045-M-TSV-MAHT-18-0047 dated on 20 April
2006);
All the contact numbers should be called only in case of emergency
In case of emergency our contact persons name and their phone numbers
are as follows;
1. Mr. Paul Nel: 5716234, Mr. Atsuta:557-9215, Mr.Huseyin:5851095
2. Dial 999 and giving the location as NDIA Bechtel Construction Site, Ras
Abu Aboud Road.
3. Dial 556-5947 NDIA Emergency Response Number
4. Dial 581-8965 Project Security to bring the emergency services to the
incident location.
4. ENVIRONMENTAL ISSUES
13.4: Contractor shall comply with all access restrictions, including prohibitions
on access to certain areas on or adjacent to the jobsite and require its
personnel and those of its suppliers and subcontractors of any tier comply with
Page 13 of 29
all signage and designations related to such restricted areas. Restricted areas
may include, but are not limited to:
i. designated wetlands;
ii. Environment mitigation study areas;
iii.cultural/historical/archaeological sites;
iv. designated fish, wildlife, or vegetative habitat.
13.5: Contractor shall immediately stop work in any area where cultural
resources or artifacts with archaeological or historical value are discovered, and
immediately notify employer. No artifacts, items, or materials shall be disturbed
or taken from the area of discovery. Neither contractor nor any of its suppliers
and subcontractors of any tier shall have property rights to such artifacts, items,
or materials, which shall be secured and guarded until turned over to Employer
or the appropriate authorities. Contractor shall also require that its personnel
and those of its suppliers and subcontractors of any tier comply with this
provision and respect all historic and archaeological sites in the area.
13.6: Contractor shall immediately stop works in any area where contaminated
soil indicators (such as odors or appearance), unknown containers, piping,
underground storage tanks, or similar structures are discovered, or any other
materials which are reasonably suspected to be toxic or hazardous. Contractor
shall then immediately notify employer and stop work area shall be confirmed
by employer. Activity in the stop work area shall only resume upon employers
written approval.
13.7: Contractor shall maintain the cleanliness of roadways when transporting
fill or spoil. Contractor shall provide appropriate facilities to ensure prompt clean
up of mud, dirt and other debris.
Page 14 of 29
4.4. Emergency Procedures
In case of any spilling, spill prevention program shall be applied.
Housekeeping on base of fire prevention shall be applied.
5. QUALITY ASSURANCE
Page 15 of 29
5.3. Inspection & Testing
ITP for Installation of Central Inverter Panel will be submitted later
6. APPENDICES
Page 16 of 29
Appendix 6.1
RISK ASSESMENT
Page 17 of 29
NOTE: THIS DOCUMENT SHOULD BE ATTACHED TO THE METHOD STATEMENT. WHEN APPROVED IT
MUST BE KEPT AT THE WORKING PLACE FOR REFERENCE PURPOSES
5 4 3 2 1
LIKELYHOOD
IF NOT VERY ALMOST
CONTROLLED UNLIKELY LIKELY VERY LIKELY
UNLIKELY CERTAIN
• Use PPE.
Ladders
E 1.3 Termination of Raceway Slip, Fall 3 3 6 M • Place the base of the ladder on a 4 5 16
into inverter panel firm, level, dry surface.
• Secure the bottom and the upper
part of the ladder, by tying them
(from stiles, not rungs) with ropes or
straps onto a stable, fixed object.
• Ladder are vendor certified as ANSI
Type A1 (ISO or equivalent )
• Two or more people do not work
from the same ladder( unless
specifically designed for 2 persons.
• Type of ladder tobe used near