10 MoU KTT DSI 30-Sep-23 20% 0% 11 RKAB 2024 31-Oct-23 20% 20% 12 Bok Putih Bridge 70% 70% Remark Follow-up the postponed FGD schedule to consultant. DSTP hardcopy document submitted by consultant. The boundaries CMS document is under preparation by consultant (Levindo)
Field visit by Perhutani done (9/6), BA issuance still on progres by
Perhutani. Prepare the Pertek request letter and other required documents to KLHK.
Visual inspection from Consultant has been carried out (9/12-15).
Waiting for minutes of inspection technical discussion from Consultant. Additional data has submitted to ESDM. Follow up site visit schedule plan by ESDM Jatim for field verification PT Bagong PJO evaluation waiting schedule by CMS The technical studies (kajian teknis) under review by GA Manager (IM)
Improvement of XRF procedure and import permit document
Permit request was submitted and under evaluation by Dirjen
Hubla in Sehati system. MoU under review by Legal Submission of matrix data by PIC deparments has started as per 23 Sep 2023, continue follow up and reminder meeting between directors BSI and Dinas PU Jatim