126 Villas, Balance work Schedule (Aluminium scope of work)

S.NO Balance Activity Block # Elevation Civil Clearance Civil Clearance Date Finish Date Remarks

22,26,35,36 civil clearance done,


1 MDB + Elec, louver door A, V 22, V26, V33, V35, V36 GF DB not proper 16/08/2023 23/08/2023
Villa 33 by 22-08-2023
3 MDB + Elec, louver door B, V37 GF DB not proper 21/08/2023 19/08/2023 Civil clearance on 22-08-2023

5 MDB + Elec, louver door C, V53, V54 GF Pipe Extension To be confirm 16/08/2023 SAIFCO, No clearance

6 Pool Fence G Right Civil work 14/08/2023 18/08/2023 LEVEL ISSUE not yet resolve

7 Shutter + pr plate + silicon + safety Glass H (1st Floor) Front Scaffolding + chemical injection To be confirm Each villa 1 shutters balance only

9 Pool Fence K, GF Civil work 14/08/2023 TOILET

10 MDB + Elec, louver door F, GF V 81 Front Pipe Extension To be confirm 16/08/2023 SAIFCO, No clearance

11 Pool Fence F, GF Toilet To be confirm TOILET


Aluminium work done, external silicon to be
14 Shutter + pr plate + silicon + safety Glass J (1st Floor) Back Scaffolding + chemical injection 16/08/2023 21/08/2023
done after civil repairing
16 MDB + Elec, louver door J, GF Front MEP + Tiles 21/08/2023 23/08/2023 SAIFCO, No clearance
Aluminium work done, external silicon to be
18 Shutter + pr plate + silicon + safety Glass E (1st Floor) Back Scaffolding + chemical injection 15/08/2023 22/08/2023
done after civil repairing
Aluminium work done, external silicon to be
19 Shutter + pr plate + silicon + safety Glass E (1st Floor) Front Scaffolding + chemical injection 15/08/2023 21/08/2023
done after civil repairing
20 MDB + Elec, louver door E, GF Front MEP + Tiles 21/08/2023 23/08/2023 SAIFCO

21 Panel door Alignment E, GF Front 22/08/2023


Aluminium work done, external silicon to be
22 Shutter + pr plate + silicon + safety Glass I (1st Floor) Back Scaffolding + chemical injection DONE 17/08/2023
done after civil repairing
23 Shutter + pr plate + silicon + safety Glass I (1st Floor) Front Scaffolding + chemical injection 16/08/2023 20/08/2023 Aluminium work will be finish by 23-08-2023

24 MDB + Elec, louver door I, GF Front MEP + Tiles 26/08/2023 28/08/2023 SAIFCO

25 Panel door Alignment I, GF Front 22/08/2023

20 Maid room sliding door (Bath) ALL Front NA NA 31/08/2023 In progress (A,B,C,G,H,F & K done)
censor fix, child safety lock latch delivering
21 Child lock (Block A) A NA NA 26/08/2023
on 22-08-2023
22 Block L Canopy L NA NA 31/08/2023 Plan delivery on 24-08-2023

22 Meeting Profile ALL ALL NA NA 28/08/2023 In progress (Block A done on 22-08-2023)