Mangla Refurbishment Project (MRPS - JV) Refurbishment of Mangla Power

Station
Daily Site Work Progress Report

Package IX – Switchyard Pictures

Weather: Clear and 28°C


A. 220/132kV Pre-Shutdown Works
No work.

B. 220/132kV Shutdown Works


1. 132kV Busbar-2 Shutdown Works :
1. Existing wiring disconnection, Dismantling existing bus bar panels, and shifting to the new B1.1
CHB relay room are in progress. B1.2
2. E3, Q22 only and E1,E2, Q21, and Q22 existing air-based mechanism cleaning and greasing B1.3
of the new motorized box in progress. B1.4
3. Cable glanding, dressing and termination -E2 of CB Q2 are in progress. B1.5
4. -E1 CT2 new box installation and termination work.
5. -E3 core cutting for GI pipes for CB & CT work is in progress.

HSE
SOPs:
1. Daily Tool Box Talk for Cable termination &Glanding, Testing and work at height.
2. Good Housekeeping maintained at high standard.
3. Social distancing among the staff and workers maintained at site premises wherever required.
4. Clean drinking water facility provided to all workers and staff.
5. PPEs including masks provided to all staff and workers.
6. Emergency walkways/paths clear from all hurdles and barriers.
Site Work Progress Pictures:

Page 1 of 2 Thursday 2023.05.11

132KV & 220KV Switchyard


Mangla Refurbishment Project (MRPS - JV) Refurbishment of Mangla Power
Station
Daily Site Work Progress Report

B1.1 B1.4

B1.3 B1.5

Page 2 of 2 Thursday 2023.05.11