Professional Documents
Culture Documents
Gestion de Proyectos - Earned Value Exercises
Gestion de Proyectos - Earned Value Exercises
A. $1800
B. $2000
C. $2200
D. $2400
3. Assuming that the COST variance experienced so far in the project will continue,
how much more money will it take to complete the project?
A. $400
B. $440
C. $2800
D. $2840
4. If the variance experienced so far were to stop, what is the project’s estimate at
completion?
A. $2400
B. $2440
Project Management
Earned Value Exercises and Solutions
Robert Antonides
C. $2600
D. $2800
A. .5
B. 1
C. 1.5
D. 2
* TCPI is the To Complete Performance Index. This would be the CPI for the
remaining part of the project.
A. 75%
B. 83%
C. 92%
D. 95%
7. Your project is expected to run for three consecutive years. Your organization is
introducing earned value management as part of the planning and managing of this
project. The project budget 100.000 $. The budget is consistent across the three
years. You are exactly 18 months into the project. 30 % of the total budget has
been spent and 40 % of the work is complete. Your project is:
A. An indicator into the speed or rate of spending compared to the value being
generated (Is the project budget on track)
B. The value of the work that should have been completed at any given point for
the total project to remain on budget and schedule
D. The difference between the planned work completed versus the amount of work
that was completed
A. 1.2
B. 0.867
C. $83,333.33
D. 0.96
10. Your Budget at Completion (BAC) for a project is $500,000. If the Cost
Performance Index (CPI) is 0.84 and the Schedule Performance Index (SPI) is 0.98,
what is the Estimate At Completion (EAC) for the project?
A. $595,238.10
B. $315,744.68
C. $235,000.00
D. $510,201.08
completed and $300,000 has been spent. What is the budget and schedule status
of this project?
13. What is the Schedule Performance Index (SPI) on day 5 of a 10 day project
that is 55% completed and has a Budget At Completion (BAC) of $10,000 with a
current Actual Cost (AC) of $6,000?
A. $-500
B. 1.1
C. $5,500
D. 0.92
B. The value of the work that should have been completed at any given point for
the total project to remain on budget and schedule
C. The indicator into the speed or rate of the work getting completed compared to
the work that was expected to be completed
D. An indicator into the speed or rate of spending compared to the value being
generated (Is the project budget on track)
15. Of the following options, which shows a project as being ahead of schedule and
under budget?
A. An indicator into the speed or rate of spending compared to the value being
generated (Is the project budget on track)
B. The difference between the planned work completed versus the amount of work
that was completed
C. The value of the work that should have been completed at any given point for
the total project to remain on budget and schedule
True
False
18. Which of the following formulas answers the question; What is the remaining
work likely to cost?
19. A project manager expects that the project would finish one month before the
planned finish date. However he expects that the project to exceed the budgeted
cost. What is true about the Schedule Performance Index (SPI)
A. SV is less than 0
A. BAC - PV
B. BAC - EV
C. EAC - PV
22. How will you calculate your EAC if the ETC work will be performed at the
budgeted rate?
A. EAC = AC + BAC – EV
C. EAC = BAC/CPI
23. What is the best way to accurately calculate Estimate to Completion (ETC)
B. BAC - EV
D. EAC - AC
24. Earned Value Measurements of a project indicate that the current CPI is 0.80
and the current SPI is 0.98. For the next phase of the project the project manager
should focus on which element of the project.
A. Schedule
B. Stakeholder Engagement
D. Cost
25. What is the best way to calculate the Estimate At Completion (EAC) when
original estimates are no longer valid.
A. EAC = AC + BAC – EV
D. EAC = BAC/CPI
26. The planned value of task A is $150,000 and task B is $500,000. After six
months the project manager does a performance analysis of the project and finds
that the project is behind schedule. The actual cost incurred in completing task A is
$175,000 and that for completing 80% of task B is $650,000. What is the cost
performance index of the project?
A. 1.66
B. 0.67
C. 0.76
D. 0.96
Project Management
Earned Value Exercises and Solutions
Robert Antonides
27. For the following project calculate SV, CV, SPI and CPI at the end of second
month.
Month 1 2 3 4
SV=
CV=
SPI=
CPI=
28. You are managing a project which is into six months of its execution. You are
now reviewing the project status and you have ascertained that project is behind
schedule. The actual cost of Activity A is 200,000 and that of Activity B is 100,000.
The planned value of these activities are 180,000 and 80,000 respectively. The
Activity A is 100% complete. However, Activity B is only 75% complete. Calculate
the schedule performance index and cost performance index of the project on the
review date.