Methodology Statement For Installing Pipe Steam Tracing

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

METHODOLOGY STATEMENT FOR Reference documents:

WP 4 – WP 6 - INSTALLING OF PIPES STEAM


TRACING

TOOLS AND EQUIPMENT.

 ARTISANS PERSONAL HAND TOOLS


 INSPECTION OF PPE
 NETTING ( SNOW NET ) BARRICADING TO PLACE AROUND WORKING AREA`S (ORANGE NETTING).
 CRANE TO LIFT PIPES
 SCAFFOLDING, BY SGB, SAFE, GREEN BOARDED.
 SPANNERS
 PLASTIC CONTAINER

PERSONAL PROTECTIVE EQUIPMENT.

 OVERALLS.
 HEAD PROTECTION.
 EYE PROTECTION.
 FACE PROTECTION.
 HAND PROTECTION.
 FOOT PROTECTION.
 HEARING PROTECTION.
 SAFETY HARNESS

EXECUTION METHOD

 OBTAIN WORK PERMIT FROM PRODUCTION PRIOR TASK EXECUTION.


 ENSURE CORRECT PIPES ARE IN POSITION BY MEANS OF PROCEDURE BY SUPERVISOR IN
CHARGE (TASK EXECUTOR).
 PREPARE WORK AREA IN TERMS OF PERMIT REQUIREMENTS, CLIENT AND COMPANY
PROCEDURES. (SPARK CONTAINMENT FORM PART OF THIS PREPARATIONS)
 PERFORM A VISUAL INSPECTION ON ALL TOOLS AND HAND TOOLS.
 CRANE WILL BE USED TO LIFT PIPES INTO POSITION.
 INSPECT THE PERSONAL PROTECTIVE EQUIPMENT OF ALL PERSONS WHO FORM PART OF THE
TASK EXECUTION TEAM.
 IDENTIFY PIPE AND CUT PIPE WITH PIPE CUTTER
 SUPERVISOR TO MONITOR LIFTING ACTIVITY
 SUPERVISOR TO IDENTIFY PIPE TO BE STRAPPED
 DISCUSS THE PERMIT AND SAFE WORKING PROCEDURE CONTENTS WITH THE TASK EXECUTORS.
 STEAM TRACING TO BE TEMPORARY STRAPPED WITH CABLE TIES
 SUPERVISOR TO CHECK ALL COUPLINGS AND CONNECTIONS
 FINAL STRAPPING TO BE WITNESSED BY SUPERVISOR
 REMOVE AL CABLE STRAPPING
 SUPERVISOR TO WITNESS AND SIGN OFF ALL PUMP TRACING
 SERVICE TEST TO BE DONE BY CLIENT