Work Pack 4 Climb Up Report

N Planned Date
Photo Area Description Corrective Action Required Signature
o Completion Completed
01 Podger found cracked and damaged. Replace tool immediately. Tools destroyed after report
by Foster Wheeler
Solidification
Building
(SGB)

02 Angle iron, broken handle and podger found not secured Removed from platform Service Provider HSE-Personnel
on elevated platform Third floor. to ensure they inspect platforms daily and these types of
Solidification materials and tools are picked up and secured
Building
(SGB & M&R)

03 Scaffold materials stacked in walkway. Remove to storage area immediately

SPD First Floor


(SGB)

04 Bolts for cable racking found on scaffold platform not Bolts and nuts as well as other small items that can fall
secured not in container to prevent falling objects through the scaffold platforms must be contained and
SPD First Floor placed in suitable containers.
(Kentz)

05 Cable straps for cable racking found on scaffold platform Cable straps as well as other small items that can fall
not secured not in container to prevent falling objects through the scaffold platforms must be contained and
SPD First Floor placed in suitable containers.
(Kentz)

06 Floor opening not properly covered. Not barricaded SGB to barricade the opening and ensure that all steel
boards are fixed with wire.
SPD First Floor
(SGB)

07 Fire proofing material lying next to opening in scaffold Concor to clean up the platform in the SPD-Area
above walkway. immediately
SPD Ground Floor
(Concor)
08 Threaded bar, re-bar, chemical anchor bolts lying around Clean up area and supply containers to store materials
Solidification First not contained or in a suitable container that are off-cuts or remove from site
Floor
(Murray &
Roberts)

09 Scaffold materials and bags lying around on floor Remove and clean up the area. Stacking and storage to
be addressed with the supervisor for this area.
Solidification First
Floor
(SGB)

10 Scaffold materials lying on floor Remove and clean up the area. Stacking and storage to
be addressed with the supervisor for this area
Solidification First
Floor
(SGB)

11 Used wire found lying on floor Remove and clean up the area. Stacking and storage to
be addressed with the supervisor for this area
Solidification First
Floor
(SGB)

12 Unsafe stacking and storage practices Stacking and storage to be addressed with the supervisor
for this area
Solidification First
Floor
(SGB)

13 Unsafe stacking and storage practices Stacking and storage to be addressed with the supervisor
for this area
Solidification First
Floor
(SGB)

14 Used wire found lying on floor Remove and clean up the area. Stacking and storage to
be addressed with the supervisor for this area
Solidification First
Floor
(SGB)

15 Loose tools and equipment found on scaffold platform Remove and clean up the area. Stacking and storage to
Solidification First where builders are busy be addressed with the supervisor for this area
Floor
(Murray &
Roberts)
16 Several Loose objects found on top of scaffold platform Remove and clean up the area. Housekeeping to be
underneath the piping underneath the second floor deck addressed with the supervisor for this area
Solidification
Second Floor
(Fluor)

17 Trestle used on top of scaffold platform, not numbered, Trestle to be removed from site
not painted and extended almost fully on the jacking
Solidification length.
Second Floor
(Fluor)

18 Piping shoes left unsecured and unattended on the Secure piping shoes and place in safe area to ensure they
scaffold platform underneath the 2nd floor deck cannot be knocked off the scaffold platform
Solidification
Second Floor
(Fluor)

19 Unsafe use of trestle on top of scaffold platform. Trestle Trestle to be removed from site
is damaged at the point of jacking. Not painted not
Solidification numbered.
Second Floor
(Fluor)

20 Off-cut pipe and pipe cover left on top of platform Remove to ground level and dispose of offcuts
underneath the 2nd floor deck.
Solidification
Second Floor
(Fluor)

21 Pipe shoe left on scaffold platform underneath 2nd floor Remove from platform or placed in approved container /
deck not secured or controlled. bucket
Solidification
Second Floor
(Fluor)

22 Spacers left on top of beam underneath the 2nd floor deck Remove from platform or placed in approved container /
not secured or controlled. bucket
Solidification
Second Floor
(Fluor)

23
24
25