Professional Documents
Culture Documents
Zhang 2022 J. Phys. Conf. Ser. 2276 012018
Zhang 2022 J. Phys. Conf. Ser. 2276 012018
Yuhong Zhang, Yantao Zhang*, Jiahui Han, Xueqiong Wang, Qiyu Chen, Jian
Zhang
State Key Laboratory of Power Grid Safety and Energy Conservation (China Electric
Power Research Institute), Haidian District, Beijing 100192, China
masterepri@126.com
Abstract. The equivalent voltage source method is recommended in IEC 60909 for short-circuit
current calculation, and the accuracy is verified by 400 kV and below voltage level power grids.
There are 500 kV, 750 kV or 1000 kV power grids in some countries where IEC standards are
applied, but there is no relevant research to verify the accuracy of the calculation method. In this
paper, verification methods for IEC 60909 calculation accuracy for the three voltage level power
grids are adopted. Calculation examples based on the operation and equipment parameters of the
500 kV, 750 kV and 1000 kV power grids are established. The results show that IEC 60909
short-circuit current calculation method is conservative, and the calculation accuracy meets the
requirements. The research expands the application scope of this standard to all AC power grids,
which is conducive to the engineering application of IEC 60909.
1. Introduction
Short-circuit calculation is one of the major tasks related to the analysis, planning and operating of
electric power systems [1-5]. This is a compromise between accuracy and calculation simplicity, provided
that the results are on the safe side, in the engineering calculation method [6]. At present, a variety of
short-circuit current calculation methods are proposed. The theoretical basis is the same, but the
calculation boundary conditions and calculation accuracy are different. In 2001, the International
Electrotechnical Commission formulated a series of IEC 60909 short-circuit current calculation
standards [7–10]. The calculation method recommended in IEC 60909 is rigorous, comprehensive, safe
and economical, and the calculation accuracy is supported by a large number of examples. Therefore it
has been recognized and applied internationally. In 2016, the standard was revised, and IEC 60909: 0-
2016 was released. The main revision contents include two points. One is to add a principled method to
calculate the short-circuit current provided by new energy. The second is to add a point of explanation:
the key coefficient in the calculation method is not defined for power grids above 400 kV voltage level.
This is because the high voltage level power grids are put into operation, but the relative calculation
accuracy is not verified. As a result, there is no standard for short-circuit current calculation of 500 kV,
750 kV and 1000 kV power system in countries using IEC 60909. This paper mainly studies methods
to prove the accuracy of the calculation method for the voltage level power grids above.
Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution
of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Published under licence by IOP Publishing Ltd 1
NEMD-2022 IOP Publishing
Journal of Physics: Conference Series 2276 (2022) 012018 doi:10.1088/1742-6596/2276/1/012018
the maximum and minimum short-circuit current of the short-circuit point. The method uses basic data
of the power grid for instance the nameplate parameters of the equipment and the standard voltage of
the system without considering the operation mode. By introducing voltage coefficient and multiple
impedance correction coefficients, and taking into account the operation constraints such as voltage
level, equipment capacity and so on, the purpose of safety and economy coordination is achieved. This
paper focuses on the maximum short-circuit current.
3. Calculation accuracy verification method for 500 kV voltage levels and above
2
NEMD-2022 IOP Publishing
Journal of Physics: Conference Series 2276 (2022) 012018 doi:10.1088/1742-6596/2276/1/012018
3.2.2. The impedance correction coefficient Kso for power station unit
A simple network is established in the IEC 60909 as figure 1, where, SrG is the rated apparent power of
the generator, UrG is the rated voltage of the generator, pG is the voltage regulation range of the generator,
SrT is the rated apparent power of the unit transformer, and UnQ is the nominal voltage of the short circuit
point Q.
G T '' Q
U rG (1 pG ) LV HV I kS k3
G
System
3~ F
S rG S rT、t U Q、U nQ
According to the equivalent voltage source method, the short-circuit current is calculated as shown
in formula (3). Equivalent impedance ZS and KSO as shown in formula (4), (5) respectively, where UrTHV
is the voltage of high voltage side of the unit transformer, pT is the range of transformer voltage
adjustment.
𝐼 (3)
√
→ → →
𝑍 𝑡 𝑍 𝑍THV (4)
𝐾 ⋅ ⋅ 1 𝑝 ⋅ " (5)
rG
Considering the operating conditions such as generator voltage, power and transformer tap, the
mathematical optimization method is used to calculate the possible maximum short-circuit current of
the superposition method as the true value of the maximum short-circuit current, and then the error
between the calculation results of the equivalent voltage source method and the true value is obtained,
as shown in Equation (6).
𝛥𝐼 ⋅ 100% (6)
4. Examples
4.1. Parameters
The 500 kV, 750 kV and 1000 kV power station units in China are investigated. The range of generator
voltage regulation is 0.9, and other parameters are listed in table 1-3.
3
NEMD-2022 IOP Publishing
Journal of Physics: Conference Series 2276 (2022) 012018 doi:10.1088/1742-6596/2276/1/012018
4
NEMD-2022 IOP Publishing
Journal of Physics: Conference Series 2276 (2022) 012018 doi:10.1088/1742-6596/2276/1/012018
5-05 2.35 2.34 0.38 7-05 1.76 1.78 -1.12 10-05 1.79 1.77 1.25
5-06 1.62 1.56 3.77 7-06 2.49 2.49 -0.13 10-06 1.73 1.71 1.20
5-07 1.47 1.45 1.52 7-07 1.71 1.73 -0.96 10-07 1.33 1.29 2.90
5-08 2.52 2.45 3.08 7-08 1.24 1.43 1.49 10-08 1.10 1.09 1.08
5-09 1.49 1.44 3.49 7-09 1.26 1.30 -3.36
5-10 1.61 1.57 2.49 7-10 1.53 1.63 -6.16
5-11 1.51 1.49 1.48 7-11 1.35 1.36 -1.07
5-12 2.24 2.19 2.43 7-12 1.26 1.30 -3.27
5-13 4.18 4.19 -0.33 7-13 1.76 1.78 -0.83
It can be seen from table 4 that the deviation between the current IEC standard calculation method
and the theoretical maximum value is-1 - +4 % for 500 kV and 1000 kV cases, and-6 - +2 % for 750 kV
cases. The deviation of the calculation results of each voltage level is further analyzed, and the results
are recorded in table 5.
Table 5. Deviation analysis of calculation results
Number of Number of negative Absolute value of
Voltage level(kV) Example number
|∆I’’kSO%|<4% deviation examples median deviation
500 13 13 2 <2.0%
750 13 12 12 <1.2%
1000 8 8 0 <1.5%
It can be seen from table 5 that the absolute value of median deviation of each voltage level is less
than 2.0%, 1.2% and 1.5% respectively. In large power grid, the possibility of multiple units providing
short-circuit current to reach the theoretical maximum at the same time is very low. Therefore, the IEC
calculation method is relatively conservative.
5. Conclusion
In this paper a parameter calibration method is adopted to study the applicability of IEC 69090 short-
circuit current calculation method for power girds above 400 kV voltage level. It is verified that IEC
69090 method is conservative and suitable for 500 kV, 750 kV and 1000 kV power grids. The research
results can provide technical support for IEC 60909 standard revision.
Acknowledgments
This paper is sponsored by SGCC R&D Project on Deepening Research and Application of Short-circuit
Current Calculation Method in Power Electronics Dominated Power Systems, (No. 5100-202055439A-
0-0-00).
References
[1] Francisco J B, Andrés H E, Alberto L B, Estefania A and Emilio G L 2021 IEEE. Trans. Power
Del. 36 2904-12
[2] Benjamin N, Imen G and Jutta H 2020 Conf. on Sustainable Energy Supply and Energy Storage
Systems(Hamburg) pp 1-6
[3] Rodolakis A. J 1993 IEEE Trans. Indu. Appl, 29 515-21
[4] Gene K and Harry S 1993 IEEE Trans. Indu. Appl, 29 625-30
[5] Zhang Y H, Zhang Y T and He Jingbo 2020 Proc. of the CSEE 40 7522-30
[6] Kaloudas C. G, Papadopoulos P. N, Papadopoulos T. A, Marinopoulos A. G. and Papagiannis G.
K. 2010 7th Med. Conf. and Exhibition on Power Generation, Transmission(Agia Napa) pp
1-7
[7] International Standard Short-circuit Currents in Three-phase a.c. Systems-Part 0:Calculation of
Currents, IEC, 2001
[8] International Standard Short-circuit Currents in Three-phase a.c. Systems-Part 1:Factors for the
Calculation of Short-circuit Currents, IEC, 2002
5
NEMD-2022 IOP Publishing
Journal of Physics: Conference Series 2276 (2022) 012018 doi:10.1088/1742-6596/2276/1/012018
[9] International Standard Short-circuit Currents in Three-phase a.c. Systems-Part 3:Currents During
two Separate Simultaneous Line-to-earth Short Circults and Partial Short-circuit Currents
Flowing Through Earth, IEC, 2003
[10] International Standard Short-circuit Currents in three-phase a.c. Systems-Part 4:Examples of Short-
circuit Currents, IEC, 2001
[11] International Standard Short-circuit currents in three-phase a.c. Systems-Part 0: calculation of
Currents, IEC, 2016
[12] IEC 60038:2009, standard voltage. International Electrotechnical Commission 2016