Timeline Testing MS

PT Georg Fischer Indonesia

Project Start Date 9/1/2023 (Friday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
28 Aug 2023 4 Sep 2023 11 Sep 2023 18 Sep 2023 25 Sep 2023 2 Oct 2023 9 Oct 2023 16 Oct 2023
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
% WORK
No TASK START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 Spool Group Size 1 Test for MS Standar Sat 9/30/23 -
1.1 Prepare Sparepart for testing Fri 9/01/23 Thu 9/28/23 28 0% 20
1.2 Prepare Component Fri 9/01/23 Thu 9/28/23 28 0% 20
1.3 Jointing Component become spool Mon 10/02/23 Tue 10/03/23 2 0% 2
1.4 Set up Spool for Testing Wed 10/04/23 Thu 10/05/23 2 0% 2
1.5 Testing Spool Fri 10/06/23 Fri 11/24/23 50 0% 36
1.6 Reporting Mon 11/27/23 Mon 11/27/23 1 0% 1
2 Spool Group Size 2 Test for MS Standar - -
2.1 Prepare Sparepart for testing Fri 9/01/23 Thu 9/28/23 28 0% 20
2.2 Prepare Component Fri 9/01/23 Thu 9/28/23 28 0% 20
2.3 Jointing Component become spool Tue 10/03/23 Wed 10/04/23 2 0% 2
2.4 Set up Spool for Testing Thu 10/05/23 Fri 10/06/23 2 0% 2
2.5 Testing Spool Sat 10/07/23 Sat 11/25/23 50 0% 35
2.6 Reporting Wed 11/29/23 Wed 11/29/23 1 0% 1
3 Spool Group Size 3 Test for MS Standar - -
3.1 Prepare Sparepart for testing Fri 9/01/23 Fri 9/01/23 1 0% 1
3.2 Prepare Component Fri 9/01/23 Fri 9/08/23 8 0% 6
3.3 Jointing Component become spool Wed 10/04/23 Thu 10/05/23 2 0% 2
3.4 Set up Spool for Testing Fri 10/06/23 Sat 10/07/23 2 0% 1
3.5 Testing Spool Sun 10/08/23 Sun 11/26/23 50 0% 35
3.6 Reporting Thu 11/30/23 Fri 12/01/23 2 0% 2
-
-