Professional Documents
Culture Documents
Estimation 075bce009 1
Estimation 075bce009 1
INSTITUTE OF ENGINEERING
PULCHOWK CAMPUS
Pulchowk, Lalitpur
24' 24'
12'-0.2" 11'-11.8"
12' 11'-11.8" 12' 11'-11.8"
23' OPENING SCHEDULE
25' 25'
11' 10'-11.9" 11.9"1'-0.2" DOOR D1 3' X 7'
1' 11' 1' 11' 1' 1' 11' 1' 11' 1' D2 3' 6" X 7'
1' 3'-3.2" 1' 3'
D3 2' 6" X 7'
WINDOW W1 5' X 4' 5"
W2 3' X 4' 5"
W3 2' X 2'
W1 W1
1
1
1
1
1
1'
1'
1'
1'
1'
1'
1'
D1
6" HIGH SKIRTING
5'-6.0"
BEDROOM KITCHEN
8'-6.0"
2'
13'
13'
14'
14'
13'
13'
14'
6.0"
14'
13'
13'
14'
W2
6.0"
3'
6.0"
FLOOR FINISH
D1
4.0"
3
4" SCREEDING
2.0"
3" PCC
ONE LAYER FLAT BRICK SOLING
TERRACE TERRACE
2'-6.0"
EARTH COMPACTION
1'-7.0"
2'
3" PCC
W3 D3 2'-5.0"
2
2
2
2
2
3'-4.0"
1'
1'
1'
1'
1'
1'
D1
3'-3.0"
32'-5.0"
32'-5.0"
33'-5.0"
34'-5.0"
34'-5.0"
33'-5.0"
33'-5.0"
34'-5.0"
34'-5.0"
33'-5.0"
1' THICK WALL
11'-6.0"
11'-6.0"
11'-6.0"
12'-6.0"
12'-6.0"
11'-6.0"
12'-6.0"
12'-6.0"
11'-6.0"
11'-6.0"
12'-6.0"
W1 11' x 11'6"
11'x 11' 6"
5'
3'-3.0"
D2
3
3
3
3
3
1'
1'
1'
1'
W1 D1
3'
2.0"
5'-11.0"
6'-11.0"
6'-11.0"
5'-11.0"
6'-11.0"
6'-11.0"
5'-11.0"
6'-11.0"
X
X
3'
4
4
4
4
1'
1'
4
1'
W1
1' 11'-0.2" 1' 3'-6.0" 2' 1' 2'-6.0" 1' 11' 1' 3' 5' 3' 2'-6.0" 1' 11' 1' 3' 5' 3'
24' 24'
A B C A B C A B C
GROUND FLOOR PLAN FIRST FLOOR PLAN
ROOF PLAN
A B C
1'-3.0"
1'
9.0" 6.0"
1'
1'-3.0"
9.0"
1
1
3'-4.0"
2
2
3
3
1'
EAST ELEVATION
4
4
SECTION AT X-X
3'-4.0"
A B C
DRAWN BY ABHINAV SHRESTHA
TRENCH PLAN
CHECKED BY
ARCH. DESIGN
STRUCTURE DESIGN ABHINAV SHRESTHA
SCALE
1:100 W E
WEST ELEVATION NORTH ELEVATION SOUTH ELEVATION DATE S
Details of measurement and quantities (estimate) Framed Structure
2 Earthwork in Filling m3
Bedroom 11' x 11' 6" 1 3.5 3.6 0.825 10.395
Living Room 11' x 11'6" 1 3.5 3.6 0.825 10.395
Kitchen 11' x 13' 1 3.5 3.975 0.825 11.4778125
Bedroom 11' x 8' 9" + Washroom + Space 1 3.5 4.125 0.825 11.9109375
Staircase 1 3.5 1.85 0.825 5.341875
Space in front of the building 1 3.5 1.85 0.825 5.341875
SUM= 54.8625
3 M15 PCC m3
3.1 Column 12 1 1 0.1 1.2
3.2 Walls
i. In X - Direction
1 .23m breadth walls 6 2.6 0.38 0.1 0.5928
2 .15m breadth walls 2 2.6 0.3 0.1 0.156
ii. In Y- Direction
1 .23m breadth walls 2 7.025 0.38 0.1 0.5339
2 .15m breadth walls 1 7.025 0.3 0.1 0.21075
Area = 1/2 * Rise * Tread; Rise = 150 mm,
3.3 Staircase Steps 18 Area= .021 0.9 0.334125 0.020625
Tread = 275mm
SUM= 3.027575
4.3 Beams
4.3.1 Ground Floor
4.3.1.1 In X-axis 4 7.5 0.35 0.35 3.675
4.3.1.2 In Y- Axis 3 10.325 0.35 0.35 3.7944375
4.3.2 First Floor
4.3.1.1 In X-axis 2 7.5 0.35 0.35 1.8375
4.3.1.2 In Y- Axis 2 1.775 0.35 0.35 0.434875
4.3.3 Plinth Beams
4.3.1.1 In X-axis 4 7.5 0.35 0.35 3.675
4.3.1.2 In Y- Axis 3 10.325 0.35 0.35 3.7944375
Deductions
Overlaps 28 0.35 0.35 0.35 1.2005
SUM= 16.01075
4.4 Columns
4.4.1 Ground Floor 12 0.3 0.3 2.5 2.7
4.4.2 First Floor 4 0.3 0.3 2.5 0.9
4.4.3 Roof Floor 4 0.3 0.3 1 0.36
SUM= 3.96
4.5 Lintel & Sill Band Over Door and Windows Assuming 150mm bearing on both sides
4.5.1 D1 4 0.3 0.23 0.1 0.0276 Lintel only for Doors
4.5.2 D2 1 0.3 0.23 0.1 0.0069
4.5.3 D3 1 0.3 0.23 0.1 0.0069
4.5.4 W1 5 0.3 0.23 0.1 0.0345
Lintel and Sill of same width for Windows
4.5.5 W2 1 0.3 0.23 0.1 0.0069
4.5.6 W3 1 0.3 0.23 0.1 0.0069
SUM= 0.0897
TOTAL SUM= 41.49332993
5 Brickwork in Foundation m3
Column
i. First Footing 12 0.725 0.725 0.15 0.946125
ii. Second Footing 12 0.6 0.6 0.15 0.648
iii. Third Footing 12 0.475 0.475 0.15 0.406125
iv. Fourth Footing 12 0.3 0.3 0.7 0.756
Walls
In X - Direction
1 .23m breadth walls
First Footing 6 3.3 0.38 0.15 1.1286 l=3.6-.3/2*2=3.3
Second Footing 6 3.3 0.23 0.4 1.8216 l=3.6-.3/2*2=3.3
2 .15m breadth walls
First Footing 2 3.3 0.3 0.15 0.297
Second Footing 2 3.3 0.15 0.4 0.396
In Y - Direction
1 .23m breadth walls
First Footing 2 9.125 0.38 0.15 1.04025 l=10.025-6*.3/2=9.125
Second Footing 2 9.125 0.23 0.4 1.679 l=10.025-6*.3/2=9.125
2 .15m breadth walls
First Footing 1 9.125 0.3 0.15 0.410625
Second Footing 1 9.125 0.15 0.4 0.5475
Deduction 12 0.075 0.075 0.15 0.010125
SUM= 10.0667
6 Brickwork in Superstructure
Ground Floor
In X - Direction
1 .23m breadth walls 5 3.3 0.23 2.85 10.81575 l=3.6-.3/2*2=3.3
2 .15m breadth walls 3 3.3 0.15 2.85 4.23225
In Y - Direction
1 .23m breadth walls 2 9.125 0.23 2.85 11.962875 l=10.025-6*.3/2=9.125
2 .15m breadth walls 1 9.125 0.15 2.85 3.9009375
3 .15m breadth walls short 1 1.35 0.15 2.85 0.577125
SUM= 31.4889375
Deduction
D1 For .23 1 0.9 0.23 2.1 0.4347
D1 For .15 2 0.9 0.15 2.1 0.567
D2 1 1 0.23 2.1 0.483
D3 1 0.5 0.15 2.1 0.1575
W1 4 1.5 0.23 1.325 1.8285
W2 1 0.9 0.23 1.325 0.274275
W3 1 0.6 0.23 0.6 0.0828
O1 1 0.775 0.15 2.85 0.3313125
O2 1 0.9 0.23 2.85 0.58995
Opening in the staircase 1 1.775 0.15 2.85 0.7588125
Opening in front of the building 1 3.3 0.23 2.85 2.16315
SUM AFTER
23.8179375
DEDUCTION=
First Floor
In X - Direction
Full Walls
1 .23m breadth walls 1 6.9 0.23 2.85 4.52295 l=7.2-.3/2*2=6.9
2 .15m breadth walls 1 6.9 0.15 2.85 2.94975
Parapet Walls 1 6.9 0.23 1 1.587
In Y - Direction
1 Full Walls 2 1.775 0.23 2.85 2.327025 l=2.375-.3*2/2=1.775
2 Parapet Walls 2 7.65 0.23 1 3.519 l =7.95-.3*2/2=7.65
Deduction
D1 1 0.9 0.23 2.1 0.4347
W1 1 1.5 0.23 1.325 0.457125
SUM AFTER
14.0139
DEDUCTION=
Roof
In X - Direction 2 6.9 0.23 1 3.174
In Y - Direction 2 1.775 0.23 1 0.8165
SUM= 3.9905
10 Plastering m2
Plaster of Ceiling in 1:3 Cement Sand
10.1
Mortar
i. Ground Floor
a Bedroom 11'x 11' 6" 1 3.53 3.6 - 12.708
b Living Room 11' x 11' 6" 1 3.37 3.6 - 12.132
c Kitchen 11' x 13' 1 3.37 3.975 - 13.39575
d Bedroom 11' x 8' 9" 1 3.53 2.625 - 9.26625
e Bathroom 1 2.325 1.35 - 3.13875
f Space 3' 5" x 4' 6" 1 1.055 1.35 - 1.42425
g Space in front of building 1 3.678 1.85 - 6.8043
SUM= 58.8693
ii. First Floor 1 7.05 1.85 - 13.0425
Total Ceiling Area to be Plastered= 71.9118
13 Painting Door m2
a D1 4 0.9 - 2.1 7.56
b D2 1 1 - 2.1 2.1
c D3 1 0.5 - 2.1 1.05
SUM= 10.71
15 25 mm DPC 1 m2
15.1 230 mm walls 1 31.75 0.23 - 7.3025 l=perimeter of 230 mm walls
15.2 150 mm walls 1 15.175 0.15 - 2.27625 l=perimeter of 150 mm walls
15.3 Columns 12 0.35 0.35 - 1.47
Deduct
a D1 3 0.9 0.35 - m2 0.945
b D2 1 1 0.35 - 0.35
c D3 1 0.5 0.35 - 0.175
d O1 1 0.775 0.35 - 0.27125
e O2 1 0.9 0.35 - 0.315
f opening in front of staircase 1 1.85 0.35 - 0.6475
g opening in front of building 1 3.19 0.35 - 1.1165
SUM= 3.82025
Total SUM= 7.2285
Schedule of Rates
Earthwork in excavation
A.Cost of materials
Sub-total A= 0.00
B. Cost of Labor
Skilled Manpower 0 /day/m^3 1030 0.00
Unskilled Manpower 0.8 /day/m^3 750 600.00
Sub-total B= 600.00
C. Cost for tool, equipments and plants
3% of the labor cost 18.00
Sub-total C= 18.00
Total= (A+B+C)= 618.00
Contractors overhead and profit(15%)=Sub-total D 92.70
Earthwork in filling
A.Cost of materials
Soil 1.5 m^3 316.8 475.20
Water 5 litre 0.26 1.30
Sub-total A= 476.50
B. Cost of Labor
Skilled Manpower 0 /day/m^3 1030 0.00
Unskilled Manpower 0.5 /day/m^3 750 375.00
Sub-total B= 375.00
C. Cost for tool, equipments and plants
Sub-total C= 0.00
Total= (A+B+C)= 851.50
Contractors overhead and profit(15%)=Sub-total D 127.73
25 mm DPC
A.Cost of materials
Cement 2.25 bags 825 1856.25
Sand 0.113 m^3 3107.7 351.17
12mm aggregate 0.25 m^3 3107.7 776.93
water proofing compound 0.25 kg 350 87.50
Water 56.25 litre 0.26 14.63
Sub-total A= 3086.47
B. Cost of Labour
Skilled Manpower 1 /day/m^3 1030 1030.00
Unskilled Manpower 1.25 /day/m^3 750 937.50
Sub-total B= 1967.50
C. Cost for tool, equipments and plants
Sub-total C= 0.00
Total= (A+B+C)= 5053.97
Contractors overhead and profit(15%)=Sub-total D 758.10
Grand Total= 5812.07
Wooden Frame
A.Cost of materials
Sal Wood 1.8 m^3 5800 10440.00
Hold Fast 92 nos 18 1656.00
Screw 185 nos 5 925.00
Sub-total A= 1656.00
B. Cost of Labour
Skilled Manpower 34 /day/m^3 1030 35020.00
Unskilled Manpower 3.4 /day/m^3 750 2550.00
Sub-total B= 37570.00
C. Cost for tool, equipments and plants
Sub-total C= 0.00
Total= (A+B+C)= 39226.00
Contractors overhead and profit(15%)=Sub-total D 5883.90
Floor Finishing with sand and 3mm cement finishing on top per 10m^2
Name of item Quantity Unit Rate Amount (Rs.)
A.Cost of materials
Sand 6.5 m^3 3145 20442.50
Cement 1.84 bags 825 1518.00
Sub-total A= 21960.50
B. Cost of Labor
Skilled Manpower 7.5 /day/m^3 1030 7725.00
Unskilled Manpower 1 /day/m^3 750 750.00
Sub-total B= 8475.00
C. Cost for tool, equipments and plants
Sub-total C= 0.00
Total= (A+B+C)= 30435.50
Contractors overhead and profit(15%)=Sub-total D 4565.33
Grand Total= 35000.83
Cost per m^2 3500.08
23'-10.1"
1'-2.0"
4'-7.5"
23'-10.1"
7'-10.0" 23'-10.1"
1'-2.0" 3' 3'-9.0" 7'-8.0" 1'-2.0"
1'-2.0" 25' 1'-2.0"
1'-2.0" 25' 1'-2.0"
2'-7.0" 5' 4'-5.0" 3' 1'-10.2" 5'
22'-8.0"
2'-6.0" 22'-8.0" 2'-6.0"
W1
2'-6.0"
1'-2.0"
1'-2.0"
W1
1'-2.0"
1'-2.0"
1'-2.0"
1
1
5'-1.5" D1
BEDROOM KITCHEN
10' 10" x 8' 1.5" 10' 8" x 12' 7.5"
13'-9.5"
13'-9.5"
13'-9.5"
3'
W2
1'-4.0"1'-2.0"
D1
TERRACE TERRACE
22' 8" X 24' 9" 22' 8" X 24' 9"
23'-5.0"
25'-11.0"
D3
2'
25'-11.0"
1'-2.0"
26'-6.0"
25'-11.0"
24'-9.0"
25'-11.0"
W3
24'-9.0"
24'-9.0"
25'-11.0"
24'-9.0"
2
2
D1
3'-3.5"
33'-3.0"
34'-5.0"
33'-3.0"
33'-3.0"
34'-5.0"
33'-3.0"
33'-3.0"
34'-5.0"
33'-3.0"
LIVING ROOM
BEDROOM
12'-1.5"
10' 8" x 10' 11.5"
12'-4.0"
W1
12'-1.5"
10' 10" x 10' 11.5"
5'
10.3"
2'-6.0"
1'-2.0"
1'-2.0"
1'-2.0"
1'-2.0"
1'-2.0"
1'-2.0"
D2
3
3
D1
W1
3'
3'
2.0"
2.0"
7'-4.0"
6'-2.0"
8'-6.0"
7'-4.0"
7'-4.0"
6'-2.0"
7'-4.0"
8'-1.0"
6'-2.0"
6'-2.0"
7'-4.0"
7'-4.0"
7'-11.0"
X
X
3'
X
3'
1'-2.0"
X
1'-2.0"
1'-2.0"
4
4
2'-6.0"
2'-6.0"
W1
2'-6.0"
2'-7.0" 8'-3.0" 3'-6.0" 1'-10.2" 5'
2'-7.0" 8'-3.0" 5' 3'
22'-8.0"
7'-10.0"
1'-2.0" 1'-2.0" 23'-10.1"
1'-2.0" 1'-2.0" 23'-10.1"
25' 1'-2.0" 1'-2.0"
15'-10.0"
25'
A B A B A B
FIRST FLOOR PLAN
3'-4.0"
1'-2.0"
1'-2.0"
EAST ELEVATION
SECTION AT X-X
3
3
4
1'-2.0"
CHECKED BY
6" HIGH SKIRTING
ARCH. DESIGN
3'-8.0"
OPENING SCHEDULE
NORTH ELEVATION
6.0" 1'-4.0"
D1 3' X 7'
DOOR
D2
D3
3' 6" X 7'
2' 6" X 7'
FLOOR FINISH
3
4" SCREEDING
3" PCC
WEST ELEVATION SOUTH ELEVATION STRUCTURE DESIGN ABHINAV SHRESTHA
6.0"
1'-7.0"
2' SCALE
2'-5.0"
3'-4.0" 1:100 W E
2 Earthwork in Filling
a Bedroom 10' 10"x 10' 11.5" 1 3.25 3.29 0.975 m3 10.4252
b Living Room 10' 8" x 10' 11.5" 1 3.2 3.29 0.975 10.2648
c Kitchen 10' 8" x 12' 7.5" 1 3.2 3.79 0.975 11.8248
d Bedroom 10' 10"x 8' 1.5" 1 3.25 2.44 0.975 7.73175
e Bathroom 6' 2" x 3' 4" 1 2 1 0.975 1.95
f Space 3' x 4' 6" 1 0.9 1 0.975 0.8775
g Staircase 10' 10" x 6' 1 3.25 1.85 0.975 5.86219
h Space in front of the building 1 3.2 1.85 0.975 5.772
SUM= 54.7082
3 M15 PCC m3
3.1 PCC in Foundation 1 56.49 1 0.15 8.4735 length= 56.49
3.2 Staircase Steps 18 Area= .021 0.9 0.33413 Area = 1/2 * Rise * Tread; Rise = 150 mm, Tread = 275mm 0.020625
SUM= 8.80763
6 Brickwork in Superstructure
i. Ground Floor 1 61.04 0.35 2.85 m3 60.8874 length= 61.04
Deduct
a D1 3 0.9 0.35 2.1 1.9845
b D2 1 1 0.35 2.1 0.735
c D3 1 0.5 0.35 2.1 0.3675
d W1 4 1.5 0.35 1.325 2.7825
e W2 1 0.9 0.35 1.325 0.41738
f W3 1 0.6 0.35 0.6 0.126
g O1 1 0.775 0.35 2.85 0.77306
h O2 1 0.9 0.35 2.85 0.89775
i opening in front of staircase 1 1.85 0.35 2.85 1.84538
j opening in front of building 1 3.19 0.35 2.85 3.18203
SUM= 13.1111
Total SUM= 47.7763
ii. First Floor
1 Full Walls 1 18.7 0.35 2.85 m3 18.6533 7.15*2+2.2*2
length of full walls=
2 Parapet Walls 1 22.7 0.35 1 7.945 18.7
Deduct 7.775*2+7.15*1
length of parapet walls=
a W1 1 1.5 0.35 1.325 0.69563 22.7
b D1 1 0.9 0.35 2.1 0.6615
Total SUM= 25.2411
iii. Roof
1 Parapet Walls 1 18.7 0.35 1 6.545 7.15*2+2.2*2
length of parapet walls=
18.7
Total Brickwork Sum= 79.5624
10 Plastering m2
10.1 Plaster of Ceiling in 1:3 Cement Sand Mortar
i. Ground Floor
a Bedroom 10' 10"x 10' 11.5" 1 3.25 3.29 - 10.6925
b Living Room 10' 8" x 10' 11.5" 1 3.2 3.29 - 10.528
c Kitchen 10' 8" x 12' 7.5" 1 3.2 3.79 - 12.128
d Bedroom 10' 10"x 8' 1.5" 1 3.25 2.44 - 7.93
e Bathroom 6' 2" x 3' 4" 1 2 1 - 2
f Space 3' x 4' 6" 1 0.9 1.35 - 1.215
g Space in front of building 1 3.54 1.85 - 6.549
SUM= 51.0425
ii. First Floor 1 6.8 1.85 - 12.58
Total Ceiling Area to be Plastered= 63.6225
15 Glazed Window Shutter Frame depth = 75mm, Rebate = 12mm; 75mm-12mm = 63mm
a W1 5 1.374 1.199 8.23713 l=length-2*63;h=height-2*63 1.374 1.199
b W2 1 0.774 1.199 0.92803 0.774 1.199
c W3 1 0.474 0.474 0.22468 0.474 0.474
Total= 9.38983
16 Painting Door m2
a D1 4 0.9 - 2.1 7.56
b D2 1 1 - 2.1 2.1
c D3 1 0.5 - 2.1 1.05
10.71
14 Reinforcement Bars for RCC MT Volume = 2.5% by volume of Total RCC Work = 2.5% of 30.74m^3 (from 3);
6.05152 Density = 7850kg/m^3; Weight = Volume * Desity
Abstract of Cost for Load Bearing Structure
Unit Rate
from SoR
Item No Particulars Quantity Unit (Rs.) Amount (Rs.) Remarks
1 Earthwork in Excavation 56.49 m^3 710.7 40,147.44
2 M15 PCC 8.807625 m^3 15510.67 136,612.16
3 M25 PCC in RCC 30.83576743 m^3 42416.59 1,307,948.10
First class brick work in 1:4 cement sand mortar in Foundation & Upto Plinth Level
4 30.9302875 m^3 15942.23 493,097.76
5 Earthwork in Filling 54.708225 m^3 979.23 53,571.94
6 25 mm DPC 17.54375 m^2 5812.07 101,965.50
7 75 mm lean concrete flooring 65.106 m^2 1268.58 82,592.17
8 12.5 mm cement floor finish 102.6565 m^2 3500.08 359,305.96
9 25 mm cement finish in roof 63.07 m^2 7000.17 441,500.72
10 First Class Brick Work in 1:6 cement sand mortar in superstructure 79.5624375 m^3 15942.23 1,268,402.68
11 12.5 mm Plaster of Indoors in 1:6 cement sand mortar 239.98575 m^2 409.31 98,228.57
12 12.5 mm Plaster of Outdoors in 1:4 Cement Sand Mortar 388.7125 m^2 435.21 169,171.57
13 Plaster of Ceiling in 1:3 Cement Sand Mortar 63.6225 m^2 515.56 32,801.22
14 Distemper of Interior Walls 217.6545 m^2 52.43 11,411.63
15 Water Proof Paint for Exterior Walls 388.7125 m^2 66.73 25,938.79
16 Woodwork for Frame 0.4905 m^3 11422.95 5,602.96
17 Door Shutter 8.575056 m^2 12372.34 106,093.51
18 Glazed Window Shutter 9.389832 m^2 14088.87 132,292.12
19 Painting Door 10.71 m^2 389.85 4,175.29
20 Reinforcement Bars for RCC 6.051519359 MT 128259.5 776,164.85
Sub Total (A) 5,647,024.93
Contingency
General 225,881.00 4% of A
Physical 564,702.49 10% of A
Financial 564,702.49 10% of A
Work 112,940.50 2% of A
Sub Total (B) 7,115,251.41
VAT 924,982.68 13% of B
Grand Total 8,040,234.09
ROAD
Road Alignment
Survey
Legend
Road Centerline
Side Drain
Right of Way
Bridge
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
Pulchowk Campus
Submitted By:
BigyanShrestha
Abhinav Thapa-076bce191
075BCE009
Submitted To:
Asst. Prof. Roshan Karki
Road Alignment
Survey
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
Pulchowk Campus
Submitted by:
Abhinav Shrestha
075BCE009
Submitted to: