Professional Documents
Culture Documents
Design Req IBS Building April2013
Design Req IBS Building April2013
Design Req IBS Building April2013
1
Design Req. For Contractor’s Proposed
IBS Building_Apr13
2
Design Req. For Contractor’s Proposed
IBS Building_Apr13
10.0 STORAGE 17
ATTACHMENT :
Lampiran I : Standardised sizes for beam, column and slab
3
Design Req. For Contractor’s Proposed
IBS Building_Apr13
1. PREAMBLE
2. GENERAL
The Contractor shall also with prior consent of the S.O employ Contractor’s
Professional Engineer (also referred to as Contractor’s PE) for the purposes
of endorsing the design and supervising the construction and completion of
the Works which relates to the Contractor’s Proposed Design.
3.1. Introduction
The Contractor shall take full responsibility for the integrity, thoroughness
and competence of the Contractor’s PE’s report and recommendation that
the relevant work (endorsement and supervision) has been adequately
carried out in accordance with accepted engineering practice, ensuring the
realization of structural integrity and stability of the proposed construction at
site.
3.2. Contractor’s PE
4
Design Req. For Contractor’s Proposed
IBS Building_Apr13
4. DESIGN REQUIREMENTS
Unless specified otherwise, the value of loads selected for design shall
reflect the expected live loads to be exerted on the floor area as well as the
dead load from all other building components including the respective
precast and cast in-situ concrete components.
5
Design Req. For Contractor’s Proposed
IBS Building_Apr13
In general, all precast and cast in-situ concrete structures shall be designed
in accordance to the British Standard BS8110 Part 1: 1997 Structural Use of
Concrete or the equivalent Malaysian Standard or any other equivalent
internationally recognised standards.
All prestressing materials shall be either in the form of wires or strands and
are produced in accordance to the British Standard BS 5896: 1980
Specification for High Tensile Steel Wire and Strand for the Prestressing of
Concrete, or the equivalent Malaysian Standard or any other equivalent
internationally recognised standards. If prestressing strands are used in the
works, they all shall be of the low relaxation type.
6
Design Req. For Contractor’s Proposed
IBS Building_Apr13
The Contractor shall provide the design for the structural system of the
building only, e.g. columns, floor slabs and beams.
7
Design Req. For Contractor’s Proposed
IBS Building_Apr13
The contractor shall ensure that all M&E works are well coordinated with the
structural components.
In the design of the lifting points, when lifting inserts are used, the inserts
shall be designed with minimum factor of safety of 4 at ULS against tensile,
shear and bonding failures. If reusable lifting hardware or rigging are used,
then they shall be designed with minimum factor of safety of 5.
The joint between the stump and the pad footing shall assumed to be pinned
to allow for uniform development of earth pressure under the footing.
8
Design Req. For Contractor’s Proposed
IBS Building_Apr13
Cast insitu infill grout shall be of grade at least 35 N/mm 2 or equal to the
grade for precast component.
When precast concrete wall panels are used as cladding, the inherent load
carrying capacity of these components may not be neglected.
The contractor shall coordinate the design of building and medical services
early to allow for appropriate design provisions be taken into consideration
during the design stage of the structural elements.
The contractor shall designed the structural element of the building in such a
way to enable the forming of all chases, holes and openings required for the
installation of building and medical services to be done during the
manufacturing of such structural element at the factory. The contractor shall
not be allowed to hack or break any building element after casting at the
factory or installation at the site without written consent of the S.O
In the normally dry area (e.g. living rooms, bed rooms and stores) approved
bituminous based water proofing membrane shall be applied on top of the
joint between the slab panels. The end of the membrane shall be at least
200mm away from the end of the precast concrete floor panel in the joint.
In the normally wet area, (e.g. bathrooms, toilets and kitchens), approved
liquid water proofing membrane shall be applied over the entire floor area
with extra 200mm minimum up the walls and vertical pipes. Water proofing
admixtures are also introduced in the concrete screeds that are subsequently
laid on top of the concrete floor topping, if the screeds are specified.
Additives are also added to the concrete placed in the joints to improve
workability and reduce shrinkage.
In both areas (dry or wet), cast in-situ concrete topping of minimum grade 35
N/mm2 shall be laid on top of the waterproofing materials.
9
Design Req. For Contractor’s Proposed
IBS Building_Apr13
In other cases, the minimum concrete topping thickness shall be 30mm only.
In the normally wet areas (e.g. bathrooms, toilets and kitchens), 24-hour
water ponding tests shall be carried out. In this test, the area to be tested
shall be inundated with 50mm deep standing water for a continuous 24 hour
period. After the 24-hour period is over, a thorough inspection is carried out
to detect any sign of water leakage in and around the test area. The test is
deemed successful when no sign of any leakage is detected.
All analysis, calculations and design works carried out for permanent (e.g
beams, columns etc) and temporary (e.g propping, shoring etc) structures
shall be carried out in such a manner to allow ease of checking and
verification. Load combinations shall be clearly itemised and identified to
enable design checking to be carried out upon the most adverse conditions.
The works above shall be documented and compiled in a Design Document.
10
Design Req. For Contractor’s Proposed
IBS Building_Apr13
The Design Document shall be certified and duly signed by the designer of
the structural elements of the building who shall be a current registered
Professional Engineer with the Board of Engineer, Malaysia.
The designer of the structural elements of the building and the Contractor’s
PE shall formalise their endorsements by putting their signatures and
professional seals onto the pages of the consolidated Design Review Report
respectively.
Scheme drawings shall consist of key plans of relevant floors including roofs,
cross-sections of buildings, cross-sections of building components, joints
details and bracing locations.
The drawings shall indicate the locations, sizes and arrangements of vertical,
sloping and horizontal concrete building components, such as floor slabs,
roof slabs, staircases and beams of both, precast and cast in-situ
components.
In addition, the scheme drawings shall also indicate in the plans and
elevations of the building, proposed arrangements of vertical, sloping and
horizontal precast concrete components, such as the precast concrete
columns, precast concrete staircases, precast concrete beams and precast
wall panels.
11
Design Req. For Contractor’s Proposed
IBS Building_Apr13
The magnitude of all loads used in the design of the precast concrete
components shall be clearly stated in the drawings. The Contractor shall also
state clearly in the drawings the designed fire rating of each proposed
structural building component.
To ensure proper handling of the precast concrete components, all lifting and
erection devices shall also be clearly shown in the construction drawings.
12
Design Req. For Contractor’s Proposed
IBS Building_Apr13
The Contractor shall submit the Design Document, the Design Review
Report, Method Statements, Quality Management System and delivery
schedules, duly certified and endorsed by the respective designer of the
structural element of the building and the Contractor’s PE to the S.O.
The Contractor shall also submit all required drawings duly certified and
endorsed by the respective designer of the structural element of the building
and the Contractor’s PE to the S.O.
13
Design Req. For Contractor’s Proposed
IBS Building_Apr13
At the end of the design review and verification process, the Contractor shall
submit the Contractor’s Professional Engineer endorsement and certification
of the design in a consolidated document called certified Design Review
Report to the S.O prior to the commencement of work.
The concrete shall be dense and hard and substantially free from chipped
edges, laitance and honey combs. It shall also be free from fractures and
cracks and from any other defects arising from faulty materials used or from
faulty methods of manufacturing.
The surface of the precast concrete components shall not be coated with
cement wash or any other preparations that may hide the actual condition of
the concrete surface. No repairs shall be permitted on the precast concrete
components under any circumstances.
14
Design Req. For Contractor’s Proposed
IBS Building_Apr13
9. INSTALLATION
9.1. General
The Contractor shall inform the S.O at least one week in advance of each
launching or installation operation and submit the following documents to the
S.O for acceptance:
a. Method statement including launching systems and transportation
b. Proposal for traffic diversion, if appropriate
c. Detailed programme of each launching or installation operation
9.2. Transportation
The Contractor shall obtain the necessary clearances for the transportation
of the precast elements and movement of the lifting equipment to the
launching site. Contractor’s method of transportation shall demonstrate that
the elements being transported would not be damaged.
The Contractor shall ensure that the precast concrete components are
loaded in sequence compatible with the required unloading and erection
sequence on site.
The ground of the launching area shall be prepared at Contractor’s own cost
to ensure that it is safe to carry the required load during installation or
launching operation. To support the assertion that the launching area is safe,
calculations certified by Professional Engineer shall be submitted to the S.O
for approval.
15
Design Req. For Contractor’s Proposed
IBS Building_Apr13
The Contractor shall be responsible for providing true level surfaces on all
site placed bearing walls and other site placed supporting members.
9.5. Erection
The removal of the temporary props, bracing or shoring devices shall only be
done after certification by the Contractor’s Professional Engineer that the
installation is stable and safe and approved by the S.O.
9.6. Alignment
16
Design Req. For Contractor’s Proposed
IBS Building_Apr13
The Contractor shall inform the S.O and obtain his approval before removing
any temporary work but such approval does not relieved the Contractor of his
responsibilities for the safety of the work.
10. STORAGE
If the support is provided at more than two points and the design is based on
more than two supports, precautions must be taken so that the component
shall not bridge over one of the support due to differential support settlement.
Particular care shall be taken for prestressed components, with consideration
made for the effect of prestressing.
17