MAHARASHTRA METRO RAIL CORPORATION LIMITED
No. NMRP/ED-R1/M/s Suhas P Bhave/192 A ]¢ \S2- Date: 31.07.2023
OFFICE NOTE
Subject: Miscellaneous works at various sections of Nagpur Metro Rail Project for
augmentation of the commuter facility. Regarding revised administrative
approval for carrying out soil stabilization activity in CONCOR ROB
approach portion.
Name of Agency: - M/s Suhas P Bhave.
Ref.
. LOA No.: Maha-Metro/ED(Proc)/N1-Misc-68/2022/LOA/811 Dated: 10/10/2022.
. VNIT Preliminary Report dated 25/03/2023.
. GC Letter no. GC/NMRP/ED-R1/S.P.Bhave/Misc. Maintenance/2022/04 dated: 27.03.2023.
. Maha Metro letter no. NMRP/ED-R1/M/s Suhas P Bhave/192 A/6014 dated: 08.05.2023,
. Maha Metro letter no. NMRP/ED-R1/M/s Suhas P Bhave/192 A/6116 dated: 30.06.2023
. M/s Suhas P Bhave letter No: Nil dated: 27.03.2023,
. GC Letter no. GC/NMRP/ED-R1/S.P.Bhave/Misc. Maintenance/2023/08 dated 31.07.2023.
Vide letter under reference 4 above, Administrative Approval for work of CONCOR ROB Soil
stabilization work was accorded by Competent Authority of Maha-Metro for an amount of Rs.
43,67,179)-. (Copy of the letter attached at CP No. 9 and reference note is placed at NP-182)
‘The work was carried out under M/s Suhas P Bhave and duly supervised by Maha Metro Project
and O&M team. As on date, the work has been completed. GC, vide letter under reference 7
above now has submitted the proposal for revised administrative approval of the given work. GC
has stated that as per the actual quantities executed at site, there is variation of quantities and
items with respect to the initial administrative approval by Competent Authority of Maha Metro,
Further, GC has stated that the proposal consists of contractor's claim towards idling charges of
Labour at site for 08 days when the work could not be carried out as the PTW could not be
granted to him. GC has proposed reimbursement of labour rates as per the minimum wages
circular dated 03/04/2023 are being proposed for consideration without any profit towards idling
charges claimed by contractor.
‘As per the proposal submitted by GC, the revised amount for administrative approval comes out
to be Rs. 50,14,556/-(inclusive of GST @ 18%). M/s Suhas P Bhave has quoted an amount of
Rs. 55,16,012/- (CP No. 18 of GC proposal) after considering the contractor's profit @10% over
and above the quoted cost of sub-vendor (M/s S&R Geotechniques Pvt. Ltd.)
The original awarded cost of work is Rs. 7,93,01,667/-. As per the last varlation proposal duly
approved by Competenet Authority of Maha Metro and conveyed vide letter under reference 5
above, the revised contract value already approved is Rs. 10,75,94,755/- (35.68% above the
original contact value) (refer CP No. 19 & 20 of GC proposal). After considering the current
proposal of Rs. 55,16,012/- as submitted by GC, the revised contract value comes out to be Rs.
11,31,10,767/- (i.e. 42.63% above the original contract value).As per amendment to para W9 (v) of SOP vide note bearing no. Maha-Metro/DF-2021 dated:
10.03.2021, it is in the power of Director Projects to accord Administrative Approval to the given
Proposal. In view of above, Competent Authority of Maha-Metro is requested to accord
Administrative Approval to the variation proposal of Rs. 55,16,012/- towards work of soil
stabilization work of CONCOR ROB with revised contract value arriving tentatively at Rs.
11,31,10,767/-.
Put up for perusal and approval of Competent Authority.
Manager (Civil)
by. conf &PS otemeee Atl
MAHARASHTRA METRO RAIL CORPORATION LIMITED
Note
NMRP/ED-R1/M/s Suhas P Bhave/192A/545'6 Date:- 01/04/2023
Subject: “Miscellaneous work at various sections of Nagpur Metro Rail Project for
‘augmentation of the commuter facility”.
‘Administrative approval for carrying out Soil stabilization activity in CONCOR
ROB approach portion,
Name of Agency:- M/s. Suhas P Bhave, Contractor, Nagpur
Reference:-
LOA No. Maha- Metro/ED(Proc)/N1-Misc-68/2022/LOA/811 Dated. 10/10/2022
VNIT Preliminary report dated. 25/03/2023
GC/NMRP/ED-R1/S.P.Bhave/Misc. Maintenance/2022/03 dated. 25/02/2023
Office of ED/R-1 note no. NMRP/ED-R1/M/s Suhas P Bhave/192A/5934 dated
14.03.2023.
5. GC/NMRP/ED-R1/S.P.Bhave/Misc. Maintenance/2022/04 dated. 27/03/2023
1. M/s. Suhas P Bhave was awarded the above mentioned work for total contract of
Rs.7,93,01,667.45/- (Inclusive of GST and all taxes)
2. Competent Authority of Maha Metro vide note dated 14.03.2023 under reference ‘4’
above has accorded Administrative Approval for a tentative variation amounting to
Rs. 2,83,42,000/- which includes extra items and quantity variation in Reach-i
fon in schedle and schedule
amounting to Rs.96.2? lakhs as well as quantity var
D as per O&M instructions amounting to Rs.95.20 Lakhs and Rs, 92.00 Lakhs as
submitted by GC vide letter under reference ‘3’ above. (Copy of the Administrative
Approval attached at NP-OL to 07.
Recently, a settlement of magnitude 24mm was observed at Nagpur side of CONCOR
ROB.
4. O&M department of Maha Metro requested Experts from VNIT to study the matter
and suggest remedial measures. In response, VNIT has proposed a scheme of soit
stabilization underneath track grade slab vide preliminary report (reference ii) placed
atcp.3t04.
5. GC was asked to carry out remedial work of soil stabilization urgently since track at
above location is in dangerous condition and further settlement at above location can
disrupt train movernent beyond New Airport Station.
6. Inresponse, GC has proposed to carry out this soil stabilization work through existing
contract of M/s Suhas P. Bhave (reference 2 and 4 above). This variation will be
amounting to additional Rs. 43,67,179/- considering 10% over and above the quoted
cost of (sub-vendor M/s S&R Geotechniques Pvt, Ltd.). The quantity estimated at
is tentative and can vary during actual execution at site.
implication on account of above-mentioned variation is as follows.
9% Vatiati
7,93,01,667.00
2,83,42,000.00 | 35.74%
2 | Administratively approved Vari
Proposal -O1
3__ | Current variation proposal __43,67,479.00 | 5.50%
5 | Revised contract value 41.24%8. In view of urgency, and in line
Variation to subject contract tents
under consideration
11,20,3 ln.
Put up for perusal and for Administrative approval of Coitbetent Authority in tine with paras
608 above.
by. combat Beda wl
a domes