Daily Report Dated 21 - 22 November 2017
Daily Report Dated 21 - 22 November 2017
- Installation cable power 3 x 2.5m of 5 unit & Pulling cable of 50m (Complete) - Installation cable power 3 x 2.5m of 5 unit & Pulling cable of 50m (Complete)
- Painting wall (containers site office no.2 & no.3 complete and Container no.4 continue) - Painting wall (containers site office no.2 & no.3 complete and Container no.4 continue)
- Fabrication & Install for support AC Office of 4 unit (Continue) - Fabrication Door & Windows Container 3 & 4
- Installation Pipe Septic tank & Ceramic installation - Installation Pipe Septic tank (Completed) & Ceramic installation (Continue)
2 Construction 2 Construction
- Handover foundation, dimension foundation & top of concrete elevation for coloumn G - H (Coloumn 12 & 11A Complete) - Continue Handover foundation, dimension foundation & top of concrete elevation for coloumn K - P
- Continue Handover foundation, dimension foundation & top of concrete elevation for coloumn K - P - Chipping foundation for Coloumn G-6A & G-7 & Coloumn H-6A & G-7
- Chipping foundation for Coloumn G-H (12 & 11A) - Check foundation for Coloumn G-10A, G-8A & Coloumn H-10A, H-8A (Continue)
- Preparation assembly starway structure at Laydown - Install Packer Plate or Coloumn G-H (12 & 11A) (Completed) and Waiting Curing Time
- Preparation assembly starway structure at Laydown (1SL-3 & 1SL-4, 2SL-3 & 2SL-4, U2SL-3 & U2SL-4, 1SL-5 & 1SL-6, 2L-1 & 2SL-2, L-SL3 & L-SL-4, L-3-SL-1 &
- Preparation Nut (Top Plate/Wassher) & Cleaning for first coloumn - Boiler Unit 1 L-3-SL-2) & Install Grating starway 111 pcs
- Prepare or Check material Frame Starway, Check Grating Stair Tread and Check bolt nut stair - Preparation Nut (Top Plate/Wassher) & Cleaning for first coloumn - Boiler Unit 1 (Continue)
- Prepare Colour Code Material Scaffolding 1m of 150 lgh, 1.5m of 50 lgh & 6m of 50 lgh - Prepare or Check material Frame Starway, Check Grating Stair Tread and Check bolt nut stair (Continue)
- Prepare Colour Code Clamp ( Fixed Clamp of 2000 each, Swifel Clamp of 1000 each, Beam Clamp of 400 each, Joint Clamp of 1000 each & Base Clamp of 500 each) - Prepare colour code asiba plank (4m of 100 each completed, 3m of 400 each & 1m of 400 each)
- Loading material scaffolding to Boiler Area - Install scaffolding for hard baricade to chipping concrete coloumn of 2 unit
- Fabrication Packer Plate (230 x 300 x 16t of 14 pcs), (130 x 200 x 16t of 56 pcs), (230 x 300 x 12t of 21 pcs) & Packer Plate (130 x 200 x 12t of 84 pcs) - Installation scaffolding for genset machine selter of size 6m x 3m (completed)
- Making formwork for concrete block 24 sets complete & 6 sets on progress - Fabrication Packer Plate (230 x 300 x 16t of 14 pcs), (130 x 200 x 16t of 56 pcs), (230 x 300 x 12t of 21 pcs) & Packer Plate (130 x 200 x 12t of 84 pcs)
- Fabrication Rebar for concrete block 30 sets (Complete) - Making formwork for concrete block 24 sets complete & 6 sets on progress completed
- Pouring Concrete Block 17 sets Complete , 7 sets On Progress and 6 sets Continue - Pouring Concrete Block 24 sets Complete , 6 sets On Progress
- Check material coloumn at Laydown PT. JEL (Continue) - Prepare Ligting Lug & Sling at warehouse PT. JEL, Prepare plate for position Crane at Boiler area & Reposisi Concrete Block (Continue)
1 - 1
2 2
3 3
4 4
5 5
6 6
Manpower - Manpower - OT
Man-hour Normal hrs ( 7am hrs - (16pm to Total Hr
to 15pm ) 18pm)
Yesterday (22/11/2017)