Professional Documents
Culture Documents
Measuring and Modeling Balanced and Unbalanced Single Circuit Lines Paper ISH 2011 Devilliers ENU
Measuring and Modeling Balanced and Unbalanced Single Circuit Lines Paper ISH 2011 Devilliers ENU
Abstract: Accurate parameters of a line are very important for protection settings
(distance protection relays and fault locators) and power system modelling. Power system
calculations and protection settings are often based on balanced line models. However,
most operational overhead transmission lines or HV cables are unbalanced. Different
models for unbalanced and balanced lines and the associated symbols are presented
since confusion of parameters has to be avoided. The conversions between the models
are stated. The paper proposes a practical method to determine the symmetrical
components of an unbalanced single-circuit by means of performing measurements. The
measurement procedure, equipment used and associated calculations to compute
symmetrical components are described. Different methods to calculate the line
impedances from the measurements are in detail discussed and analyzed. A case study
is presented and the results are assessed.
three non-diagonal elements ZL12, ZL13 and the non-diagonal element ZL12.
ZL23.
2.4 Symmetrical Components of a Balanced
IL1 ZL12 ZL13 ZL11
Line
IL2 ZL23 ZL22 The impedance matrix of the balanced single-
circuit line in symmetrical components is
IL3 ZL33 uncoupled
1 a
a the zero sequence impedance Zs00.
2
1
T 1 a a
2
(3) Is1 Zs11
3
1 1 1 positive Us1-
Us1
sequence Us1
The diagonal elements Zs11 and Zs22 are equal the element of phases Zp and
Zs11 Zs22 (6)
the element of earth ZE.
It should be mentioned that this model should only
2.3 Physical Model of a Balanced Line be applied for balanced line modelling. It is not
The entries of the impedance matrix of a balanced useful to assign the phase elements different
line meet the conditions values, like
ZL12 ZL13 ZL23 and ZL11 ZL22 ZL33 (7) Zp1 Zp2 Zp3 (9)
The model of a balanced line is determined by two in order to model unbalanced lines. The
parameters differences of the phase elements only influence
the diagonal elements of the physical model (see
the diagonal element ZL11 and
XVII International Symposium on High Voltage Engineering, Hannover, Germany, August 22-26, 2011
equation (1)). Additionally, a model with four ZLii is the arithmetic mean value of the
parameters is created instead of the models in
section 2.1 and 2.2, which both contain six diagonal elements of the unbalanced
parameters. physical model and
IL1 Zp
ZLik is the arithmetic mean value of the
non-diagonal elements of the unbalanced
IL2 Zp UBa=UAa-Ua+UE physical model.
Equation (12) and (13) are important on a
IL3 Zp UBb=UAb-Ub+UE
measurement point of view. They point out that the
parameters of a balanced line model can be
UBc=UAc-Uc+UE determined by calculation of the arithmetic mean
UAa UAb UAc
value using the measurement values of an
IE ZE unbalanced line.
The equations to convert the parameters of the 4.1 Measurement of Line Parameters
different models are specified in this section.
With a single-phase source seven measurements
The equation to transfer the unbalanced models is can be performed (see section 5.3). Every
already specified in equation (4). unbalanced model is described by six parameters;
every balanced model is described by two
3.1 Conversion Between Balanced Line parameters. This means there are measurements
Models left for a plausibility check.
The three balanced models presented in sections Table 1 shows the measured loops, the measuring
2.3, 2.4 and 2.5 are completely equivalent results and the determined parameters for an
according to the boundary condition unbalanced line. Equation (12) and (13) are used
to determine the parameters of a balanced line
IE IL1 IL2 IL3 (9) model.
The three models are defined by two parameters. Table 1: Measured loops, measuring results and
These parameters can be converted with determined parameter
and U m U L1 U L3
L1-L3 ZL13
Zs00 Zp 3ZE ZLii 2ZLik (13) Im I L1
ZL11 ZL33 2ZL13
where
XVII International Symposium on High Voltage Engineering, Hannover, Germany, August 22-26, 2011
U m U L2 U L3 5 CASE STUDY
L2-L3 ZL23
Im I L2 5.1 Malfunction of Distance Protection Relay.
ZL22 ZL33 2ZL23 A line fault occurred in close vicinity to Substation
B on the transmission line between Substation A
“U0- U m Us0 1 and B (Figure 5). Both relays at Substation A and
Zs00 Zs00
Substation C interpreted the fault as ZONE 1 and
3I0” Im 3Is0 3 consequently both relays tripped. The relay at
station C consequently overreached and
incorrectly tripped the line between Substation B
and Substation C.
4.2 Calculations and Modern Measurement
Equipment A B C
Compared to calculations, measurements of line
parameters including the k-factors are relatively Figure 5 Line diagram indicating the position of the
straightforward, when using modern measurement fault.
equipment.
The affected utility experiences an unnecessary
Historically, the problem when measuring line false trip and decided to measure the sequence
parameters was to overcome disturbances and impedance to check the relay settings.
interferences from other live systems. Therefore,
either currents close to or above the nominal 5.2 Line Data
current had to be used. Alternatively, big diesel
generators were needed to allow the beat method The 115 kV overhead transmission line, between
to be applied. substation B and C, was 9.5 km long. The line is
not transposed and consists of a mixture of vertical
Today, electronic generators allow the use of and delta tower types, as depicted in (Figure 6).
signals with frequencies shifted away from the The phase allocations are also indicated in Figure
mains. By applying a frequency-selective 6.
measurement that measures only the part of the
incoming signal that matches the generated The k-factor setting of the relay was based on the
frequency accurate results are delivered - even in following simulated sequence impedance data:
an environment that experiences major
Z s 00 _ SIM
disturbances. With this method it is possible to k o _ SIM
work with currents that are a fraction of the nominal Z L _ SIM
line current and consequently the weight of the
equipment becomes comparable with components 3.643 - 5.23
weighing less than 30 kg (Figure 4). where : (14)
Surge arrestors that are part of the measurement Z s11_ SIM 0.6213 3.9675i
system can safely discharge currents of up to 30
kA to ground. These provide optimum safety during Z s 00 _ SIM 3.5713 14.1882i
testing in case of an unexpected event on the
cable, such as a fault on an adjacent system. 5.3 Practical Measurements
In total, seven measurements per system were
performed, three for each combination of phase-to-
phase loops (Figure 7), three for each phase-to-
ground (Figure 8) and one for all three phases-to-
ground (Figure 9).
L1
A
L2
L3
Ground wire
L1
A
L2
V
L3
Figure 6 Overhead transmission in case study
Ground wire
L1
A
L2
Table 2 Positive sequence impedance and It is remarkable to note that the two calculations,
average calculated from the individual phase-to- which are based on different measurement loops,
phase loops. deliver nearly identical values for the zero
sequence impedance when comparing the result
R [Ω] X [Ω] Z [Ω] Phi (°) obtained from equation 17 with the average value
Zs11(L1) 0.627 4.186 4.233 81.479 in Table 3.
Zs11(L2) 0.628 3.567 3.622 80.011 Finally, the measured k-factors can be expressed
as
Zs11(L3) 0.696 4.163 4.221 80.514
Z s 00( M 7 )
Zs11 ko 2.455 - 5.13 (18)
(Average) 0.650 3.972 4.025 80.702 Z s11
This measured k-factor differs 48.4% (in
From this result, a close correlation can be noted magnitude) from the original k-factor which the
by comparing this measured result (Table 2) with utility obtained by using a simulation program.
original calculated line data as given in equation It was interesting to note that after some detailed
(14). investigations, the utility discovered that the
From the next three phase-to-ground loop change from steel ground wire to optical ground
wire (OPGW) was not incorporated in the
measurements (ZM4 to ZM6), the individual earth
simulation program. Due to potential errors that
impedances and consequently the average earth
can occur by using simulations and calculations,
impedance can be calculated. For phase 1 the
the utility decided to measure the line impedance
earth impedance can be calculated as follows:
of all major lines to ensure correct relay settings
U and thereby avoiding unnecessary false trips.
Z E _ FROM _ M 4 LE Z L Z M 4 Z L1
I LE (16)
By substituting the measured phase impedance Overhead lines and cables are normally
and earth impedance values to equation 13 the unbalanced but short circuit calculation and
zero sequence impedance can be calculated. The distance protection are using the balanced models.
results are shown in Table 3. Therefore, a conversion from unbalanced to
Table 3 Zero sequence impedance and average balanced models is needed. The different models
calculated from the individual phase to ground and conversion between models are described in
loops. this paper. A practical case study highlights the
importance to measure the sequence impedance
R [Ω] X [Ω] Z [Ω] Phi (°) since simulations are prone to errors. The case
study also shows how practical measurements of
Zs00(L1-E) 2.428 8.858 9.185 74.670 an unbalanced line can be used to get the right
Zs00 (L2-E) 2.376 10.497 10.763 77.246 parameters for distance protection relay settings.
The distance protection relay would have operated
Zs00 (L3-E) 2.438 9.374 9.686 75.422 correctly (not over-reaching) if the settings were
Zs00 based on the measured sequence impedance data
at the time of the fault.
Average 2.414 9.577 9.876 75.851