Interim Payment Valuation under the terms of the Contract
MASTERPIECE VILLA, SIX SENSES ULUWATU
For the works known as: Date of Application: 30-May-22 BALI
LS Ref Q.22/1137 Date of Valuation: 30-May-22
Package: Main Contract Masterpiece Villa For Cartificate No.: 1
Requires that an interim payment as detailed below is due:
From the Employer: HARTONO FRANSCESCO
Cluster Bellagio F6 No. 2
RT/RW 004/005
Serpong
To the Contractor: PT. TRIYAMA MITRA PERSADA
Jl. Palapa Raya No. 1 Ruko Green Park Tangerang Selatan
Commencement Date: Works carried out by Contactor Rp. -
Contract Completion Date: Variation orders Rp. -
Time for Completion (days): Sub-total Rp. -
Percentage time complete: Less Retention 5% Rp. -
Contact Sum (excl PPN) Rp 10,243,820,180 Sub-total Rp. -
Add Advace payment 20% Rp. 2,048,764,036
Sub-total Rp. 2,048,764,036
Percentage value complete 0.0000% Rp. -
Less Sums previously certified Has the Taking-over Certificate been issued? No Rp. 2,048,764,036 (Yes/No) Sub-total Retention Calculation 5% Value of work Rp. 0 Add PPN (11%) Rp. 225,364,044
Rupiahs, Two Billion Two Hundred Seventy Four Million One
Amount due for payment Rp. 2,274,128,080 Hundred Twenty Eight Thousand and Eighty Rupiah
Prepared by Accepted by
Signed Putu Arya Canti (Director) Signed: Hartono Franscesco
For and on behalf of PT. Lantera Sejahtera Indonesia