Precedence Networks
Precedence networks
Precedence networks are the most common type of network
schedule in use today
1
3/20/2023
Precedence networks
Often called Precedence Diagramming Method (PDM)
Precedence networks
In precedence diagrams,
activities are represented as
Install roofing
nodes
Relationships are
represented as arrows
Set trusses and
Note that “install roofing” roof frame
can not start until “set
trusses and roof frame” has
been completed
An activity can not start Install siding
also until all its
predecessors have been
completed
2
3/20/2023
Precedence networks
15 19
Early Start Date Early Finish Date
510
Activity ID
Rebar slab on grade
Activity Description Area
4
Duration
21
Late Start Date 25
Late Finish Date
Precedence networks
Note that all activities except Mobilize equipment
3
3/20/2023
Precedence networks
Mobilize equipment
5
Burst
Obtain permits
3
Precedence networks
Issue Taking over
certificate
Merge
Remedy defects
4
3/20/2023
Precedence networks
When more than one Mobilize equipment
5
activity starts or ends the
network, a milestone must
be added to the precedence
network to adhere to the
one activity start, one Notice to Proceed
0
Erect site fence
2
“Notice to Proceed”
Precedence networks
Issue Taking over
certificate
Remedy defects
5
3/20/2023
Precedence networks
Issue Taking over
certificate
(right to left)
connecting arrows
Remedy defects
6
3/20/2023
Network Calculations
7
3/20/2023
Forward pass
The forward pass establishes the early start (ES) and early
finish (EF) dates for each activity
ES and EF calculations
ES and EF calculations
8
3/20/2023
ES and EF calculations
ES and EF calculations
9
3/20/2023
ES and EF calculations
ES and EF calculations
Note that ES and EF are calculated from the first activity in
the network to the last activity
10
3/20/2023
Backward pass
The backward pass provides the late start (LS) and late
finish (LF) for each activity
These dates are shown below each box and are used to
show the criticality of each activity and to identify any
available float
LS and LF calculations
Late Start (LS)
The latest time that an activity can start without
delaying the project completion
11
3/20/2023
LS and LF calculations
Late FinishActivity = Minall successors (Late StartSuccessor)
LS and LF calculations
12
3/20/2023
LS and LF calculations
Backward pass
Note that the backward pass begins at the last activity in
the network and proceeds until the first activity in the
network
For the last activity in the network, we set
LF = EF
LS = ES
The result of the backward pass should show that
LS = ES for the first activity in the network
13
3/20/2023
Network Calculations
Example
Float
Total Float (TF)
The amount of time that an activity can be delayed
before it impacts the completion date of the project
14
3/20/2023
Float calculations
Total Float Activity = Late Finish Activity - Early Finish
Activity
TF Activity = LF Activity – EF Activity
TF Activity = LS Activity – ES Activity
Example
12
6 12 16
C R
6 4
10 16 20
16
5 6 6 9 9 23
G L A
1 3 14
6 9 9 23
6 16 16 18
O J
10 2
8 18 18
20
15
3/20/2023
Critical path
The path(s) from the first activity to the last activity in the
network that passes through only those activities that have a
TF of Zero
Relationships Types
16
3/20/2023
Lag
Lag is the amount of time that exists between the EF of
an activity and the ES of a specified succeeding activity
(in the case of FS)
FS with a lag value other than Zero are often used to
account for resource constraints such as: concrete
curing, crane movement, or equipment utilization
17
3/20/2023
Note that “Cure Concrete” consumes time only and uses no resources
Basically, used to enforce a delay on the succeeding activity
We can make use of FS28
TF = LF Act – EF Act
18
3/20/2023
19
3/20/2023
20
3/20/2023
TF = LF Act – EF Act
21
3/20/2023
22
3/20/2023
(4) Start-To-Finish
Used to identify activities whose starts are related to the
follower’s finish
Set concrete
Tie rebar Pour concrete
forms
5
SF
Order concrete
from supplier
23
3/20/2023
(4) Start-To-Finish
In this example, order of ready-mix concrete has to be
placed 5 days prior to pouring the concrete
(4) Start-To-Finish
24
3/20/2023
Example
25
3/20/2023
Example
26