Professional Documents
Culture Documents
Section 2 - Contract (Brothers Concept) June 23
Section 2 - Contract (Brothers Concept) June 23
Section 2 - Contract (Brothers Concept) June 23
JAMES
Bill Nr.2 - MEASURED WORKS
FACILITATION WORKS
DEMOLITION
Site Generally
Individual Structures
E Take down all equipment for tennis court and set aside
as instructed by the Supervising Officer. 1 Sum $60,000.00 $60,000.00
MBRC/2.0/1/1
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
SUBSTRUCTURE
DISPOSAL
FILLING TO EXCAVATIONS
TO COLLECTION $3,697,620.00
MBRC/2.0/2/2
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
D 16mm diameter in strip foundation as links. (In Nr.624) 985 kg $290.00 $285,650.00
Formwork
BLOCK WALLING
TO COLLECTION $11,752,970.00
MBRC/2.0/2/3
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
BLOCK WALLING
TO COLLECTION $44,080.00
COLLECTION
SUBSTRUCTURE $15,494,670.00
TO SUMMARY
MBRC/2.0/2/4
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
FRAMING
K 10mm diameter in beams and belt beams as stirrups. 1257 kg $290.00 $364,530.00
(In Nr.1360)
nd th
Second (2 ) to Fifth (5 ) Floors
N 10mm diameter in beams and belt beams as stirrups. 5818 kg $290.00 $1,687,220.00
[In Nr.6298]
TO COLLECTION $15,169,930.00
MBRC/2.0/3/5
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
E 10mm diameter in beams and belt beams as stirrups. 628 kg $290.00 $182,120.00
[In Nr.1020]
th
Seventh (7 ) Floor
K 10mm diameter in beams and belt beams as stirrups. 1543 kg $290.00 $447,470.00
[In Nr.1670]
Circular Columns
Formwork
st
First (1 ) Floor
N Sides and soffit of beams. 153 m2 $4,150.00 $634,950.00
nd th
Second (2 ) to Fifth (5 ) Floors
Q Sides and soffit of beams. 620 m2 $4,150.00 $2,573,000.00
TO COLLECTION $7,229,740.00
MBRC/2.0/3/6
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Formwork
th
Sixth (6 ) Floor
A Sides and soffit of beams. 80 m2 $4,150.00 $332,000.00
Circular Columns
TO COLLECTION $1,884,750.00
COLLECTION
FRAMING $24,284,420.00
TO SUMMARY
MBRC/2.0/3/7
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
BLOCK WALLING
Formwork
PLANTERS
J 10mm diameter in beams and belt beams as stirrups. 131 kg $290.00 $37,990.00
[In Nr.213]
FORMWORK FOR INSITU CONCRETE
Formwork
TO COLLECTION $8,998,390.00
MBRC/2.0/5/9
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
PLASTERED/RENDERED/ROUGHCASTCOATINGS
C Sides of staircase 300mm cut to profile of tread and risers. 70 m $1,200.00 $84,000.00
STONE/CONCRETE/QUARRY/CERAMICTILING/ MOSAIC
Porcelain Tiling
PAINTING/CLEAR FINISHING
I Sides of staircase 300mm cut to profile of tread and risers. 70 m $300.00 $21,000.00
K 12mm x 50mm post 1050m high with one (1) end plated
with 200mm x 200mm, 6mm thick plate and bolted to 84 m $5,100.00 $428,400.00
concrete floor.
TO COLLECTION $4,299,120.00
MBRC/2.0/5/10
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
PAINTING/CLEAR FINISHING
A Metal work of girth not exceeding 250mm girth. 504 m $260.00 $131,040.00
MBRC/2.0/5/11
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Formwork
PLASTERED/RENDERED/ROUGHCASTCOATINGS
TO COLLECTION $1,653,110.00
MBRC/2.0/5/12
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
th
The following in 4 No. Staircases at Fifth (5 ) and
th
Sixth (6 ) Floors
PLASTERED/RENDERED/ROUGHCASTCOATINGS
STONE/CONCRETE/QUARRY/CERAMICTILING/ MOSAIC
Porcelain Tiling
PAINTING/CLEAR FINISHING
TO COLLECTION $2,132,700.00
MBRC/2.0/5/13
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Formwork
STONE/CONCRETE/QUARRY/CERAMICTILING/ MOSAIC
Porcelain Tiling
TO COLLECTION $610,969.00
MBRC/2.0/5/14
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
th
Staircase from Sixth (6 ) Floor to Roof
PAINTING/CLEAR FINISHING
PAINTING/CLEAR FINISHING
F Metal work of girth not exceeding 100mm girth. 840 m $250.00 $210,000.00
TO COLLECTION $694,380.00
COLLECTION
UPPER FLOORS
CONCRETE WORKS
Formwork
Q Soffit of slab. st
[First (1 ) Floor] 925 m2 $4,150.00 $3,838,750.00
R Soffit of slab. nd th
[Second (2 ) - Fifth (5 ) Floors] 2848 m2 $4,150.00 $11,819,200.00
S Soffit of slab. th
[Sixth (6 ) Floor] 611 m2 $4,150.00 $2,535,650.00
T Soffit of slab. th
[Seventh (7 ) Floor] 640 m2 $4,150.00 $2,656,000.00
TO COLLECTION $20,000,544.00
COLLECTION
Formwork
CEMENT:SAND/CONCRETE SCREEDS/TOPPINGS
TO COLLECTION $5,357,010.00
MBRC/2.0/7/19
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Waterproofing
PAINTING/CLEAR FINISHING
Knot, prime, stop and apply one (1) undercoat and two
(2) coats acrylic enamel on:
IRONMONGERY
TO COLLECTION $2,497,637.50
MBRC/2.0/7/20
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
COLLECTION
MBRC/2.0/7/21
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
GENERAL FIXTURES/FURNISHINGS/EQUIPMENT
The following primed structural steel work is to be
fabricated and installed on the roof of a seven (7) storey
building; the Contractor shall make all necessary
allowances for transporting, hoisting, framing and
erecting the works:
E Allow for all additional plates and clips necessary for the
fabrication and erection of the metal work. 1 Sum $500,000.00 $500,000.00
Sheeting
IRONMONGERY
PAINTING/CLEAR FINISHING
MBRC/2.0/8/22
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
WINDOWS/ROOFLIGHTS/SCREENS/LOUVRES
MBRC/2.0/9/23
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
WINDOWS/ROOFLIGHTS/SCREENS/LOUVRES
Screens
IRONMONGERY
TO COLLECTION $16,222,727.09
MBRC/2.0/9/24
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
DOORS/SHUTTERS/HATCHES
TO COLLECTION $15,508,042.11
MBRC/2.0/9/25
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
DOORS/SHUTTERS/HATCHES
TO COLLECTION $8,788,136.70
MBRC/2.0/9/26
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
COLLECTION
Extra for:
MBRC/2.0/10/28
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
INTERNAL DOORS
DOORS/SHUTTERS/HATCHES
G Door overall size 1829mm x 2388mm with equal leaves. 1 Nr $110,261.37 $110,261.37
(D/05)
TO COLLECTION $6,574,754.04
MBRC/2.0/11/29
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
DOORS/SHUTTERS/HATCHES
IRONMONGERY
PAINTING/CLEAR FINISHING
Knot, prime, stop and apply one (1) undercoat and two
(2) finishing coats gloss oil paint on:
TO COLLECTION $3,088,281.78
COLLECTION
FLOOR FINISHES
STONE/CONCRETE/QUARRY/CERAMICTILING/ MOSAIC
Mosaic Tiling
PAINTING/CLEAR FINISHING
G Prepare and apply one (1) undercoat and two (2) finishing
coats emulsion paint on Plycem skirting 200mm high. 855 m $230.00 $196,650.00
MBRC/2.0/12/31
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
WALL FINISHES
PLASTERED/RENDERED/ROUGHCASTCOATINGS
STONE/CONCRETE/QUARRY/CERAMICTILING/ MOSAIC
I 300mm x 200mm glazed ceramic porcelain tiles
(PC Sum $600.00/tile) fixed to masonry walls with an
approved adhesive and grouted in matching grout. 960 m2 $14,760.00 $14,169,600.00 10200 33.552632 4560
(Provisional)
TO COLLECTION $63,448,520.00
MBRC/2.0/13/32
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
PAINTING/CLEAR FINISHING
TO COLLECTION $11,886,000.00
COLLECTION
MBRC/2.0/13/33
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
CEILING FINISHES
Ground Floor
First (1st) Floor
Second (2nd) - Fourth (4th) Floors
Fifth (5th) Floor
Sixth (6th) Floor
Equipment Room
Stair wells
PAINTING/CLEAR FINISHING
Prepare and apply one (1) undercoat and two (2) finishing
coats emulsion paint on:
MBRC/2.0/14/34
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
KITCHEN CUPBOARDS
TO COLLECTION $24,491,500.00
MBRC/2.0/15/35
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
BATHROOM CUPBOARDS
SHELVING
TO COLLECTION $13,839,890.00
MBRC/2.0/15/36
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
COUNTERTOPS
TO COLLECTION $8,834,670.00
MBRC/2.0/15/37
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Handrails
Shading Devices
TO COLLECTION $36,197,000.00
COLLECTION
MBRC/2.0/15/38
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
RECREATIONAL AMENITIES
SWIMMING POOL
Formwork
PLASTERED/RENDERED/ROUGHCASTCOATINGS
PROVISIONAL SUMS
SANITARY APPLIANCES
SANITARY APPLIANCES/FITTINGS
Water Closets
Lavatory Basins
Shower Trays
Bath Tubs
Kitchen Sinks
Laundry Bowls
F Stainless steel single bowl laundry sink (PC Sum
$30,000.00) with trap and connecting to supply and
waste pipes. 24 Nr $40,000.00 $960,000.00
TO COLLECTION $25,669,800.00
MBRC/2.0/17/40
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
E Toilet roll holder (PC Sum $10,000.00) fixed to wall. 55 Nr $12,500.00 $687,500.00
MIRRORS
TO COLLECTION $7,543,055.00
COLLECTION
EXTERNAL WORKS
SUBSTRUCTURE
Disposal
B Excavated material disposed off site. 3 m3 $1,500.00 $4,500.00
Filling to Excavations
D Filling with excavated material from foundations. 3 m3 $800.00 $2,400.00
TO COLLECTION $327,950.00
MBRC/2.0/18/42
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
SUBSTRUCTURE (Cont'd)
TO COLLECTION $661,810.00
MBRC/2.0/18/43
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Cement:Sand/Concrete Screeds/Toppings
E Cement and sand (1:3) screed laid on roof slab. 13 m2 $2,260.00 $29,380.00
Membrane
F 5mm thick waterproofing membrane as supplied by
Spectrum Systems Limited (455 - 457 Spanish Town
Road Kingston 11, Telephone: 876-979-8683) and
painting with two (2) coats reflective paint. 13 m2 $4,400.00 $57,200.00
Doors
I 875mm x 2100mm Poplar or equal hardwood door hung
on and including butt hinges. 2 Nr $46,387.69 $92,775.38
Ironmongery
L Pairs mild steel butt hinges. 6 Nr $1,000.00 $6,000.00
Knot, prime and apply one (1) undercoat and two (2)
gloss finishing coats on:
N General surfaces of doors. 8 m2 $830.00 $6,640.00
TO COLLECTION $476,239.38
MBRC/2.0/18/44
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Item Description Quantity Unit Rate Amount
FLOOR FINISHES
Porcelain Tiling
A 450mm x 600mm porcelain tile (Prime Cost Sum $500.00
each) laid on and including thinset mortar and grouted
in matching grout. 9m $2,500.00 $22,500.00
WALL FINISHES
Ceramic Tiling
G Glazed ceramic tiles 600mm x 600mm laid in approved
adhesive on rendered walls and grouted in matching
grout. 6 m2 $6,500.00 $39,000.00
CEILING FINISHES
H Cement and sand (1:3) render in two (2) coats on soffit
of slab including hacking or bonding agent. 13 m2 $2,260.00 $29,380.00
Painting
I Prepare and apply one (1) undercoat and two (2) finishing
coats emulsion paint on rendered soffits. 13 m2 $830.00 $10,790.00
SANITARY APPLIANCES
Water Closets
J Kohler one-piece water closet, including seat, angle
valve etc. and fixing to floor and connecting to supply
and waste pipes. (PL 01) 1 Nr $40,000.00 $40,000.00
Lavatory Basins
K Kohler or equal undermount lavatory basin including
angle valves, flex tubes etc. and fixing in position and
connecting to supply and waste pipes. (PL 03) 1 Nr $40,000.00 $40,000.00
TO COLLECTION $398,370.00
MBRC/2.0/18/45
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Mirrors
B 600mm x 600mm copper-backed mirror with bevelled
edge fixed to masonry walls with four (4) chromium-
plated dome headed screws. 1 Nr $1,560.00 $1,560.00
TO COLLECTION $109,560.00
COLLECTION
MBRC/2.0/18/46
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
EXTERNAL WORKS
SUBSTRUCTURE
Filling to Excavations
D Filling with excavated material from foundations. 3 m2 $800.00 $2,400.00
TO COLLECTION $302,080.00
MBRC/2.0/18/47
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
SUBSTRUCTURE (Cont'd)
Block Walls
A 150mm thick precast concrete block work laid in cement
and sand mortar (1:3) and having all pockets filled solid
and building around rod reinforcement. 12 m2 $7,800.00 $93,600.00
TO COLLECTION $554,400.00
MBRC/2.0/18/48
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Cement:Sand/Concrete Screeds/Toppings
E Cement and sand (1:3) screed laid on roof slab. 9 m2 $2,260.00 $20,340.00
Membrane
F 5mm thick waterproofing membrane as supplied by
Spectrum Systems Limited (455 - 457 Spanish Town
Road Kingston 11, Telephone: 876-979-8683) and
painting with two (2) coats reflective paint. 11 m2 $4,400.00 $48,400.00
Doors
I 875mm x 2100mm Poplar or equal hardwood door hung
on and including butt hinges. 2 Nr $46,387.69 $92,775.38
Ironmongery
L Pairs mild steel butt hinges. 6 Nr $1,000.00 $6,000.00
Knot, prime and apply one (1) undercoat and two (2)
gloss finishing coats on:
N General surfaces of doors. 8 m2 $830.00 $6,640.00
TO COLLECTION $481,169.38
MBRC/2.0/18/49
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
FLOOR FINISHES
Porcelain Tiling
A 450mm x 600mm porcelain tile (Prime Cost Sum $500.00
each) laid on and including thinset mortar and grouted
matching grout. 7 m2 $6,000.00 $42,000.00
WALL FINISHES
Cement and sand (1:3) render in two (2) coats including
hacking or bonding agent:
C Block or concrete walls. 53 m2 $2,260.00 $119,780.00
Prepare and apply one (1) undercoat and two (2) finishing
coats emulsion paint on:
E Rendered walls. 53 m2 $830.00 $43,990.00
Ceramic Tiling
G Glazed ceramic tiles 600mm x 600mm laid in approved
adhesive on rendered walls and grouted in matching
grout. 5 m2 $6,000.00 $30,000.00
CEILING FINISHES
H Cement and sand (1:3) render in two (2) coats on soffit
of slab including hacking or bonding agent. 11 m2 $2,260.00 $24,860.00
Prepare and apply one (1) undercoat and two (2) finishing
coats emulsion paint on:
C Rendered soffits. 11 m2 $830.00 $9,130.00
SANITARY APPLIANCES
Water Closets
D Kohler one-piece water closet, including seat angle
valve etc. and fixing to floor and connecting to supply
and waste pipes. (PL 01) 1 Nr $40,000.00 $40,000.00
Lavatory Basins
E Kohler or equal undermount lavatory basin including
angle valves, flex tubes etc. and fixing in position and
connecting to supply and waste pipes. (PL 03) 1 Nr $40,000.00 $40,000.00
TO COLLECTION $371,740.00
MBRC/2.0/18/50
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Mirror
B 600mm x 600mm copper-backed mirror with bevelled
edge fixed to masonry walls with four (4) chromium-
plated dome headed screws. 1 Nr $1,650.00 $1,650.00
TO COLLECTION $109,650.00
COLLECTION
MBRC/2.0/18/51
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Item Description Quantity Unit Rate Amount
EXTERNAL WORKS
KERBS
TO COLLECTION $9,961,130.00
MBRC/2.0/18/52
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
KERBS
TO COLLECTION $1,871,570.00
COLLECTION
EXTERNAL WORKS
RETAINING WALLS
MIXING/CASTING/CURING/INSITU CONCRETE
J 10mm diameter in belt beams as stirrups. (In Nr.380) 351 kg $290.00 $101,790.00
Formwork
K Sides of foundations. 68 m2 $4,150.00 $282,200.00
EXTERNAL WORKS
MIXING/CASTING/CURING/INSITU CONCRETE
MBRC/2.0/18/55
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
EXTERNAL WORKS
BOUNDARY WALLS
MIXING/CASTING/CURING/INSITU CONCRETE
K 10mm diameter in belt beams as stirrups. (In Nr.1120) 690 kg $290.00 $200,100.00
Formwork
M Sides of strip foundation. 201 m2 $4,150.00 $834,150.00
TO COLLECTION $7,207,990.00
MBRC/2.0/18/56
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Formwork
BLOCK WALLS
PLASTERED/RENDERED/ROUGHCASTCOATINGS
G Prepare and apply one (1) undercoat and two (2) finishing
coats emulsion paint on rendered wall. 1065 m2 $1,000.00 $1,065,000.00
PROVISIONAL SUMS
TO COLLECTION $20,260,360.00
MBRC/2.0/18/57
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
COLLECTION
MBRC/2.0/18/58
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
MIXING/CASTING/CURING/INSITU CONCRETE
Formwork
40 m2 $4,150.00 $166,000.00
H Sides of base.
BLOCK WALLS
TO COLLECTION $1,350,430.00
MBRC/2.0/18/59
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
PLASTERED/RENDERED/ROUGHCASTCOATINGS
SOAK-AWAY PIT
TO COLLECTION $1,756,880.00
COLLECTION
MBRC/2.0/18/60
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
EXTERNAL WORKS
E Extra over excavations for rock or hard concrete and get 300 m3 $7,800.00 $2,340,000.00
out.
Disposal
Filling
MIXING/CASTING/CURING/INSITU CONCRETE
TO COLLECTION $5,560,960.00
MBRC/2.0/18/61
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
MIXING/CASTING/CURING/INSITU CONCRETE
I 10mm diameter as stirrups in belt beam. (In Nr.240) 185 kg $290.00 $53,650.00
Formwork
TO COLLECTION $5,021,790.00
MBRC/2.0/18/62
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Formwork
WATERPROOFING
BLOCK WALLS
PLASTERED/RENDERED/ROUGHCASTCOATINGS
TO COLLECTION $3,531,150.00
MBRC/2.0/18/63
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
PROVISIONAL SUMS
TO COLLECTION $50,000.00
COLLECTION
MBRC/2.0/18/64
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
EXTERNAL WORKS
Disposal
Filling
MIXING/CASTING/CURING/INSITU CONCRETE
TO COLLECTION $7,004,000.00
MBRC/2.0/18/65
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
Formwork
TO COLLECTION $1,710,750.00
MBRC/2.0/18/66
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
WATERPROOFING
BLOCK WALLS
PLASTERED/RENDERED/ROUGHCASTCOATINGS
PROVISIONAL SUMS
MBRC/2.0/18/67
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
COLLECTION
MBRC/2.0/18/68
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
EXTERNAL WORKS
Extra for
MANHOLES
TO COLLECTION $2,380,850.00
MBRC/2.0/18/69
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
GREASE TRAPS
TO COLLECTION $99,050.00
COLLECTION
MBRC/2.0/18/70
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
EXTERNAL WORKS
EXTERNAL WORKS
MBRC/2.0/18/72
Proposed MONTEGO BAY RACQUET CLUB CONDOMINIUMS & SPA, SEWELL AVENUE, MONTEGO BAY, ST. JAMES
Bill Nr.2 - MEASURED WORKS
SUMMARY
Page No.
FACILITATION WORKS MBRC/2.0/1/1 $1,531,300.00
MBRC/2.0/20/73