Professional Documents
Culture Documents
Test Bank For Operations and Supply Chain Management For The 21st Century 1st Edition by Boyer Download
Test Bank For Operations and Supply Chain Management For The 21st Century 1st Edition by Boyer Download
Student: ___________________________________________________________________________
3. Because projects are limited in time, budgeting, and resources, they generally have very little risk involved.
True False
4. It is normally sufficient for a Project manager to have expertise in human resources and leave other areas to
subordinates.
True False
5. The project plan reports estimated costs and cash flow requirements at different project stages.
True False
6. The project execution phase of project management involves the actual completion of all activities that are
part of the project.
True False
10. Since the introduction of computer software, Gantt charts are obsolete in project management.
True False
11. Visual techniques, such as precedence diagrams and Gantt charts, add little value to project management.
True False
12. The activity on node (AON) approach to designing a network diagram illustrates activities by the use of an
arrow.
True False
13. Industry uses both AON and AOA for designing network diagrams.
True False
14. In an AON network diagram, arrows can point to any direction from a node.
True False
15. The path in a network diagram with the most activities is the critical path.
True False
17. In project management, "critical activities" are activities that quality managers must be involved with.
True False
18. Using CPM, any activity with no predecessors can start as soon as the project is initiated.
True False
19. Slack time can only be calculated by finding the difference in the late start and early start.
True False
20. The difference in the early start and the early finish is the slack time.
True False
22. Additional resources can rarely be used to speed up a project once it is behind schedule.
True False
23. Any activity that has not been completed is a candidate for a cost and time trade-off analysis.
True False
24. The goal of crashing a project is to reduce the time at the least expensive rate.
True False
25. In a PERT analysis, the "most likely time" is the minimum possible time required to complete an activity.
True False
30. A project risk assessment plan involves developing a comprehensive list of all potential problems that might
hinder project completion.
True False
33. Which of the following terms does not describe a project management technique?
A. CPM
B. Uncertainty analysis
C. Cost and time trade-off analysis
D. Resource allocation techniques
E. Process selection team
34. Being an expert in information integration, project scope, time management, quality management, human
resources, communications, risk, and procurement are beneficial skills for what member of a project
management team?
A. Project planner
B. Project sponsor
C. Project manager
D. Project accountant
E. Project auditor
35. Which of the following relationships between cost, time, and scope is not realistic?
A. Increased scope, decreased cost, and decreased time
B. Increased scope, increased cost, and increased time
C. Decreased time, increased cost, and decreased scope
D. Decreased cost, decreased time, and decreased scope
E. All of these options are realistic
37. Which of the following statements accurately describes the following Gantt chart?
Activity Week Week Week Week Week Week Week Week Week Week
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
G
H
I
42. Activity 7 is directly preceded by two activities, activity 5 and activity 6. Activity 5 has an expected time of
5 and ES time of 6. Activity 6 has an expected time of 7 and an ES time of 7. Activity 7 has an expected time of
10. The ES for activity 7 is
A. 10
B. 11
C. 14
D. 21
E. 24
43. For an activity, the ES is 0, the EF is 2, the LS is 3, and the LF is 5. What is the slack?
A. 0
B. 2
C. 3
D. 5
E. 8
44. This is zero for all of the first activities on a CPM network diagram.
A. Slack
B. Late start
C. Late finish
D. Early start
E. Early finish
45. The amount of leeway each activity has in its starting time and duration without delaying the project.
A. Standard time
B. Normal time
C. Crash time
D. Slack time
E. Critical time
46. Which project management tool introduces uncertainty into the project planning process?
A. CPM
B. Work breakdown structure
C. Precedence relationships
D. Network diagram
E. PERT
48. When computing the expected time for a project, which time estimate is weighted the most?
A. Critical time
B. Optimistic time
C. Pessimistic time
D. Most likely time
E. Expected time
49. Using PERT, the project completion time closely resembles what distribution?
A. Uniform distribution
B. Poisson distribution
C. Normal distribution
D. Negative binomial distribution
E. Variance distribution
51. The critical factors in project failure include all of the following except
A. Change in initial project expectations
B. Change in complexity
C. Change in technical difficulties
D. Change in regulatory problems
E. Change in personnel
52. Project risk can be grouped into four categories. Which of the following is not one of the categories?
A. Severity
B. Probability
C. Timing
D. Dynamic risk
E. Personnel
53. The percentage of the project's scope that will be affected by a problem defines which project risk
classification?
A. Severity
B. Probability
C. Timing
D. Dynamic risk
E. Personnel
54. Which of the following is not a reason projects succeed?
A. Strong project leadership
B. Clear, measurable goals
C. Declining material prices
D. Well-defined implementation plan
E. A sense of urgency
55. An approach to reduce the amount of fluctuations in day-to-day resource requirements within an
organization is
A. Contingency planning
B. Project risk management
C. Resource management
D. Resource breakdown structure
E. Resource leveling
58. List and briefly describe three of the six project planning documents described in the text.
59. Describe the time, cost, and scope constraints related to project management and discuss how they are
related.
61. Identify and describe the four parameters used to calculate the critical path for CPM.
62. Identify and describe the three different estimates for activity times in the PERT method.
63. Identify four broad categories of risk associated with projects.
65. Identify and describe how leadership can impact project success.
66. List the paths for the following network diagram and determine the duration of the project.
67. Determine the amount of slack in each activity.
68. An activity with a duration of 8 days has an early start time of 25. Another activity has a duration of 5 days
and an early start time of 25 days. Both activities precede activity M. Activity M has a duration of 4 days. What
is the early start time for activity M?
69. All the following activities are on the critical path. If the project needs to be reduced by 3 days, and no other
paths become shorter than the current critical path, which activities should be crashed and in what order? What
is the total cost of crashing?
70. If an activity has an optimistic time of 5 days, a pessimistic time of 10 days, and a most likely time of 8
days, what is the expected time for the activity?
71. If an activity has an optimistic time of 5 days, a pessimistic time of 10 days, and a most likely time of 8
days, what is the variance for the activity?
72. If a project has an expected completion time of 40 days, with a standard deviation of 2 days, what is the
amount of time this project will be completed in, 95% of the time?
73. Draw a network diagram using the AON convention for the following project.
Activity A has a duration of 4 days and no predecessor.
Activity B has a duration of 2 days and has A as a predecessor.
Activity C has a duration of 2 days and has A as a predecessor.
Activity D has a duration of 3 days and has B as a predecessor.
Activity E has a duration of 4 days and has C as a predecessor.
Activity F has a duration of 1 day and has D and E as predecessors.
3. Because projects are limited in time, budgeting, and resources, they generally have very little risk involved.
FALSE
4. It is normally sufficient for a Project manager to have expertise in human resources and leave other areas to
subordinates.
FALSE
5. The project plan reports estimated costs and cash flow requirements at different project stages.
FALSE
6. The project execution phase of project management involves the actual completion of all activities that are
part of the project.
TRUE
10. Since the introduction of computer software, Gantt charts are obsolete in project management.
FALSE
11. Visual techniques, such as precedence diagrams and Gantt charts, add little value to project management.
FALSE
12. The activity on node (AON) approach to designing a network diagram illustrates activities by the use of an
arrow.
FALSE
13. Industry uses both AON and AOA for designing network diagrams.
TRUE
14. In an AON network diagram, arrows can point to any direction from a node.
FALSE
15. The path in a network diagram with the most activities is the critical path.
FALSE
17. In project management, "critical activities" are activities that quality managers must be involved with.
FALSE
18. Using CPM, any activity with no predecessors can start as soon as the project is initiated.
TRUE
19. Slack time can only be calculated by finding the difference in the late start and early start.
FALSE
20. The difference in the early start and the early finish is the slack time.
FALSE
22. Additional resources can rarely be used to speed up a project once it is behind schedule.
FALSE
23. Any activity that has not been completed is a candidate for a cost and time trade-off analysis.
FALSE
24. The goal of crashing a project is to reduce the time at the least expensive rate.
TRUE
25. In a PERT analysis, the "most likely time" is the minimum possible time required to complete an activity.
FALSE
30. A project risk assessment plan involves developing a comprehensive list of all potential problems that might
hinder project completion.
TRUE
33. Which of the following terms does not describe a project management technique?
A. CPM
B. Uncertainty analysis
C. Cost and time trade-off analysis
D. Resource allocation techniques
E. Process selection team
34. Being an expert in information integration, project scope, time management, quality management, human
resources, communications, risk, and procurement are beneficial skills for what member of a project
management team?
A. Project planner
B. Project sponsor
C. Project manager
D. Project accountant
E. Project auditor
35. Which of the following relationships between cost, time, and scope is not realistic?
A. Increased scope, decreased cost, and decreased time
B. Increased scope, increased cost, and increased time
C. Decreased time, increased cost, and decreased scope
D. Decreased cost, decreased time, and decreased scope
E. All of these options are realistic
37. Which of the following statements accurately describes the following Gantt chart?
Activity Week Week Week Week Week Week Week Week Week Week
1 2 3 4 5 6 7 8 9 10
A
B
C
D
E
F
G
H
I
42. Activity 7 is directly preceded by two activities, activity 5 and activity 6. Activity 5 has an expected time of
5 and ES time of 6. Activity 6 has an expected time of 7 and an ES time of 7. Activity 7 has an expected time of
10. The ES for activity 7 is
A. 10
B. 11
C. 14
D. 21
E. 24
43. For an activity, the ES is 0, the EF is 2, the LS is 3, and the LF is 5. What is the slack?
A. 0
B. 2
C. 3
D. 5
E. 8
44. This is zero for all of the first activities on a CPM network diagram.
A. Slack
B. Late start
C. Late finish
D. Early start
E. Early finish
45. The amount of leeway each activity has in its starting time and duration without delaying the project.
A. Standard time
B. Normal time
C. Crash time
D. Slack time
E. Critical time
46. Which project management tool introduces uncertainty into the project planning process?
A. CPM
B. Work breakdown structure
C. Precedence relationships
D. Network diagram
E. PERT
48. When computing the expected time for a project, which time estimate is weighted the most?
A. Critical time
B. Optimistic time
C. Pessimistic time
D. Most likely time
E. Expected time
49. Using PERT, the project completion time closely resembles what distribution?
A. Uniform distribution
B. Poisson distribution
C. Normal distribution
D. Negative binomial distribution
E. Variance distribution
51. The critical factors in project failure include all of the following except
A. Change in initial project expectations
B. Change in complexity
C. Change in technical difficulties
D. Change in regulatory problems
E. Change in personnel
52. Project risk can be grouped into four categories. Which of the following is not one of the categories?
A. Severity
B. Probability
C. Timing
D. Dynamic risk
E. Personnel
53. The percentage of the project's scope that will be affected by a problem defines which project risk
classification?
A. Severity
B. Probability
C. Timing
D. Dynamic risk
E. Personnel
54. Which of the following is not a reason projects succeed?
A. Strong project leadership
B. Clear, measurable goals
C. Declining material prices
D. Well-defined implementation plan
E. A sense of urgency
55. An approach to reduce the amount of fluctuations in day-to-day resource requirements within an
organization is
A. Contingency planning
B. Project risk management
C. Resource management
D. Resource breakdown structure
E. Resource leveling
Resource plan¾lists the labor, equipment, other resources, components, and raw materials required to complete
the project activities. The quantities of different resources required during different project stages are estimated.
Financial plan¾reports estimated costs and cash flow requirements at different project stages.
Quality plans¾provides details on quality targets, control, and potential improvement measures.
Communications plan¾includes updates on project status relative to schedule, which needs to be communicated
to key stakeholders.
Risk plan¾provides an assessment of potential risks and uncertainties, and actions that might be necessary to
overcome the challenges.
59. Describe the time, cost, and scope constraints related to project management and discuss how they are
related.
These three constraints are interrelated and are negatively correlated: for example, an increased scope typically
means increased time and increased cost, a short time constraint could mean increased costs and reduced scope,
and a limited budget could mean increased time and reduced scope.
The critical path method is an algorithm for scheduling the activities within a project to achieve the fastest and
most efficient execution of that project. The critical path is the path that takes the longest time to complete.
61. Identify and describe the four parameters used to calculate the critical path for CPM.
Early start time (ES): the earliest time at which an activity can start, considering the beginning and ending times
for each of the preceding activities.
Early finish time (EF): the sum of the early start time (ES) and the time required to complete the activity.
Late start time (LS): the latest time at which an activity can start, considering all the precedence relationships,
without delaying the completion time for the project.
Late finish time (LF): the sum of the late start time and the time required to complete the activity.
62. Identify and describe the three different estimates for activity times in the PERT method.
Optimistic time (to): the minimum possible time required to complete an activity, assuming that everything
proceeds better than is normally expected.
Pessimistic time (tp): the maximum possible time required to complete an activity, assuming that everything
proceeds at the slowest possible pace.
Most likely time (tm): the best estimate of the time required to accomplish a task, assuming that everything
proceeds normally.
Financial resource risk, such as cash overruns, budget shortfalls, and cash flow problems
Supply risk, such as suppliers not providing the required materials on time
Quality risk, or the possibility that the quality of individual tasks gets compromised when trying to keep up with
the project schedule
64. Identify five of the critical factors in project failure.
65. Identify and describe how leadership can impact project success.
Successful execution of a project requires a strong project leadership. The project manager must focus on
meeting the three constraints: scope, time, and budget. A successful project means that all deliverables are
completed on time, within budget, and at a level of quality that is acceptable to the project's sponsors and
stakeholders.
66. List the paths for the following network diagram and determine the duration of the project.
ABEF: 23
ABDEF: 29
ACDEF: 31
The project duration will be 31 days.
67. Determine the amount of slack in each activity.
68. An activity with a duration of 8 days has an early start time of 25. Another activity has a duration of 5 days
and an early start time of 25 days. Both activities precede activity M. Activity M has a duration of 4 days. What
is the early start time for activity M?
The first activity will have an early finish time of 33, and the other activity will have an early finish time of 30.
Activity M cannot begin while either activity is still being conducted, so it can start at time 33.
69. All the following activities are on the critical path. If the project needs to be reduced by 3 days, and no other
paths become shorter than the current critical path, which activities should be crashed and in what order? What
is the total cost of crashing?
Activity D should be crashed a week for $100, then another week for $100, and finally Activity B should be crashed a week for $160. The total cost
would be $360.
70. If an activity has an optimistic time of 5 days, a pessimistic time of 10 days, and a most likely time of 8
days, what is the expected time for the activity?
71. If an activity has an optimistic time of 5 days, a pessimistic time of 10 days, and a most likely time of 8
days, what is the variance for the activity?
72. If a project has an expected completion time of 40 days, with a standard deviation of 2 days, what is the
amount of time this project will be completed in, 95% of the time?
The number of days for completion, 95% of the time, is (1.645*2) + 40 = 43.29 days
73. Draw a network diagram using the AON convention for the following project.
Activity A has a duration of 4 days and no predecessor.
Activity B has a duration of 2 days and has A as a predecessor.
Activity C has a duration of 2 days and has A as a predecessor.
Activity D has a duration of 3 days and has B as a predecessor.
Activity E has a duration of 4 days and has C as a predecessor.
Activity F has a duration of 1 day and has D and E as predecessors.
Test Bank for Operations and Supply Chain Management for the 21st Century 1st Edition by Boy
Activity A slack = 0 - 0 = 0
Activity B slack = 5 - 4 = 1
Activity C slack = 4 - 4 = 0
Activity D slack = 7 - 6 = 1
Activity E slack = 6 - 6 = 0
Activity F slack = 10 - 10 = 0
75. Activity C is directly preceded by two activities, activity A and activity B. Activity A has an expected time
of five and early start time of six. Activity B has an expected time of seven and an early start time of seven.
Activity C has an expected time of ten. What is the early start for activity C?