Professional Documents
Culture Documents
01 Dredging 35 24 00
01 Dredging 35 24 00
01 Dredging 35 24 00
Authority
Authority
PART 1 GENERAL
1.2.1 Definitions
The following definitions are applicable in this document and associated field works:
Meaning
Port Shuwaikh Port Authority
Final Grade Level Final top level of the island platform as specified in the project layout and
sections
Earth Fill Any filling placed using onshore hauling equipment, above water levels
and compacted using surface compaction methods
Reclamation Fill Any filling placed hydraulically to reclaim land from current seabed up to
the final grade level as specified in the Drawings.
NCT New Container Terminal at Shuwaikh Port
Surveys The execution of all required data gathering, site surveys, site
investigations etc. necessary to complete the NCT Design.
1.2.2 Abbreviations
Meaning
BS British Standard
Authority
Meaning
HSE Health, Safety and Environment
QA Quality Assurance
QC Quality Control
Authority
BS 6349 (2016) Part 5 - Maritime Structures – Code of Practice for Dredging and Land
Reclamation;
BS EN 933-7:1998 Tests for Geometrical Properties of Aggregates, Part 7: Determination of
Shell Content, Percentage of Shells in Coarse Aggregates; and
FM 5-555: 2000 Florida Method of Test for Shell Content of Coarse Aggregate.
1.4.2
PORT’s Requirement Project Specifications
Rockworks Specification
Authority
In case of conflict between documents in the same level of hierarchy, the most stringent requirement shall apply.
Such interpretation of the most stringent requirement shall be subject to EMPLOYER’s approval utilizing a
technical query sheet. In all such cases of conflict, EMPLOYER’s decision shall be final.
The CONTRACTOR shall make all necessary arrangements for supply of his own utilities and facilities, including
telephone line, VHF, water, electricity, sewage, and all other facilities and services he may need. He shall cover
the whole cost of installations, use, charges, and maintenance of these facilities and services to the completion
of the WORK.
The CONTRACTOR shall keep the area allocated to offices and facilities/services clean and tidy throughout the
duration of the WORK. The CONTRACTOR shall make his own arrangements for disposal of any kind of waste,
rubbish, debris, and sewage in an appropriate manner acceptable to the relevant authorities. Disposal in the sea
shall not be allowed under any circumstances.
The CONTRACTOR shall avoid spillage of dirt or any hazardous materials on roads and/or land areas during the
execution of the WORK and shall make all necessary arrangement for cleaning up such spillage, if occurs, to the
satisfaction of the PORT.
The CONTRACTOR shall give notice to the relevant local authorities at least two weeks in advance of
commencement of any new activity involving either marine craft or reclamation over existing seabed. He shall
provide all information on working areas, types of craft and durations of marine-related activities and shall also
advise on completion of each and every separate activity. In particular, at least one-months’ notice shall be given
Authority
to the relevant local authorities for removal and/or relocation of any navigation or mooring buoys affected by the
WORK.
The Notice to Mariners should be reviewed on a daily basis and there should be daily communication with other
parties in the field through specific communication channels stated in the Notice to Mariners.
All correspondence between the CONTRACTOR and relevant Local Authorities, including all submissions, shall be
copied to the PORT.
The CONTRACTOR shall provide information as to the proposed navigation buoys and marks to the PORT and
relevant Local Authorities at least one month before its installation. The proposed locations shall be in terms of
both the land-based grid and Latitude and Longitude. The CONTRACTOR shall confirm the locations of the
navigation buoys and marks after installation and shall take all necessary measures to maintain them in good
conditions and at the correct locations.
The CONTRACTOR shall mark all temporary underwater obstructions, which are a consequence of the WORK,
with buoys and lights in addition to any other measures necessary for the safety of navigation and shall remove
these obstructions at the earliest possible time.
The CONTRACTOR shall liaise with the relevant Local Authorities if any existing navigation aids need to be
removed or relocated during the WORK.
CONTRACTOR’s vessels should adhere to specific navigational routes approved by PORT. These navigational
routes will be informed by the recommendations of the HSEIA to allow for avoidance of highly sensitive areas.
Vessel movement outside of these specific navigational routes shall be strictly prohibited.
During site activities, items accidentally lost in water that can be considered a navigation obstacle shall be
reported to the relevant local authorities in the fastest possible way, with a copy to the PORT.
The CONTRACTOR shall proceed with recovery of lost items as soon as possible and shall report to the above-
mentioned parties when the recovery operation has been completed.
The CONTRACTOR shall comply with the requirements of the relevant Local Authorities with respect to marine
traffic related to the WORK. All vessels, including crafts and floating plants, shall be registered and certified and
shall have characteristics in line with the requirements of the International Regulations for Preventing Collisions
at Sea 1972 (COLREGs), so that all marine crafts working/passing in the area proximity are aware of the nature of
their work.
Floating plants shall be maintained in a satisfactory condition and shall be provided with adequate ropes, lines
and moorings, sound, and lights in addition to adequate attendance by competent seamen at all times. The
CONTRACTOR shall be fully responsible for the safety of all floating plants and personnel engaged by him at all
times. Where work is carried out from dumb lighters, pontoons or other non-self-propelled floating plant, a
suitably powered craft shall be in attendance at all times.
Authority
Vessels used in transporting material shall be properly maintained so that losses of material on route between
various areas of the site are avoided. Leaking hopper barges shall be taken out of service and properly repaired
in order to allow them to re-operate on site.
If site investigation work is carried out over shallow or deep water, marine craft, pontoons, or platforms shall be
adequately braced, secured, and anchored and of such size and construction as to ensure a satisfactory
performance of the WORK. The marine craft shall also be fitted out to allow the types of investigation, sampling,
and in situ testing required to be carried out to the satisfaction of the PORT. The CONTRACTOR shall provide the
PORT with adequate assistance for gaining access to the marine craft, pontoons or platforms.
Areas of temporary anchorage of CONTRACTOR's marine craft shall be approved by the PORT and other
relevant Local Authorities. These areas shall generally be outside any permanent or temporary navigation
channels and shall be clearly marked with marker buoys or other system. The CONTRACTOR shall ensure that
temporary anchorages are not located in sensitive locations. It is recommended to ensure there is a visual survey
before anchors are deployed, particularly in sensitive areas, to avoid anchoring on coral reefs, seagrass beds,
etc.
Work boats shall be kept available for use by the PORT for supervision and inspection.
The CONTRACTOR shall restrict speed of vessels according to the requirements of PORT, HSEIA and CEMP (The
HAZID/ENVID report recommends a speed limit of 10 knots in Hail)
At least one Marine Mammal and Reptile Observers (MMROs) should be on all boats, boats, vessels and dredgers
within MPA zone. MMRO’s should be provided basic training (by the CONTRACTOR’ marine ecologist or by an
approved Environmental Consultant) in spotting marine mammals/reptiles.
Reference is made to the PROJECT Design Criteria about information on tides, etc.
The CONTRACTOR shall be responsible for all setting out of the works on basis of existing benchmarks indicated
by the PORT, and he shall prepare all the plans, reports, etc. concerning grids and datum in the specified system
indicated in the CONTRACT.
Authority
The CONTRACTOR shall keep daily records of all measured tide levels in an agreed computer-readable
electronic format. Data points shall represent tide level at intervals not exceeding five minutes.
When instructed or on completion of the WORKS, whichever is the earlier, the CONTRACTOR shall remove and
dispose of the tide gauges and supporting structures (e.g. brackets) and reinstate the area occupied to the
satisfaction of the CONTRACTOR.
1.6.11.1 General
The CONTRACTOR shall always comply with all local rules and regulations, including the rules for health, safety
and environment (HSE), in addition to the requirements of the following sections.
The plan shall consist of working procedures that describes the measures taken to mitigate the environmental or
working environmental impact related to the specific activity. The procedures must include the name of the
person in the CONTRACTOR’s organization being responsible for implementation of the procedure. Procedures
must as a minimum cover the following:
• Waste management
• Environmental management procedures – (water quality, marine mammal, and turtle management, etc.)
Authority
The HSE plan shall include an emergency plan that describes how the CONTRACTOR, and his employees react in
case of accidents, fire or spillage of materials that can have environmental impact (oil, petrol, chemicals, etc.).
The CONTRACTOR shall comply with all the measures identified in approved Construction Environmental
Management Plan (CEMP) for marine works, i.e., scum booms, silt curtains, etc.
The CONTRACTOR shall present the HSE plan in a safety meeting for all site personnel when WORK commence
on site and arrange for relevant training as per the HSE Plan. A signed register shall confirm attendance of this
meeting by all site personnel, and signed certificates shall document the satisfactory completion of relevant
training.
Follow-up meetings are to be held as necessary to ensure compliance and identify any needs for revisions of the
HSE plan. Up to five persons from the PORT site staff shall be given relevant briefing/training on site, free of
charge, to allow them to supervise the WORK on the dredging equipment in conformity with the HSE plan
procedures.
The CONTRACTOR shall comply with the approved HSEIA and CEMP requirements in terms of mitigation
measures, monitoring, and compliance to threshold limits. The CONTRACTOR shall carry out environmental
monitoring according to the requirements of the PORT. This shall include, but not limited to, seawater quality
monitoring (using fixed, continuous monitoring buoys and daily, in-situ measurements, weekly water sampling,
and laboratory testing), sediment sampling and testing, observation of marine mammals and reptiles, ambient
and underwater noise monitoring, generation of waste including solid/liquid and hazardous/non-hazardous
waste, emissions from vessels/plant/equipment, etc.
The CONTRACTOR shall take all due reasonable precautions to minimize nuisance arising from noise, dust, etc.
Diesel and petrol engines shall be fitted with efficient silencers, which are not necessarily those supplied by the
manufacturer. If noise levels exceed those stated in the CONTRACT or as required by Local Authorities, then,
where practicable, the equipment shall be screened with acoustic materials.
1.7 SUBMITTALS
Authority
• Methodology for reclamation works to include necessary measures to eliminate accumulation of silt during
reclamation.
• Quality assurance and control procedures, including field and laboratory testing and criteria for
acceptance/approval of dredging works.
• Type of dredging proposed for each stage of the WORK, including details of performance and estimated
production.
• Working method and sequence of all work detailed in accordance with the CONTRACT.
• Description of expected spill from dredging equipment and description of proposed mitigation measures
including spill monitoring.
The CONTRACTOR shall indicate in detail the method used to control any negative environmental impacts
associated with dredging works.
The CONTRACTOR shall submit, for review and approval of the PORT, progress reports at the end of each
working week (Weekly Activity Report). The report shall include, but not limited to, the following:
• Results of quality assurance measures including field and laboratory tests (in both pdf and an agreed native
spreadsheet format)
Authority
The CONTRACTOR shall submit three copies in accepted electronic (soft) media, in a form acceptable to the
PORT, the following:
• Overall assessment of site conditions including conformity to ground improvement acceptance criteria.
• As-built native and processed records set forth in Section 7.7 in hard copies.
• As-built records of ground improvement works, including compaction point coordinates and level of treated
ground surface, etc.
Authority
PART 2 PRODUCTS
2,1 Dredging Works
The CONTRACTOR shall obtain all necessary licenses and consents for dredging operations, including the
disposal of unsuitable materials.
• Sourcing reclamation fill material for the island construction from project designated borrow areas, that shall
conform the PROJECT Specifications
• Dredging harbour area, including the side slopes, that shall conform to the project drawings/documents and
is confirmed by the PORT during construction.
• Dredging the navigation/access channels to the islands and between the islands, including the side slopes,
that shall conform to the PROJECT drawings/documents and be confirmed by the PORT during construction.
• Dredging of any unsuitable material under the footprint of the artificial islands
The CONTRACTOR shall ensure that all operations are performed in compliance with all local and international
regulations.
• Vertical tolerances in reference to the dredging levels shown in the PROJECT documents shall be +0.0 and -
500 mm.
• Dredging on the side slopes shall follow, as closely as practicable to the lines indicated or specified in the
project documents. The horizontal tolerances in reference to these side slope lines are 1.0 m to outside and
0.0 m to inside.
In case dredged material is deemed potentially suitable as a fill material, this material shall be tested once per
batch of 10,000 m3 or as instructed by the PORT. Testing shall be carried out by an accredited laboratory
approved by the PORT in order to verify compliance with material requirements specified in sections 8.2, 8.3,
and 9.3.
Authority
The CONTRACTOR shall be responsible, at his expense, for the disposal of material deemed by the PORT to be
unsuitable at the PROJECT designated disposal site. A proposed disposal plan shall be submitted to the PORT
for approval.
2,1.6 Stockpiling
Material arising from the dredging operations is to be carefully handled and stockpiled in a manner that will
exclude foreign or undesirable material.
If deemed required, a temporary stockpile area shall be assigned by the CONTRACTOR subject to PORT
approval.
Stockpiles are to be neatly and compactly constructed in an approved manner adjacent to excavations or
elsewhere on site as directed.
Stockpiles placed adjacent to dredging operations shall be kept an adequate distance away from dredging edges
(setback distance) so as not to adversely affect the stability of dredged slopes. Calculations of setback
distances shall be submitted to the PORT for approval.
Separate and stockpile dredged topsoil required to carry out subsequent top soiling activities.
Similarly, sampling and laboratory testing shall be undertaken as per the requirements of PORT and local
authorities’ guidelines/requirements. Number of sampling locations and frequency of sampling/testing shall be as
per recommendations of the HSEIA and CEMP.
In-situ water quality monitoring during dredging shall consist of the measurement of the following parameters:
• pH
• Electrical conductivity
• Dissolved oxygen
• Turbidity
• Temperature
• Salinity
Water samples shall be analyzed at an approved laboratory where the concentration of the following shall be
determined:
• Aluminium (Al);
Authority
• Cadmium (Cd);
• Chromium (Cr);
• Copper (Cu);
• Nickel (Ni);
• Lead (Pb);
• Zinc (Zn);
• Mercury (Hg);
• Arsenic (As);
• Iron (Fe)
• Faecal Coliform
For all samples, logs should be provided, including a list of contaminants, date and time of sampling, and depth
of sampling, etc. All testing shall be carried out by an approved laboratory and in accordance with the MOE
requirements.
Authority
PART 3 EXECUTION
3.1 Dredging
All temporary bunds (if deemed required) must be removed, and the seabed returned to the original depth upon
completion of the dredging works.
The CONTRACTOR ‘s method and sequences of dredging and reclamation shall be such that localized
deterioration of water quality is kept to a minimum. The CONTRACTOR is responsible for undertaking—at his own
cost—all appropriate mitigation measures deemed necessary to protect the environment.
Site vegetation and turf directed to be retained are to be protected from damage, preserved, and maintained by
the CONTACTOR in a manner approved by the PORT.
Site vegetation and turfs not required to be retained and protected may, at PORT's discretion, cost, and profit
considerations, be removed and sold, or left to be included with existing topsoil, where applicable.
Authority
Unless instructed otherwise, the CONTRACTOR shall reinstate all waterways upon completion of earthworks to
the satisfaction of the PORT.
Where an approved Environmental Impact Assessment (EIA) is available, the specific recommendations relating
to allowable suspended solid limits given therein shall be strictly followed. Results shall be submitted in writing
daily to the PORT. Locations and timing/frequency of measurements shall be agreed with the PORT. In the event
of suspended solids exceeding the specified level the PORT may order the CONTRACTOR to change his
methods or cease dredging operations.
3.4 SURVEYS
Prior to the commencement of dredging and reclamation works, the CONTRACTOR shall perform the Joint Pre-
Survey of the work areas.
Joint post-surveys of the completed works, or completed parts as instructed by the PORT, shall be conducted
by the CONTRACTOR.
The pre- and post-surveys shall be conducted using established survey controls. The PORT may assign staff to
check the CONTRACTOR work and may arrange for independent checks as necessary. In case no agreement is
reached, PORT’s view shall prevail.
Joint Pre- and Post-Surveys shall be carried with multibeam echosounder operating the equipment in straight
lines with a resolution of 1m x 1m. Native files for the inner area shall be produced for the WORK with 1m x 1m
resolution; however, drawings shall be readable and preferably be produced with 10m x 10m resolution.
Multibeam survey lines will be run at appropriate spacing to provide 100% bathymetric coverage. The survey
lines shall be run at a spacing to obtain 20% overlap of the bathymetry data.
In areas where water depth does not allow accurate surveying by means of multibeam equipment, a single beam
echosounder shall be used. In the case of single-beam survey, the sounding lines shall not be more than 15 m
apart with soundings taken at 2.5 m intervals along each line.
Cross check lines must be at every 100 m. Reduced soundings from primary sounding lines shall agree with
reduced soundings from cross check lines within ±0.1 meters for 85% of all soundings or be rejected. In shallow
water areas, hand sounding methods may be used with soundings on a 10 m grid or at such other intervals as the
PORT may request. All soundings shall be referenced to the Chart Datum indicated on the PROJECT’s Drawings.
Authority
The least depth over wrecks and obstructions of significant seabed features, if any, shall be determined by
closer examination survey.
For each Joint Post-Survey of the completed WORK, or sections or parts thereof, the final agreed survey results
shall be recorded on drawings scaled at 1:1,000. These drawings shall be the basis for the Taking-Over of the
works, or sections or parts thereof, and together with the Joint Pre-Survey drawings shall be the basis for the
final measurement of quantities under this Contract. Five copies of the drawings and digital files (AutoCAD latest
version and ASCII format) of the soundings shall be provided to the PORT.
The surveying equipment shall be modern (less than five years old) and well maintained/calibrated. The
necessary certifications for the surveying equipment shall also be presented to the PORT. Site calibration and
testing shall be carried out at regular intervals as per the approved survey method statement and shall be
witnessed by the PORT.
To ensure the proper positioning of the survey launch and dredging equipment, the CONTRACTOR shall mobilize
and operate a Differential Global Positioning System (DGPS) throughout the duration of the work. The type and
make of the DGPS must be approved by the PORT.
The accuracy of the electronic positioning system shall be ±20 mm on horizontal coordinate positions and shall
be calibrated at weekly intervals to the satisfaction of the PORT.
For work adjacent to existing or future structures, electronic positioning shall be augmented by more accurate
visual or laser methods of positioning.
The CONTRACTOR shall maintain an adequate stock of spare parts and exchange units on the site to avoid
disruption of the monitoring program.
Soundings shall be taken from a suitable launch fitted with an approved echo sounder and positioning system.
The frequency of the echosounder shall be between 200 and 500 kHz for all surveys to be conducted
throughout the duration of the Works project. The CONTRACTOR shall provide a survey launch for the full
duration of the reclamation work and shall be responsible for operating the launch with personnel trained in the
use of the equipment.
Sounding equipment shall operate with an accuracy of 1% of the indicated depth or 100mm whichever is greater,
and shall have the following facilities:
The echo sounding equipment shall be calibrated, by using a bar check, prior to the commencement of each
day’s sounding and checking on completion of each day’s work. The PORT may request additional calibration
checks.
The echo sounder shall be interfaced with the computer navigation and position fixing system in order that
logging of depth and position occurs instantaneously.
The CONTRACTOR shall provide the PORT, within three working days of survey completion, with two sets of
paper colour prints of the survey plots and contours accompanied by a CDs, appropriated indexed, with the
survey data. The drawings shall include the date, the scale, the type of equipment used and the Total
Propagated Errors (TPE).
Authority
Where the electronic data is dependent on the CONTRACTOR own proprietary or specialist software, the
CONTRACTOR shall provide the PORT, free of charge, with a copy of the relevant software, including all licenses.
Alternatively, the CONTRACTOR may convert the data, without loss of detail, into a format that may be read,
copied, and edited by other appropriate software approved by the PORT.
The CONTRACTOR shall submit a progress report one day before each progress meeting in a format approved
by the PORT. Progress reports shall include, but not limited to, information on:
• Schedule of all activities indicating the programmed percentage completion and actual percentage
completion of each activity at the date of reporting.
• Plant, equipment, and work force for each working day from last progress report.
• Brief daily reports with photographs, work progress, manpower on site etc.
• Detailed monthly progress reports with the content and in the format approved by the PORT shall be
submitted at the end of each month.
3.4.4.1 General
The surveys specified in Sections 2.7, 6.1 and 6.2 shall provide adequate documentation for:
• Acceptance of the Work for taking-over, i.e., verification of compliance with levels and lines as specified
under the Contract.
• Requirements to surveys accuracy have been met at all times during survey.
• Requirements to survey coverage have been met all over the area to be surveyed.
3.4.4.2 Scope
Surveys shall consist of the following:
• One pre-survey, which shall cover the entire dredging and reclamation areas. The survey shall include
physical landmark objects, as specified in Section
Authority
If a dedicated project co-ordinate system is required by PORT/Local Authorities, then the system shall be
identified through at least 5 control stations established in and around the WORK areas. Of these, two will be
made available to the CONTRACTOR for setting up reference stations and the like. The local coordinate system
will be based on the following:
• A Tranverse Mercator Projection uniformly identified through several parameters, such as Central meridian,
Scale at central meridian, False Easting, and False Northing.
During survey activities, the CONTRACTOR’s surveyor must keep a detailed daily log. This log must contain all
information relevant to the execution of the survey and for the post-processing. In addition, comprehensive logs
must be kept associated with all calibrations and with the survey lines.
A backup of all relevant data must be secured at the end of each survey day. A daily report must be prepared,
containing all logs and other information of relevance from the day.
• Calibration of Multi-beam echosounder. Patch-test through which the time-delay together with the yaw-,
roll- and the pitch C-O values must be determined. Test against the physical target (depth and position). If
the test at the end of the day fails all observed data of that day is rejected; and
In order for multi-beam survey to fulfil the accuracy requirements, the major error-contributors must be identified
and minimized by the CONTRACTOR’s surveyor. In addition to the calibrations mentioned in the foregoing, also
the uncertainties associated with the SV determination are major error-contributors. It is, therefore, important to
define and implement efficient methods for the avoidance of such contributions. For example, it may be
necessary to perform SV measurements at small intervals of two hours or less.
3.4.4.8 Reporting
The survey documentation shall be submitted on CD with two paper copies. Maps must be produced in 1:2,500
scale or as instructed by the PORT. The following must be presented on these maps:
Authority
• Physical features such as quay walls, buoys, breakwaters. Quay walls and breakwaters shall be incorporated
from available digital drawings but coordinates to all quay wall and wharf corners and true position of the
breakwater heads—as well as buoy locations—shall be verified as part of the In-Survey so that these
features are shown true in the survey drawings.
In addition to the bathymetric maps, coverage plots and difference plots must be made along similar guidelines.
Also, plots showing the number of observations per cell relative to the six observations per cell requirement are
required.
The difference plots must visualize in colour the relation between in- and out-survey and between design and
as-built (out-survey). An x-y-z file shall be included on CD only, in a format that will facilitate checking of volume
calculations.
The survey documentation shall consist of a report that include, but not limited to, the following:
• Information about water levels with time-series plots in which a comparison between the data originating
from the shore-based tide-gauge and those originating from the RTK-heights are depicted.
Volumes between pre-Survey levels and the lines and levels according to the drawings, subject to the tolerances
set out in this specification, shall be calculated by the CONTRACTOR and checked by the PORT. Requirements
for the volumes calculations shall include:
The DTM models from which the volumes are generated must be averaged models.
All models used in calculations and surveys must use identical grid shape, grid size, and
placing for similar areas.
Measurement shall be made against completed dredged ground within 30 days after notice of completion by the
CONTRACTOR and shall be confirmed within 30 days of submittal of the CONTRACTOR's measurements.