Machinary Rates

SL No. CATEGORY UNIT Dry Charges


1 Excavator Ex-200 for 300 hrs per mnth 210,000 210,000
2 Tipper for 300 hrs per mnth 120,000 120,000
3 Excavator Breaker for 300 hrs per mnth 225,000 270,000
4 Grader for 300 hrs per mnth 260,000 260,000
5 Water tanker for 300 hrs per mnth 50,000 50,000
HSD ltr 72 65
6 Roller for 300 hrs per mnth 100,000 100,000

7 JCB Breaker per mnth 85,000 85,000

8 JCB with Bucket per mnth 65,000 65,000

Pick & Carry Crane per mnth 90,000 90,000

FOR EXCAVATION WORKS

Rate analysis for Excavation in Ordinary Soil (Structure Works)

Scope of Work / Item description

Construction of Road - All Charges for earthwork in excavation by mechanical means in ordinary soil and
disposal of the same at designated Location within 1 km lead as per the instruction of the EIC.

Sr.NO. Item Description UOM Qty Rate


For productivity cum 287850 (per Month)
A Material Cost
Government royalty cum 287,850 0.00

Productivity 959.50 cum/hr

B Plant Cost
Excavator EX-200-Dry Charges m/c month 13.00 210000
Excavator EX-200-Fuel Charges Ltrs 58,500.00 72.0
Tipper-Dry Charges m/c month 69.00 120000
Tipper-Fuel Charges Ltrs 51,216.49 72.00

C Labour Cost
High Skilled m'days 30 880.00
Skilled m'days 30 795.00
Semi Skilled m'days 60 680.00
Unskilled m'days 60 640.00

Total Amount For qty. cum 287,850


Amount for one cum
Add 10% for Overhead, retention,
WC, Admn charge etc(on Labor
Cost)
Add 12% for S/C Profit on Labour
Cost

Rate per excluding Royalty

Prepared By Planning Manager


Cycle Time for
Tipper :-
Riversing Time 1.00 min
Loading Time 7.00 min
Unloading Time 1.00 min
Journey tiime 28.80 min
Misleaneus time 1.00 min
Total cycle time 38.80 min
1.55 No of trips by a single dumper
Diesel required 2.47 ltr/hour

Required
productivity
Structures 50.00 cum/hr
Required
productivity 76.00 cum/hr
Required
productivity 50.00 cum/hr
Required
productivity 23.33 cum/hr

ructure Works)

means in ordinary soil and


tion of the EIC.

Amount

2730000
4212000
8280000
3687588

26400
23850
40800
38400

19039037.63
66.14

0.04

0.07

Rs. 66.0 /Cum

Project Manager
Considering 9 Cum per dumper

Cosidering 25 Km/hr speed and 12 km avg lead

a single dumper

For Soil Excavation in Structure Works

For Soil Excavation

For SR Excavation

For HR Excavation